Yanpet MM21-U/O K-7701 Compressor O/H RFQ No# 5500392869: TOTAL (Excluding VAT)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Yanpet MM21-U/O K-7701 Compressor O/H RFQ No# 5500392869

ITEM TASK M.P/QTY UNITS / DAYS U. RATE T. COST


1 - WEL Rotor Balancing
1 Offsite rotor balancing 1 1 - 10000
2 - -
3 - - -
SUB TOTAL # 1 10,000.0
2 - ENG TOOLS + ADDITIONNAL TOOLS
1 TOOLS 2 8 0 10,000.0
2 Hytorque - 0 0 -
3 Air Compressor 1 0 0 -
4 Diesel Generator 1 0 0 -
SUB TOTAL # 2 10,000.0
3 - MTR MATERIAL & CONSUMMABLE
1 Transportation Fare - - 0.0
2 Spear parts - - 0.0

3 Consummable (ruggs, Hands gloves, WD40, 1 1,500.0 1,500.0


cleaner….)
SUB TOTAL # 3 1,500.0
4- CRN Facilities on site
1 Container house for TA 0 - -
2 Container house for Worker 1 0 600.0 -
workers (refer to Caqluse 2.3.3)
3 40 ft Container for spare parts 0 500.0 -
4 Container house for Toilet 1 27 550.0 -
Disposal of waste
5 1 27 500.0 -
(refer to Clause 2.4.8)
SUB TOTAL # 4 0.0
5 -TRP TRANSPORTATION
1 TRICYCLE 0
2 Car 0 1 0.0 0.0
3 BUS 1 1 0.0 0.0
4 TRUCK FOR MOB & DEMOB
5 MATERIAL TRANSPORTATION
SUB TOTAL # 5 0.0
6- MP MANPOWER
1 ManPower 11 6 29,970.0
2 PPE 11 6 125.0 1,000.0
3 Accomodation 11 6 75.0 4,950.0
4 Water + Coffee 11 6 10.0 660.0
SUB TOTAL # 6 36,580.0
6- CRN EXTERNAL SERVICES
Crane TUV certified 50 Tons 50 1 45,000.0
1

Tower Sacffolding (cu.m) 1,444 40 51,020.0


2
3 Suspended Scaffolding (sq.m) 217 40 16,470.0

4 Insolation
SUB TOTAL # 6 0.0

SUB-TOTAL 58,080.0
CONTENGENCY (not be less than 5% for Projects less than SR1M and min 3% for >SR1M) 1,742.4
Overhead Cost (not be less than 5% for Projects less than SR1M and min 3% for >SR1M) 1,742.4
Benefits (25%) 11,616.0
TOTAL (Excluding VAT) 73,180.8
MAN POWER BREAKDOWN PRICES
QUOTATION
Number of Days 12
Sharq TA
HOURLY
Category Items Nb RATE
OT H. RATE TOTAL N.H T. OT Total Cost
Supervisor 1 60 90 96 44.0 9,720.0
Foreman 0 45 67.5 0 - 0.0
Mechanical Fitter 2 25 37.5 192 88.0 8,100.0
Tig Welder 0 30 45 0 - 0.0
Electrical Technician 0 25 37.5 0 - 0.0
Instrument Technician 1 25 37.5 96 44.0 4,050.0
Helper 2 25 37.5 192 88.0 8,100.0
12 working days Tools keeper 0 25 37.5 0 - 0.0
Safety Officer 0 40 60 0 - 0.0
QA/QC 0 45 67.5 0 - 0.0
Work Permit Receiver 0 40 60 0 - 0.0
Fire watch 0 25 37.5 0 - 0.0
Drivers 0 25 37.5 0 - 0.0
Admin / Logistics / Purshase 0 25 37.5 0 - 0.0
total man power 6 Sub-total 1 29,970.0
Sharq TA
HOURLY
Category Items Nb RATE
OT H. RATE TOTAL N.H T. OT Total Cost
Supervisor 1 60 90 0 - 0.0
Foreman 0 45 67.5 0 - 0.0
Mechanical Fitter 2 25 37.5 0 - 0.0
Tig Welder 0 30 45 0 - 0.0
Electrical Technician 0 25 37.5 0 - 0.0
Fabricator 0 25 37.5 0 - 0.0
Helper 2 25 37.5 0 - 0.0
Mob/Demob
3 Days Tools keeper 0 25 37.5 0 - 0.0
Safety Officer 0 40 60 0 - 0.0
QA/QC 0 45 67.5 0 - 0.0
Work Permit Receiver 0 40 60 0 - 0.0
Fire watch 0 25 37.5 0 - 0.0
Drivers 1 25 37.5 0 - 0.0
Admin / Logistics / Purshase 0 25 37.5 0 - 0.0
total man power 6 Sub-total 1 0.0
Sharq TA
3 Days 29,970.0