Professional Documents
Culture Documents
Power Plant Fire Fighting Design Philosophy
Power Plant Fire Fighting Design Philosophy
1. GENERAL
2. APPLICABLE STANDARDS
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
1. GENERAL
The purpose of the present document is to specify the design philosophy for
all the Fire Fighting Systems required for the protection of the areas,
equipment and facilities of the Power Plant…
2. APPLICABLE STANDARDS
The Fire Fighting Systems are generally designed and shall be installed in
accordance with the latest edition of the following standards with order of
priority as set below:
a) Factory Mutual, FM
b) Underwriter's Laboratory, UL.
c) Verband der Sachversicherer, VdS.
3.1 General
Page 2 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
(*) the numbers inside the parenthesis denote that the operating
temperature is greater than the flash point (1) or less (2).
Page 3 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 4 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 5 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
The fire fighting system of the Plant shall operate on sea water
coming from the sea water intake structure. The fire fighting
network will be always under pressure and filled with desalinated
water from the service tank to avoid excessive corrosion.
4.1.2 Foam
4.1.3 CO2
They are accounted as minor fire fighting agents and are applied
through portable extinguishers as a back up to the main fire
fighting agents (water, foam, CO2).
Page 6 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
4.2.1.1 Tanks
a. Foam
b. Cooling water
Page 7 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
c. Tanks spacing
Page 8 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
4.2.1.4 Transformers
Page 9 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
a. Foam
b. Water
c. Dry chemicals
4.2.1.6 Buildings
Page 10 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
- Parking area
- Service bus stop area
- Roads and pavements
- Outdoor storage area
- Service vehicles shed
Page 11 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 12 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Desalinated water from the two Distilled Water Storage Tanks with
a capacity of 1500 m3 each, is used in order to keep the fire
fighting network under pressure. It is also required for the
transformers water spray system supply, because seawater is not
applicable due to high conductivity.
In case of fire or test, the main fire fighting pumps (first the
electrical and afterwards the diesel driven) will start automatically
with pressure drop sensor at the distribution network, driving sea
water to the network.
The main fire fighting pumps shall alternatively start from the
control board of fire fighting system located at the CCR of the
station and from the local electrical board of the pumps.
The fire fighting pumps shall be stopped only manually from the
local control electric board of the pumps.
Page 13 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Fire water is provided to all the fire fighting systems needing water,
that is the outdoor hydrants, the indoor hose stations, the water
spray systems and the tanks cooling water systems described
here bellow and the foam water fixed systems described in
paragraph 4.3.4.
All means are provided (pipes, valves, drains) for flushing of all
the parts of the network system with desalinated water after use
or test.
The main fire water piping is DN280 (for the main rings
carrying the maximum flow rate) and DN200 (for all the
other rings) in diameter while the branches to individual
hydrants are DN160. Branches to individual stand pipe
systems are DN100.
Page 14 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
a. Outdoor hydrants
Page 15 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
b. Hose Cabinets
Page 16 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 17 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 18 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 19 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 20 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
- One (1) for the protection of the Heavy Fuel Oil and
Diesel Fuel Oil Storage tanks, the Oily Sludge Tank
and their safety basins and the fuel pumpstation
located at the fire fighting pumping station (building
nr.37).
Page 21 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
- Foam compound
- Foam compound storage tank
- Automatic pressure differential foam proportioner
- Two (2) foam compound pumps (one electrically
and one diesel driven) or one (1) water driven foam
pump alternatively.
- All interconnecting piping, valves and instrument,
between the above mentioned equipment.
a. Foam Compound
Page 22 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 23 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 24 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
One (1) foam top pourer set is installed for each tank of
the Plant, except from the 22500m3 HFO storage
tanks, where four (4) top pourer sets are required per
tank.
Page 25 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
a. Foam Generator
b. Foam Chamber
c. Foam Deflector
Page 26 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 27 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 28 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
All electrical rooms of the buildings and the Machine Hall and
Annexes, including battery rooms, switchgear rooms, electronic
controller rooms, cubicle rooms are equipped with a CO2 total
flooding system (according to Project Specifications B.1.H.4.5).
Page 29 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 30 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 31 of 32
CONTRACTOR: PROJECT:
DATE :
OWNER:
FIRE FIGHTING
REV. :
DESIGN PHILOSOPHY
Page 32 of 32