Professional Documents
Culture Documents
C.Booth - N0839602 - DESN40117
C.Booth - N0839602 - DESN40117
Design Aspects of
Suspension Bridges
DESN40117
CONTENTS
1.1 Origins................................................................2
1.2 New Materials ...................................................2
1.3 Evolution of the Modern Day Suspension .........3
1.4 20th Century Bridge Construction .....................4
2. Types of Suspension Bridges ...................................... 6
Appendix ....................................................................... 19
1. Suspension Bridges – 2
Overview
A suspension bridge is a type of bridge where a composite deck is supported by two main
suspension cables. The principal structural elements of a suspension bridge include, vertical
suspenders, stiffening girders, suspension cables, towers, and anchorages. The main cables are
typically suspended between two towers and are connected to anchorages buried in the ground at
the ends. Vertical rods transfer the self-weight of the deck and the variable traffic loads to the
cables. The tensile load of the cables is then transferred into the towers and anchorages. The main
cables, are considered the primary load carriers, made of high-strength steel, their whole cross-
section is a highly efficient load bearing member lowering the chance of buckling. Thus, allowing
the overall weight of the bridge structure to greatly reduce and hence allowing for longer spans.
Modern day suspension bridges are used to carry road and/or rail traffic as well as pedestrians, the
more advanced versions can carry all three (Lin&Yoda 2017).
1.1 Origins
Using suspended natural fibres as a support to navigate a natural feature originated in ancient
times, examples of them had been discovered around the same time in Central and South America
and the Far East. The design of the modern-day suspension bridge has its origins in an age-old
bridge design, where three vines arranged in a triangle (two as handrails, one as the deck) with
vertical lengths tied at intervals between the upper and lower vines were used as a form of bridge
crossing by ancient civilizations. This primitive suspension bridge design has been in use for
centuries by indigenous peoples, who could build crossings from natural materials even though
they had little exposure to modern civilization. However, to
call this design primitive is a disservice when one considers
that, despite the limited and basic nature of the resources
and tools available, it was still possible to build such an
advanced structure. A disadvantage was that the natural
materials deteriorated over time. This type of suspension
bridge did not exist in the Western world until 1515, built
Figure 1 Primitive suspension
bridge. (Metcalfe 1970)
over the Padus River by the German and Swiss military (Chen
& Duan, 2000).
1.2 New Materials
The earliest record of an iron suspension bridge
being used in the UK was the Winch Bridge (Fig.2),
built in 1741 over the river Tees in Teesside. The
bridge was suspended on iron chains, stretched
from rock to rock over a gorge 18m deep, it was
21m long and 60cm wide. A handrail was on one
Figure 2 The Winch Bridge in Britain (Kawada
side and the deck was planked in such a manner Et Al, 2014)
that the pedestrian experienced all the vibrations of
the chain whilst being suspended over a rapid river.
The structure is a primitive design using advanced materials, but the key characteristics and design
remained the same, requiring the traveller to walk along the cable which also served as the deck,
the only difference was that the cables were made of iron. The design may have been primitive,
1. Suspension Bridges – 3
Overview
but the suspension bridge was in use for 60 years, demonstrating the clear superiority of iron as a
raw material when compared to plant fibres. It was clear, using iron chains greatly extended the
service life of suspension bridges, yet the Winch Bridge was not the structural equivalent of a
modern suspension bridge, primarily because the cable itself constituted the deck.
Whether iron chains or plant fibres, provided that the cables formed the deck and pedestrians
walked directly on them along their curve, it remains a primitive suspension bridge. Before the
suspension bridge could support vehicles, two critical inherent design problems must be
addressed. First, the deck should not follow the catenary of the main cables but instead should
form a flat deck or roadway. Secondly, to avoid excessive lateral excitation from traffic movement,
a degree of stiffness was essential (Kawada Et Al, 2014).
Overview
But it was the USA where the largest progress in suspension bridge design was made, by mid 1800s
a key figure in bridge design, John Roebling, had overseen the construction of the Wheeling bridge
which at the time was the longest span in the world (308m span) until 1851 and later collapsed.
Roebling was also heavily involved with the 250m span Niagra Bridge completed 1855, 322m span
Cincinatti-Covington bridge completed 1866 and 486m span Brooklyn Bridge completed in 1883. It
was during the construction of the Niagra Bridge that Roebling invented a revolutionary technique
for manufacturing the two main cables. It is called the Aerial spinning method and is still the
preferred method of construction to this day (Ryall, Et Al, 2000).
Remaining in service for almost 100 years the Strait in Japan and is the world’s longest
Grand Pont Suspendu (Sarine valley, bridge span, measuring 1,991m and boasting
Switzerland) was the first example of a major six lanes of traffic It took 10 years to complete
suspension bridge supported by wire cables. this stiffened truss suspension bridge and
Completed in 1834 it became the longest span critical to its design is its ability to withstand
in the world (273m), exceeding the Menai 290km/h wind speeds and 8.5 magnitude
Bridge’s record at the time. earthquakes. Shown in pink in Fig. 5 below,
Of course, engineering design never stands still illustrated is the magnitude of this enormous
and the desire to design and build ever longer structure in comparison to other structures.
spans was the driving force behind some of the In three years’ time, however, this record will
world’s super structures. Advances in be surpassed by the Çanakkale 1915 Bridge in
engineering and material science have made North Western Turkey featuring a tower to
this possible. The Akashi-Kaikyo Bridge (Fig tower span of 2023m due to be completed in
1.4), completed in 1998, spans the Akashi. the year 2023 (Hürriyet Daily News 2017).
1. Suspension Bridges – 5
Overview
Closer to home is the Humber Bridge (Fig. 6), Each tower rises 155.5m high above the piers
spanning the Humber Estuary near Hull, with two side spans in addition to the main
holding the record for the world’s longest span. Its main purpose was to cut journey
bridge until 1997, it is now only the ninth times, the round trip between Grimsby and
longest in the world. The central span is Hull was 50 miles and took over an hour,
1,410m, with a total length of 2,220m. It severe congestion on single carriageway roads
comprises two dual carriageways for road made the trip even longer. In the construction
traffic as well as footpaths and cycleways and of the concrete towers and installation of
is designed for a lifespan of 120 years. main cables, a combination of saddle offset
Approximately 480,000 tonnes of concrete and pull back of the tower was the selected
and 27,500 tonnes steel were used in its option.
construction and the two main cables of the Both these feats of engineering excellence, as
bridge carry a combined load of 19,400 advanced as they are, clearly have their origins
tonnes. The deck of the Humber Bridge is in the primitive, early bridge designs used
formed of the streamlined box girder concept. hundreds of years ago by ancient civilizations
Interestingly one tower is positioned in the (Chen & Duan, 2000).
Humber and the other on land meaning
different design concepts were required for
consideration.
2. Types of Suspension 6
Bridges
There are numerous ways in which suspension bridges can be classified, these include the
construction technique, number of spans, cable anchorage method, stiffening girder supports and
hanger orientation.
Bridges
Specifications
In this next section a comprehensive review, design and analysis of a three span, externally
anchored suspension bridge will be performed. Figure 12 below illustrates the key structural
elements of a typical suspension bridge. The quality of a bridge may be measured by its success in
satisfying the basic objectives implicit in bridge design. These are functionality, structural integrity,
economic and aesthetically pleasing. As Engineers the primary concern is for the structural
sufficiency of the bridge. However besides continuing to stand, the bridge must also avoid
performance issues which reduce its efficiency or increase maintenance costs. Prior to a full-scale
model like Fig. 12 being produced, the design team must first establish the overall composition of
the bridge (O'Connor, 1971). The most significant of these decisions being:
• Main span length – usually the first decision made and as the preferable structure for long
spans, most suspension bridges are used to provide a crossing over a navigable waterway.
• Sag-to-span ratio of the main cable span – typically dictated by the span length, tower
foundations and clearance requirements, the sag/span ration will almost certainly lie
between one-eighth to one-twelfth of the span length.
• Main span length to side span length ratio – primarily governed by most economical
position to construct the cable anchors, but also must not be greater than 50% of the span
length due to the effects on the vertical stiffness of the main bridge span. (Ryall, Et Al, 2000)
Further to the design decisions above the designer must also specify:
• Side span supports (cable or towers)
• Variety of deck structure (open truss stiffening girder, plate girder, box girder)
• Necessary clearance below
the deck structure
Design Codes
structural design and detailing, EN 1997 for geotechnical aspects and EN 1998 for design against
earthquakes. The main Eurocode parts used for the design of concrete, steel and composite
bridges are given in Table II. These codes are calibrated to achieve a uniform level of structural
safety for ordinary loading situations (i.e. self-weight). Thus, probabilistic methods can
subsequently be used to calibrate the safety factors for loads and/or design situations that are not
covered by these codes of practice (Poljansek Et Al, 2012).
Architecturally the towers also provide the opportunity to offer the Figure 13 Tower Types,
Left top down (Truss, Portal, Combined)
client with a structure that satisfies the aesthetical criteria in the brief. Right top down (Rigid, Flexible, Rocker)
It was Roebling, when presenting his Brookylyn bridge proposal in
1867, who once said “the great towers will be ranked as national monuments. As a great work of
art and a successful specimen of advance bridge engineering” (Billington, 1983).
10
3. Structural Components
Specifications
Cost is the leading factor when specifying the material for the towers, reinforced concrete
materials must be compared to fabricated steel. As the towers are loaded in compression, concrete
is the obvious choice. However due to the excessive self-weight a concrete tower will create an
uneconomical foundation may be required when compared with a steel tower of similar
proportions (Ryall, Et Al, 2000).
3.2 Cables
For modern long-span suspension bridges, cold drawn and galvanized steel wires are generally
used, the first example of this was in the construction of the Brooklyn Bridge in 1883. Strands are
wound into a circular shape to form one main cable from which the suspender cables are attached.
This type has been used in almost all modern long-span suspension bridges. Suspender cables
attaching the deck to the main cable and can be steel rods, bars or wire ropes (Chen & Duan, 2000).
The cables, towers, and anchorages are the primary load carrying system of the bridge with the
cable profile in each span creating an equilibrium polygon for the loading of that span. Main cables
are primarily subject to axial tensile stress, although there are some bending and compression
stresses, mainly from the tower, splay saddles, the cable clamps and the anchorages. Until
relatively recently the generally adopted design philosophy for main cable design was based on a
working stress approach in which the maximum stress derived from the most adverse combination
of the specified nominal design loadings was
compared with an allowable stress derived by
applying a single safety factor to the ultimate
tensile strength of the cable wire, as unlike
weldable structural steels, high strength wire
does not have a clearly defined yield point.
Figure 15 Suspension Bridge Load Distribution
11
3. Structural Components
Specifications
To ascertain the maximum allowable tensile stress in the main cables a working stress design
philosophy should be adopted, this is project specific however in practice has been taken as 40-
45% of the minimum guaranteed ultimate tensile stress of the cables. The reason for this method is
because national bridge design codes do not specify allowable stresses for parallel cables due to
the relative infrequency of suspension bridge designs when compared with non-cable supported
bridges. A more rational approach to finding the structural design safety margins is to apply limit
state design principles, this requires comparisons between what has been previously been
accepted in practice with the overall safety margin obtained by combining the strength
determination (γm) and loading (γF) partial factors to be made. The predominant loading for long-
span suspension bridges is the dead load of the cables and deck structure which can represent
between 80 and 90% of the total loading, and as a result the effective partial factor γF on the total
loading is quite low (approximately) 1.1–1.2). This requires the m factors to be applied to the
determination of cable tensile strength should be of the order 1.8 on ultimate tensile strength or
1.4 on the 0.2% proof strength of the cable (Ryall, Et Al, 2000).
Predominantly there are three main varieties of strand used in suspension bridge design, these are:
• Spiral Bridge strands - manufactured by the helical winding of multiple layers of round steel
wires onto a straight centre core wire. The helical twist of the wires results in a decrease of
around 15–25% in the stiffness of the strand relative to that of plain straight wires and
reduces the strand strength to around 90%.
• Locked coil strand - produced by the helical winding of multiple layers of round steel wires
onto a straight centre core wire. They differ from spiral bridge strands in that the final
layers of wires are made up of interlocking Z-shaped wires, giving a larger proportion of
wire area to strand area and, more importantly, a smooth easily protected exterior surface.
Their stiffness and other characteristics are generally like those of spiral strands.
• Parallel wire cables - Parallel wire cables are the most widely used type of cable, and consist
of the required number of individual wires, laid straight and parallel throughout the
complete cable length from anchorage to anchorage and compacted together into a single
mass of parallel wires contained within a circular profile. Parallel wire cables are
constructed by either aerial in situ spinning of the wires, or by the assembly of a number of
prefabricated parallel wire strands. (Parke&Hewson, 2008).
The basic element for all cables is high-strength steel wire which, for parallel wire cables, will have
a wire diameter of between 5 and 5.5 mm. Wire of this size is generally produced
with a tensile strength of 1570 N/mm2, and a 0.2% proof stress of around 1200 N/mm2, but higher-
strength wire with a minimum tensile strength of 1800 N/mm2 is now produced, and has been used
for the cables of the Akashi Kaikyo Bridge. The wire is produced from steel rods with a much higher
carbon content than weldable structural steels, and its high tensile strength is obtained by cold
drawing through a series of dies to reduce its diameter from the initial rod size down to the final
wire size, producing wire with consistently accurate dimensions, and a smooth flaw free surface.
The production of high-strength wire by this method does however have the disadvantage that the
resultant wire has low ductility, with the elongation at fracture being typically only about 4%
(Parke&Hewson, 2008).
The main cables are the primary structural elements of the bridge
and, although limited local replacement of corroded outer wires
has been carried out on some earlier bridges, the complete in-
service replacement of a large diameter compacted parallel wire
cable would be an extremely difficult and expensive operation that
has thus far never been carried out. It is therefore essential to
provide the main cables with corrosion protection which, with Figure 17 Golden Gate
Bridge Cable Cross Section
reasonable care and maintenance, will ensure that the cables will
have a service life equal to the design life of the bridge. Traditionally, parallel wire cables have been
protected against corrosion by a three-stage process, with the primary protection being the
galvanised zinc coating on the wires, combined with coating the exterior surface of the cable by a
red lead and linseed oil paste contained by circumferential wrapping with tightly spaced low-
strength galvanised steel wire to prevent, as far as possible, water ingress into the cable, and a final
series of coats of paint applied over the wrapping wire. As the use of lead-based products is no
longer environmentally acceptable, wrapping pastes based on metallic zinc powder have been
employed on recently constructed bridges such as the Hoga Kusten and Storebaelt (Ryall, Et Al, 2000).
Whether comprised of a single small-diameter wire, or an assembly of such wires laid parallel or
wound in a helical formation, all cables have a very low resistance to bending moments and shear
forces, and have a negligible capacity to resist compressive buckling forces.
For most practical calculations, the bending stiffness of such cables can be neglected, and the cable
treated as being a perfectly flexible tensile member incapable of resisting bending moments and
axial compressive forces. Clearly in the absence of any bending and shear capacity, the only way in
which such a cable can resist vertical (e.g. gravitational) loading is by adopting a shape in which at
all points the vertical component of the net tensile force is in equilibrium with the applied vertical
loading. To achieve this equilibrium, angular changes must occur at each point where vertical load
is applied, and these result in the familiar vertical curvature of suspended cables.
13
3. Structural Components –
Review, Design
In order for a suspended cable to sustain any transverse loading, its ends must be secured against
horizontal movement, and a horizontal reacting force is thus generated at these ends. In all cases
where the cable is subjected only to vertical (i.e. gravitational) forces, with no horizontally applied
loads, these horizontal end reactions must necessarily be equal, and it follows that the horizontal
component of the cable tension must therefore be the same at all points along its length.
(Parke&Hewson, 2008).
3.3 Anchorages
The anchorages secure the ends of the main cables and transfer their force into the ground. The
direction of the cable forces is determined by the side span geometry, but is predominantly
horizontal with a smaller upward component. The requirement for the anchorages to resist a large,
predominantly horizontal force makes their design difficult unless reasonably good ground
conditions (preferably sound rock) exist where they are positioned (Parke&Hewson, 2008). Anchors
are crucial components in suspension bridge design and construction, bearing most of the weight
and load from the bridge which is transferred via the cables to the anchorage system. Anchorage
structures generally include the foundation, anchor block, bent block, cable anchor frames and a
protective housing. The cables inside the anchorage are spread over a large area to evenly
distribute the load and to prevent them breaking free or suffering damage caused by the
concentrated cable forces. The anchorage blocks are usually made out of concrete and weigh
more than the total weight of the cables holding up the deck. They have to bear a huge proportion
of the weight of the roadway and must be strong enough to withstand loads from road traffic
crossing the bridge. There are two common anchorage choices, gravity or tunnel. Gravity
anchorage, Fig 17, uses huge concrete blocks, the mass of the block counters the tension of the
main cables, the majority of suspension bridges use this form of anchorage system. Tunnel
anchorage, Fig 17 transfers the forces from the main cables directly into the ground, it’s therefore
crucial to ensure a full geotechnical survey is carried out to establish that the right geological
conditions are present before this anchorage system can be used (Chen & Duan, 2000).
This stiffness requirement is effectively related to the hanger spacing and as this is a small
proportion of the span length, the contribution of the deck bending stiffness to the overall vertical
stiffness of the structure is generally insignificant, with that of the cable system dominating. This is
not however the case for torsion where the torsional stiffness of the deck can make a significant
contribution to the overall structure stiffness, with consequent increase in the torsional natural
frequency and improvement in aero- dynamic properties. A high torsional stiffness is therefore an
important requirement of the deck structure.
It is a characteristic of all bridges that the contribution of dead load to total bridge loading rapidly
increases with increase in span length, and for suspension bridges this effect is illustrated in Figure
17 showing, for a single span with a given allowable cable stress and span/sag ratio, the rapid
increase in the ratio of cable weight to suspended deck weight as span length is increased. An
efficient design therefore requires a suspended structure with the minimum self-weight consistent
with the achievement of other design requirements, and structural steel is therefore invariably
used for the deck and stiffening girder. An important contribution to the minimisation of dead load
is the use of an orthotropically stiffened steel deck plate, combined with the thinnest surfacing
layer that will provide an adequate deck fatigue life. Any reduction in deck weight also produces
savings in the other elements of the cable system (hangers, towers and anchorages), with the
benefit becoming increasingly significant as the span length increases. The options for the
suspended deck stiffening girder structure are:
The suspender cables or hanger ropes connect the decking to the steel cables and help shape the
bridge. The suspender cables prevent the roadway from swaying out of control and help to
reinforce the decking. They can be steel rods, steel bars, stranded wire ropes or parallel wire
strands. Stranded wire rope is most common in modern suspension bridges. Stranded wire rope is
most common in modern suspension bridges. The Akashi Kaikyo Bridge and the Kurushima Kaikyo
Bridge, use parallel wire strands covered with polyethylene tubing as a barrier to corrosion (Chen &
Duan, 2000).
At the towers, each main cable must be supported by a saddle consisting of a longitudinally curved
trough to deflect the cable through the required angle and which is supported on a grid of
longitudinal stiffeners and radial ribs to transmit and diffuse the cable load into the supporting
tower structure (Parke&Hewson, 2008). These saddles support forces from the cable pulling
downwards in to the tower, the saddle itself can move forwards and backwards via rollers or a
rocker. This is to allow for expansion and contraction of the steel.
At the anchorages a splay saddle separates the cable into its individual strands, deviating them
both laterally and vertically to their individual connection points within the anchorage. In order that
strands can be placed layer by layer during cable construction, without the need for tem- porary
restraint, all strands should be deviated downwards relative to the cable centreline at the lower
end of the side span, to produce an overall downwards deflection of the cable centreline
(Parke&Hewson, 2008).
16
4. Analysis Methods
The difference between the two theories is whether cable deflection resulting from live load is
considered. The bending moment, M(x), of the stiffening girder after loading the live load is shown
as follows:
Elastic Theory:
𝑀(𝑥) = 𝑀0 (𝑥) – 𝐻𝑝 𝑦(𝑥)
Deflection Theory:
Where:
𝑀0 (𝑥) - bending moment resulting from the live load applied to a simple beam of the same span
length as the stiffening girder
𝑦(𝑥) - longitudinal position of the cable
𝜂(𝑥) - deflection of the cable and the stiffening girder due to live load
𝐻𝑤 , 𝐻𝑝 - cable horizontal tension due to dead load and live load, respectively
Billington, D. (1983). The tower and the bridge. New York: Basic Books.
Chen, W. and Duan, L. (2000). Bridge engineering handbook. Boca Raton [etc.]: CRC Press.
Hürriyet Daily News. (2017). Groundbreaking ceremony for bridge over Dardanelles to take place on
March 18 - Latest News. [online] Available at:
https://www.hurriyetdailynews.com/groundbreaking-ceremony-for-bridge-over-dardanelles-to-
take-place-on-march-18-110948 [Accessed 11 Feb. 2020].
Kawada, T., Scott, R. and Ohashi, H. (2014). History of the Modern Suspension Bridge. Reston:
American Society of Civil Engineers.
Lin, W. & Yoda, T. (2017). Bridge engineering: Classifications, design loading, and analysis methods.
Metcalfe, L. (1970), Nuffield Resources for Learning Project. Bridges and bridge building. London:
Blandford Press.
Poljansek, M., Tsionis, G. and Pinto, A. (2012). Bridge design to Eurocodes. Luxembourg:
Publications Office.
Schlaich, J., 2004. Buchbesprechung: Bridge Engineering— A Global Perspective von L. F. Troyano.
Beton- und Stahlbetonbau, 99(7), pp.623–624. 10.1002/best.200490153.
Seward, D. (2009). Understanding structures. Basingstoke: Palgrave Macmillan.
Tom F. Peters (1987-01-01). Transitions in Engineering: Guillaume Henri Dufour and the Early 19th
Century Cable Suspension Bridges. Birkhauser. p. 260. ISBN 3-7643-1929-1.
18
References
Figure Credits
Bridge Loading
Cables
For corrosion protection, the wire is galvanised after final drawing, the weight of zinc coating being
typically 300 g/m2, and for storage and delivery, the final wire product is formed into coils of 250–
1200 kg, with an internal diameter of about 1500 mm, which is sufficient to ensure that, when
uncoiled, the wire is sufficiently straight for subsequent cable spinning or strand manufacturing
operations. As the construction of large suspension bridges occurs relatively infrequently, wire for
the construction of parallel wire cables is produced specifically for each project. Longspan bridges
require very large quantities of wire, and an extended production period before the
commencement of cable work at site is generally required, leading to the need for temporary
storage of large quantities of wire coils in a controlled environment to prevent corrosion damage
20
Appendix
Design Procedure
A general design procedure for a suspension bridge superstructure is shown in Figure b. Most
rational structure for a particular site is selected from the result of preliminary design over various
alternatives. Then final detailed design proceeds.
Performance Failures
Bridges are important assets. Their main function is to provide uninterrupted and save traffic
(transport and people) flow over man or nature made structures/obstacle. To ensure that existing
bridges are safe for use and fit for purpose regular condition assessments in a form of inspections
are practiced. The inspection regime consists of multiple inspections – general, principal and
special inspections. General inspections are carried out no longer than two years after the previous
general or principal inspection. General inspections are mainly based on evaluation of data
collected using visual observations.
Several early suspension bridges were designed without the appreciation of wind effects. Large
deflections were developed in the flexible decks and wind loading created unstable oscillations. The
problem was largely solved by using inclined hangers. The suspension bridge is essentially a
catenary cable prestressed by dead weight. The cables are guided over the support towers to
ground anchors. The stiffened deck is supported mainly by vertical or inclined hangers.
competition to design and build a bridge across the Thames, the first in 100 years. Designed by Sir
Norman Foster, the Millennium Bridge was described as an innovative "blade of light".
The bridge opened on 10 June 2000 and the interest generated by the bridge on opening day
surpassed expectations, up to 100,000 people crossed the bridge on the opening day, with as many
as 2000 people on the bridge at any one time. Shortly after the opening, visitors reported that the
bridge began to sway from side to side. It appeared that this lateral movement occurred when a
large number of pedestrians were on the bridge. The movement was not continuous and died
down if the number of people on the bridge reduced or stopped walking and further reduced by
the fact that beyond a certain level, many of the pedestrians started to experience difficulty in
walking, holding the balustrades for support. The bridge was closed two days later on 12 June
2000.
Following closure, investigations were undertaken to determine the cause of the large amplitude
vibrations. It was discovered that the Millennium Bridge movement was caused by sideways
pedestrian loads i.e. walking. As the pedestrians’ steps caused slight sideways movements of the
bridge, it became more comfortable for the pedestrians to walk in synchronisation with the
movement of the bridge, instinctively they synchronized their pace with the motion of the bridge,
this in turn amplified the movement. This continued to the point beyond which pedestrians could
no longer keep their balance and had to stop walking and hold the handrail and the lateral
movement subsided. This phenomenon is known as ‘synchronous lateral excitation’ (SLE) and had
been seen before with the Toda Park Bridge in Japan which exhibited similar vibrations. Analysis of
video footage revealed that the head motion of approximately 20% of the pedestrians was
synchronous with the motion of the bridge.
Tests conducted in the laboratory and on site identified it was possible to calculate the number of
pedestrians that will cause excessive sideways movement. They discovered a similar effect can
occur on any type of bridge with a lateral frequency of less than 1.3 Hz, the normal walking pace of
pedestrians. A critical number of pedestrians is required to create the phenomenon, directly
related to the mass of the bridge, its frequency and its damping. The test results confirmed the
observed behaviour of the bridge on opening day and made two key discoveries;
22
Appendix
i) there is no lower limit to the frequencies that could be affected by SLE but there was an upper
limit of 1.3Hz;
ii) pedestrians act as ‘negative dampers’ and when they reach a critical number they reduce the
inherent structural damping of the bridge to zero, causing lateral motion.
Stabilising the London Millennium Bridge; Tony Fitzpatrick FREng and Roger Ridsdill Smith; Ingenia
Online