Professional Documents
Culture Documents
Table 4.2.2 Typical Sludge Production For Mechanized Plant
Table 4.2.2 Typical Sludge Production For Mechanized Plant
Table 4.2.2 Typical Sludge Production For Mechanized Plant
4-6
The Study on Improvement of Planning Capability in Sewerage Sector in Malaysia Final Report
Onsite Strategy
Centralized Strategy
By introducing revenue and by estimating the O&M costs properly, the option of a larger
STP may have a greater chance of selection as a priority project. Due to the STP’s
centralized and rationalised operations, there is a high probability that tariff revenue will
increase in direct proportion to the capacity of the STP.
While O&M costs may also increase as STP capacity increases, they do so at a lower rate.
These two approaches contribute to minimizing net loss over the lifecycle of the sewerage
project.
4-7
The Study on Improvement of Planning Capability in Sewerage Sector in Malaysia Final Report
Table 4.2.3 shows a comparison of two evaluation methods (with two option): the current
financial analysis approach and the new method, which introduces revenue. In Option A,
the developer plans to construct an STP in the catchment area; but in Option B, the plan is
to connect to an existing STP outside the area (Figure 4.2.5). Under the present financial
analysis, O&M costs are a percentage of capital costs. As a result, Option A, which has a
smaller NPV, is selected as the priority project. Under the new financial analysis, the
O&M costs of option B are lower than those of option A because it utilizes the existing STP.
Revenue is the same for both options as they serve the same PE. However, option B,
which has a larger NPV, is selected as priority project. This new financial analysis method
is anticipated to contribute to the rationalisation of existing sewerage systems.
Option A Option B
STP
Figure 4.2.5 Options A and B for Comparison of Current and New Financial Analysis
Approaches
In order to include revenue when performing financial analysis of the options, standardized
unit tariff revenues are calculated and are described in the Guidelines as follows:
Figure 4.2.6 shows the average tariff revenue per PE unit based on the billed amount data
for all types of customer and the total Population Equivalent for the period May 2001 to
December 2007. This figure is presented in the Guidelines to calculate the tariff revenues
of the options. Collection efficiency must also be considered to calculate revenue, since it
is based on billed amounts.
Estimates of revenue and expenditures are put into the Revenue and Expenditure Stream in
Table 4.2.4. The NPV of the difference between revenues and expenditures of each year is
4-8