Professional Documents
Culture Documents
Roadway Strata Management
Roadway Strata Management
Roadway Strata Management
Strata management is a critical and now necessary requirement in Recent developments in strata management can be summarised as
the New South Wales underground coal mining industry. follows:
As a formal and structured process, strata management allows (i) Strata Failure Management Plans
ground support and mining methods to be tailored to the anticipated
and encountered geotechnical environment in a controlled manner. As a minimum standard, the legislation stipulates that a Strata
Failure Management Plan must consider each of the following:
In its application, strata management therefore enables operators to
identify and control geotechnical hazards and the risks they pose to (a) The estimation of geological conditions likely to be
the mining operation, including risks to personnel safety and mine encountered during roadway development.
production. (b) The assessment of roadway stability.
(c) The recording of geological conditions that may affect
The paper considers recent developments in strata management in roadway stability.
the New South Wales underground coal mining industry. Points (d) The development of support measures that will provide
covered include the statutory requirements stipulated in the Coal roadway stability in the anticipated geological conditions.
Mine Health and Safety Regulations, Geotechnical Hazard Plans, (e) The monitoring of roadway stability.
tiered support plans, the Authority to Mine concept, Trigger Action (f) The training of operators in support design principles, the
Response Plans and monitoring. correct installation and removal of support, understanding the
need for and the importance of the various support systems in
Several successful and unsuccessful case studies are included use at the mine and the recognition of any changes that may
which make specific reference to roadway development and affect roadway stability.
longwall retreat and in doing so, the unique demands imposed by
these two different aspects of the mining operation on strata Although not specified in the legislation, other points that should be
management. incorporated in a Strata Failure Management Plan include;
operating standards (eg. for processing roof monitoring data, the
Introduction collection of geotechnical data, the installation of roof support etc.),
roles and responsibilities, and document control.
Strata management is a concept which aims to formalise the
decision making processes associated with ground support design. (ii) Geotechnical Hazard Plans
Used correctly, strata management allows ground support and
mining methods to be tailored to the anticipated and encountered Whilst Geotechnical Hazard Plans aim to capture a number of the
geotechnical environment in a controlled manner. points raised in the Coal Mine Health and Safety Regulations
namely, the estimation and recording of geological conditions that
In recent years strata management has become an integral part of may affect roadway stability, critical items to be addressed in a
coal mine safety and ground support design in New South Wales. Geotechnical Hazard Plan can be summarised as follows:
Recent changes to the Coal Mine Health and Safety Regulations
(2006) have further clarified the need for a formal strata a) Geological Structure
management process, critical to which is now the mandatory
requirement for all mines to have what is termed a “Strata Failure As a general comment, the following geological structures are of
Management Plan”. most relevance to roadway stability; reverse or thrust faults, mid-
angled structures (see Figure 1), almost any structure aligned at a
shallow (ie, <30o) angle to the roadway and any areas where two or
26th International Conference on Ground Control in Mining
more geological structures intersect.
100
90
Displacement (mm)
ribline 70
60
Total
50 0.5m
40 1.5m
2.4m
Roof block liable 30
4.0m
to slip 20
10
0
0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000
Figure 1 – Schematic Illustration of a Mid-angled Structure Elapsed Time (hours)
Driven Roof Fall
7 7 10
6 0
6
0 10 20 30 40 50 60 70 80 90 100
Surge related to
roadway development
Displacement (mm)
Elapsed Time
a) Simplicity
5 5
1 1
Figure 10 – Example of TARP used at Mine B
0
0 50 100 150 200 250 300
0
0 50 100 150 200 250 300
(iii) Successful – Mine C
Displacement (mm) Displacement (mm)
Mine C is located at an approximate depth of 350m and the roof is
Figure 9 – Roof Displacements Measured Before and After the characterised by a 4m thick unit of coal which is interbedded with
Installation of 4m Long Cables off the Continuous Miner in several bands of weak tuffaceous claystone.
Mine A
Previously in a highly disturbed geological zone, during roadway
(ii) Successful Case – Mine B development the roof often guttered immediately at the face up to
heights of 1 to 1.5m. This required PUR injection at the face, the
In Mine B, which mines with a 5 to 6m thick coal roof, a installation of 8m long cables off the continuous miner and where
significant deterioration in roof behaviour was experienced in and the cavities proved too high, the miner had to be moved out of the
around areas of high horizontal stress. roadway so that spiles could be installed into the face and the roof
bolts installed off hand-held drill rigs.
In areas the roof guttered and slabbed up to a height of 1.5m
immediately at the face. This in turn, slowed down the rate of As a result of these conditions, the mine decided to implement the
roadway development by view of the fact that the operators had to following initiatives, the overall aim of which was to tailor the
bar down the fractured roof material before the bolts could be installed support to the anticipated ground conditions and in effect,
installed and the continuous miner had to be stopped on a frequent limit the size of any gutters or cavities at the:
basis to enable the operators to install 8m long cables.
- Shield tilt rams were added to the continuous miner to allow
To help control the roof guttering and slabbing and so maximise the the roof bolts to be installed closer to the face.
rate of roadway development, two changes were made to the strata
management process at the mine. - Detachable self-drilling spiling rigs were added to the
continuous miner so that the roof could be pre-reinforced with
- The first change concerned the installation of 4m long cables 2.5m long bolts ahead of mining.
off the miner. Again, as per Mine A, the aim of the 4m cables
was to maximise beam retention in the immediate roof at the - In addition to the 2.1m long roof bolts, 4m and 8m long pre-
face of the development unit. tensioned and post-grouted cables were installed off the
continuous miner.
These were installed in addition to 6 x 2.4m long roof bolts
every 1m and in the context of the tiered support plans already - The use of a TARP based primarily on the height and width of
in use at the mine, were termed “Single Red” where 2 x 4m roof guttering.
long cables every 2m was required, “Double Red” where 2 x
4m long cables every 1m was required and “Triple Red” As a result of these changes, the height of roof guttering was
support where 4 x 4m long cables every 1m was required. The typically restricted to a maximum of 0.5m and where the roof did
other support plans in use at the mine include “Green” which drop out to greater heights at the face, the amount of time required
specified 6 x 2.4m long roof bolts every 1m and “Yellow” to install the spiles was reduced from seven to one 8 hr shift.
which specified 8 x 2.4m long roof bolts every 1m.
Overall, roof behaviour outbye of the face also improved (see
- The second change involved the introduction of a TARP Figure 11) and compared to previous structure zones, roadway
system which empowered the operators to assess for development rates improved by nearly 50%.
26th International Conference on Ground Control in Mining
100 Ultimately, the onset of buckling type behaviour exceeded the
90
reinforcing capability of the 4 x roof bolts per 1.5m pattern and the
80
roof fell up to the top of the tuffaceous sandstone. Critically from
Development Displacement (mm)
50
MG1 Points to note in relation to this incident include; a) the failure to
MG2
40
identify a significant change in the geological environment, namely
the neighbouring geological structure and its resulting impact on
30
joint frequency and cross-grade and b) the failure to identify the
20
geotechnical significance of the above, namely the associated
10 reduction and weakening of the coal beam and the increasing
0 significance of the stiff and therefore highly stressed tuffaceous
0 500 1000 1500 2000 2500 3000
Also importantly, at the time of the incident the mine did not have a
Figure 11 – Typical Example of the Measured Improvement in
Geotechnical Hazard Plan, an ATM or a TARP.
Roof Behaviour in Geologically Disturbed Ground in Mine C
(v) Unsuccessful Case – Mine E
(iv) Unsuccessful Case – Mine D
In the shallower areas of Mine E, where the depth of cover reduced
In Mine D the roof was characterised by a 2 to 2.5m thick coal unit
to around 130m, the roof typically retained static to low level
which in turn, was overlain by a reasonable competent and stiff
buckling behaviour during roadway development (see Figure 13).
tuffaceous sandstone.
As a result of these favourable conditions, all roadways and
During roadway development the roof was typically characterised
intersections in this area of the mine were supported with 4 x 2.1m
by static to low level buckling behaviour (ie, <10mm of
long roof bolts every 1m.
displacement) and was successfully supported with 4 x 1.8m long
roof bolts every 1.5m; effectively the thick coal roof maintained a
However, as a result of the increasing predominance of
significant amount of beam behaviour and was in itself viewed as
carbonaceous shale in the immediate roof, the CMRR reduced from
one of the main supporting members.
45 to 25 and a number of roof falls were experienced. Critically,
these falls occurred both at the face of the development unit during
However, in one area of the mine where a maingate panel was
the formation of intersections and several months after roadway
being driven next to a major fault / dyke zone, the jointing in the
development.
coal roof increased and the coal seam started to dip across the
roadway. The ensuing cross-grade meant that the operators could
As a result of the roof falls, a number of points were concluded in
not control the thickness of the coal beam and as a result, on the left
the succeeding investigation:
hand side of the roadway the thickness of the coal beam reduced to
around 0.8m (see Figure 12).
- The mine did not respond to a deterioration in roof quality
2m Thick Coal Beam
identified previously in the mine’s exploration programme.
1 1 Coal - In the outbye area of the panel where a major horizontal stress
Carbonaceous Shale
Coal / Carbonaceous Shale
Coal
was anticipated, the density of secondary support was
0 0 increased to 3 x 8m long cables every 1m in the mid-pillar
areas and 3 x 10m long cables every 1m and 2 x 6m long floor
0 50 100 150 200 250 300 0 50 100 150 200 250 300
Figure 13 – Examples of Low Level Buckling and Shale Driven The changes made to the secondary support design were based
High Level Buckling Roof Behaviour in Mine E primarily on an empirical understanding of roof quality and major
and minor horizontal stress notching.
As a result of these conclusions, the mine now tracks the thickness
of carbonaceous shale and all roadways where the shale is >1.5m The resulting increase in LW Acceleration Positions (which as
thick, are supported with 6 x 2.1m long bolts every 1m and all described in Thomas and Wagner (2006), relates to the position
intersections with 1 or 2 x 6m long cables every 2m. outbye or inbye of the face where the roof displacement first
exceeds a rate of 10mm per week) measured in the channel edge
Longwall Retreat Case Studies and the major horizontal stress notch areas indicated that the
decision to increase the density of secondary support was warranted.
In terms of longwall retreat, the main aim of strata management is
to ensure that the longwall is able to produce without strata related 100 LW Acceleration Position No. of cables per metre 4
the need to prevent falls of ground, but also in the case of maingate 90
70
40
20
are subjected to a minor horizontal stress notch during longwall Cut-through No.
retreat.
Figure 14 – LW Acceleration Positions and Secondary Roof
As a result of these conditions, the maingate roadways are typically Support Densities Installed in a Maingate Roadway at Mine F
supported with 1 x 8m long cable every 1 to 2m. However, in a
new area of the mine two distinct changes in the geotechnical (ii) Successful Case – Mine G
environment were identified during roadway development; a) in the
inbye area of the panels a massive sandstone channel with an In Mine G, which is located at an approximate depth of 220 to
estimated CMMR of 70 was encountered in the immediate roof and 270m, a 5 to 6m thick competent coal roof enabled the mine to
b) in the outbye end of the panels, the horizontal stress re- develop and retreat maingate roadways on as little as 4 x 1.8m long
orientated such that the maingate roadway would be subjected to a roof bolts every 1.4m.
major horizontal stress notch during longwall retreat.
However, in the northern area of the mine a notable deterioration in
roof behaviour was experienced, such that during roadway
development the density of roof support was increased to 6 to 8 x
1.8m long roof bolts every 1m and during longwall retreat, to 2 to 3
x 8m long cables every 1m.
26th International Conference on Ground Control in Mining
Although the causal factor or factors behind the deterioration in Position of <30m outbye of the face indicated that the roof had
roof behaviour were not clear, the main point of note to the mine been over-supported.
with regard to strata management was that the LW Acceleration
concept could be used as an “early warning system” to determine The density of secondary roof support was therefore reduced in
whether or not additional secondary support was necessary during accordance with the magnitude of the preceding LW Acceleration
longwall retreat. Positions and as a means of checking the adequacy of any changes
made to the secondary support design, the condition of the roof was
Although LW Acceleration Positions in other deeper, more highly again monitored during longwall retreat.
stressed maingate roadways typically range between 60 and 160m
outbye of the face, on occasions the roof started to buckle and
accelerate in response to the retreating longwall between 150 and LW Acceleration Position No. of Cable bolts per metre
300m outbye of the face (see Figure 15). 200 4
300
0 0
LW18 LW19 1500 LW20
LW Acceleration Position (m outbye face)
180
Figure 16 – Measured Reduction in LW Acceleration Positions
150
and Subsequent Reduction in Cable Bolt Densities in Mine H
120
30 In Mine I, where the depth of cover ranged between 150 and 250m,
0 secondary roof support was generally not required during longwall
0 50 100 150 200 250 300 350 400 450 500 550 600
retreat.
Depth of Cover (m)
Figure 15 – Copy of the Australian LW Acceleration Database These favourable conditions were primarily attributed to a thickly
Showing Data Measured in the Northern Area of Mine G bedded to massive sandstone roof with an estimated CMRR of
around 80 and a minor horizontal stress notch.
(iii) Successful Case – Mine H
In the eastern area of the mine where, despite a reduction in the
In Mine H, which is located at an approximate depth of 500m and depth of cover to 90m, a roof fall was however experienced in the
is characterised by a laminated to thinly bedded sandstone roof, maingate during longwall retreat.
between 300 and 500mm of roof deformation was experienced in
the maingate during longwall retreat. The subsequent investigation demonstrated that the mine failed to
identify a) a change in roof lithology to an interlaminated sandstone
This deterioration in roof behaviour was related to the fact that the / siltstone with an estimated CMRR of 40 and b) as a result of the
longwall in question was the first in a new area of the mine and was re-orientation of the longwall blocks, a major horizontal stress
therefore subjected to a full major horizontal stress notch ie, with notch.
no associated stress relief from a neighbouring goaf.
Importantly, a subsequent borescope survey undertaken outbye of
As a result of these conditions, the mine installed up to 3 x 8m long the fall indicated that the roof did not start to buckle in response to
cables every 1m along the majority of the maingate. However, in the retreating longwall until less than 10m outbye of the face (see
the subsequent longwall blocks, where as a result of the formation Figure 17).
of a neighbouring goaf an improvement in roof conditions was
experienced, the mine was able to reduce the density of cables This meant that in such a highly laminated roof where the transition
down to as low as 1 x 8m long cable every 1m. from static to buckling behaviour was associated with large-scale
beam breakdown, any deterioration in roof behaviour would
A critical factor in this reduction was the use of the LW probably give very little warning. Moreover, it was also concluded
Acceleration concept, as prior to any reduction in cable density, the that the LW Acceleration concept was not appropriate and that if
mine first demonstrated that the preceding LW Acceleration the roof did start to sag or gutter, it would more than likely occur
Position had reduced to an acceptable level. within 5m or so of the face where the installation of additional
support would prove practically impossible.
As a general rule, the mine’s strata management process worked on
the basis that any LW Acceleration Position of <60m outbye of the As a result of these conclusions, the mine decided to not rely on
face was an acceptable result and that any LW Acceleration any “soft” monitoring type controls and reinforced all areas of
laminated roof with 1 to 2 x 6m long cables every 1m.
26th International Conference on Ground Control in Mining
In Mine K the roof was however not monitored when the longwall
Development 8 to 2m Outbye of Longwall started production, and in doing so the mine failed to react to the
8 8
deterioration in roof behaviour. Ultimately, the roof over a 150m
7 7
long section of roadway displaced between 300 and 500mm and in
two areas, the roof fell.
6 6
Although it could be argued that both “back-notches” where poorly
managed, it is of note that through monitoring, Mine J averted a
Height into Roof (m)
Height into Roof (m)
5 5
roof fall and the significant costs and risks associated with the
4 4
ensuing recovery work.
3 3
Conclusions
2 2
Strata management is now a necessary requirement in the New
South Wales underground coal mining industry. Used correctly,
1 1
strata management allows ground support and mining methods to
be tailored to the anticipated and encountered geotechnical
0 0
environment in a controlled manner, thereby improving mine site
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100 safety and productivity.
Displacement (mm) Displacement (mm)
100
90
80
Displacement (mm)
70 Total
60 0.5m
50 3.0m
5.0m
40
30
20
10
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000
Elapsed Time (Hours)