Job Safety Analysis - For Geotechnical Work
Job Safety Analysis - For Geotechnical Work
Team Composition:
Task Description: Geotechnical Work
Site Supervisors, Drillers, Helpers, Drivers. Grouting team.
Step No. Description of Hazard - Potential Who or What Control Measures / Action /
Task Step Incident Might be Harmed Recovery Responsible
Measures Party
01 Job plan Lack of coordination Job 1) Pre job meeting shall be held with clients or ACES
contractors.
2) All operative persons to have received site
induction.
3) All tasks carried out by trained, authorized and
competent personnel only.
4) Apply all PTW & support documents prior to start of
job.
5) Discuss the JSA & work procedures prior to start of
work.
02 Mobilization of RTA(Regional Personnel 1) The drilling machine is inspected and certified Worksite
equipment and Transportation & by a third party. Supervisor
transportation of Authority) Equipment 2) All third party certificates shall be checked.
drilling machine 3) All personnel will wear the appropriate PPE for
their specific task.
4) Follow the KSA traffic regulations.
5) Drivers must have valid driving license.
6) All vehicles must be properly maintained and
must be tested before mobilization.
7) Allow only licensed individuals to operate the
Doc No. 15000006/ACES/HSE/JSA 02 1
vehicles. Comply with KSA regulations.
8) Know the traveling height (overhead clearance),
width, length and weight of the drill rig with carrier
and know the highway and bridge load, width and
overhead limits.
9) Never move a drill rig unless the vehicle brakes
are in sound working order.
10) Watch for low hanging electrical lines,
particularly at the entrances to drilling sites,
restaurants, motels or other commercial sites.
11) Never travel on a street, road or highway with
the mast (derrick) of the drill rig in the raised or
partially raised position.
12) Do not permit passengers to ride on the drill
rig.
03 Pre-work safety Lack of understanding Job, Personnel & 1) Work permit shall be obtained in the areas Worksite
meeting & toolbox Equipment where the boreholes will be drilled. Supervisor
talk 2) Toolbox talk shall be dispensed daily to enforce
the required safety instructions.
3) All operative persons must recognize the
emergency procedures.
4) Attention for wearing full PPE all times.
Work permit shall be permanently in place of work.
04 Barricading and Accidents & Injuries Personnel & 1) Working area shall be barricaded and access Worksite
setting warning sign Equipment shall be restricted. Supervisor
2) Use safety cones bounded by safety caution
tape to cordon the working area.
Warning signs will be settled in place of work for
attention
05 Inspection of the Equipment breakdown Personnel & 1) Daily equipment pre-operational inspection shall Worksite
equipment and Equipment be carried. Supervisor
drilling tools before 2) Ensure all third party certificates are valid.
start of work
06 Excavation of trial Hitting underground Underground 1) Checking and studying all available services Worksite
pits and utility pits services – confined service & maps and using cable detector locator. Supervisor
space Personnel 2) Work permit shall be obtained in the areas
where trial pits shall be excavated near.
3) Toolbox talk shall be inducted.