Structure RFI Status Summary For The Month of December-2021

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Structure RFI Status Summary for the Month of December-2021

Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of Shuttering, Reinforcement and Pouring of RCC M-35 grade
GCL/STR/21-22/ 2384 21-Dec-21 9:00 AM MNB 14+710 - RHS Nos. 1 Not Approved 22-Dec-21
for MNB raft RA1
Checking of Reinforcement and Profile of MJB (Cast in Situ) PSC Outer
GCL/STR/21-22/ 2385 21-Dec-21 11:00 AM MJB 15+100 - LHS Nos. 1 Approved 22-Dec-21
Girder G-1/2 (LP1-LP2)
GCL/STR/21-22/ 2386 21-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-16 17+475 - - Nos. 1 Approved 22-Dec-21
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2387 21-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 22-Dec-21
MJB Pre-Cast PSC girder G-16
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2388 21-Dec-21 10:00 AM Box Culvert 19+110 - BHS Nos. 1 Approved 22-Dec-21
box culvert Wall final lift with top Haunch & Slab A1,A2
Checking of Reinforcement, Shuttring and Pouring of RCC M-35 grade for
GCL/STR/21-22/ 2389 21-Dec-21 12:00 PM Box Culvert 19+585 - LHS Nos. 1 Approved 22-Dec-21
box culvert wall 1st lift with Bottom haunch (A1&A2)
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2390 21-Dec-21 10:00 AM MNB 20+416 - BHS Nos. 1 Approved 22-Dec-21
grade for MNB Wall 5th lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2391 21-Dec-21 2:00 PM R.Wall 19+200 - RHS Nos. 1 Approved 22-Dec-21
grade for Box Culvert Return wall final Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2392 21-Dec-21 11:00 AM MNB 25+053 - RHS Nos. 1 Approved 22-Dec-21
grade for MNB Wall 2nd lift (RA2)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2393 21-Dec-21 4:00 PM R.Wall 130+600 130+620 RHS Rmt 20 Approved 22-Dec-21
Retaining Wall 1st Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2394 21-Dec-21 10:00 AM R.Wall 142+885 142+895 LHS Rmt 10 Approved 22-Dec-21
Retaining Wall 1st Lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2395 21-Dec-21 11:00 AM Block Wall 136+925 136+955 LHS Rmt 30 Approved 22-Dec-21
Block Wall final lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2396 21-Dec-21 12:00 PM R.Wall 16+590 16+602 LHS Rmt 12 Approved 22-Dec-21
Retaining Wall 5th lift.
Checking of Layout excavation, level and Laying of PCC M-15 for box
GCL/STR/21-22/ 2397 21-Dec-21 9:00 AM R.Wall 16+602 16+612 LHS Rmt 10 Approved 22-Dec-21
culvert Retaining wall.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2398 21-Dec-21 9:00 AM R.Wall 127+300 127+350 RHS Rmt 50 Approved 22-Dec-21
Retaining Wall 6th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2399 21-Dec-21 1:00 PM R.Wall 19+588 19+598 LHS Rmt 10 Approved 22-Dec-21
Retaining Wall 2nd lift.
Checking of Reinforcement, Shuttring, and Pouring of RCC M-35 grade
GCL/STR/21-22/ 2400 21-Dec-21 10:00 AM Box Culvert 132+007 - LHS Nos. 1 Approved 22-Dec-21
for box culvert Raft.
Checking of Shuttering,reinforcement and Pouring of concrete M-35 grade
GCL/STR/21-22/ 2401 21-Dec-21 1:00 PM R.Wall 152+553 152+563 RHS Rmt 10 Approved 22-Dec-21
Retaning Wall 3rd lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2402 21-Dec-21 12:00 PM Block Wall 155+428 155+464 LHS Rmt 36 Approved 22-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2403 21-Dec-21 9:00 AM Block Wall 136+955 136+965 LHS Rmt 10 Approved 22-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2404 21-Dec-21 5:00 PM Block Wall 136+965 136+980 LHS Rmt 15 Approved 22-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2405 21-Dec-21 9:00 AM Block Wall 20+120 20+140 RHS Rmt 20 Approved 22-Dec-21
Block Wall 3rd lift.
Checking of Reinforcement, shuttering and concrete pouring M-40 grade
GCL/STR/21-22/ 2406 21-Dec-21 5:00 PM Friction Slab 133+706 133+750 RHS Rmt 44 Approved 22-Dec-21
for Friction Slab Haunch RA2
Checking of Reinforcement, Shuttering & Pouring of Concrete RCC M-40
GCL/STR/21-22/ 2407 21-Dec-21 9:00 AM MNB 138+252 - RHS Nos. 1 Not Approved 22-Dec-21
grade for Inner and Outer Crash Barrier (A1-A2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2408 21-Dec-21 9:00 AM Block Wall 131+490 131+505 LHS Rmt 15 Approved 22-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2409 21-Dec-21 11:00 AM Block Wall 155+510 155+536 LHS Rmt 26 Approved 22-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2410 21-Dec-21 3:00 PM Block Wall 134+610 134+660 LHS Rmt 50 Approved 22-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2411 21-Dec-21 11:00 AM Block Wall 25+170 25+190 RHS Rmt 20 Approved 22-Dec-21
Block Wall 6th lift.

Page 1 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of Reinforcement, shuttering and concrete pouring M-30 grade
GCL/STR/21-22/ 2412 21-Dec-21 6:00 PM PUP 25+280 - RHS Nos. 1 Approved 22-Dec-21
for PUP Approch Slab A1
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2413 21-Dec-21 10:00 AM Block Wall 134+874 134+936 LHS Rmt 62 Approved 22-Dec-21
Concrete Block Wall
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2414 21-Dec-21 10:00 AM Block Wall 131+515 131+520 LHS Rmt 5 Approved 22-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2415 21-Dec-21 10:00 AM Block Wall 134+678 134+698 RHS Rmt 20 Approved 22-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2416 21-Dec-21 10:00 AM Block Wall 138+410 138+430 LHS Rmt 20 Approved 22-Dec-21
Block Wall 1st lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2417 21-Dec-21 9:00 AM Block Wall 134+600 134+625 RHS Rmt 25 Approved 22-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2418 21-Dec-21 11:00 AM Block Wall 134+733 134+776 RHS Rmt 43 Approved 22-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2419 21-Dec-21 9:00 AM Block Wall 155+402 155+412 LHS Rmt 10 Approved 22-Dec-21
Block Wall 4th lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2420 21-Dec-21 12:00 PM R.Wall 131+694 - LHS Nos 1 Not Approved 22-Dec-21
grade for Box Culvert Return wall 3rd Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2421 21-Dec-21 10:00 AM G-S 142+568 - RHS Nos. 1 Not Approved 22-Dec-21
grade for GS Pier Cap (RP1)
Checking of Shuttering, Reinforcement and Pouring of RCC M-35 grade
GCL/STR/21-22/ 2422 22-Dec-21 9:00 AM MNB 14+710 - RHS Nos. 1 Approved 23-Dec-21
for MNB raft RA1
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-50)
GCL/STR/21-22/ 2423 22-Dec-21 11:00 AM MJB 15+100 - LHS Nos. 1 Not Approved 23-Dec-21
Grade For MJB (Cast in Situ) PSC Outer Girder G-1/2 (LP1-LP2)
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-35
GCL/STR/21-22/ 2424 22-Dec-21 9:00 AM R.Wall 20+169 - LHS Nos. 1 Approved 23-Dec-21
grade for Box Culvert Return wall 2nd Lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2425 22-Dec-21 10:00 AM Block Wall 134+625 134+658 RHS Rmt 33 Approved 23-Dec-21
Block Wall 3rd lift.
Checking of Reinforcement, Shuttring and Pouring of RCC M-35 grade for
GCL/STR/21-22/ 2426 22-Dec-21 11:00 AM Box Culvert 19+585 - LHS Nos. 1 Not Approved 23-Dec-21
box culvert wall 2nd lift (A1&A2)
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-40)
GCL/STR/21-22/ 2427 22-Dec-21 3:00 PM MNB 18+972 - RHS Nos. 1 Approved 23-Dec-21
Grade For MNB RCC End Cross Girder (RA1)
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2428 22-Dec-21 4:00 PM R.Wall 19+200 - LHS Nos. 1 Approved 23-Dec-21
grade for Box Culvert Return wall 4th Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2429 22-Dec-21 9:00 AM MNB 25+053 - RHS Nos. 1 Approved 23-Dec-21
grade for MNB Wall 3rd lift & Return wall 3rd Lift (RA2)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2430 22-Dec-21 4:00 PM R.Wall 130+600 130+620 RHS Rmt 20 Approved 23-Dec-21
Retaining Wall 2nd Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2431 22-Dec-21 12:00 PM R.Wall 142+885 142+895 LHS Rmt 10 Approved 23-Dec-21
Retaining Wall 2nd Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2432 22-Dec-21 11:00 AM MJB 24+635 - LHS Nos. 1 Not Approved 23-Dec-21
grade for MJB Pier cap (LP1)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2433 22-Dec-21 10:00 AM R.Wall 16+590 16+602 LHS Rmt 12 Approved 23-Dec-21
Retaining Wall 6th lift.
Checking of Shuttering,reinforcement and Pouring of concrete M-35 grade
GCL/STR/21-22/ 2434 22-Dec-21 10:00 AM R.Wall 16+602 16+612 LHS Rmt 10 Approved 23-Dec-21
Retaning Wall Raft
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2435 22-Dec-21 9:00 AM R.Wall 127+300 127+350 RHS Rmt 50 Approved 23-Dec-21
Retaining Wall 7th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2436 22-Dec-21 1:00 PM R.Wall 19+588 19+598 LHS Rmt 10 Approved 23-Dec-21
Retaining Wall 3rd lift.
Checking of Reinforcement, Shuttring and Pouring of RCC M-35 grade for
GCL/STR/21-22/ 2437 22-Dec-21 12:00 PM Box Culvert 132+007 - LHS Nos. 1 Approved 23-Dec-21
box culvert wall 1st lift with Bottom haunch (A1&A2)
Checking of Shuttering,reinforcement and Pouring of concrete M-35 grade
GCL/STR/21-22/ 2438 22-Dec-21 9:00 AM R.Wall 152+553 152+563 RHS Rmt 10 Approved 23-Dec-21
Retaning Wall 4th lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2439 22-Dec-21 9:00 AM Block Wall 155+428 155+464 LHS Rmt 36 Approved 23-Dec-21
Block Wall 3rd lift.

Page 2 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2440 22-Dec-21 1:00 PM Block Wall 136+955 136+965 LHS Rmt 10 Approved 23-Dec-21
Block Wall 3rd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2441 22-Dec-21 9:00 AM MJB 20+800 - LHS Nos. 1 Not Approved 23-Dec-21
grade for MJB Pier cap (LP2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2442 22-Dec-21 10:00 AM Block Wall 20+120 20+140 RHS Rmt 20 Approved 23-Dec-21
Block Wall 4th lift.
Checking of Reinforcement, Shuttering & Pouring of Concrete RCC M-40
GCL/STR/21-22/ 2443 22-Dec-21 9:00 AM MNB 138+252 - RHS Nos. 1 Approved 23-Dec-21
grade for Inner and Outer Crash Barrier (A1-A2)
GCL/STR/21-22/ 2444 22-Dec-21 9:00 AM Pipe Culvert Laying of GSB Material for pipe Bedding 22+798 - LHS Nos. 1 Approved 23-Dec-21
GCL/STR/21-22/ 2445 22-Dec-21 6:00 PM Pipe Culvert Checking of Pipe laying and jointing NP.4 Hume Pipe of 1200 mm dia 22+798 - LHS Nos. 1 Approved 23-Dec-21
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2446 22-Dec-21 11:00 AM Block Wall 134+610 134+660 LHS Rmt 50 Approved 23-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2447 22-Dec-21 9:00 AM Block Wall 25+170 25+190 RHS Rmt 20 Approved 23-Dec-21
Block Wall final lift.
Checking of layout excavation, level and laying of PCC M-15 for PUP
GCL/STR/21-22/ 2448 22-Dec-21 11:00 AM PUP 25+280 - RHS Nos. 1 Not Approved 23-Dec-21
Approach slab (A2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2449 22-Dec-21 10:00 AM Block Wall 134+874 134+936 LHS Rmt 62 Approved 23-Dec-21
Block Wall 1st lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2450 22-Dec-21 12:00 PM Block Wall 131+515 131+520 LHS Rmt 5 Approved 23-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2451 22-Dec-21 10:00 AM Block Wall 134+678 134+698 RHS Rmt 20 Not Approved 23-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2452 22-Dec-21 11:00 AM Block Wall 138+410 138+430 LHS Rmt 20 Approved 23-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2453 22-Dec-21 10:00 AM Block Wall 134+600 134+625 RHS Rmt 25 Approved 23-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2454 22-Dec-21 11:00 AM Block Wall 134+733 134+776 RHS Rmt 43 Approved 23-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2455 22-Dec-21 2:00 PM Block Wall 155+402 155+412 LHS Rmt 10 Approved 23-Dec-21
Block Wall final lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2456 22-Dec-21 12:00 PM R.Wall 131+694 - LHS Nos 1 Approved 23-Dec-21
grade for Box Culvert Return wall 3rd Lift
Checking of reinforcement, shuttering and pouring of RCC M-30 grade for
GCL/STR/21-22/ 2457 22-Dec-21 10:00 AM G-S 142+568 - RHS Nos. 1 Not Approved 23-Dec-21
G-S Pier Shaft 2nd Lift LP1
Checking of Reinforcement and Profile of MJB (Cast in Situ) Outer PSC
GCL/STR/21-22/ 2458 23-Dec-21 9:00 AM MJB 17+475 - LHS Nos. 1 Not Approved 24-Dec-21
girder G1/2 (LP4-LP5)
Checking of Reinforcement and Profile of MJB (Cast in Situ) Inner PSC
GCL/STR/21-22/ 2459 23-Dec-21 11:00 AM MJB 17+475 - LHS Nos. 1 Not Approved 24-Dec-21
girder G1/2 (LP4-LP5)
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-50)
GCL/STR/21-22/ 2460 23-Dec-21 9:00 AM MJB 15+100 - LHS Nos. 1 Approved 24-Dec-21
Grade For MJB (Cast in Situ) PSC Outer Girder G-1/2 (LP1-LP2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2461 23-Dec-21 11:00 AM Block Wall 134+625 134+658 RHS Rmt 33 Approved 24-Dec-21
Block Wall 4th lift.
Checking of Reinforcement, Shuttring and Pouring of RCC M-35 grade for
GCL/STR/21-22/ 2462 23-Dec-21 11:00 AM Box Culvert 19+585 - LHS Nos. 1 Approved 24-Dec-21
box culvert wall 2nd lift (A1&A2)
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-40)
GCL/STR/21-22/ 2463 23-Dec-21 9:00 AM MNB 18+972 - RHS Nos. 1 Approved 24-Dec-21
Grade For MNB RCC End Cross Girder (RA2)
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2464 23-Dec-21 10:00 AM R.Wall 19+200 - LHS Nos. 1 Not Approved 24-Dec-21
grade for Box Culvert Return wall 5th Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2465 23-Dec-21 11:00 AM MNB 25+053 - RHS Nos. 1 Approved 24-Dec-21
grade for MNB Wall 4th lift & Return wall 4th Lift (RA2)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2466 23-Dec-21 4:00 PM R.Wall 130+600 130+620 RHS Rmt 20 Approved 24-Dec-21
Retaining Wall 3rd Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2467 23-Dec-21 11:00 AM MJB 24+635 - LHS Nos. 1 Approved 24-Dec-21
grade for MJB Pier cap (LP1)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2468 23-Dec-21 12:00 PM R.Wall 16+590 16+602 LHS Rmt 12 Approved 24-Dec-21
Retaining Wall 7th lift.

Page 3 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2469 23-Dec-21 9:00 AM R.Wall 16+602 16+612 LHS Rmt 10 Approved 24-Dec-21
Retaining Wall 1st lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2470 23-Dec-21 10:00 AM R.Wall 127+300 127+350 RHS Rmt 50 Not Approved 24-Dec-21
Retaining Wall Final lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2471 23-Dec-21 2:00 PM R.Wall 19+588 19+598 LHS Rmt 10 Approved 24-Dec-21
Retaining Wall Final lift.
Checking of Reinforcement, Shuttring and Pouring of RCC M-35 grade for
GCL/STR/21-22/ 2472 23-Dec-21 10:00 AM Box Culvert 132+007 - LHS Nos. 1 Not Approved 24-Dec-21
box culvert wall 2nd lift (A1&A2)
Checking of Shuttering,reinforcement and Pouring of concrete M-35 grade
GCL/STR/21-22/ 2473 23-Dec-21 10:00 AM R.Wall 152+553 152+563 RHS Rmt 10 Approved 24-Dec-21
Retaning Wall 5th lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2474 23-Dec-21 1:00 PM Block Wall 155+428 155+464 LHS Rmt 36 Approved 24-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2475 23-Dec-21 10:00 AM Block Wall 136+955 136+965 LHS Rmt 10 Approved 24-Dec-21
Block Wall 4th lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2476 23-Dec-21 9:00 AM MJB 20+800 - LHS Nos. 1 Approved 24-Dec-21
grade for MJB Pier cap (LP2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2477 23-Dec-21 12:00 PM Block Wall 20+120 20+140 RHS Rmt 20 Approved 24-Dec-21
Block Wall final lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2478 23-Dec-21 10:00 AM Pipe Culvert 22+798 - LHS Nos. 1 Not Approved 24-Dec-21
grade for Pipe culvert Head wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2479 23-Dec-21 10:00 AM Block Wall 126+650 126+700 LHS Rmt 50 Approved 24-Dec-21
Block Wall
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2480 23-Dec-21 9:00 AM Block Wall 134+610 134+660 LHS Rmt 50 Not Approved 24-Dec-21
Block Wall 5th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2481 23-Dec-21 9:00 AM Block Wall 134+658 134+678 RHS Rmt 20 Approved 24-Dec-21
Block Wall 3rd lift.
Checking of layout excavation, level and laying of PCC M-15 for PUP
GCL/STR/21-22/ 2482 23-Dec-21 11:00 AM PUP 25+280 - RHS Nos. 1 Not Approved 24-Dec-21
Approach slab (A2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2483 23-Dec-21 11:00 AM Block Wall 134+874 134+936 LHS Rmt 62 Approved 24-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2484 23-Dec-21 11:00 AM Block Wall 131+515 131+520 LHS Rmt 5 Approved 24-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2485 23-Dec-21 10:00 AM Block Wall 134+678 134+698 RHS Rmt 20 Not Approved 24-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2486 23-Dec-21 9:00 AM Block Wall 138+410 138+430 LHS Rmt 20 Approved 24-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2487 23-Dec-21 9:00 AM Block Wall 134+600 134+625 RHS Rmt 25 Approved 24-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2488 23-Dec-21 2:00 PM Block Wall 134+698 134+733 RHS Rmt 35 Approved 24-Dec-21
Block Wall 2nd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2489 23-Dec-21 10:00 AM R.Wall 131+694 - LHS Nos 1 Not Approved 24-Dec-21
grade for Box Culvert Return wall 4th Lift
Checking of reinforcement, shuttering and pouring of RCC M-30 grade for
GCL/STR/21-22/ 2490 23-Dec-21 10:00 AM G-S 142+568 - LHS Nos. 1 Approved 24-Dec-21
G-S Pier Shaft Final Lift LP1
Checking of Reinforcement and Profile of MJB (Cast in Situ) Outer PSC
GCL/STR/21-22/ 2491 24-Dec-21 9:00 AM MJB 17+475 - LHS Nos. 1 Approved 25-Dec-21
girder G1/2 (LP4-LP5)
Checking of Reinforcement and Profile of MJB (Cast in Situ) Inner PSC
GCL/STR/21-22/ 2492 24-Dec-21 10:00 AM MJB 17+475 - LHS Nos. 1 Approved 25-Dec-21
girder G1/2 (LP4-LP5)
Checking of Reinforcement and Profile of MJB (Cast in Situ) Inner PSC
GCL/STR/21-22/ 2493 24-Dec-21 11:00 AM MJB 17+475 - LHS Nos. 1 Approved 25-Dec-21
girder G2/2 (LP4-LP5)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2494 24-Dec-21 12:00 PM Block Wall 134+625 134+658 RHS Rmt 33 Approved 25-Dec-21
Block Wall final lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2495 24-Dec-21 10:00 AM R.Wall 19+200 - LHS Nos. 1 Approved 25-Dec-21
grade for Box Culvert Return wall 5th Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2496 24-Dec-21 9:00 AM MNB 25+053 - RHS Nos. 1 Approved 25-Dec-21
grade for MNB Wall 5th lift & Return wall 5th Lift (RA2)

Page 4 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2497 24-Dec-21 10:00 AM R.Wall 130+600 130+620 RHS Rmt 20 Approved 25-Dec-21
Retaining Wall 4th Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2498 24-Dec-21 9:00 AM MJB 24+635 - RHS Nos. 1 Not Approved 25-Dec-21
grade for MJB Pier cap (RP1)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2499 24-Dec-21 11:00 AM R.Wall 16+590 16+602 LHS Rmt 12 Not Approved 25-Dec-21
Retaining Wall 8th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2500 24-Dec-21 3:00 PM R.Wall 16+602 16+612 LHS Rmt 10 Approved 25-Dec-21
Retaining Wall 2nd lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2501 24-Dec-21 10:00 AM R.Wall 127+300 127+350 RHS Rmt 50 Approved 25-Dec-21
Retaining Wall Final lift.
Checking of Reinforcement, Shuttring and Pouring of RCC M-35 grade for
GCL/STR/21-22/ 2502 24-Dec-21 10:00 AM Box Culvert 132+007 - LHS Nos. 1 Approved 25-Dec-21
box culvert wall 2nd lift (A1&A2)
Checking of Shuttering,reinforcement and Pouring of concrete M-35 grade
GCL/STR/21-22/ 2503 24-Dec-21 12:00 PM R.Wall 152+553 152+563 RHS Rmt 10 Approved 25-Dec-21
Retaning Wall 6th lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2504 24-Dec-21 10:00 AM Block Wall 155+428 155+464 LHS Rmt 36 Approved 25-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2505 24-Dec-21 1:00 PM Block Wall 136+955 136+965 LHS Rmt 10 Approved 25-Dec-21
Block Wall final lift.
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2506 24-Dec-21 12:00 PM Block Wall 26+075 26+095 RHS Rmt 20 Approved 25-Dec-21
Concrete Block Wall
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2507 24-Dec-21 10:00 AM Pipe Culvert 22+798 - LHS Nos. 1 Not Approved 25-Dec-21
grade for Pipe culvert Head wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2508 24-Dec-21 12:00 PM Block Wall 126+650 126+700 LHS Rmt 50 Approved 25-Dec-21
Block Wall 1st lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2509 24-Dec-21 10:00 AM Block Wall 134+610 134+660 LHS Rmt 50 Approved 25-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2510 24-Dec-21 3:00 PM Block Wall 134+658 134+678 RHS Rmt 20 Approved 25-Dec-21
Block Wall 4th lift.
Checking of layout excavation, level and laying of PCC M-15 for PUP
GCL/STR/21-22/ 2511 24-Dec-21 11:00 AM PUP 25+280 - RHS Nos. 1 Approved 25-Dec-21
Approach slab (A2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2512 24-Dec-21 1:00 PM Block Wall 134+874 134+936 LHS Rmt 62 Approved 25-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2513 24-Dec-21 9:00 AM Block Wall 131+505 131+520 LHS Rmt 15 Approved 25-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2514 24-Dec-21 10:00 AM Block Wall 134+678 134+698 RHS Rmt 20 Approved 25-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2515 24-Dec-21 3:00 PM Block Wall 138+410 138+430 LHS Rmt 20 Approved 25-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2516 24-Dec-21 9:00 AM Block Wall 134+733 134+776 RHS Rmt 43 Approved 25-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2517 24-Dec-21 11:00 AM Block Wall 134+698 134+733 RHS Rmt 35 Approved 25-Dec-21
Block Wall 3rd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2518 24-Dec-21 10:00 AM R.Wall 131+694 - LHS Nos 1 Approved 25-Dec-21
grade for Box Culvert Return wall 4th Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2519 24-Dec-21 10:00 AM G-S 142+568 - LHS Nos. 1 Not Approved 25-Dec-21
grade for GS Pier Cap (LP1)
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-50)
GCL/STR/21-22/ 2520 25-Dec-21 9:00 AM MJB 17+475 - LHS Nos. 1 Approved 26-Dec-21
Grade For MJB (Cast in Situ) Outer PSC Girder G1/2 (LP4-LP5)
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-50)
GCL/STR/21-22/ 2521 25-Dec-21 10:00 AM MJB 17+475 - LHS Nos. 1 Approved 26-Dec-21
Grade For MJB (Cast in Situ) Inner PSC Girder G2/2 (LP4-LP5)
Checking of Reinforcement, Shuttering & Pouring of Concrete (M-50)
GCL/STR/21-22/ 2522 25-Dec-21 11:00 AM MJB 17+475 - LHS Nos. 1 Approved 26-Dec-21
Grade For MJB (Cast in Situ) Outer PSC Girder G2/2 (LP4-LP5)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2523 25-Dec-21 12:00 PM R.Wall 142+885 142+895 LHS Rmt 10 Not Approved 26-Dec-21
Retaining Wall 3rd Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2524 25-Dec-21 3:00 PM R.Wall 19+200 - LHS Nos. 1 Not Approved 26-Dec-21
grade for Box Culvert Return wall final Lift

Page 5 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2525 25-Dec-21 12:00 PM MNB 25+053 - RHS Nos. 1 Approved 26-Dec-21
grade for MNB Wall final lift( RA2)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2526 25-Dec-21 9:00 AM R.Wall 130+600 130+620 RHS Rmt 20 Approved 26-Dec-21
Retaining Wall 5th Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2527 25-Dec-21 9:00 AM MJB 01+085 - BHS Nos. 1 Not Approved 26-Dec-21
grade for MJB Abutment shaft final Lift P6 (ACC Link Road)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2528 25-Dec-21 12:00 PM R.Wall 16+590 16+602 LHS Rmt 12 Approved 26-Dec-21
Retaining Wall final lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2529 25-Dec-21 10:00 AM R.Wall 16+602 16+612 LHS Rmt 10 Approved 26-Dec-21
Retaining Wall 3rd lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2530 25-Dec-21 10:00 AM R.Wall 136+360 136+370 RHS Rmt 10 Not Approved 26-Dec-21
Retaining Wall 5th Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2531 25-Dec-21 10:00 AM R.Wall 136+370 136+380 RHS Rmt 10 Approved 26-Dec-21
Retaining Wall 4th Lift
Checking of Shuttering,reinforcement and Pouring of concrete M-35 grade
GCL/STR/21-22/ 2532 25-Dec-21 10:00 AM R.Wall 152+553 152+563 RHS Rmt 10 Approved 26-Dec-21
Retaning Wall final lift
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2533 25-Dec-21 10:00 AM Block Wall 131+020 131+030 LHS Rmt 10 Approved 26-Dec-21
Concrete Block Wall
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-40
GCL/STR/21-22/ 2534 25-Dec-21 1:00 PM VUP 139+680 - BHS Nos. 1 Not Approved 26-Dec-21
grade vup for Outer Crash Barrier
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2535 25-Dec-21 10:00 AM Block Wall 26+075 26+095 RHS Rmt 20 Approved 26-Dec-21
Block Wall 1st lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-40
GCL/STR/21-22/ 2536 25-Dec-21 10:00 AM Pipe Culvert 133+660 133+720 LHS Rmt 60 Not Approved 26-Dec-21
grade Friction Slab Crash Barrier
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2537 25-Dec-21 11:00 AM Block Wall 126+650 126+700 LHS Rmt 50 Approved 26-Dec-21
Block Wall 2nd lift.
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2538 25-Dec-21 10:00 AM Block Wall 20+450 20+500 RHS Rmt 50 Approved 26-Dec-21
Concrete Block Wall
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2539 25-Dec-21 11:00 AM Block Wall 134+658 134+678 RHS Rmt 20 Approved 26-Dec-21
Block Wall final lift.
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2540 25-Dec-21 11:00 AM Block Wall 26+095 26+105 RHS Rmt 10 Approved 26-Dec-21
Concrete Block Wall
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2541 25-Dec-21 3:00 PM Block Wall 134+874 134+936 LHS Rmt 62 Approved 26-Dec-21
Block Wall 4th lift.
Checking of Layout excavation, level and Laying of PCC M-15 for pipe
GCL/STR/21-22/ 2542 25-Dec-21 9:00 AM Pipe Culvert 137+220 - RHS Nos. 1 Approved 26-Dec-21
culvert Head Wall
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2543 25-Dec-21 1:00 PM Block Wall 134+678 134+698 RHS Rmt 20 Approved 26-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2544 25-Dec-21 10:00 AM Block Wall 138+410 138+430 LHS Rmt 20 Approved 26-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2545 25-Dec-21 12:00 PM Block Wall 134+733 134+776 RHS Rmt 43 Approved 26-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2546 25-Dec-21 4:00 PM Block Wall 134+698 134+733 RHS Rmt 35 Approved 26-Dec-21
Block Wall 4th lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2547 25-Dec-21 10:00 AM Pipe Culvert 22+798 - LHS Nos. 1 Approved 26-Dec-21
grade for Pipe culvert Head wall 2nd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2548 25-Dec-21 9:00 AM G-S 142+568 - LHS Nos. 1 Not Approved 26-Dec-21
grade for GS Pier Cap (LP1)
Checking of Shuttering, Reinforcement and Pouring of RCC M-(30) grade
GCL/STR/21-22/ 2549 25-Dec-21 12:00 PM Box Culvert 151+380 - RHS Nos. 1 Approved 26-Dec-21
for box culvert Slab
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2550 25-Dec-21 3:00 PM MJB 24+635 - RHS Nos. 1 Not Approved 26-Dec-21
grade for MJB Pier cap (RP1)
GCL/STR/21-22/ 2551 26-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-17 17+475 - - Nos. 1 Approved 27-Dec-21
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2552 26-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 27-Dec-21
MJB Pre-Cast PSC girder G-17

Page 6 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of Shuttering, Reinforcement and Pouring of RCC M-35 grade
GCL/STR/21-22/ 2553 26-Dec-21 11:00 AM MNB 14+710 - LHS Nos. 1 Not Approved 27-Dec-21
for MNB raft LA1
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2554 26-Dec-21 12:00 PM R.Wall 142+885 142+895 LHS Rmt 10 Approved 27-Dec-21
Retaining Wall 3rd Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2555 26-Dec-21 3:00 PM R.Wall 19+200 - LHS Nos. 1 Not Approved 27-Dec-21
grade for Box Culvert Return wall final Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2556 26-Dec-21 12:00 PM MNB 20+416 - BHS Nos. 1 Not Approved 27-Dec-21
grade for MNB Wall final lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2557 26-Dec-21 11:00 AM R.Wall 130+600 130+620 RHS Rmt 20 Approved 27-Dec-21
Retaining Wall final Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2558 26-Dec-21 9:00 AM MJB 01+085 - BHS Nos. 1 Not Approved 27-Dec-21
grade for MJB Abutment shaft final Lift P6 (ACC Link Road)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2559 26-Dec-21 12:00 PM R.Wall 16+602 16+612 LHS Rmt 10 Approved 27-Dec-21
Retaining Wall 4th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2560 26-Dec-21 10:00 AM R.Wall 136+360 136+370 RHS Rmt 10 Approved 27-Dec-21
Retaining Wall 5th Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2561 26-Dec-21 12:00 PM R.Wall 136+370 136+380 RHS Rmt 10 Approved 27-Dec-21
Retaining Wall 5th Lift
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2562 26-Dec-21 9:00 AM Block Wall 131+020 131+030 LHS Rmt 10 Approved 27-Dec-21
Block Wall 1st lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-40
GCL/STR/21-22/ 2563 26-Dec-21 1:00 PM VUP 139+680 - BHS Nos. 1 Approved 27-Dec-21
grade vup for Outer Crash Barrier
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2564 26-Dec-21 11:00 AM Block Wall 26+075 26+095 RHS Rmt 20 Approved 27-Dec-21
Block Wall 2nd lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-40
GCL/STR/21-22/ 2565 26-Dec-21 10:00 AM Friction Slab 133+660 133+720 LHS Rmt 60 Approved 27-Dec-21
grade Friction Slab Crash Barrier
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2566 26-Dec-21 9:00 AM Block Wall 126+650 126+700 LHS Rmt 50 Approved 27-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2567 26-Dec-21 2:00 PM Block Wall 20+450 20+500 RHS Rmt 50 Approved 27-Dec-21
Block Wall 1st lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2568 26-Dec-21 10:00 AM Block Wall 26+095 26+105 RHS Rmt 10 Approved 27-Dec-21
Block Wall 1st lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2569 26-Dec-21 9:00 AM Block Wall 134+874 134+936 LHS Rmt 62 Approved 27-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2570 26-Dec-21 10:00 AM Block Wall 134+678 134+698 RHS Rmt 20 Approved 27-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2571 26-Dec-21 9:00 AM Block Wall 134+698 134+733 RHS Rmt 35 Approved 27-Dec-21
Block Wall final lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2572 26-Dec-21 9:00 AM G-S 142+568 - LHS Nos. 1 Not Approved 27-Dec-21
grade for GS Pier Cap (LP1)
GCL/STR/21-22/ 2573 27-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-18 17+475 - - Nos. 1 Approved 28-Dec-21
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2574 27-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 28-Dec-21
MJB Pre-Cast PSC girder G-18
Checking of Shuttering, Reinforcement and Pouring of RCC M-35 grade
GCL/STR/21-22/ 2575 27-Dec-21 11:00 AM MNB 14+710 - LHS Nos. 1 Not Approved 28-Dec-21
for MNB raft LA1
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2576 27-Dec-21 12:00 PM R.Wall 142+885 142+895 LHS Rmt 10 Approved 28-Dec-21
Retaining Wall final Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-25
GCL/STR/21-22/ 2577 27-Dec-21 3:00 PM R.Wall 19+200 - LHS Nos. 1 Approved 28-Dec-21
grade for Box Culvert Return wall final Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2578 27-Dec-21 12:00 PM MNB 20+416 - BHS Nos. 1 Not Approved 28-Dec-21
grade for MNB Wall final lift with top haunch & slab A1,A2
Checking of Layout excavation, Level and Laying of PCC M-15 for box
GCL/STR/21-22/ 2579 27-Dec-21 11:00 AM Box Culvert 158+464 - LHS Nos. 1 Approved 28-Dec-21
culvert.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2580 27-Dec-21 9:00 AM MJB 01+085 - BHS Nos. 1 Approved 28-Dec-21
grade for MJB Abutment shaft final Lift A2 (ACC Link Road)

Page 7 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of reinforcement, shuttering and pouring of RCC M-25 grade for
GCL/STR/21-22/ 2581 27-Dec-21 12:00 PM C.F.Wall 22+770 22+780 LHS Rmt 10 Not Approved 28-Dec-21
Stem and Counterfort wall 9th lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2582 27-Dec-21 12:00 PM R.Wall 16+602 16+612 LHS Rmt 10 Approved 28-Dec-21
Retaining Wall 5th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2583 27-Dec-21 10:00 AM R.Wall 136+360 136+370 RHS Rmt 10 Approved 28-Dec-21
Retaining Wall 6th Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2584 27-Dec-21 12:00 PM R.Wall 136+370 136+380 RHS Rmt 10 Approved 28-Dec-21
Retaining Wall 6th Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2585 27-Dec-21 10:00 AM Box Culvert 19+585 - LHS Nos. 1 Not Approved 28-Dec-21
box culvert Wall final lift with top Haunch & Slab A1,A2
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2586 27-Dec-21 9:00 AM Block Wall 131+020 131+030 LHS Rmt 10 Not Approved 28-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2587 27-Dec-21 11:00 AM Block Wall 26+075 26+095 RHS Rmt 20 Approved 28-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2588 27-Dec-21 9:00 AM Block Wall 126+650 126+700 LHS Rmt 50 Approved 28-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2589 27-Dec-21 2:00 PM Block Wall 20+450 20+500 RHS Rmt 50 Approved 28-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2590 27-Dec-21 10:00 AM Block Wall 26+095 26+105 RHS Rmt 10 Approved 28-Dec-21
Block Wall 2nd lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2591 27-Dec-21 12:00 PM Pipe Culvert 137+220 - RHS Nos. 1 Approved 28-Dec-21
grade for Pipe culvert Head wall 1st lift.
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2592 27-Dec-21 10:00 AM Pipe Culvert 22+798 - LHS Nos. 1 Approved 28-Dec-21
grade for Pipe culvert Head wall 3rd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2593 27-Dec-21 9:00 AM G-S 142+568 - LHS Nos. 1 Approved 28-Dec-21
grade for GS Pier Cap (LP1)
GCL/STR/21-22/ 2594 28-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-19 17+475 - - Nos. 1 Approved 29-Dec-21
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2595 28-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 29-Dec-21
MJB Pre-Cast PSC girder G-19
Checking of Shuttering, Reinforcement and Pouring of RCC M-35 grade
GCL/STR/21-22/ 2596 28-Dec-21 11:00 AM MNB 14+710 - LHS Nos. 1 Approved 29-Dec-21
for MNB raft LA1
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2597 28-Dec-21 12:00 PM Block Wall 131+020 131+030 LHS Rmt 10 Approved 29-Dec-21
Block Wall 2nd lift.
GCL/STR/21-22/ 2598 28-Dec-21 3:00 PM MJB Checking Launching of RCC Girder for MJB RP2 to RA2. 16+475 - RHS Nos. 1 Approved 29-Dec-21
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2599 28-Dec-21 12:00 PM MNB 20+416 - BHS Nos. 1 Approved 29-Dec-21
grade for MNB Wall final lift with top haunch & slab A1,A2
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2600 28-Dec-21 11:00 AM Box Culvert 132+007 - LHS Nos. 1 Not Approved 29-Dec-21
box culvert Wall final lift with top Haunch & Slab A1,A2
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2601 28-Dec-21 9:00 AM MJB 01+085 - BHS Nos. 1 Approved 29-Dec-21
grade for MJB Pier shaft 7th Lift P6 (ACC Link Road)
Checking of reinforcement, shuttering and pouring of RCC M-25 grade for
GCL/STR/21-22/ 2602 28-Dec-21 12:00 PM C.F.Wall 22+770 22+780 LHS Rmt 10 Approved 29-Dec-21
Stem and Counterfort wall 9th lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2603 28-Dec-21 9:00 AM MJB 24+635 - RHS Nos. 1 Not Approved 29-Dec-21
grade for MJB Pier cap (RP1)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2604 28-Dec-21 12:00 PM R.Wall 16+602 16+612 LHS Rmt 10 Approved 29-Dec-21
Retaining Wall 6th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2605 28-Dec-21 10:00 AM R.Wall 136+360 136+370 RHS Rmt 10 Approved 29-Dec-21
Retaining Wall 7th Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2606 28-Dec-21 9:00 AM R.Wall 136+370 136+380 RHS Rmt 10 Approved 29-Dec-21
Retaining Wall 7th Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2607 28-Dec-21 10:00 AM Box Culvert 19+585 - LHS Nos. 1 Approved 29-Dec-21
box culvert Wall final lift with top Haunch & Slab A1,A2
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2608 28-Dec-21 9:00 AM Block Wall 130+710 130+730 LHS Rmt 20 Approved 29-Dec-21
Concrete Block Wall
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2609 28-Dec-21 9:00 AM Block Wall 26+075 26+095 RHS Rmt 20 Approved 29-Dec-21
Block Wall 4th lift.

Page 8 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2610 28-Dec-21 12:00 PM Block Wall 126+650 126+700 LHS Rmt 50 Approved 29-Dec-21
Block Wall final lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2611 28-Dec-21 10:00 AM Block Wall 20+450 20+500 RHS Rmt 50 Not Approved 29-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2612 28-Dec-21 11:00 AM Block Wall 26+095 26+105 RHS Rmt 10 Approved 29-Dec-21
Block Wall 3rd lift.
GCL/STR/21-22/ 2613 28-Dec-21 9:00 AM Pipe Culvert Laying of GSB Material for pipe Bedding 137+220 - RHS Nos. 1 Approved 29-Dec-21
GCL/STR/21-22/ 2614 28-Dec-21 12:00 PM Pipe Culvert Checking of Pipe laying and jointing NP.4 Hume Pipe of 1200 mm dia 137+220 - RHS Nos. 1 Approved 29-Dec-21
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2615 28-Dec-21 2:00 PM G-S 142+568 - RHS Nos. 1 Not Approved 29-Dec-21
grade for GS Pier Cap (RP1)
GCL/STR/21-22/ 2616 29-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-20 17+475 - - Nos. 1 Approved 30-Dec-21
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2617 29-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 30-Dec-21
MJB Pre-Cast PSC girder G-20
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2618 29-Dec-21 9:00 AM Block Wall 131+020 131+030 LHS Rmt 10 Approved 30-Dec-21
Block Wall 3rd lift.
Checking of Layout excavation, level and Laying of PCC M-15 for box
GCL/STR/21-22/ 2619 29-Dec-21 10:00 AM R.Wall 20+169 - RHS Nos. 1 Approved 30-Dec-21
culvert Return wall (A1&A2)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2620 29-Dec-21 11:00 AM Box Culvert 132+007 - LHS Nos. 1 Approved 30-Dec-21
box culvert Wall final lift with top Haunch & Slab A1,A2
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2621 29-Dec-21 11:00 AM MJB 01+085 - BHS Nos. 1 Approved 30-Dec-21
grade for MJB Pier shaft 8th Lift P6 (ACC Link Road)
Checking of reinforcement, shuttering and pouring of RCC M-25 grade for
GCL/STR/21-22/ 2622 29-Dec-21 9:00 AM C.F.Wall 22+770 22+780 LHS Rmt 10 Not Approved 30-Dec-21
Stem and Counterfort wall 10th lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2623 29-Dec-21 10:00 AM MJB 24+635 - RHS Nos. 1 Approved 30-Dec-21
grade for MJB Pier cap (RP1)
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2624 29-Dec-21 9:00 AM R.Wall 16+602 16+612 LHS Rmt 10 Approved 30-Dec-21
Retaining Wall 7th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2625 29-Dec-21 11:00 AM R.Wall 136+360 136+370 RHS Rmt 10 Approved 30-Dec-21
Retaining Wall final Lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2626 29-Dec-21 12:00 PM R.Wall 136+370 136+380 RHS Rmt 10 Approved 30-Dec-21
Retaining Wall final Lift
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2627 29-Dec-21 10:00 AM MJB 23+100 - BHS Nos. 1 Not Approved 30-Dec-21
grade for MJB Pier cap (P6)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2628 29-Dec-21 11:00 AM Block Wall 130+710 130+730 LHS Rmt 20 Approved 30-Dec-21
Block Wall 1st lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2629 29-Dec-21 12:00 PM Block Wall 26+075 26+095 RHS Rmt 20 Approved 30-Dec-21
Block Wall 5th lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2630 29-Dec-21 12:00 PM MJB 20+800 - RHS Nos. 1 Not Approved 30-Dec-21
grade for MJB Abutment Shaft 9th Lift (RA1)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2631 29-Dec-21 3:00 PM Block Wall 20+450 20+500 RHS Rmt 50 Approved 30-Dec-21
Block Wall 3rd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2632 29-Dec-21 9:00 AM Block Wall 26+095 26+105 RHS Rmt 10 Approved 30-Dec-21
Block Wall 4th lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-35
GCL/STR/21-22/ 2633 29-Dec-21 9:00 AM R.Wall 20+169 - LHS Nos. 1 Not Approved 30-Dec-21
grade for Box Culvert Return wall 3rd Lift
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2634 29-Dec-21 12:00 PM Pipe Culvert 137+220 - RHS Nos. 1 Not Approved 30-Dec-21
grade for Pipe culvert Head wall 2nd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2635 29-Dec-21 10:00 AM G-S 142+568 - RHS Nos. 1 Not Approved 30-Dec-21
grade for GS Pier Cap (RP1)
Checking of layout excavation, level and laying of PCC M-15 for MJB
GCL/STR/21-22/ 2636 29-Dec-21 9:00 AM MJB 141+100 - RHS Nos. 1 Approved 30-Dec-21
Approach slab (A1 ,A2)
GCL/STR/21-22/ 2637 29-Dec-21 11:00 AM MJB Checking of Elongation for Stressing of Girder 1 & 2(A1-P1) 20+800 - LHS Nos. 1 Approved 30-Dec-21
GCL/STR/21-22/ 2638 30-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-21 17+475 - - Nos. 1 Approved 31-Dec-21
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2639 30-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 31-Dec-21
MJB Pre-Cast PSC girder G-21

Page 9 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2640 30-Dec-21 10:00 AM Block Wall 131+020 131+030 LHS Rmt 10 Not Approved 31-Dec-21
Block Wall 4th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2641 30-Dec-21 9:00 AM R.Wall 20+169 - RHS Nos. 1 Not Approved 31-Dec-21
Return Wall Raft for Box Culvert A1,A2
Checking of layout excavation, level and laying of PCC-M15 for Plum
GCL/STR/21-22/ 2642 30-Dec-21 11:00 AM Block Wall 130+810 130+825 LHS Rmt 15 Approved 31-Dec-21
Concrete Block Wall
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2643 30-Dec-21 9:00 AM MJB 01+085 - BHS Nos. 1 Approved 31-Dec-21
grade for MJB Pier shaft 9th Lift P6 (ACC Link Road)
Checking of reinforcement, shuttering and pouring of RCC M-25 grade for
GCL/STR/21-22/ 2644 30-Dec-21 9:00 AM C.F.Wall 22+770 22+780 LHS Rmt 10 Not Approved 31-Dec-21
Stem and Counterfort wall 10th lift
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2645 30-Dec-21 12:00 PM R.Wall 16+602 16+612 LHS Rmt 10 Approved 31-Dec-21
Retaining Wall final Lift
Checking of Reinforcement, Shuttering & Pouring of Concrete RCC M-40
GCL/STR/21-22/ 2646 30-Dec-21 11:00 AM MNB 18+972 - RHS Nos. 1 Not Approved 31-Dec-21
grade for MNB Deck Slab (RA1-RA2)
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2647 30-Dec-21 10:00 AM MJB 23+100 - BHS Nos. 1 Approved 31-Dec-21
grade for MJB Pier cap (P6)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2648 30-Dec-21 9:00 AM Block Wall 130+710 130+730 LHS Rmt 20 Approved 31-Dec-21
Block Wall 2nd lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2649 30-Dec-21 10:00 AM Block Wall 26+075 26+095 RHS Rmt 20 Approved 31-Dec-21
Block Wall final lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2650 30-Dec-21 12:00 PM MJB 20+800 - RHS Nos. 1 Not Approved 31-Dec-21
grade for MJB Abutment Shaft 9th Lift (RA1)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2651 30-Dec-21 10:00 AM Block Wall 20+450 20+500 RHS Rmt 50 Approved 31-Dec-21
Block Wall 4th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2652 30-Dec-21 11:00 AM Block Wall 26+095 26+105 RHS Rmt 10 Approved 31-Dec-21
Block Wall 5th lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-35
GCL/STR/21-22/ 2653 30-Dec-21 9:00 AM R.Wall 20+169 - LHS Nos. 1 Approved 31-Dec-21
grade for Box Culvert Return wall 3rd Lift
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2654 30-Dec-21 12:00 PM Pipe Culvert 137+220 - RHS Nos. 1 Approved 31-Dec-21
grade for Pipe culvert Head wall 2nd lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-30
GCL/STR/21-22/ 2655 30-Dec-21 10:00 AM G-S 142+568 - RHS Nos. 1 Approved 31-Dec-21
grade for GS Pier Cap (RP1)
Checking of Reinforcement, shuttering and concrete pouring M-30 grade
GCL/STR/21-22/ 2656 30-Dec-21 9:00 AM MJB 141+100 - RHS Nos. 1 Approved 31-Dec-21
for MJB Approch Slab A1,A2
Checking of Layout excavation, level and Laying of PCC M-15 for
GCL/STR/21-22/ 2657 30-Dec-21 11:00 AM R.Wall 20+610 20+620 LHS Rmt 10 Approved 31-Dec-21
Retaining wall.
GCL/STR/21-22/ 2658 31-Dec-21 9:00 AM MJB Checking of Reinforcement and Profile of MJB PSC girder G-22 17+475 - - Nos. 1 Approved 01-Jan-22
Checking of Reinforcement, Shuttering & Pouring of RCC M-50 grade for
GCL/STR/21-22/ 2659 31-Dec-21 5:00 PM MJB 17+475 - - Nos. 1 Approved 01-Jan-22
MJB Pre-Cast PSC girder G-22
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2660 31-Dec-21 10:00 AM Block Wall 131+020 131+030 LHS Rmt 10 Approved 01-Jan-22
Block Wall 4th lift.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2661 31-Dec-21 9:00 AM R.Wall 20+169 - RHS Nos. 1 Not Approved 01-Jan-22
Return Wall Raft for Box Culvert A1,A2
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2662 31-Dec-21 9:00 AM Block Wall 130+810 130+825 LHS Rmt 15 Approved 01-Jan-22
Block Wall 1st lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-40
GCL/STR/21-22/ 2663 31-Dec-21 11:00 AM MJB 01+085 - BHS Nos. 1 Not Approved 01-Jan-22
grade for MJB Pier shaft 10th Lift P6 (ACC Link Road)
Checking of reinforcement, shuttering and pouring of RCC M-25 grade for
GCL/STR/21-22/ 2664 31-Dec-21 9:00 AM C.F.Wall 22+770 22+780 LHS Rmt 10 Not Approved 01-Jan-22
Stem and Counterfort wall 10th lift
GCL/STR/21-22/ 2665 31-Dec-21 12:00 PM MJB Checking of Elongation for Stressing of Girder-3 (A1-P1) 20+800 - LHS Nos. 1 Approved 01-Jan-22
Checking of Reinforcement, Shuttering & Pouring of Concrete RCC M-40
GCL/STR/21-22/ 2666 31-Dec-21 11:00 AM MNB 18+972 - RHS Nos. 1 Approved 01-Jan-22
grade for MNB Deck Slab (RA1-RA2)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2667 31-Dec-21 10:00 AM Block Wall 130+710 130+730 LHS Rmt 20 Approved 01-Jan-22
Block Wall 3rd lift.
GCL/STR/21-22/ 2668 31-Dec-21 10:00 AM MJB Checking of Elongation for Stressing of Girder-1,2,3 (A1-P1) 20+800 - RHS Nos. 1 Approved 01-Jan-22

Page 10 of 11
Structure RFI Status Summary for the Month of December-2021
Requested Dated: 26-Dec-21

Inspection Inspection Chainage


RFI No. Item Description of Work Side Unit Length (M) Status Status Date Remarks
Date Time
From To
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-35
GCL/STR/21-22/ 2669 31-Dec-21 12:00 PM MJB 20+800 - RHS Nos. 1 Approved 01-Jan-22
grade for MJB Abutment Shaft 9th Lift (RA1)
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2670 31-Dec-21 11:00 AM Block Wall 20+450 20+500 RHS Rmt 50 Not Approved 01-Jan-22
Block Wall 5th lift.
Checking of shuttring and pouring of PCC M-15 grade for Plum Concrete
GCL/STR/21-22/ 2671 31-Dec-21 1:00 PM Block Wall 26+095 26+105 RHS Rmt 10 Approved 01-Jan-22
Block Wall final lift.
Checking of Reinforcement, Shuttering & Pouring of concrete RCC M-35
GCL/STR/21-22/ 2672 31-Dec-21 11:00 AM R.Wall 20+169 - LHS Nos. 1 Not Approved 01-Jan-22
grade for Box Culvert Return wall 4th Lift
GCL/STR/21-22/ 2673 31-Dec-21 12:00 PM MJB Checking Launching of RCC Girder for MJB RP1 to RP2. 16+475 - RHS Nos. 1 Approved 01-Jan-22
Checking of Reinforcement, Shuttering & pouring of Concrete RCC M-20
GCL/STR/21-22/ 2674 31-Dec-21 10:00 AM Pipe Culvert 137+220 - RHS Nos. 1 Approved 01-Jan-22
grade for Pipe culvert Encasing.
Checking of shuttring, reinforcement and pouring of RCC M-35 grade for
GCL/STR/21-22/ 2675 31-Dec-21 9:00 AM R.Wall 20+610 20+620 LHS Rmt 10 Approved 01-Jan-22
Return Wall Raft for Box Culvert A1,A2

Page 11 of 11