Critical Path Method (Replacement of Tiles)
Critical Path Method (Replacement of Tiles)
Critical Path Method (Replacement of Tiles)
A MOBILIZATION - B 1 0 1 0 1 0 0
B SITE PREPARATION A C 1 1 2 1 2 0 0
C LAYOUT B D 1 2 3 2 3 0 0
E TILE LAYING D F 4 5 9 5 9 0 0
H SITE CLEARING G I 1 12 13 12 13 0 0
I DEMOBILIZATION H - 1 13 14 13 14 0 0
LEGEND: E A E
A = ACTIVITY ES = EARLY START LS = LATE START
D
= ACTIVITY EF = EARLY FINISH LF = LATE FINISH S F CRITICAL PATH = A-B-C-D-E-F-G-H-I-J-K
L D L
S F
0 A 1 B 2 C 3 D 5 E 9 F 1 G 1 1 1
H I
1 2 3 4
0 1 1 1 2 1 3 2 5 4 9 2 1 1 1 1 1 1 1
1 2 3 4