Critical Path Method (Replacement of Tiles)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

DMCJ GLASS AND ALUMINUM SUPPLY

JUAN LUNA ST. TARLAC CITY 0925-776-0806/606-7137

PROJECT: REPLACEMENT OF WALL & FLOOR TILES


LOCATION: MALIWALO, TARLAC CITY, TARLAC

CRITICAL PATH METHOD


ACTIVITIES DESCRIPTION PREDECESSOR SUCCESSOR DURATION EARLY START (ES) EARLY FINISH (EF) LATE START (LS) LATE FINISH (LF) FREE FLOAT (FF) TOTAL FLOAT (TF)

A MOBILIZATION - B 1 0 1 0 1 0 0

B SITE PREPARATION A C 1 1 2 1 2 0 0

C LAYOUT B D 1 2 3 2 3 0 0

D DEMOLITION & CHIPPING C E 2 3 5 3 5 0 0

E TILE LAYING D F 4 5 9 5 9 0 0

F INSTALLATION OF FIXTURES & E G 2 9 11 9 11 0 0


FITTINGS
G PAINTINGS F H 1 11 12 11 12 0 0

H SITE CLEARING G I 1 12 13 12 13 0 0

I DEMOBILIZATION H - 1 13 14 13 14 0 0

LEGEND: E A E
A = ACTIVITY ES = EARLY START LS = LATE START
D
= ACTIVITY EF = EARLY FINISH LF = LATE FINISH S F CRITICAL PATH = A-B-C-D-E-F-G-H-I-J-K
L D L
S F
0 A 1 B 2 C 3 D 5 E 9 F 1 G 1 1 1
H I
1 2 3 4
0 1 1 1 2 1 3 2 5 4 9 2 1 1 1 1 1 1 1
1 2 3 4