Machinery movement for The CELL Plan Duration Complete Actual (beyond plan) Complete (beyond plan)

MOVEMENT DETAILS Start Location


End Location WHO 08.06.2021 09.06.2021 10.06.2021 11.06.2021 12.06.2021 13.06.2021 14.06.2021 15.06.2021 16.06.2021 17.06.2021 18.06.2021 19.06.2021 20.06.2021 21.06.2021 22.06.2021
1 to 2 Planning to move the engineering office within the production to allow space for PTK PR2000 Line 7. 1/1-C34 1/1-C11 MA & IR
Bulding Maintenance Assessment for fitness, suitability and requirements for the transitioning. - 1/1-C11 DW
H&S Assessment for fitness, suitability and requirements for the transitioning. - 1/1-C11 AB
Removing spare machinery from the new Engineering Office and moving it upstairs. - 1/1-C11 IR & MA
Fitting Ethernet Sockets in the new engineering room & workshop. - 1/1-C11 DW
Completing the engineering office move by phisicaly moving equipment. - 1/1-C11 MA
3 to 4 Planning to remove PTK PR2000 Line 7 from the CELL and placing it in the old engineering office. 1/1-C06 1/1-C34 MA & IR
Electrical Assessment for suitability and requirements to host the PTK PR2000 Line 7. - 1/1-C34 Roy
Hoover Line Assessment for suitability, materials and labour to be extended in the engineering room. - 1/1-C34 MA, DW & AB
Fitting a 32 Amper Socket in the engineering room to supply electricity to the PTK PR2000 Line 7. - 1/1-C34 Roy
Extending the Hoover Line into the engineering office to supply air to the PTK PR2000 Line 7. - 1/1-C34 DW & AB
Phisicaly removing PTK PR2000 Line 7 from the CELL and placing it in the old engineering office. 1/1-C06 1/1-C34 MA & IR
5 to 6 Planning to move King 2 upstairs, to allow space for the Bosch 3005 to be removed from the CELL. 1/1-C24 1/2-C04 MA, DP & IR
Clearing the Holding Area in Blending to accommodate the King 2. TBC IR
Moving King 2 upstairs to allow space for Bosch 3005. 1/1-C24 1/2-C04 MA & DP
7 to 8 Planning to remove the Bosch 3005 from the CELL and placing it in the old King 2's room. 1/1-C44 1/1-C24 MA, DW, IR & Roy
Electrical Assessment for suitability and requirements to host the Bosch 3005. - 1/1-C24 Roy
Hoover Line Assessment for suitability, materials and labour to be extended in the engineering room. - 1/1-C34 MA, DW & AB
Fitting a 32 Amper Socket in the engineering room to supply electricity to the Bosch 3005. - 1/1-C24 Roy
Extending the Hoover Line into the engineering office to supply air to the PTK PR2000 Line 7. - 1/1-C24 DW & AB
Moving the Bosch 3005 out of the CELL and placing it in the old King 2's room. 1/1-C44 1/1-C24 MA
Hardwirring the newly moved Bosch 3005 according to 18th Edition of Wiring Regulations. - 1/1-C24 Roy
9 to 10 Planning to move the PTK PR2000 Line 4 within the CELL into the old Bosch 3005's room. 1/1-C07 1/1-C44 MA
Assessment for suitability and requirements of the Bosch 3005 room to host the PTK PR2000 Line 4. - 1/1-C44 MA
Phisically moving the PTK PR2000 Line 4 into the old Bosch's room. 1/1-C07 1/1-C44 MA
11 to 12 Planning to move the ORB 1000, from upstairs, inside the CELL. 1/2-C04 1/1-C07 MA, DP & IR
HACCP Assessment for suitability of mounting a door between the new Splitting and Blending Rooms. 1/1-C06 1/1-C07 NF
An additional door to be considered for the new Blending Room. - 1/1-C07 AB
Phisically moving the ORB 1000 inside the CELL. 1/2-C04 1/1-C07 MA & DP
13 to 14 Moving the Splitting room, from upstairs, inside the CELL. 1/2-C09 1/1-C06 IR