Bid Addendum Report

Khando River Training Project

Khando River Training Project


Rajbiraj
Rajbiraj, Saptari
Nepal

Addendum No: 3

Published On: 10-02-2020 22:00

Invitation No: KRMP/Triyuga/RB-01/076-077

Dated On: 13-01-2020 10:00


Following changes are made in the bid document

Chapter: General Information


Sl. No. Relavant Clause Existing Clause Modified Clause
No / Name

1 Clarification 2020-02-10 06:00:00 2020-02-10 22:00:00


Submission Date
Chapter: Bill of Quantities

1 Provisional Sum
Procument Item Details

SL. Unit Rate(in


Item Description Unit Quantity Amount(in NPR)
No NPR)

1 Before Execution of works Insurance of Works as per P.S. 1 83305 83305


condition of Contract(0.15%)
2 Before Execution of works Third party Insurance as per P.S. 1 83305 83305
condition of Contract( 0.15% )
3 Before Execution of works Insurance against accident of P.S. 1 83305 83305
workmen as per condition of Contract ( 0.15% )
4 As Built drawing submittrd three hard copies and P.S. 1 27768 27768
electronic soft copies . ( 0.05 % )
5 During the working Period the compaction and other P.S. 1 30000 30000
necessary tests as per condition of contract .
2 Construction work
2.1 River Training Work

2.1.1 General Item

Procument Item Details

SL.
Item Description Unit Quantity Bidder's Rate(NPR) Bidder's Rate (in words) Total Amount(NPR)
No

Cutting, uprooting & disposal of


1 grass with light compaction, m2 19893.0
leveling & Clearing the site.
Earth work in filling for
construction of embankment by
local available borrow earth in
2 m3 33818.1
specified layer with proper
compaction etc. with all lead
and lift all complete.
Supplying and Laying 50 cm
thick local available sweet Soil
3 m3 8396.94
over the Embankment (slope
and top ) all complete.
Earth work in excavation for
launching apron in gravel mixed
4 m3 4222.8
soil with all lead and lift etc all
complete .
Supply and filling of boulder
into gabion boxes including
5 placing ,packing, tying etc m3 6523.2
including lead and lift all
complete.
Supply and weaving
(handmade) of 10 SWG (heavy
zinc coated) rectangular gabion
6 boxes mesh size m2 34869.6
100mm*100mm with two way
knotted including wire cutting ,
netting etc all complete.
Procument Item Details

SL.
Item Description Unit Quantity Bidder's Rate(NPR) Bidder's Rate (in words) Total Amount(NPR)
No
Supply of Machine Made
gabion box of 3mm HZC
(Heavy zink Coated) SWG GI
Wire with Hexagonal Mesh
7 Size 10cm *12cm,Mechanically m2 17589.6
selvedge with 3.9mm wire and
lacing wire 2.64mm, ( Gabion
box with 2 diaphrams )
including all complete.
Supply & Laying Geo.textile
Medium type TS 30 in the
8 slope & launching apron before m2 7329.0
laying gabion boxes all
complete .
Grass sodding works including
sod cutting transporting,placing
9 m2 15341.14
in position & water sprinkling
all complete.
Diversion work during the
10 L.S. 1.0
completion of the works
Khando River Management Project
Rajbiraj, Saptari.

Addendum No: 3
Published On: 10-02-2020 22:00

This is informed that to all concerned bidder that the following addendum-3 has
been made for contract no: KRMP/Triyuga/RB-01/076-077 issued by Khando
River management Project, Rajbiraj invitation of bids published in Nagrik dainik
on 13th January 2020.
The following Changes are made
1 The Revenue Code Number 14227 has been corrected to 14229.
2. The Office Code Number 308011502 has been corrected to 308031502.

3. Section II Bid Data Sheet


ITB.-40.1-Line of Credit / Cash flow Shall be of Nrs.1,40,00,000.00

Project Manager