METHOD STATEMENT NIGHT SHIFT

a. Worker
1. Supervisor/Site Enggineer
2. Safety man
3. Labour
4. worker
b. Equipment
1. Drill Machine
2. Genset
3. Plat 1.5 x 3 M, thickness 20 mm
4. Boom truck
c. Method statement
1. Preparatory work is done by checking generators, drilling machines etc. condition of truck and
boom truck at 08.00 PM – 09.00 PM
2. determination of the work area on the west and east sides of the Pintu Besar Selatan
3. workers carry out tile and carsteen material removal activities at 09.00 PM
4. the next job is dismantling the base coune until it reaches the uditch depth
5. Demolition work done up to a maximum of 03.30 AM
6. some workers carry out debris removal and boom trucks carrying plates immediately to the site
at 04.00 AM
7. boom truck lifts plate material to be placed in demolition area
8. the plate placement must be neat and precise because it will be used as a track by the building
owner for mobilization
9. the area must be neat and clean from all the remnants of work debris at 05.00