Daily Report
Contractor: CCCC Section:S2 No.: CCCC(KTP)-S2-West-1097
Remarks (Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrence’s, etc.)
-1-
中国交建卡纳普里河底隧道项目联合经理部
CCCC PROJECT MANAGEMENT BOARD OF MULTI-LANE ROAD TUNNEL UNDER THE
RIVER KARNAPUHLI CHITTAGONG-BANGLADESH
Daily Report
Contractor: CCCC Section:S2 No.: CCCC(KTP)-S2-West-1097
PART KARNAPHULI TUNNEL Date:01.01.2021
II:
Night
PROJECT
Shift Location: The left line of Shield Tunnels Weather:Sunny
Chinese NO. Bangladeshi NO.
NO. Manpower Su Su
1 2 3 4 5 6 1 2 3 4 5 6
m m
Managers/En
1 1 4 8 13 1 5 6
gineers
Skillful
2 9 9 2 6 10 18
Workers
3 Labors 10 5 15 5 13 23 41
Equipment NO.
NO. Equipment Types
1 2 3 4 5 6 Sum
1 Forklift CPCD35 1 1
Concrete
2 ZZ5167GJBG3815C1 4 4
Mixer
3 Dump Truck ZZ3257N3847A 1 1 2
4 Loader 955N 1 1
Mixing
5 HZS60Q 1 1
Station
QY55KA_Y/ MQ30t-38m-
6 Crane 1 1 2
10m/ QUY500
7 Excavator LGC920EZCHC109781 1 1
8 Crane MQ30-38 1 1
Description of Work Performed Today:
NO Description of Completion
Location Accumulation Remarks
. Works Quantity
Remarks (Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrence’s, etc.)
-2-