MS-E011-ALF-MS For Installation of LVAC Panels
MS-E011-ALF-MS For Installation of LVAC Panels
MS-E011-ALF-MS For Installation of LVAC Panels
(Electrical)
AMENDMENTS
Prepared by
Reviewed by
Approved by
Method Statement for
Erection and Installation Effective Date :
LVAC Panels Document No : MS-011 -
Electrical
Revision No :0
Page No : Page 2 of 7
Approved By :
SUPPLY AND INSTALLATION OF NEW 220/33kV GRID
PROJECT
STATION AT GHANTOOT –N2107 LOT 1A
CONTENTS
1. Activity
2. Introduction
3. Terminology
6. Sequence of activities
7. Requirements
7.2. Trainings
8. Emergency procedures
9. References
10. Attachments
Method Statement for
Erection and Installation Effective Date :
LVAC Panels Document No : MS-011 -
Electrical
Revision No :0
Page No : Page 3 of 7
Approved By :
SUPPLY AND INSTALLATION OF NEW 220/33kV GRID
PROJECT
STATION AT GHANTOOT –N2107 LOT 1A
1) Activity
Installation of LVAC Panels in ADDC LVAC Room and TRANSCO LVAC Room as per the approved GA and panel
support Detailed drawing.
2) Introduction
The Panels will be installed on to the respective Panel Support structures by using Pallet Trolley.
3) Terminology
Hazards
Fall of materials
Slip / trip / fall – same level
Slip / trip / fall – Heights
Hand tools
Crane Hazards
Manual Handling
Usage of crane
Toolbox talks to be given to the workmen by concerned supervisor about the hazards and the precautions to be
taken.
Method Statement for
Erection and Installation Effective Date :
LVAC Panels Document No : MS-011 -
Electrical
Revision No :0
Page No : Page 4 of 7
Approved By :
SUPPLY AND INSTALLATION OF NEW 220/33kV GRID
PROJECT
STATION AT GHANTOOT –N2107 LOT 1A
All openings through which persons my fall down shall be covered appropriately. Skilled and experienced persons
shall be involved in the activity.
Area to be cordoned off and warning signs to be displayed.
If any temporary access platform is provided, it shall be properly erected.
All lifting gears (D-shackles, lifting belt, pallet trolley and chain pulley block) must have valid test certificate.
Tag line to be used and to be connected to the load.
Walk ways / Gangways to be kept free from small wooden blocks and cables.
Use of PPEs like heavy duty hand gloves, safety shoes, and hard hat.
While using pallet trolleys, the load shall be placed in a stable manner and the pulling action shall be gentle.
Engineer
Supervisor / Foreman
Workmen
Safety Officer
6) Sequence of activities
Site Preparation
The platform around the panel room to be arranged and clear the area of the panel access.
Check the calibration of hydraulic trolley and lifting belts D-shackles, bottle jacks.
Identify the order of panels & unpack the panels.
Level to be checked based on the approved drawings.
Panel marking to be done as per the corresponding drawings.
Crane entry permits requirements to be fulfilled before commencing lifting activities wherever applicable.
Obtain clearance from other departments for panel erection.
Control measures stated in risk assessment to be complied.
Openings should be covered & barricaded near the panel movements.
Checking for proper fitting & lifting eyebolts, tightening of locking screw ends.
Installation of Panels
Method Statement for
Erection and Installation Effective Date :
LVAC Panels Document No : MS-011 -
Electrical
Revision No :0
Page No : Page 6 of 7
Approved By :
SUPPLY AND INSTALLATION OF NEW 220/33kV GRID
PROJECT
STATION AT GHANTOOT –N2107 LOT 1A
Install the panel support structure in the location marked in the respective room where applicable.
Unpack the panels and shift it to the offloading platform using mobile crane
Lift the Panels using Monorail Hoist and lift into the corresponding Floor and position it over the hydraulic trolley.
Panels to be moved by hydraulic trolley (wherever applicable) up to its final location.
Lift the panel slowly and place the panels on foundation or channel supports.
Check the level & positioning of panels on foundation or channel supports.
Clean the panel with vacuum cleaner.
7) Requirements
7.2 Training
Risk assessment shall be reviewed site specifically prior to work start to ensure the existing controls are
adequate.
7.4 PPEs
Safety helmets, safety shoe, goggles, gloves and coverall, safety harness
Manpower
Supervisor/foreman - 01 No
Technicians - Fitters - 02Nos
Technicians – Electricians - 02 Nos
Rigger - 01 No
Method Statement for
Erection and Installation Effective Date :
LVAC Panels Document No : MS-011 -
Electrical
Revision No :0
Page No : Page 7 of 7
Approved By :
SUPPLY AND INSTALLATION OF NEW 220/33kV GRID
PROJECT
STATION AT GHANTOOT –N2107 LOT 1A
Helpers/Standby person -03 Nos
Equipment / tools
Hydraulic crane 25 ton for offloading of panels, Nylon belts Range: 02 meter, 1.5 ton, D-shackles, Nail bar / Crow
bar for breaking package and leveling, Pallet Trolley Range: 02 Ton, Wooden Planks for placing panels, Roller
pipes for moving panels, Fitter tool box, Ratchet box, Torque wrench, Bottle jack Range: 05 Ton, Sprit level for
level checking, Electrician tool box, Vacuum machine for cleaning.
First aid facilities with trained first aider and fire fighter shall be made available.
8) Emergency procedures
In case of fire
9) References
TRANSCO Specification
Approved Panel arrangement drawings
Factory Acceptance Test Report (FAT)
10) Attachments