CURRICULUM VITAE – PROJECT CONTROL/PROJECT ENGINEER

Name: C MANI VACHAGAN

Date of Birth: April 06,1964

Education: Masters Degree in Chemical Engineering, 1991


AC Technology, Guindy
Anna University, Chennai, India

Professional Affiliation: Associate Member of Institution Engineers

Nationality: Indian

Contact no:

Passport no: (Valid upto Jan 2009)

VISA Status: Valid UAE residence visa

E mail address vach21@yahoo.com

Computer proficiency Primavera, MS Project, MS Excel, Access, Word

Total years of Experience 15 years

CURRENT RESPONSIBILITIES

Project Control Manager for 4Th Train sweetening and stabilisation project,
Karachaganak,Kazaksthan. Responsible for Planning, Scheduling and Progress
Monitoring for Project consisting of Oil treatment plant and Gas treatment plant

KEY FUNCTIONS HANDLED

Planning / scheduling with Primavera, Project Management, Engineering Co-


ordination, Manhour control, Invoicing and Progress reporting for EPC Projects in
Oil & Gas and Petrochemical field.

C.Manivachagan Page 1 of 5
SUMMARY:

¾ Developed, updated and monitored CPM schedules Level-1, Level-2 & Level-3
using Primavera for EPC projects in Oil & Gas and Petrochemical plants.
Schedules prepared for Green field projects and Revamp projects involving
Multi-disciplinary activities. Critical path analysis carried out for monitoring the
project and delay claims.

¾ Prepared and updated S-Curves, Histograms, Engineering & Procurement


Document registers. Developed Progress Measurement system based on Man-
hours/Cost and monitored progress.

¾ Review of Construction Subcontractor’s and Vendors’ progress and


schedules to arrive at recovery plans needed to bring the progress on track.

¾ Prepared detailed Construction schedules, Commodity curves, Man-hour


estimates for Construction of Oil & gas and Petrochemical facilities

¾ Prepared detailed Commissioning schedules for Oil & Gas projects. Familiar
with ICAPS.

¾ Man-hour control, Invoicing and Cash flow preparation for EPC projects

¾ Change management, Claim analysis and What if analysis for the project
based on the project’s present status

¾ Monthly/Weekly Progress reports as scheduling, report writing summarising


areas of concerns & corrective actions / remedies as per contractual
requirement, approval from project management & final submission to client

¾ Supervision of Planning engineers, Schedulers & various Projects control staff.

¾ Attending the weekly / monthly meeting with Client to appraise Client about
the project progress & to discuss various issues concerning the actual progress,
timely completion of Project etc.

¾ Experience in Project Management and Project engineering for


Petrochemical projects. Coordinated engineering activities, reviewed
engineering documents of various disciplines, resolved interface issues,
monitored document control activities and took up control of engineering man-
hours.

¾ Worked as Shift-in-charge for NPK Fertiliser complex consisting of Sulphuric


acid, Phosphoric acid, Fertiliser and utilities including Bagging plant.

C.Manivachagan Page 2 of 5
Details of Experience and Projects handled

Petrofac International Ltd.


Shrajah

June 2001 – to Date


• Project Control Manager – Aug 2006-To date
• Karachaganak 4th Train stabilization &
sweetening project, Kazhakisthan
Client :AGIPKCO
Oil Treatment plant & Sour Gas Compression.
Responsible for Project Schedule, Progress
Measurement System, Progress Reporting for
EPC Project

• Project Control Manager – Oct 2004-To date


• Kashagan Field Experimental Development
Progarm , Kazhakisthan
514 M USD Project
Oil Treatment plant(165kopd) , Gas treatment
plant, Sulphur plant.
Client : AGIPKCO with ECMT from KBR
Responsible for Project Schedule, Progress
Measurement System, Progress Reporting for
Engineering & Procurement activities
• Lead Planner – Nov 2001-Oct 2004
• Dorood Project Onshore Facilities, Kharg
Island
Water injection ,Oil treatment, Gas injection,
Pipeline facilities
Elf Petroleum Iran(Total)
250 Million USD
Responsible for Development of Project Schedule,
Progress Measurement System, Progress Reporting
and Invoicing for EPC Contract from Engg stage to
Commissioning stage
Responsible for leading the Construction &
Commissioning planning team.
Involved in detailed monitoring of Engg dwgs
through Technical Document Register, Man-hour
control and Disciplinewise Productivity.
• Planning engineer – June 2001-Nov 2001
• Munga Field Production Facility, Munga
GNPOC, Sudan
25 Million USD
Responsible for Development of Project Schedule,
Progress Measurement System, Progress Reporting
and Invoicing for EPC Contract

Howard Finley Al Khaleej Planning Engineer

C.Manivachagan Page 3 of 5
Apr,2000 – May,2001 Responsible for Preparation of Technical
specifications, Inventory data, Spare Part
Identification, Conversion of data for CMMMS
package for Umm Al Nar Power plant, Abu dhabi
for ADWEA Cataloguing Project.

DB IDEA Ltd, Chennai Manager (Projects & Services)


Aug,94-Mar,2000 Responsible for Project Management, Engineering
Co-ordination, Planning & Scheduling for
Petrochemical Projects.
Involved in Review of Engineering
drawings/Documents, Co-ordination among all
engineering disciplines, Co-ordination with
Procurement and Construction for the
purpose of Engineering deliverables, Change
order preparation and Man-hour control.

• Project Engineer
• Bonny Terminal Integration Project, Nigeria
Bouyges Offshore Services
Responsible for Engineering co-ordination of
Pre-bid Engineering contract

• Project Engineer
• Polyethylene plant revamp Project, Hazira
Reliance Polyethylene Ltd
Project Mgmt & Engineering Co-ordination

• Planning Engineer
• Dukhan Consolidated Facilities Upgradation
Project
Qatar General Petroleum Corporation, Doha
Responsible for Planning for shut down work ,
pre-commissioning and Commissioning of
Khatiya Main Degassing unit, Dukhan Oil field

• Project Engineering Manager


• C4 Hydrogenation Unit, Haldia
Haldia Petrochemicals Ltd, Haldia
Responsible for Project Engineering Co-
ordination,
Co-ordination with Procurement &
Construction, Field Engineering activities of
EPCM Contract
Rupees 220 Million
C.Manivachagan Page 4 of 5
• Project Engineering Manager
• Pyrolysis Gasoline Hydrogenation Unit,
Haldia
Lurgi India Company Ltd
Responsible for Project Management and
Engineering Co-ordination of Detailed
Engineering Contract
Rs 320 Million

• Project Manager
• Fumed Silica Project
Chemplast, Mettur
Responsible for Project Management and
Engineering Co-ordination for EPCM Contract
Rs 100 Million

• Project Engineer
• Butadiene Revamp Project, Baroda
Indian Petrochemicals Corporation Ltd
Responsible for Co-ordination among
Engineering, Procurement and Construction
during the Construction phase of EPCM
contract. Responsible for Shut down planning
for revamp project.
Rs 500 Million

EID Parry (I) Ltd,Chennai Senior Executive(Shift)


Nov,91 – July,94 Responsible for Operation ,Maintenance and
Administrative activities for NPK Fertiliser
Complex during Shift

Pentasia Chemicals Ltd,Cuddalore Process Engineer


Aug,91 – Oct,94 Responsible for Operation of Pentaerythrosite
and Sodium Formate Plant

Ramani Chemasea Entech Systems Project engineer


Apr,91-July,91 Responsible for Line sizing for Utility lines for
Monochrotophos Project

C.Manivachagan Page 5 of 5