PT.

INSANI BARA PERKASA


Daily Report Breakdown
Bulan JUNI 2021
TANGGAL
NO CODE UNIT LOKASI B/D No NPB TGL NPB PART READY KERUSAKAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Breakdown
423 11-Apr
Mixing oil engine, Washing main frame ( completed from engine Assy
1 Dozer 02 KM 11 24/Mar/21 424 11-Apr
DZ 03/canibal ) P P P P P P P P P P P P P P P P P P P P P P P P P P P P
478 23-Apr
Boom cyl,bucket cyl,main pump,carier roller,seal crank shaft,gasket
2 EXCA 200-01 KM 11 15/Apr/21 463 20-Apr cover head,dll P P P P P P P P P P P P P P P P P P P P P P P P P P P P
3 EXCA 330-04 Embalut 12/Jun/21 059 16-Jun Top Overhaul Engine P L L L L L L L L L L L L L L L L
567 19-May
4 EXCA 330-09 KKE 10/May/21 583 21-May Bushing arm,bucket,link I,Link H,adapter tooth L L L L L L L L L L L L L L L L L L L L L L L L L L L P
620 2-Jun
610 31-May
Equalizer bar broken, Remove engine assy (canibal to Dozzer 02)
5 DOZER 03 BAR 30/May/21 progress completed Mekanik L L L L L L L L L L L L L L L L L L L L L L L L L L L L
TANGGAL TOTAL DAY PERSENTASE
PROGRESS
B.DOWN
29 30 PLANT LOGISTIK

P P 98 100% UNIT SCRAF / JUAL

P P 76 100% UNIT SCRAF / JUAL

L L 18 6% 94% Waiting Parts

P P 51 25% 75% Proses instal bucket by mekanik

Remove engine assy (canibal to Dozzer 02) progress


L L 31 6% 94% completed Mekanik,waiting part Engine dz 03
PT. INSANI BARA PERKASA
Daily Report Breakdown
Bulan JULI 2021
TANGGAL
NO CODE UNIT LOKASI B/D No NPB TGL NPB PART READY KERUSAKAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Breakdown
739 29-Jun 12-Jul
1 Dozer 02 KM 11 24/Mar/21
861 28-Jul
Mixing oil engine, Washing main frame ( completed from engine Assy DZ 03/canibal ) L L L L L L L L L L L P P P P P P P P P P P P P P P

878 30-Jul
610 31-May
Equalizer bar broken, Remove engine assy (canibal to Dozzer 02) progress completed
2 DOZER 03 BAR 30/May/21
Mekanik L L L L L L L L L L L L L L L L L L L L L L L L p p
TANGGAL TOTAL DAY PERSENTASE
PROGRESS
B.DOWN
27 28 29 30 31 PLANT LOGISTIK

P P P P L 290 34% 66% Engine dz 03 sudah terinstall di unit DZ 02,(Waiting Part)

Proses Mekanik perakitan part yg sudah datang,(ada


p p p p p 223 1% 99% penambhan part lagi)
AGUSTUS
NO CODE UNIT LOKASI B/D No NPB TGL NPB PART READY KERUSAKAN TANGGAL TOTAL DAY PERSENTASE
PROGRESS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 B.DOWN PLANT LOGISTIK
Breakdown
739 29-Jun 12-Jul
861 28-Jul Mixing oil engine, Washing main frame ( completed from engine Assy DZ
1 Dozer 02 KM 11 24/Mar/21 03/canibal ) L L L L L L P P P P P P P P P P P L L L L L L L L P P P P P P 290 34% 66% Complated Instal cover engine dan canopy
878 30-Jul
918 9-Aug
610 31-May 16-Jul
611 31-May 18-Jul
Equalizer bar broken, Remove engine assy (canibal to Dozzer 02) progress
2 DOZER 03 BAR 30/May/21 657 10-Jun 14-Jul completed Mekanik P P P P P L L L L L L L L L L P P P P P P P P P P P P P P P P 223 12% 88% Complated
796 12-Jul 18-Jul
903 5-Aug
3 Exca Hitachi 350 Fit Karyono 11/Aug/21 939 13-Aug 28-Aug Idler roller broken,control valve leak,Bucket oblak,Side plate bucket aus P P L L L L L L L L L L L L L L L L P P P P 150 4% 96% Proses Reseal control valve

30/Jul/21 Tie rod bengkok -->> DOWN tgl 3-Agust


4 CWE 01 Embalut L P P P P P P P P P P P L L L L L L L L L L L L L L L L L L L 157 6% 94% Waiting Part (LOG Embalut) Part datang 31 Agust sore
4/Aug/21 121 13-Aug Seal Crankshaft leak
1/Aug/21 Bearing Tensioner broken -->> DOWN tgl 7 Agust 21 P P P P P P P Proses pengerjaan (Susah masuk gig) Continue trun transmisi
5 CWE 02 Embalut P P L L L L L L P P P P P P P P P P 147 8% 92% lagi est 1 sept
14/Aug/21 135 16-Aug 22-Aug Dish Clutch Aus
962 19-Aug
6 CWE 208 KKE 18/Aug/21 Seal front axle leak P L L L L L L L L L L L L L 143 1% 99% Waiting Part est 1-2 sept
965 20-Aug
508 29-Apr 17-Jun Seal crankshaft broken Waiting Panel, panel di kembalikan karna tidak bisa di sett
7 TL - 04 workshop 31/May/21 L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 222 5% 95% ( pengiriman msh terkendala dari pusat Altrack akibat PPKM )
639 4-Jun 19-Jun capasitor broken est 1-2 sept
8 HARTECH 03 workshop 25/Jun/21 573 20-May 6-Jul Top Overhaul Engine P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P 197 29% 71% Waiting Mekanik (Fokus ke unit yg productif)
9 FT 01 KKE 4/Aug/21 906 6-Aug Transmisi ubnormal P P L L L L L L L L L L L L L L L L L L L L L L L L L L 157 1% 99% Wait Part
18/Aug/21 Overheat (radiator buntu) -->> Down tgl 20 Agus 21 P P P
10 LV 29 workshop p L L L L L L L 137 1% 99% Proses waranty service Radiator
24/Aug/21 987 25-Aug Radiator Bocor
READY FOR USE
1 VOLVO workshop 17 Jul 826 17-Jul 4-Aug Velg trailer,wheel hub and drum brake (bolt broken + hole bolt wrnout) L L L P 18 11% 89% RFU

668 14-Jun 3-Aug


2 CWA 06 workshop 26 Mei Fabrikasi sekat tangki & chute inlet water tank L L P P P P 72 21% 79% RFU
849 26-Jul 29-Jul
3 WP CAT 05 Fit Asi 2/Aug/21 884 3-Aug Overheat P P L L P P P 7 71% 29% RFU
4 Doosan 500-03 KKE 10/Aug/21 Trouble shooting starting relay P P P 2 100% RFU
5 Dozer D115-6 KKE 10/Aug/21 trouble shooting error 15sflh transmisi abnormal P P P 2 100% RFU
6 Hitachi 330-03 KKE 11/Aug/21 hose swipel joint bocor 2pcs P P P P 3 100% RFU
847 24-Jul 28-Jul
7 LV 29 workshop 23/Jul/21 AC Panas (Evap bocor) P P L L L L L L p p p p 23 43% 57% RFU
888 3-Aug
8 LV 37 workshop 2/Aug/21 890 4-Aug Engine sinjal,stearing keras P P L L L L L L L L p p p 12 42% 58% RFU
01 Agu Tyre no 10 bocor-->> DOWN tgl 2 Agust P P
9 CWE 07 Embalut P P P P P P P P P P P 11 100% RFU
04 Agu Tie rod bengkok
10 CWE 208 KKE 9/Aug/21 Spring Front Broken P P L L L L P 7 43% 57% RFU
11 Grader 01 workshop 28/Jul/21 863 29-Jul 1-Aug OVERHEAT L L L L L L L L L L L P P P P P 19 37% 63% RFU
800 14-Jul 16-Aug
805 14-Jul 23-Jul Rubber spring blakang broken, sacle spring depan RH,LH aus + seal final
12 CWE 10 KKE 16/Jul/21
865 29-Jul Drive rear bocor + alternator L L L L L L L L L L L P P P P L L L 34 24% 76% RFU

916 10-Aug 24-Aug


10/Aug/21 Dish Clutch slip -->> DOWN TGL 16 Agust 21 P P P P P P P
13 CWE 209 KKE p p 1 100% RFU
19/Aug/21 Spring front no 1 Broken
14 Kobelco 210-03 Seam F 4/Aug/21 680 15-Jun Line boaring attachment L L L L L L L L L L L L L L L L P 16 6% 94% RFU
15 CWE 206 KKE 11/Aug/21 Dish Clutch slip P P P P P P P P P P P 10 110% RFU
927 18-Aug
16 CWB 102 KM 11 16/Aug/21 End tie rod RH,LH - Drag link broken P L L L L P 5 40% 60% RFI
952 19-Aug
17 LV 32 workshop 14/Jul/21 806 15-Jul 11-Aug Timing belt putus,rocker arm patah L L L L L L L L L L L P P P P P P P P P P 38 29% 71% RFU
18 LV 12 workshop 26/Jul/21 855 28-Jul 11-Aug Front Axle & Suspension broken L L L L L L L L L L L P P P P P P P P P P 26 46% 54% RFU
16/Aug/21 Bolt roda RR/RH broken dan tyre no 9 bocor-->> DWN 16 Agust 21 P
19 CWB 101 KM 11 P P P 2 100% RFU
22/Aug/21 Trouble AC Panas
20 CWE 203 KKE 13/Aug/21 Dish Clutch slip P P P P P P P P P P P P P 12 108% RFU
KM 5 21/Jul/21 830 22-Jul 28-Jul Track link Putus -->> DOWN tgl 6 Agust 21 L L L L L P
21 DOZER 01 P L L L L L L L P P P P P P P 14 57% 43% RFU
Workshop 12/Aug/21 926 13-Aug 20-Aug Linning blade (Blade Worn Out)
02 Agu Tyre no 5 Bocor -->> DOWN tgl 3 Agust 21 P P
22 CWB 105 workshop P P L L L L P P P P P P 11 73% 27% RFU
20/Aug/21 972 22-Aug 26-Aug Disch clutch broken,spring broken,shipter fork patah
23 CWM 116 KM 11 21/Aug/21 987 22-Aug 26-Aug Hose AC bocor P L L L L P P P P P P 10 70% 30% RFU
24 LV 04 workshop 23/Aug/21 983 24-Aug 28-Aug Hand breake putus & KM speedometer Error P L L L L P P P P 8 63% 38% RFU
25 CWE 204 Embalut 29/Aug/21 Tyre Bocor P P P 2 100% RFU

PIC : LOG
PIC : PLANT
IN
OUT CWB 105,CWM 116,CWE 204,LV 04
PT. INSANI BARA PERKASA
Daily Report Breakdown
Bulan Nov 2021

NO CODE UNIT LOKASI B/D No NPB TGL NPB PART READY KERUSAKAN November TOTAL DAY
PERSENTASE
B.DOWN PROGRESS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 PLANT LOGISTIK

Breakdown
1014 1-Sep 22-Sep
2/Sep/21 1032 4-Sep Hyd pump low pressure -->> 7 Oct (Canibal dr GD 01) Waiting Approval management,Fip sudah ready di
gudang
1 Grader 02 km 11 1145 2-Oct L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 40 8% 93%

21/Oct/21 1231 23-Oct Valve intake cyl head broken,sael shaft impeller leak (Engine Noise)
5/Oct/21 Trouble seal adjuster track RH bocor -->> DOWN 8 Oct Prosess penghitungan biaya perbaikan by log dan
2 HITACHI 09 KKE P P P P P P P P P P P P P P P P L L L L L L L L L L L L L L 40 68% 33% approval management
21/Oct/21 1344 19-Nov Muffler broken,water pump broken,blow by (kebocoran kompresi)
3 Doosan 01 km 11 29/Oct/21 1300 5-Nov Engine Blow by P P P P P P P P P P L L L L L L L L L L L L L L L L L L L L 32 41% 59% Waiting persetujuan management

4 HITACHI 07 Embalut 7/Nov/21 263 15-Nov Control valve bocor P P P P L L L L L L L L P P P P P P P P P P P P 23 70% 30% Proses pemasangan oring control valve est 3 des

7/Sep/21 Radiator bocor,Planetary gear Final drive broken -->> DOWN tgl 8 sep

11/Sep/21 AC compressor jammed,Seal governor FIP bocor,internal leak motor swing


RH >> DOWN Tanggal 15 Sept
25/Sep/21 Trouble AC ubnormal -->>Down tgl 29 sept
29/Sep/21 Bucket Noise (Pembuatan sim bucket) -->> DOWN tgl 1 Oct P
5 Doosan 500-03 KKE P P P P P P P P P P P P P P P P P P P P P P P P 24 100% 0% Waiting Move to km 11
5/Oct/21 Trouble arus unit abnormal -->> DOWN tgl 7 Oct
22/Oct/21 Trouble AC (Compressor jammed) -->> DOWN tgl 23 oct
30/Oct/21 Fip leaking dan seal cylinder arm bocor--Down tgl 1 Nov
6/Nov/21 Arm crack
Waiting Approval management
6 kobelco 03 Chong lee 9/Nov/21 1333 12-Nov Road arm cyl damage P P L L L L L L L L L L L L L L L L L L L 21 10% 90%
7 Dozer 02 Chong lee 14/Nov/21 Transmisi abnormal P P P P P P P P P P P P P P L L 16 88% 13% Progress hitung cost partial dan opsi PTA

8 Hitachi 04 Embalut 30/Nov/21 Gear final drive broken P 0 100% 0% Progress pembonkaran by mekanik&recom part

1170 8-Oct
Bolt propeler shaft broken,flange yoke broken,Cover PTO dan selonoid PTO
9 CWE 209 KKE 7/Oct/21 broken L L L L L L L L L L L L L L L L p p p p p p p p p p p p p p 54 28% 72% Part Ready,progress menyicil pemasangan part (80 %)
1181 11-Oct

1/Nov/21 Dump tidak bisa naik -->> Down tgl 3 nov P P P


10 CWE 202 SEPARI P P P P P P P P P P L L L L L L L L L L L L L L 24 100% 0% Progress by Vendor LAT
6/Nov/21 Insident termundur Grader
11 CWA 509 KM 11 18/Nov/21 1384 23-Nov Break system abnormal P L L L L L L L L L L L L 12 8% 92% Wait Part (kurang seal shaft rear axle)
7/Nov/21 Tyre pos 1 bocor -->> Down tgl 10 nov P P P P
12 CWE 207 SEPARI P L L L L L L L L L L 10 10% 90% Canibal dr Ex engine DI warehose
20.11.2021 Water pump leaking
10/Nov/21 Overheat & electrical system abnormal -- >> Down tgl 12 nov P P P
13 CWB 105 KM 11 P P P L L L L L 7 100% 0% Wait Approve
23/Nov/21 1391 25-Nov Disc Clutch Aus
8/Nov/21 Spring broken no 4 -->> Down tgl 11 Nov P P P P
14 CWE 203 KKE P P P P P 4 100% 0% Proses TIR & Recom part
26/Nov/21 Top Overhaul Engine (bridge klep patah,lobe cam shaft patah)
7/Nov/21 AC panas,radio mati,adjust break RR P P P P P P P P P P P P P
15 CWE 208 KKE P 0 100% 0% Progress mekanis est 1 des
30/Nov/21 Spring no 4 putus
20.11.2021 Spring Front no 4 broken down tgl 21 nov P P
16 CWE 206 KKE p 0 100% 0% Progress mekanis est 1 des
30.11.2021 Tie rod bengkok
573 20-May 6-Jul
P P P P P P P P P P P P P P P P P P P P P P P P P
17 HARTECH 03 workshop 25/Jun/21 1067 10-Sep 14-Oct Top Overhaul Engine P L L L L 158 77% 23% Waiting Selenoid

1404 28-Nov
18 LV 01 KM 11 1/Sep/21 1042 7-Sep Over Heat,brake system,power stearing,cyl head bend L L L L L L L L L L L L L L L L L P P P P P P P P P P P P P 90 21% 79% Progress mekanik est 28 nov

19 WP 03 Chong lee 5/Sep/21 1045 7-Sep 6-Oct Radiator broken,fan radiotor broken,bolt mounting engine broken P P P P P P P P P P P P P P P P P P L L L L L L L L L L L L 86 55% 45% Waiting shaft sleeve (dtng 30 sore)

906 6-Aug 13-Sep


Baut transmisi ready tgl 24 (progress pemasngan) est
20 W.Truck PS 125 KM 11 12/Sep/21 1099 21-Sep Transmisi canibal ke FT 01 site KKE P P P P P P P P P P L L L L L L L L L L L L L L P P P P P P 79 76% 24% 3 des
1325 11-Nov 25-Nov

1229 23-Oct
21 LV -46 KM 11 20/Oct/21 Cap cam shaft broken,timing belt putus,check bend cyl head L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 41 7% 93%
Waiting cyl head (dtng 30 sore)
1278 1-Nov
22 TL - 07 KM 11 14/Nov/21 1343 15-Nov Engine overheat,engine bubble P L L L L L L L L L L L L L L L L 16 6% 94% Waiting Part
23 LV 31 KM 11 25/Nov/21 1400 26-Nov Dish clutch aus P L L L L L 5 20% 80% Waiting Approval
24 LV 37 KM 11 25/Nov/21 1402 26-Nov Stering Keras P L L L L L 5 20% 80% Waiting Approval
25 PS 125 Embalut 29/Nov/21 P L 1 100% 0% Waiting Part
READY FOR USE
1 CWE 205 KKE 30/Oct/21 Seal Dump bocor P P 3 100% 0% RFU

2 WT 06 KM 11 13/Oct/21 Overheat (Down 29 oct),trouble AC abnormal, water temp & Electrical system P P P 21 100% 0% RFU

3 CWE 204 SEPARI 7/Nov/21 Spring LH no 1&2 Broken P P 1 100% 0% RFU


4 WT 08 KM 11 11/Nov/21 bolt exhaust manifolt patah P P 1 100% 0% RFU

1270 30-Oct
Drive shaft ke gardan dalam RH bermasalah, bracket kaliper rem LH patah,
5 LV - 08 KKE 30/Oct/21 L L L L L L L L L L L L L L L 16 6% 94% RFU
1278 1-Nov cross joint double oblak/aus,gardan depan broken/abnormal
1311 9-Nov
6 CWE 204 SEPARI 16/Nov/21 Water pump leaking P P 1 100% 0% RFU
7 DOZER 05 KKE 16/Nov/21 1357 v-belt ac aus bearing cluth compressor ac P P L L P P 3 133% -33% RFU
8 TL - 04 KKE 20/Nov/21 Radiator Bocor P P P 2 100% 0% RFU

1111 24-Sep
9 TL - 05 KKE 14/Sep/21 Engine Ubnormal ( selenoid cut off FIP bermasalah) L L L L L L L L L L L L L L L L L L L L L L L L 72 15% 85% RFU
1337 12-Nov
10 HITACHI 350 Chong lee 16/Nov/21 1368 19-Nov Leaking hyd pump P P L L L L L L L 8 25% 75% RFU
11 CWM 116 KM 11 22.11.2021 1385 23-Nov AC Abnormal P L L L P 4 50% 50% RFU

PIC : LOG
PIC : PLANT
IN CWE 206, 208,hitachi 04
OUT
PT. INSANI BARA PERKASA
Daily Report Breakdown
Bulan Des 2021

NO CODE UNIT LOKASI B/D No NPB TGL NPB PART READY KERUSAKAN DESEMBER TOTAL DAY
PERSENTASE
PROGRESS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 B.DOWN PLANT LOGISTIK

Breakdown
1014 1-Sep 22-Sep
2/Sep/21 1032 4-Sep Hyd pump low pressure -->> 7 Oct (Canibal dr GD 01) Wait part
1 Grader 02 km 11
1145 2-Oct L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 71 4% 96%

21/Oct/21 1231 23-Oct Valve intake cyl head broken,sael shaft impeller leak (Engine Noise)
5/Oct/21 Trouble seal adjuster track RH bocor -->> DOWN 8 Oct
2 HITACHI 09 KKE L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 71 38% 62% Waiting approval management
21/Oct/21 1344 19-Nov Muffler broken,water pump broken,blow by (kebocoran kompresi)
3 Doosan 01 km 11 29/Oct/21 1300 5-Nov Engine Blow by L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 63 21% 79% Waiting approval management

Proses pemasangan oring control valve READY


4 HITACHI 07 Embalut 7/Nov/21 263 15-Nov Control valve bocor ,wait f.drive (ordering part F.drive) P P P P L L L L L L L L L L L L L L L L L L L L L L L L L L L 54 37% 63% ,Waitingf final drive (final drive canibal ke hitachi 04)

7/Sep/21 Radiator bocor,Planetary gear Final drive broken -->> DOWN tgl 8 sep

11/Sep/21 AC compressor jammed,Seal governor FIP bocor,internal leak motor swing


RH >> DOWN Tanggal 15 Sept
25/Sep/21 Trouble AC ubnormal -->>Down tgl 29 sept
5 Doosan 500-03 KKE 29/Sep/21 Bucket Noise (Pembuatan sim bucket) -->> DOWN tgl 1 Oct L L L P P P P P P P P P P P P P P P P P P P P P P P P P P P P 55 89% 11% progress pelebaran track frame est 31 des
5/Oct/21 Trouble arus unit abnormal -->> DOWN tgl 7 Oct
22/Oct/21 Trouble AC (Compressor jammed) -->> DOWN tgl 23 oct
30/Oct/21 Fip leaking dan seal cylinder arm bocor--Down tgl 1 Nov
6/Nov/21 Arm crack
6 Dozer 02 Chong lee 14/Nov/21 Transmisi abnormal L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 47 30% 70% Progress hitung cost partial dan opsi PTA
7 KOBELC130-01 KM 11 13/Dec/21 1405 29-Nov Line boaring bucket P L L L L L L L L L L L L L L L L L L 18 6% 94% progress line boaring
8 Hitachi 330-03 KM 11 17/Dec/21 1491 18-Dec Harness engine abnormal,contol valve bocor,leaking engine P P P L L L L L L L L L L L L 14 21% 79% Wait Approve part
8/Nov/21 Spring broken no 4 -->> Down tgl 11 Nov
9 CWE 203 KKE 1422 P L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 35 17% 83% Wait perbaikan cyl head by vendor
26/Nov/21 Top Overhaul Engine (bridge klep patah,lobe cam shaft patah)
1423
INSIDEN (progeress by NBI untuk perbaikan external
10 CWB 102 KM 11 13/Dec/21 Termundur DT P P L L L L L L L L L L L L L L L L L 18 11% 89% by vendor)
11 WP 02 workshop 21/Dec/21 Repair thread engine broken & thread lock sleeve nozzle broken P P P P P P P P P P P 10 100% 0% Progress pelepasan engine dari vonton
12 LV 01 KM 11 1/Sep/21 1042 7-Sep Over Heat,brake system,power stearing,cyl head bend P P P P P P L L L L L L L L L L L L L L L L L L L L L L L L L 121 21% 79% Waiting fuse box dan primning pump
906 6-Aug 13-Sep
1099 21-Sep
13 W.Truck PS 125 KM 11 12/Sep/21 Transmisi canibal ke FT 01 site KKE P P P P P P P P P P P P P P P P P P P P P P P P P L L L L L L 110 77% 23% wait cyl atas dan bawah
1325 11-Nov 25-Nov
1513 25-Dec
14 TL - 07 KM 11 14/Nov/21 1343 15-Nov Engine overheat,engine bubble L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L L 47 2% 98% Waiting Part est 31 des
15 LV 41 KM 11 7/Dec/21 Dish clutch aus P P P P P P P P P P P P P P P P P P P P P P L L L 24 100% 0% WAIT YOKE
READY FOR USE
7/Nov/21 AC panas,radio mati,adjust break RR
1 CWE 208 KKE P 1 100% 0% RFU
30/Nov/21 Spring no 4 putus
20.11.2021 Spring Front no 4 broken down tgl 21 nov
2 CWE 206 KKE p 1 100% 0% RFU
30.11.2021 Tie rod bengkok

3 Hitachi 04 Embalut 30/Nov/21 Gear final drive broken P P P 3 100% 0% RFU

7/Nov/21 Tyre pos 1 bocor -->> Down tgl 10 nov


4 CWE 207 SEPARI P P P 13 31% 69% RFU
20.11.2021 Water pump leaking
5 LV 37 KM 11 25/Nov/21 1402 26-Nov Stering Keras L L P 8 25% 75% RFU
6 PS 125 Embalut 29/Nov/21 Master Coupling broken L L L P 4 50% 50% RFU

7 CWA 509 KM 11 18/Nov/21 1384 23-Nov Break system abnormal L L L P 16 13% 88% RFU

10/Nov/21 Overheat & electrical system abnormal -- >> Down tgl 12 nov
8 CWB 105 KM 11 L L L L L L L L 15 20% 80% RFU
23/Nov/21 1391 25-Nov Disc Clutch Aus
9 CWE 201 SEPARI 4/Dec/21 Leak oil shaft rear P P L L L 4 50% 50% RFU
10 CWE 205 KKE 6/Dec/21 Disc Clutch Aus P P 1 100% 0% RFU
1170 8-Oct Bolt propeler shaft broken,flange yoke broken,Cover PTO dan selonoid PTO
7/Oct/21 broken -- Down tgl 3 des p p p
11 CWE 209 KKE 1181 11-Oct P P P P P 4 100% 0% RFU
6/Dec/21 PTO dump Abnormal ( Tidak bisa dump)

1229 23-Oct
12 LV -46 KM 11 20/Oct/21 Cap cam shaft broken,timing belt putus,check bend cyl head L P P P P P P P P 50 22% 78% RFU
1278 1-Nov
13 CWM 116 KKE 13/Dec/21 Spring FRont no 1 DAN 2 broken P P P P 1 100% 0% RFU
14 WT-03 KM 11 7/Dec/21 Brake system dan exhaust break abnormal P P P P P P P P 7 100% 0% RFU
15 CWB 101 KM 11 2/Dec/21 1443 3-Dec Disc Clutch Aus P L L L L L L L L L L L L L L 14 7% 93% RFU
16 LV 31 KM 11 25/Nov/21 1400 26-Nov Dish clutch aus L P P P P P P P P P P P P P P P P 22 77% 23% RFU
1/Nov/21 Dump tidak bisa naik -->> Down tgl 3 nov RFU
17 CWE 202 SEPARI L L L L L L L L L L L L L L L L L L L L 44 23% 77%
6/Nov/21 Insident termundur Grader RFU

18 WP 03 Chong lee 5/Sep/21 1045 7-Sep 6-Oct Radiator broken,fan radiotor broken,bolt mounting engine broken L L P P P P L L L L L L L L L L L L L L 107 48% 52% RFU

19 LV 36 KM 11 7/Dec/21 1455 12-Dec Dish clutch aus P P L L L L L L L L L L 11 18% 82% RFU


1333 12-Nov RFU
20 kobelco 03 Chong lee 9/Nov/21 Road arm cyl damage L L L L L L L L L L L L L L L L L L L L L P 44 7% 93%
1441 3-Dec RFU
573 20-May 6-Jul
21 HARTECH 03 workshop 25/Jun/21 1067 10-Sep 14-Oct Top Overhaul Engine L L L L L L L P P P P P P P P P P P P P P P P P P P P 185 77% 23% RFU

1404 28-Nov
22 LV 12 KM 11 20/Dec/21 Trouble kaki2,stering,hand break abnormal P P P P P P P P P 8 100% 0% RFU
PIC : LOG
PIC : PLANT
IN
OUT