IEL CONSORTIUM ASSOCIATES

Unit Price Schedule


Code Description Type/Size Unit Unit Price'10
Activity wise EPSILON rate
A01 Earth work in excavation cu.m 209
A02 Brick Flat Soling sq.m 33.25
A03 CC Casting in foundation concrete cu.m 1092.5
A04 Reinfore Cement Concrete Boundary Wall cu.m 1092.5
A04a RCC in Pile Cap / Footing / Foundation Base cu.m 2180.25
A04b RCC in padestal column/Ring wall cu.m 2850
A04c RCC in grade beam cu.m 2850
A04d RCC in column / Wall above PL cu.m 2850
A04e RCC in Sunshed & Lintel / caping cu.m 2945
A04f RCC in floor/roof slab in/c beam cu.m 2180.25
A04g RCC in 1st Floor [C30] cu.m 2275
A04h RCC in situ pile casting cu.m 830
A05 Cement, Sand & Khoa consolidation cu.m 836
A06 Polytheen laying sq.m 9.5
A07 Rebar fabrication ton 3800
A07a Rebar fabrication for pile ton 3800
A07b Rebar fabrication other than pile ton 3800
A08 Brick work in foundation cu.m 418
A09 250mm Brick work in wall cu.m 465.5
A10 Damp proof course sq.m 61.75
A11 125mm Brick work sq.m 95
A12 125mm pointing Brick work sq.m 104.5
A13a Tiles fitting (Floor) sq.m 190
A13b Tiles fitting (Wall) sq.m 190
A14a 12mm Plastering sq.m 80.75
A14b 6mm Plastering sq.m 80.75
A15 Plastering with Net Cement Finishing sq.m 109.25
A15a Only Net Cement Finishing sq.m 33.25
A16 Sand filling / Back filling cu.m 171
A17a Boring for casting in situ pile (500mm dia) Rm 130
A17b Boring for casting in situ pile (900mm dia) Rm 2500
A18 Pile head breaking cu.m 1529.5
A19 Barbed wire fancing sq.m 76
A20 Chain link fancing 10 SWG GI wire with mesh 5cmx5cm sq.m 456
A21 C.I. sheet roofing sq.m 375
A22 False ceilling with aluminum channel sq.m 505
A23 Improved sub-grade cu.m 171
A24 Sub-Base course cu.m 190
A25 Base course cu.m 202
A26 Paving block laying sq.m 81
A27 Brick on edging Rm 14
A28 Sanitary fitting LS 10000
A29 Electrical fitting LS 15000
A30 Window grill fitting sq.m 85.5
A31 Lime terracing work 2:2:7 cu.m 1501
A32 Wooden door frame cu.m 7000
A33 Wooden door shutter sq.m 1050
A34 Aluminum sliding/fixed window fixing sq.m 150
A35 Collapsible gate sq.m 550
A36 Internal paint with Plastic Paint: sq.m 80
A37 Weather coat Paint/Snowcem Work sq.m 80
A38 Synthetic enamel paint/Varnish Work: sq.m 80
A39 Surface Drain: Rm 510
A40 Apron Work: sq.m 300
A41a 50 mm dia CONDUITS (Type 1000uPVC) Installation Rm 55
A41b 160 mm dia CONDUITS (Type 1000uPVC) Installation Rm 165
A41c 110 mm dia CONDUITS (Type 1000uPVC) Installation Rm
A42 Subgrade preparation sq.m 15
A43 Karb stone RM 38
A44 Permanent steel casing installation 900mm dia Rm 1600
A45 Installation of Fender pile Rm 1400
A46 uPVC door frame fitting Rm 50
A47 uPVC door shutter fitting each 150
A48 Supplying fitting fixing of hand rail (stair) sq.m 1050
A49 Aluminum mosquito net fixing sq.m 100
A50 SFF hasp bolt each 100
A51 Stone pitching cu.m 836
A52 Drip course work Rm 38
A55a Category-1(600x600x450mm) Nos 225
A55b Category-2(600x600x1700mm) Nos 300
A55c Category-3(1500x1500x2500mm) Nos 1015

569162297.xls 01/08/2022
RATE FOR SUB-CONTRACTORS ITEMS
(Boundary wall and Building works)

Approved Rate
Sl. No. Description of Item of works Unit Remarks
in Taka
1 Earth work in Excavation :
a) Up to 5 feet Depth Cft. 1.20
b) Above 5 feet Depth Cft. 1.50
2 Back filling with Compaction Cft. 0.30
3 Sand filling with Compaction Cft. 0.25
4 Polythene Laying Sft. 0.10
5 C.C work (M-10) Sft. 0.300
6 Mass Concrete work in Floor (M-20) Cft. 0.300
7 Brick Flat Soling (with levelling & Dressing) Sft. 0.70
8 Shuttering Works :
i) Wooden shuttering, fixing in/c making Sft. 5.50
ii) Steel shuttering, fixing only Sft. 5.00
9 M.S Rod Fabrication & Placing GI wire (40/60Grade) including kg. 1.80
10 R.C.C works (M-25) :
i) Bottom Raft Cft. 4.50
ii) Wall Cft. 5.75
iii) Slab Cft. 5.50
11 R.C.C works (M-15/20) :
i) Column Footing Cft. 5.00
ii) Foundation / Grade Beam Cft. 5.50
iii) Column Cft. 6.00
iv) Copping Rft. 4.00
12 R.C.C works in Building (M-20) :
i) Footing & Pedestal Cft. 5.00
ii) Grade Beam Cft. 5.50
iii) Column Cft. 6.00
iv) Lintel & Tic-Beam Cft. 6.00
v) Floor Beam Cft. 5.75
vi) Floor Slab Cft. 5.50
vii) Sunshade,Drop Wall, Cornice & Railing Sft. 3.00
13 75 mm Damp Proof Coarse Sft. 2.50
14 1st. Class Brick work - 10" Cft. 3.50
15 1st. Class Brick work - 5" Cft. 2.50
16 Chipping of RCC surface Sft. 0.50
17 12 mm Plastering work Sft. 2.50
18 6 mm Plastering work Sft. 2.00
19 Neat Cement Finishing work Sft. 0.50
20 Drip Course Rft. 2.00
E/Pintu/Sub-contractor bill formet
21 Wooden Door Frame making Cft. 120.00
22 Wooden Door shutter Sft. 75.00
23 Wooden Grill fitting Sft. 2.50
24 Wooden Stair Railing making & fixing Rft. 75.00
Collapsible Gate supplying , Fitting complete in/c.
25 Fabrication by 1" x 1" Angle Sft. 150.00

26 Barbed wire Fencing Rft. 0.25


Supplying &fixing of Aluminium Sliding/fixed in Window in/c. materials
27 with 5 mm tinted glass. Sft. 165.00

Supplying &fixing of Aluminium swing Door fitting complete in/c. materials


28 with 5 mm tinted glass. Sft. 400.00

29 Wall Tiles work in/c. mortar base Sft. 12.00


30 Floor Tiles work in/c. mortar base Sft. 13
31 Patent stone work in Floor with stone chips Sft. 2.50
32 Plastic Painting work Sft. 2.75
33 Snowceam painting work Sft. 2.00
34 Varnishing work Sft. 3.00
35 Surface drain (125 mm Brick wall) Rft. 19.00
36 Apron work (50 mm c.c M-15) Sft. 2.50
37 Sand screening only plaster Cft. 0.50
38 Khoa/stone screening Cft. 0.75

RATE FOR SUB-CONTRACTORS ITEMS

Approved Rate
Sl. No. Description of Item of works Unit Remarks
in Taka

1 Mason / Mistry No. 150.00

2 Labour / Helper No. 100.00

3 Door Fitting No. 75.00

4 Window Fitting No. 50.00

5 Clamp Fitting No. 5.00

6 C.I sheet Fitting Sft. 2.00

7 Pan Fitting No. 200.00

8 PVC pipe fitting (4" dia) Rft. 12.00

9 PVC pipe fitting (2 ~ 3" dia) Rft. 10.00

10 Inspection Pit ( >2' - 6" x 2' - 6") No. 300.00


11 Low - Down Fitting No. 150.00
12 Cobla (Door/Window/Pillar) Rft. 1.75
13 Manhole Cover (Toilet Septic Tank) No. 50.00
14 M.S Plate Setting for Asphalt (18"x18"x3/8" No. 35

E/Pintu/Sub-contractor bill formet


15 All water supply pipe line fixing (3/4" ~ 1" dia) Rft. 2.00

E/Pintu/Sub-contractor bill formet


Unit Price Schedule
Code Description Type/Size Unit Unit Price'98
Materials:
M01 Acrylic emulsion paint (wall/ceiling) ltr
M02 Aluminum section rft
M03 Anchorage set 1,700.00
M04 B.T. veneered board (walling) sft
M05 Bamboo m 20.00
M06 Bentonite bag 60.00
M07 Bitumen kg 13.75
M08 Borrow Soil m3 20.00
M09 Boulder 300~500mm m3 1,630.00
M10 Brick ea 3.00
M11 Brick Chip m3 1,150.00
M12 C.I sheet (Coloured) sft
M13 C.I sheet (Galvanised) .45mm thick sft
M14 Cement Admixture kg 180.00
M15 Coarse Sand (FM 2.5) m3 389.00
M16 Cupler fo Duct no.
M17 Duct 50mm dia 5m long m
M18 Epoxy for external ltr 1,200.00
M19 Epoxy for injection ltr 3,000.00
M20 Fiber glass Sheet 5~7 mm m2 1,292.00
M21 Form Oil ltr 280.00
M22 Form Tie ea 15.00
M23 Fuel ltr 15.70
M24 G.I Wire & Misc kg 47.00
M25 Gabion sqm 95.00
M26 Geotextile sqm 100.00
M27 Gunny Bag No 7.00
M28 Gypsum board sft
M29 H.T Strand ton 59,000.00
M30 High Yield Re-Bar Grade 60 ton 22,000.00
M31 Hydrated lime ton 2,000.00
M32 Lime kg
M33 Local Sand (F.M 1.2) m3 141.00
M34 Marbel stone sft
M35 Mild Steel Deformed Bar Grade 40 ton 20,000.00
M36 MS Angle 100x100x10mm ton 19,000.00
M37 MS Plate 150x19mm ton 18,000.00
M38 Nail kg 45.00
M39 Nut & Bolt dia 12 x 300mm ea 15.00
M40 Pea Gravel m3 525.00
M41 Perforated PVC Pipe dia. 150mm m 900.00
M42 Plastic emulsion Paint ltr
M43 Plywood 4'x8x5/8" pcs 1,000.00
M44 Portland Cement ltr 500.00
M45 PVC Pipe dia. 100mm m 370.00
M46 RCC Pipe dia 600 m 2,500.00
M47 RCC Pipe dia 900 m 3,800.00
M48 Scafilding m2 100.00
M49 Sealer ltr
M50 Shuttering Material m2 1,900.00
M51 Steel Pipe dia. 75mm x 2.5m ea 1,925.00
M52 Stone Chip m3 1,412.00
M53 Synthetic enamel Paint ltr
M54 Synthetic polyvinyl distemper ltr
M55 Tem. Steel Casing dia. 750mm m 250.00
M56 Tem. Steel Casing dia. 900mm m 300.00
M57 Thinner ltr
M58 Timber cft 750.00
M59 Vinyl board (ceiling) sft
M60 White cement kg
M61 Wire Mesh for Basket 1.5x1.5x0.3m ea 125.00

Plumbing
P01 Commode nos. 5,700.00
P02 Pan nos. 2,000.00
P03 Hand Wash Basin nos. 2,600.00
P04 Standing Urinal: nos. 2,250.00
P05 Towel Rail nos. 450.00
P06 Mirror nos. 500.00
P07 Glass Shelf nos. 350.00
P08 Soap Tray nos. 150.00
P09 Toilet Paper Holder nos. 175.00
P10 G.I. Pipes 20mm dia Rm. 465.00
P11 G.I. Pipes 25mm dia Rm. 475.00
P12 U.P.V.C. Soil Pipe 100mm dia Rm. 150.00

Electrical
W01 PVC Pipe ¾" (20mm) dia Rm. 45.00
W02 Cable Rm. 45.00
W03 Earth cable Rm. 85.00
W04 Switches and Switch/Regulator Boards Sets 2,000.00
W05 56" Ceiling Fan nos. 1,500.00
W06 300mm dia Exhaust Fan nos. 1,200.00
W07 1 x 4' x 40 watt. fluorescent tube light Sets 350.00
W08 2 x 4' x 40 watt fluorescent tube light Sets 450.00
W09 Distribution Board Sets 1,500.00
W10 Circuit breakers nos. 2,500.00
W11 Water Pump nos. 7,500.00
W12 Fire Extinguisher nos. 2,500.00

Equipment Equip & Operator


E01 Air Compresor Hr. 113.75
E02 Asphalt Finisher 2.5 - 4.5 M. Hr. 199.5
E03 Asphalt Plant 120 Ton/Hr. Hr. 2406
E04 Bitumen Distributer 3000L Hr. 542.25
E05 Boring Rig Complete Hr. 280
E06 Cargo Truck 8 ton Hr. 176.75
E07 Cargo Truck 2.5 ton Hr. 70.75
E08 Concrete Mixture 10 cft Hr. 49.75
E09 Concrete Mixture 5 cft Hr. 43.75
E10 Concrete Vibrator Hr. 48.75
E11 Crusher Plant 100 Ton/Hr. Hr. 2501
E12 Cutting & shaping m/c
E13 Diesel Winch Hr. 25
E14 Dozer 18 Ton Hr. 645.75
E15 Drill m/c, rowel bolts, G.I. wire, in/c m/c
E16 Dump Truck 15 Ton Hr. 304.75
E17 Excavator 0.45 M3 Hr. 425.25
E18 Excavator 1.0 M3 Hr. 286.25
E19 Excavator 0.15 M3 Hr. 227.25
E20 Excavator 0.80 M3 Hr. 305.25
E21 Fork Lift 5 Ton Hr. 185.75
E22 Generator 640 kw Hr. 389.75
E23 Generator 456 kw Hr. 375.75
E24 Generator 32 kw Hr. 103.75
E25 Generator 48 kw Hr. 77.75
E26 Grader 3.6M Hr. 584.25
E27 Grouting Pump Hr. 250
E28 Local Trucks 5 Ton Hr. 318.75
E29 Mechanical broom Hr. 56
E30 Mechanical Road marker Hr. 50
E31 Mini Loder .31 cum Hr. 122.75
E32 Mini Roller 0.31 M3 Hr. 65
E33 Plate Compactor Hr. 38.75
E34 Polishing m/c
E35 Stressing Jack Hr. 1000
E36 Tandem Roller 9.73 Ton Hr. 322
E37 Tire Roller 8.57 TON Hr. 260
E38 Tractor / Trailer Hr. 387.5
E39 Tremie Hr. 25
E40 Vibratory Roller 10 Ton Hr. 290
E41 Water Pump Hr. 48.75
E42 Water Trucks 20000 ltr Hr. 189.75
E43 Wheel Loader 3.5 M3 Hr. 697.25
E44 Wheel Loader 2.3 M3 Hr. 354.25

Manpower:
L01 Supervisor Hr. 25
L02 Mason Hr. 10
L03 Skilled labour Hr. 17.5
L04 Ordinary labour Hr. 9.25
Disel Lubricant
96.2 19
126.16 25
14195 0
189.24 53

199.55 88
59.93 26
47 1
37.6 1
31 8
0
375.33 101

332.75 146
414.93 166
279.13 70
37.85 15
222.36 89
199.55 88
2200.7 440
1649.5 330
208.16 42
310.67 62
242.86 310

199.5 88

64.66 47
70.97 6
23.5 5

250
145.08 12
184.51 37
406.87 155

184.51 83
21.15 4
354.83 156
384.79 281
257.05 188
250 Brick Work 125 Brick Work
100cft =2.83cum 100 sft=10.76sqf
Foundation Super str. Super str. Expo. Str. Super str.
(1:6) (1:6) (1:4) (1:4) (1:6)

Code A. Material Tk. 4766 4766


M52 S.Agg cft
M10 Brick nos. 1100 1100 1100 1100 480
M33 F. Sand cft 36 36 40 40 18
M15 C. Sand cft
M44 Portland Cement bag 4 4 6 6.5 1.75
M60 White cement kg
M32 Lime kg
M13 Galvanised C.I sheet bundle (150sft=72rft=67kg)
M12 Coloured C.I sheet bundle (150sft=72rft=67kg)
M24 G.I wire kg
M34 Marbel stone sft
M53 Synthetic enamel Paint liter
M54 Synthetic polyvinyl distemper liter
M42 Plastic emulsion Paint liter
M01 Acrylic emulsion paint (wall/ceiling) liter
M49 Sealer liter
M57 Thinner liter
M04 B.T. veneered board (walling) sft
M59 Vinyl board (ceiling) sft
M28 Gypsum board sft
M02 Aluminum section rft

B. Labour, machinery, fuel andtk 863 863


Manpower
L01 FM/H. mason no. 0.2 0.2 0.2 0.5 0.2
L02 Mason no. 1 1 1 1.5 0.5
L03 Skilled labour no. 1 2 2 2 1
L04 Ordinary labour no. 6 9 9 9 4

Equipment
E09 Mixture m/c no.
E10 Vibrator m/c no.
E05 Rig in/c bentonite no.
E12 Cutting & shaping m/c
E34 Polishing m/c
E15 Drill m/c, rowel bolts, G.I. wire, in/c m/c % of aluminum cost

C. Form Work
shuttering tk
scaffolding sft 25 25 25 25
Laying cost tk
125 Brick Work BFS HBB Edging RCC
100 sft=10.76sqf 100sft 100 rft 100 cft
Super str. Footing Col G.Beam Lintel Slab Stair
(1:4) (1:2:4) (1:2:4 (1:2:4) (1:2:4)(1:2:4) (1:2:4)

90 90 90 90 90 90
480 300 550 250 850 850 850 850 850 850
16 5 10 2 22.5 22.5 22.5 22.5 22.5 22.5
22.5 22.5 22.5 22.5 22.5 22.5
2.6 18 18 18 18 18 18

0.2 0.125 0.25 0.125 0.2 0.2 0.2 0.2 0.2 0.2
0.75 0.25 0.5 0.25 1 1 1 1 1 1
1 1 2 1 1 1 1 1 1 1
4 6 6 6 6 6 6

0.2 0.2 0.2 0.2 0.2 0.2


0.2 0.2 0.2 0.2 0.2 0.2

950 7400 2520 5275 5400 5275


25
Fabrication Lime C.I sheet Pileing Floor fitting
1 ton Terracing roofing 400 dia 500 dia 600 dia 100 sft
100cft 150sft 20m long 20m long 20m long Marble sto
/day /day /day Carrara
Venus
Ariston

1050
4.2
4.2
3.7
4
540
1

20
100

1 1 0.125 1 1.25 1.5 1


4 1 0.375 1 1.25 1.5 5
15 2 0.375 3 4 5 5
34 0.75 6 10 10 6

1 1.25
1
3

21.75
Floor fitting Plastering NCF Painting
100 sft 100 sft 100 sft 100sft 100 sft 100 sft
Tiles 12mm (1:4)12mm (1:6)12mm (1:4) Synthetic distemperi Plastic
(2:1) dado 2coat 2coat 2coat
door/windo wall wall/ceiling

6.25 5 6 7.5

2.5 1 0.75 2
3.6

1
1
1

1 1 1
1

2 0.25 0.25 0.25


2 1 1 1.25 1 1 1
3 1 1 1.25
3 2 2 2.5 1 1 1

21.75
False Ceiling
100 sft
gypsum

100
120

5
5
5

40%

100