DRILLING
Jack Up Rigs: Evolution of Design
Jean Cahuzac
Jean Chevallier
Lee Turner
‘Montrouge, France
In August 1988, Sedco Forex’s jack up tg,
Trident 1X, spudlded a well for Cabinda Gulf
il Company (Chevron Corp.) off the coa
ff Angola in a record water depth of 391
feet (119 meters). Built in 1982, Trident 1x
vas the first jack up developed for depths
Lup to 400 feot [122 meters] (right). Until the
late 1970s, most jack up rigs were designed
to operate in shallow water, up to 250 fect
[76 meters}, and in mild environments,
Today, several jack ups are capable of work
Jing at 400-foot depths and in adverse ocean
nd weather conditions previously reserved
for semi-submersibles and cil ships
Sell-levating jack ups are the most com
‘mon offshore drilling unit. A jack up has
several advantages that may appeal to the
‘operator, the most important being, cost. A
jack up is less expensive to build than any
‘ther type of offshore rig and this con:
tributes to a lower day rate and therefore
Tower operating costs forthe oil company.
Logistical expenses are also lower. lack ups
require a smaller crew than other rigs, and
less powerful boats fo move them. A jack up
usualy requites no anchoring.
Jack ups also have lower maintenance
costs, There is no subsea blowout preven:
tion system and the wellhead assembly is
much simpler. Cost may also be reduced
Volume 1 Number 1
seco Foren’ Tide 1 jack up rig cil in 2 record water depth of 391 eet [19 meters) in
showe Angola,
because of less down time. Once on loca:
tion, the rig’ lack of mobility makes drilling
‘operations more straightforward than on rigs
that move with the ocean swell
The limitations of jack ups are safety and
water depth, although as the Trident IX
record suggests the depth limitation is being,
stretched. A jack up's legs must be firmly
implanted on the ocean floor and stay there
throughout the drilling operation. Two
major problems can arise. Firs, the legs
may not be long enough to accommodate
the water depth and some penetration into
the ocean sediments. Second, during
drilling, one oF more of the legs may sud
‘denly punch through a weak layer of formas
tion, toppling the rig into the ocean.
‘Another safety limitation with jack ups isthat they cannot be moved off location in
case of a blowoul or other mishap.
‘Most jack up rigs have three legs.! Each
leg is formed from a lattice of K-shaped
trusses fabricated with reinforced steel
tubes. The tubular leg extremities may be
set in place directly on the ocean floor if it
can withstand the rig’s pressure of about
140 pounds per square inch (psi) [10 kilo
trams per square centimeter (kg/cm). For
‘cean floors of intermediate strength, the
legs are equipped with so-called spud cans
that reduce pressure to about 40 psi
3kgy/em?| by distributing the ri’s weight
‘over a larger area (below). The spud can is
cular of polygonal and constructed with a
heavy point to penetrate the hardest sea
floor. The point also serves to ease retrieval
from soit floors. Most jack ups are designed
to allow about 30 feet [9 meters} of leg pen:
tetration into the ocean floor. ln exceptional
Circumstances, up to 150 feet [46 meters} of
penetration has been experienced,
Very soft ocean floors may require so
called mat jack ups (right). A steel mat
welded to the bottom of the ig’ legs, dis
ibutes the weight ofthe rig evenly on the
‘ocean floor reducing pressure to 4 psi (0.3,
kg/cm]. However, a mat requires a rather
flat ocean floor, ree of irregularities that
might damage the mat
1, Seco Forex only Jick op wth our eg he
vr nth rd quis 9 four eg ai.
2. Seaco Fare ack ups excep he Tent i
Cons
36
1One of Tent 1s
three spud ean ding
‘om Toyo ship:
sate ig was
ering Co
(Mode) and delivered
in 1983. The te ver
thal bes at the spud
ect with the g's
three vertical cho
The tubes sre 60 feet
118.3 meters)
loescate
The trend toward using jack up rigs in
deeper water and more hostile conditions
stimulated several innovations in leg and
the jack up system design, jack up's st:
bility depends on its weight resisting the
horizontal loads of the wind, waves and
Current of the worst possible storm. A crit
cal point is where bending moments caused
by the horizontal forces exerted on the legs
are transmitted to the main body of the rig
or hull
'A matiyp jack up, the Seco Fore “Luan
in tans. The sec, horseshoe shaped mit
fnange is welded to the bron of te rs eas
to pronide sale weigh dstbution on soft oces
floors. The igi. ed on the cack of
2 carir vessel 0 fod ther,
the vessel submerged dep enough to at the
‘up. Then the tansport vessels debated.
Oilfield ReviewUppers
iv
7
ewer use
‘radial facing system, in which overturn
Jing moment fs mainly borne by gues above ards
Delow the jack house, Vertical rst forces hick
arm at the jacks rack aa pinion mechanism
‘are equal both sides ofthe eg, indicating that the
Jacks bear only the ry’ buoyant weight. The
‘vertuming moment is canted bythe hovizniad
thas forces a the guides. Note te ri’ rao
and ney legs
Volume 1 Number 1
Jacking Up System
In the traditional jack up rig, the jacks are
strong enough to elevate the hull, but ean-
not bear any bending moment.? The
‘moment is resisted at guides above and
bplow the rack and pinion mechanisms that
raise and lower each leg. This design
requites some distance between the upper
and lower guides and slender, heavily con-
structed legs (lef) In the Trident IX, the
jacking units are more robust andthe bene
ing moment is sustained mainly atthe rack
and pinion mechanisms mounted on the
three vertical elements of each leg, called
chor.) Only a small part of the moment is
tome by guides below)
To sustain bending moment in this way
required increasing the distance between
chhords to 60 feet [18.3 meters. This leads
to large but ight legs, which in tum leads to
A less expensive rg, ‘Tident X's legs weigh
only 1.74 tons per foot 0.53 tons per meter
compared with 2.13 tons per foot 10.65 tons
ident Ws jcking
ssten in which
benelng moment is
mainly bome at the
Jack hooses be
fei. The vertical ust
forces a the jacks
either ide of es are
‘neq, indicating
substantia overtaing
‘moment i being
Pied there. Tiden Xs
Ter les oe es
resistance to wind and
‘water detper meter] for conventional legs. Their size
pprovides increased rigidity while offering
less resistance to wind, waves and current.
Theis lager spud cans create less pressure
‘an the acean floor
den 1X jacking system also provides
yreased lilting capacity, making for speedy
and safe operation (above and right). Tis is
particularly important during preloading
when sea water is pumped into special
tanks to artificially increase the weight of
the rig, Preloading ensures that at a new
location the legs have sufficiently penetra
fd and compacted the ocean bottom, giving
the fig a firm foundation for the worst
environmental conditions. For safety,
preloading is performed with the hull a few
Feot above water level, so in case a leg sud:
dlenly punches through weak ocean sedi
ments, the rig simply floats.
A third advantage of the new jacking sy
tem isis simplicity, permitting accurate and
reliable computer modeling of the legs and
Jacking system.
38
Rig Stability
The ultimate design eterion for any jack up
sigisthat once jacked up it mst remain sa
bile under the most adverse environmental
conditions, Design engineers must ensure
that ther’ gravity load can withstand the
horizontal forces of wind, waves and ocean
current. Formulas developed trom either
‘wind tunnel experiments and laboratory
Simulated ocean conclitions of established
by the American Bureau of Shipping (ABS)
ae used to pret these forces (a ight)
For the Trident IX, wind provides the
majority ofthe overturning moment. The
wind aets primarily on the portion of the
legs above the hull, and the load increases
|One of nine ack houses beng hosted into
place ering consbuction of Ident above
{eid ene ack rack aa pinion mechs
(abot. Each fe haste jack houses, one per
Chord: each ack house houses 6 jacks, making
total of 4 jack for tho ig. Te jacks ave National
Series 400 type each fs 220 tors elevating
‘apt oe 500 tons hot eapacity. Ta i
Jig capacity 11,880 tons ander nonmalcand
toms aad 13,500 tons ina emengenc. Jaciog
sce sly 13 fot (045 meters or mine
as the square of wind speed. Meteorologists
ategorize wind speed according to the time
interval used to record it. The 3-second
just, defined as the highest likely wind
speed during a 3-second interval, s use for
designing individual steel members. The 1
minute wind speed is used for calculating
rig stability, An unrestricted ABS-class jack
Lp (unrestricted in the geographic sense) Is
designed to survive a 100-knot wind and to
drill in a 70-knot wind. A restricted ABS:
class jack up is designed fora wind speed! of
50 knots
Waves and ocean currents are minor con
tributoes to Trident X's overturning moment.
Wave forces depencl on the height andl peri
cd ofthe waves anl water dept, Empicical
formulas predict the bo components, iner
tia and dag, of the wave's force against the
logs assuming the worst case scenario, the
50-year wave. Water depth influences these
forces because it affects wave shape.
Ocean current load is hard to predict
because its velocity and direction vary with
depth. The velocity of tidal currents is con-
stant versus water depth whereas that of
wind generated currents decreases linearly
to ze10 at some depth. Current drag can be
important, For the Trident IX siding a ou
sea—40-foot [12-meter] waves with 12-sec-
‘ond period—a 2-knot current increases the
‘ocean's horizontal loa! by 70 percent
The Trident IX was built for a specific set
‘of dosign criteria (see “Trident IX Speciica-
lions,” page 40:
Water depih 400 feet [122 meters}
Wave height 40 fet [13 meters}
Wave period 12 seconds
Surface curtent knot
Bottom curent 0 knot
Wind speed 100 knot
Ait gap 30 feet |9.1 meters)
(Ocean floor
penetration 25 feet (7.6 meters)
Safe operation, however, depends on local
conditions, and if they exceed the equiv.
lent design criteria, rig stability is eevalua
ced. This assessment procedure uses labora
tory data and lengthy model calculations.
Take ocean floor penetration as an example,
Leg penetration is predicted before the
is relocated by taking samples ofthe ocean
floor and studying its undrained shear
strength. In deep water, safe penetration is
limited by leg length. in shallow water, a
small penetration will cause the legs to
extend high above the jack house and
Oilfield ReviewIncrease horizontal wind loads. A minimum
leg reserve of 5 feet [1-5 meters) above the
top of the jack house is required since the
penetration estimation is inexact.
Water depth and air gap, important for
calculating wave and current loads, must
also be carefully estimated. Water depth is
the distance between the ocean floor and
the stll-water evel, which corresponds to
the highest annual tide plus a storm surge, 2
raising ofthe ocean level by low barometric
pressure. This information is obtained
through the local meteorological office. The
air gap, measured from the mean water
level to the bottom ofthe hull, must be suf:
Cient to avoid the crest of any wave staking
Volume 1 Number 1
Wave and
Caren!
the hull. For safety, an extra 4 feet [1.2
meters} or 10 percent of the air gap is
added.
The relative strengths of the overturning
moments from wind and water (inelucling
wave and current), OTM-wind and OTM:
‘water, vary from one jack up to the next. For
‘example, consider the following operating
Conditions, somewhat different irom the Ti:
dent 1X design criteria:
Water depth 300 feet [91 meters}
Wave height 48 feet [15 meters]
‘Wave period 15 seconds
Surface current 0 knot
Bottom current Oknot
Wind speed 100 knot
Air gap 30 feet |9.1 meters)
‘Ocean floor
penetration 25 feet (7.6 meters}
The envioement's
horizontal cine on
2 ack up doco wind,
‘save orl ocean cu
reat The lowing
resisted the su
In this setting, the overturning moments
{units are metvic ton-meters [ton-m)) for
three Sedco Forex. jack ups ae:
Wideot IV Teident VE Tident x
Mobil shel BP
Nigeria Nigoria North Sea
OtMewind 43773 38.237 56589
Otmissater 34.551 4,980 20,118
WindiWaler 12725528
OMMot 78,28 5321776707
‘The square legs of the Trident IV have a
trapezoidal chord section that produces a
large underwater drag giving ita high OTM
‘ater. The Trident VI, built like the Trident
IX with fixed jacking unit and lighter legs,
hhas a lower OTiMwater. The Trident X has a
high OTMawind because its leg:hull con-
nection is Located outside the hull, increas:
ing the projected area ofthe hull
The Tident 1X operating under its design
criteria conditions experiences the following,
moments: OTM-wind = 62,190 ton-m,
OTMwater = 20,100 tan-m, OTM04
62,190 + 20,100 = 82,290 ton-m. Wind 10
water ratio is 3.09, more than any of the
Jack ups above. In 120-knot winds, 20 knots
more than in the design criteria, OTM-wind
increases to 62,190 |1 20/100)? = 89,600
ton-m, giving an OTMVetotal of 109,700 ton-
‘A jack up rig remains upright if the over-
turning moment is less than the stabilizing
‘moment, Si ofthe rg’ wravity load,
SM= (WBE
inwhich Wis rig weight, B is its buoyancy
and Jis the distance between the rigs center
‘of gravity and axis of rotation, considered 10
39DRILLING
Daaw.worke
[Gavaner Denver 1650 = 2,000 Fo
Pumps
(Gardoor Denver PZ11— 1,600 Hp
Darrick
Branram=—Ta7 HeaOT SOON
[Gross nominal capacty—1,982,000 >
Static hook load, API 4E with 12 ines—1,044,000 ib
Maximum wind vith ated setback inthe dock 135 mph
Maximum pitch 0 rl or ransi—-20 degrees, 10 seconds
Powor
4 Cat D 299 TA diesel engines:
{4GE 1 500:KVa generators
‘Slicon-contolled rector
a Graharn=a 11200 KW 600 V
‘BOPs
[Camoron 135%, 10:000-psi rams
Hye 20 in, 2.000 psi
Hy 195i in, 5,000 psi
canes is Fastin) a on AT AAT
Tiving quarters cagaciy—103 poopie
MARINE
Dimensions Tarawa Ea
fit, ova aie 8 2n [7502]
Depth of Full 26H Fin [863m] i
Cong offs siet (158m)
| Spud ean cross-sectional area (per can) 7 Beessqn [240 m"
[Cantilever 7 45 fix 24 ft [13,.72mx 7.31 m)
Lightship weight 9,542 tons
Tien dat Thi ein 80m)
Helpor damier ZH GAT
Design evra ‘Operating water depth with 5 ponovaton and | aan (122m)
Dit ai oa)
Rated aaa see TOOT SRM
Wave eight aon (219m)
Wave pared Tesco
Surface current ‘Oknots: mi
Baton curert Tats
Wind spood oni
ook [a National ees #00 ase, each having 220 088 z
tiovating, 500 tons hoeing capac.
Storage 77] Vanabie toad (excluding 1,250 kips hook and set ‘5400 kips [2.695 tons]
back oa 1 ip = 1,000)
FoRTa OE
Potable water 3 4,000 bbl 1636.0 ma}
Dawater R00 sss
igodmad aT] iY
/Proload and ballast El 47,200 bor 174917 wey
[Dry bulk and mud 4,600 cult [130.2 m']
erent Fava TMT
40 Oilield Reviewbe a fine joining the base of two of the rie’s
feet—which two depends on the direction
ff the overturning force, which in turn
depends on the direction of the storm
leigho,
The gravity load of the Tidlent IX includes
6,049 tons of fixed load, 1,225 tons of vari-
able load—drill pipe, cement, and other
movable material—and 3,475 tons of legs
and spud cans. The buoyancy of the 400,
feet (122 meters) of immerse legs i 3.6 ton
per meter. The distance from the center of
‘gravity to the rotational axis is 44 feet (13.5
meters} Thus, the stabilizing moment is:
SM = (6,089 4 1,225 + 3,475
3.6 x 121.93 legs) «13.5,
= 127,338 ton-m,
‘well in excess of the overturning moment
‘under the design criteria of 82,290 ton-m.
But a simple excess is not enough. The
stability moment must exceed the overtum:
ing moment by a safety factor of SM/OTM.
The UK Department of Energy requires a
safely factor of at least 1.1 for independent
leg jack up rigs and 1.5 for mat-supported
jack ups. The Trident IX safety factor lor the
design criteria is 1.55. Wind more than any=
thing else reduces this. Sensitivity analysis,
however, shows that even in a worst storm it
‘won't dip below the 1-1 limit (see “ident
1X Sensitivity Analysis,” below)
‘Another application of the overturning
‘moment is determining how much preload
is necessary to simulate the maximum reac
tion the tig would experience during worst
case conditions, Consider the Trident IX
fully loaded subjected to its design criteria:
as before, the OTM-iotal is 82,290 ton-m.
Suppose a storm approaches from aft
(behind), and the distance between the aft
legs and the forward leg is 133 feet (40.52
‘Wind
Deviation from Desk
Giteta Moment
Weight
Genter of
Geauiy
aa:
Weathor
Breeton
\Verical sabitieing
Waveeurrent
Moment
Total
See
Moment a
Factor
foe ana jack up
its weight minus the
legs buoyancy.
Design erteria 52,190
20,100
82,290 155
Wind increases 20 knots 89,600
20,100
108,700 148
Wave hi. incteases 15 62.180
38,260
100.440 127
Current increases 2 knots | 62,190
93,815
96,005 193)
Water depth deer. 100 1 49,700
15,200
64,900 196:
Penevation increases 258 | 65,900
21,500
186 800 147
Volume 1 Number 1
ameters). Theo, the additional force on the
forward spuxl Can is 82,290/40,52 = 2,031
tons. This may be simulated by preloading.
‘The 1olal preload required to load the three
logs simultaneously is 2,031 x 3 = 6,093
tons, less than the Trident IX maximum
preload capacity of 7,663 tons. Some mar
sn i eequired to test ocean floos that night
‘permit a potential punch thiowgh (ight,
Elovating the rig with full preload is a
major breakthrough for recently built jack
vp rigs like the Tdtent 1X that are designed
for hash conditions and deep water. Inthe
future, the trend toward cleap water will
continue, athough i's unlikely jack ups will
‘evor operate in depths greater than 500 fet
1150 meters}. Future jack ups will almost
coitainly use Trident 1X's design technolo.
‘ay-—large, lightly constructed legs 10 reduce
the ocean’s overturning moment ancl a sim:
plo, powerful jacking system that bears most
‘0 the moment atthe rack and pinion mech
nism rather than at the guides. This tech-
nology has enough flexibility 10 ensure
compliance with increasingly tough safety
regulations. Jack ups may even become 2
safe alternative (@ conventional production
facilities. MR
42
Ponetration
Mud Line
Prooad
Blovated Storm
| Load
|
Buoyant Weight
LiPeneration vesus a
rigs buoyant woight
‘ving reloading
when there is no
punch doh top).
{he maxima preload
compacts the ocean
‘oor mare tn fre
cast forthe worstcase
Won thre pune
‘rou nie.
buoyant weight suc
ely eres Move
preload success
achieves the ested
‘Sew main beyond
Comcton ofthe
Sean for ores or
the worstcase stam,
Apseload tat lst
achievea punch
‘ough that occurs
far ding aster
spells poten eaas:
tophe thoton.
Oilfield Review