Professional Documents
Culture Documents
Technip Malaysia Petronas Carigali Turkmenistan Block 1 Feed
Technip Malaysia Petronas Carigali Turkmenistan Block 1 Feed
PETRONAS CARIGALI
TURKMENISTAN BLOCK 1 FEED
Distribution
Technip Malaysia Attn: John Sarbinowski
File: g:\projects\trc\20043120\report\l21713-2.doc
TURKMENISTAN BLOCK 1 FEED PROJECT
TRANSPORTATION METOCEAN DATA
CONTENTS
SECTION PAGE NO.
1 SUMMARY 6
1.1 INTRODUCTION 6
1.2 TRANSPORT DETAILS 6
1.3 TRANSPORTATION METOCEAN DESIGN CRITERIA 7
1.4 WAVE FREQUENCY TABLES 8
1.5 PORTS OF REFUGE AND SAFE HAVEN 8
1.6 SCOPE OF WORK 8
1.7 ADDITIONAL SCOPE OF WORK 10
2 PASIR GUDANG TO MARIUPOL 11
2.1 INTRODUCTION 11
2.2 SUMMARY 11
2.3 ROUTE DESCRIPTION 11
2.4 DEPARTURE DATES 12
2.5 CALCULATION OF VOYAGE SPEED 12
2.6 ROUTE SECTORS, DISTANCES AND HEADINGS 12
2.7 MEAN WAVES AND CURRENTS ALONG THE ROUTE 13
2.8 WORST ROUTE SECTORS 14
3 MARIUPOL TO ROSTOV 16
3.1 INTRODUCTION 16
3.2 SUMMARY 16
3.3 ROUTE DESCRIPTION 16
3.4 DEPARTURE DATES 17
3.5 ROUTE CONDITIONS 17
3.6 WORST ROUTE SECTOR 17
4 ROSTOV TO ASTRAKHAN 18
4.1 INTRODUCTION 18
4.2 SUMMARY 18
4.3 ROUTE DESCRIPTION 18
4.4 DEPARTURE DATES 18
4.5 WORST ROUTE SECTOR 19
5 ASTRAKHAN TO KIYANLY 20
5.1 INTRODUCTION 20
5.2 SUMMARY 20
5.3 ROUTE DESCRIPTION 20
5.4 DEPARTURE DATES 21
5.5 ROUTE CONDITIONS 21
5.6 WORST ROUTE SECTORS 21
6 KIYANLY TO MAGTYMGULY 22
6.1 INTRODUCTION 22
6.2 SUMMARY 22
6.3 ROUTE DESCRIPTION 22
6.4 INSTALLATION DATES 23
6.5 ROUTE CONDITIONS 23
6.6 WORST ROUTE SECTOR 23
6.7 TABLES FOR IN-PLACE FATIGUE 23
7 KIYANLY TO OWEZ 24
7.1 INTRODUCTION 24
7.2 SUMMARY 24
7.3 ROUTE DESCRIPTION 24
7.4 INSTALLATION DATES 24
L21713/NDC/MDS Rev: 2 28/12/2006 Page 2
File: g:\projects\trc\20043120\report\l21713-2.doc
TURKMENISTAN BLOCK 1 FEED PROJECT
TRANSPORTATION METOCEAN DATA
TABLES
Table 2-1 Route sectors, headings and distances 13
Table 2-2 Mean waves and currents along the route 14
Table 2-3 Pasri Gudang to Mariupol - worst route sectors 15
Table 9-1 Satellite wave data areas 30
Table 9-2 VOF wave data areas 31
Table 10-1 Choice of spectral model 36
L21713/NDC/MDS Rev: 2 28/12/2006 Page 3
File: g:\projects\trc\20043120\report\l21713-2.doc
TURKMENISTAN BLOCK 1 FEED PROJECT
TRANSPORTATION METOCEAN DATA
FIGURES
Figure 1-1 Map of assumed routes 7
Figure 2-1 Route (a) Pasir Gudang to Mariupol 11
Figure 3-1 Route (b) Mariupol to Rostov 16
Figure 4-1 Route (c) Rostov to Astrakhan 18
Figure 5-1 Route (d) Astrakhan to Kiyanly 20
Figure 6-1 Location of Magtymguly and Owez fields 22