Professional Documents
Culture Documents
Earthen Embankment
Earthen Embankment
Earthen Embankment
As a part of Coursework of
B.TECH ( Civil Engineering)
Submitted By
NAME - KUNAL KUMAR
BRANCH – Civil Engineering
SEMESTER – 7th
REGN NO – 18101128048
ROLL NO. – 18147
P a g e |1
PREFACE
P a g e |2
ACKNOWLEDGEMENT
P a g e |3
TABLE OF CONTENTS
2. PROJECT INFORMATION 6
4. EARTHEN EMBANKMENT 8
5. METHODS OF CONSTRUCTION 9
6. CONSTRUCTION PROCEDURE 10
12. CONCLUSION 24
P a g e |4
INTRODUCTION AND BACKGROUND
P a g e |5
PROJECT INFORMATION
Name of project :
BAGMATI FLOOD CONTROL MANAGEMENT SCHEME PHASE
III A
PURPOSE:
Raising and strengthening of the existing Hayaghat Karachin
Embankment from 123.52 KM(0.00KM) to 165.52 KM(42.00KM),
Karchin BadlaGhat Embankment from 198.52KM (0.00KM) to
246.02KM (47.50KM), Badlaghat Nagarpara Embankment from
246.02KM (0.00KM) to 264.03KM (18.00KM) and construction of 99
nos. of earthen dhala, 107 nos. of vehicle crossing platforms, 17 nos.
of Anti Flood Sluice.
BENIFITTED POPULATION : 3.75 Lakh
REVISED ESTIMATED COST : Rs 980.81 CR
BENFIT COST RATIO : 1:1.119
CONCERNED DEPARTMENTS
Flood Control and Drainage, WRD Samastipur
Flood Control Circle , Khagaria
Flood Control Division – 2, Khagaria
DESIGN CRITERIA
Top width of retire embankment has been taken as 5.0m, river side
slope and country side slope has been taken as 3H:1V respectively.
Hydraulic gradient taken as 5:1.
P a g e |6
STAGES OF THE PROJECT
Any government project undergoes through certain steps or stages. The stages
are mentioned below:
I. Discussion in the Government about the need of the project.
II. After that committee is allotted to check the feasibility of the project. In
order to check the feasibility certain steps are taken which are
mentioned below:
i) Initial screening is conducted based on river profile and topographic
maps.
ii) Reconnaissance plan is developed using only already available data.
iii) Pre-feasibility plan is developed with a little exploration and
additional field data.
iv) Feasibility plan is developed with extensive exploration and collection
of additional field data.
v) Then if the project is found feasible, detailed survey is done in order
to collect more data.
vi) After it public opinion, environmental issues and effect on aquatic life
is taken in consideration.
vii) If all above results are satisfactory then the project is passed by
Government.
III. Design stage: point tests/surveys are conducted to finalize the design of
dams. At each succeeding stage, more data is collected and the plan is
firmed up with more precise details, dimensions and analysis. The design
stage ends up with drawings appropriate for construction activities. Still
further details/revision continues well during the construction of the
dam as new information is gathered or some already available
information is found to be incorrect and not valid.
IV. Phase wise detailed estimate is prepared
V. Tender is opened for the project
VI. Tender bid winner submits the working estimate
VII. Then the work is started with the authenticity of concerned government
division of that area.
P a g e |7
EARTHEN EMBANKMENT
P a g e |8
METHODS OF CONSTRUCTION
There are two methods of constructing earthen dams:
The slush, flowing towards the centre of the bank, tends to settle down. The coarser
particles get deposited soon after the discharge near the outer edge, while the fines
get carried and settle at the centre, forming a zoned embankment having a relatively
impervious central core.
Since the fill is saturated when placed, high pore pressures develop in the core
material, and the stability of the dam must be checked for these pressures. This type
of embankment is susceptible to settlement over long periods, because of slow
drainage from the core.
Hydraulic-fill method is, therefore, seldom adopted these days. Rolled-fill method
for constructing earthen dams is, therefore, generally and universally adopted in
these modern days.
P a g e |9
CONSTRUCTION PROCEDURE
Earth fill dam, also called earth dam or embankment dam, dam built up by
compacting successive layers of earth, using the most impervious materials to
form a core and placing more permeable substances on the upstream and
downstream sides. A facing of crushed stone prevents erosion by wind or rain,
and an ample spillway, usually of concrete, protects against catastrophic
washout should water overtop the dam.
Compared with concrete, soils and rock fragments lack strength, are much
more permeable, and possess less resistance to deterioration and disturbance
by flowing water. These disadvantages are compensated for by a much lower
cost and by the ability of earthfill to adapt to deformation caused by
movements in the dam foundation. This assumes, of course, sufficient usable
soil or rockfill is available near the dam site. Earth fill is often quite economical,
provided that a suitable “borrow” area can be utilized close to the construction
site.
Because of their great base widths, earth fill dams can be constructed on
unfavourable sites, such as open-joined rock or weaker and possibly locally
permeable clay. It is necessary, however, either to check or to harmlessly drain
away the seepage water that would otherwise weaken the downstream parts
of the dam and, in extreme cases, cause it to fail. Several countermeasures,
possibly in combination, can be employed: the foundation can be grouted or a
cut-off trench excavated and backfilled with an impermeable material; a
drainage blanket can be constructed at the base of the downstream part of the
dam, or individual drainage wells or galleries can be excavated; the length of
the seepage paths under the dam can be extended by means of an
impermeable blanket laid on the upstream side of the dam; or additional free-
draining fill can be placed at the downstream toe of the dam.
P a g e | 10
P a g e | 11
BULL DOZER AT WORK
P a g e | 12
SITE SELECTION AND INVESTIGATION FOR
EARTHEN EMBANKMENT/DAM
A) Hydraulic Failure
Hydraulic failure accounts for over 40% of earth dam failure and may be due to
one or more of the following:
(ii) Erosion of Downstream Toe: The toe of the dam at the downstream side
may be eroded due to heavy cross-current from spillway buckets or tail
water. When the toe of downstream is eroded, it will lead to failure of dam.
This can be prevented by providing a riprap at downstream side up to a height
above the tail water depth. Also, the side wall of the spillway should have
sufficient height and length to prevent possibility of cross flow towards the
earthen embankment.
(iii) Erosion of Upstream Surface: During winds, the waves developed near the
top water surface may cut into the soil of upstream dam face which may cause
slip of the upstream surface leading to failure. For preventing against such
failure, the upstream face should be protected with stone pitching.
(iv) Erosion of Downstream Face by Gully Formation: During heavy rains, the
flowing rain water over the downstream face can erode the surface, creating
gullies, which could lead to failure. To prevent such failures, the dam surface
should be properly maintained. All cuts\cracks should be filled on time and
surface should be well grassed to reduce the effect of surface runoff. Berms
could be provided at suitable heights and proper drainage should be
maintained.
P a g e | 13
B) Seepage Failure
Seepage always occurs in the dams. If the magnitude is within design limits, it
may not harm the stability of the dam. However, if seepage is concentrated or
uncontrolled beyond limits, it will lead to failure of the dam. Following are
some of the various types of seepage failure.
(i) Piping through Dam Body: Seepage starts through the poor soils in the body
of the dam, small channels are formed which transport dam’s material
downstream. As more materials are transported downstream, the channels
grow bigger and bigger which could lead to wash out of dam.
C) Structural Failure
About 25% of failure is attributed to structural failure, which is mainly due to
shear failure causing slide along the slopes. The failure may be due to:
(i) Slide in Embankment: When the slopes of the embankments are too steep,
the embankment may slide resulting in its failure. This occurs when there is a
sudden drawdown or drastic decrease in the upstream water level due to
some means, which is critical for the upstream side. Because of this,
development of extremely high pore pressures takes place which decreases
the shearing strength of the soil. The downstream side can slide especially
when dam is full. In this case upstream embankment failure is not as serious as
downstream failure.
P a g e | 14
If fissured rocks, such as soft clay, or shale exist below the foundation, the side
thrust of the water pressure may shear the whole dam and cause its failure. In
such failure the top of the dam gets cracked and the lower slopes moves
outward and forms large mud waves near the dam heel.
(iv) Earthquake may Cause the Following Types of Failure to Earth fill
Dams:
Cracks may develop in the core wall, causing leakages and piping failure.
Slow waves may set up due to shaking of reservoir bottom, and dam may
fail due to overtopping.
Settlement of dam which may reduce freeboard causing failure by
overtopping.
Sliding of natural hills causing damage to dam and its appurtenant
structures.
Fault movement in the dam site reducing reservoir capacity and causing
overtopping.
Shear slide of dam.
Failure of slope pitching.
P a g e | 15
COMPONENTS OF EARTHEN DAM
P a g e | 16
STRENGTHENING OF EARTHEN
EMBANKMENTS
P a g e | 17
Geo Textile Sand Bags
for Slope Protection
on the Embankment
P a g e | 18
ANTI FLOOD SLUICE
A sluice is a water channel controlled at both sides by a gate or lock. In this
project its main function is to control the flow of water from riverside to
country side.
P a g e | 19
ACTUAL PICTURE OF AFS
TERMINOLOGY RELATED :
H.F.L : The level of the highest flood ever recorded or the calculated level for
the highest possible flood discharge in a stream or river is called Highest Flood
Level (HFL)
WING WALL : A wing wall (also "wingwall" or "wing-wall") is a smaller wall
attached or next to a larger wall or structure.
BREAST WALL : Breast wall is the wall which is built to sustain the face of a
natural bank of the earth.
PARAPET : The parapet walls of the dams are constructed on the crest of the
dam.
SHEET PILES : Sheet piles are sections of sheet materials with interlocking
edges that are driven into the ground to provide earth retention and
excavation support. Sheet piles are most commonly made of steel, but can also
be formed of timber or reinforced concrete.
RCC BARREL TYPE : It is a straight forward single curvature shell construction.
P a g e | 20
CONSTRUCTION OF AFS AT PINNED LOCATION
P a g e | 21
GATE WALL 1ST LIFT RCC AT
10.5 KM
P a g e | 22
ADVANTAGES AND SHORTCOMINGS
P a g e | 23
CONCLUSION
The industrial training at FCD, Hathauri, Samastipur has been a very good
learning experience for me. The knowledge of theoretical subject is not enough
for any engineering stream. One has to have the practical knowledge to
remove the gap between the actual and expected performance.
Training helped me to know and develop various technical and
communication skills. It also gives us a lot of knowledge about the process, its
equipment and operational phases. The training is an important step towards
us becoming successful engineers.
The most important lesson that I have learned and co-operation is
discipline, management. With the immense cooperation at FCD not only did I
grasp technical knowledge regarding the public issues and operations but also
filled in the gap that always existed in real while studying a theoretical subject
with the same being put into practical use.
P a g e | 24