Professional Documents
Culture Documents
BS8485 - Code of Practice For The Characterization and Remediation From Ground Gas in Affected Developments
BS8485 - Code of Practice For The Characterization and Remediation From Ground Gas in Affected Developments
BRITISH STANDARD
gas in affected
developments
ICS 91.120.99; 91.200
© BSI 2007
Publication history
First published 31 October 2007
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
Contents
Foreword ii
Introduction 1
1 Scope 2
2 Normative references 2
3 Terms and definitions 2
4 Overview of ground gas characterization and assessment 3
5 Site categorization 3
6 Risk assessment objective – Estimation of a site characteristic
hazardous gas flow rate 6
7 Solutions choice 9
Annexes
Annex A (informative) Estimation of underfloor ventilation and
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
pressurization performance 13
Annex B (informative) Checklist of factors to take into
consideration 19
Bibliography 22
List of figures
Figure 1 – Ground gas characterization and assessment flowchart 4
Figure A.1 – Performance assessment criteria of ventilation layer for
methane hazard (from PiT [7]) 16
List of tables
Table 1 – Characteristic gas situation by site characteristic hazardous
gas flow rate 9
Table 2 – Required gas protection by characteristic gas situation and
type of building 10
Table 3 – Solutions scores 12
Table A.1 – Summary of gas dispersal characteristics of different
ventilation media on idealized foundations 17
Table A.2 – Comparison of PiT gas regime and CIRIA 665/BS 8485
calculated hazardous gas flow rate by gas screening value in l/hr 18
Table B.1 – Variables and common factors to be considered in the
application of this code of practice – Source variables 20
Table B.2 – Variables and common factors to be considered in the
application of this code of practice – Pathway variables 20
Table B.3 – Variables and common factors that should be considered in
the application of this code of practice – Target variables 21
Summary of pages
This document comprises a front cover, an inside front cover,
pages i and ii, pages 1 to 22, an inside back cover and a back cover.
© BSI 2007 • i
BS 8485:2007
Foreword
Publishing information
This British Standard is published by BSI and came into effect
on 31 October 2007. It was prepared by Technical Committee I/-/2,
Brownfield developments. A list of organizations represented on this
committee can be obtained on request to its secretary.
Presentational conventions
The provisions in this standard are presented in roman (i.e. upright)
type. Its recommendations are expressed in sentences in which the
principal auxiliary verb is “should”.
Commentary, explanation and general informative material is
presented in smaller italic type, and does not constitute a
normative element.
ii • © BSI 2007
BS 8485:2007
Introduction
When building/developing on or adjacent to: brownfield sites, sites
where degradable materials are present within the ground, and in areas
of mineworkings, there is a potential risk of the generation of ground
gases and accumulation of these gases within buildings. Under adverse
circumstances, methane and carbon dioxide gases can build up to
hazardous concentrations within confined spaces giving rise to a
potential risk of explosion or asphyxiation. Indeed, there are
documented cases of loss of life and damage to property resulting from
ground gas accumulation.
Guidance available up to the date of this British Standard has generally
focused on the occurrence and methods of measurement of ground
gases and the incorporation of protection measures into buildings to
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
mitigate the risk of building on sites affected by ground gas. The issue
of how to undertake assessment of gas monitoring data in order to
determine suitable parameters to be used in the design of protection
measures has, until recently, not been developed to any significant
degree and, as a result, design solutions often lack a rigorous
assessment of data and have often resulted in overly conservative
solutions or insufficient measures being adopted.
This standard is intended to provide a framework in line with
CLR 11 [1] that will allow designers to judge the adequacy of ground
gas and related site investigation data, and provides an approach to
determine appropriate ground gas parameters that can be used to
identify a range of possible construction solutions that will mitigate
against the presence of ground gas on a development site. Importantly,
it allows the identification of those sites where gas protection measures
are not required. The framework is not prescriptive and judgement may
be made as to the acceptability of risk and whether there is a cost
benefit in undertaking more rigorous site assessment or adopting
conservative measures in design. Emphasis is placed on the justification
and recording of risk assessments and design decisions throughout the
process.
This standard is intended to be used by designers of gas protection
measures and regulators involved in the assessment of design solutions.
It recognizes that there are a number of factors requiring consideration
which affect the sensitivity of the development to the effects of ground
gas, and that there are a range of solutions available for different
situations. In this regard it is anticipated that specialist advice will be
required in the assessment of the ground gas data and in the risk
assessment phase.
© BSI 2007 • 1
BS 8485:2007
1 Scope
This British Standard gives recommendations and describes methods
for the investigation and assessment of the ground gases methane and
carbon dioxide during new development of affected sites, and is not
intended for the assessment of completed developments.
It details a process that can be used to effectively demonstrate that risks
posed by the potential presence of ground gas have been adequately
considered and addressed.
It presents the assessment and decision making stages in the form of a
process flowchart, accompanying information and explanatory
guidance and, where appropriate, references to other guidance and
information.
The standard does not consider ground gases other than methane and
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
carbon dioxide.
NOTE Other gases might require specific risk assessments and have to be
considered separately.
2 Normative references
The following referenced documents are indispensable for the
application of this document. For dated references, only the edition
cited applies. For undated references, the latest edition of the
referenced document (including any amendments) applies.
BS 10175:2001, Investigation of potentially contaminated sites –
Code of practice
Card G, Hutchings H, Mallett H, Oliver S, Wilson S. CIRIA C665,
Assessing risks posed by hazardous ground gases for buildings.
CIRIA. 2007. (Formerly issued as C659.)
BRE Report 414. Johnson R. Protective measures for housing on gas
contaminated land. 2001.
2 • © BSI 2007
BS 8485:2007
5 Site categorization
5.1 Desk Study
COMMENTARY ON 5.1
The main objectives of the desk study are to start the process of
constructing a conceptual model of the likely gas sources on or near the
site, the likely migration pathways and receptors. This will inform further
site investigation which will in turn revise and augment the conceptual
model. Relevant guidance on the requirements and objectives of a desk
study can be found in BS 10175:2001. Site investigations ought to be
designed in accordance with BS 5930 and published guidance such as the
AGS Guidelines for Good Practice in Site Investigation [2]. Detailed advice
on investigation of ground gas can be found in CIRIA C665.
The primary requirements and objectives of the desk study should all be
met, which are as follows.
a) Have all potential gas sources been identified or discounted? The
assessment should include identification of natural geological
sources, mine workings, waste materials, landfills, and an
understanding of the nature of the gas generation processes
involved.
b) Have the site history and current use been evaluated and any likely
gas sources, migration pathways and receptors arising from site
uses been identified?
c) Is there a clear understanding of the geology and hydrogeology of
the site, and the presence of contamination, and how it might
affect gas sources and gas migration? This includes the effect of
groundwater level variations, including tidal variations (and how
these can affect gas sources and gas migration).
d) Have all potential pathways been identified or discounted? This
includes natural geological pathways, services, underground
structures and mine workings.
e) Have potential receptors, both on and off site, been identified and
their sensitivity assessed?
© BSI 2007 • 3
BS 8485:2007
Remediation method
selection, remediation design
OPTIONS
APPRAISAL Could the remedial
costs be significantly reduced by
Yes
improving the data quality to "comprehensive"
and reducing characterestic
emission rates?
No
Implement remediation
IMPLEMENTATION OF
REMEDIATION STRATEGY
Undertake appropriate validation
4 • © BSI 2007
BS 8485:2007
© BSI 2007 • 5
BS 8485:2007
6 • © BSI 2007
BS 8485:2007
© BSI 2007 • 7
BS 8485:2007
8 • © BSI 2007
BS 8485:2007
Table 1 Characteristic gas situation by site characteristic hazardous gas flow rate
Characteristic Hazard potential Site characteristic Additional factors
gas situation hazardous gas flow
rate, Qhgs
lh–1
1 Very low <0.07 Typically u1% methane concentration and u5% carbon
dioxide concentration (otherwise consider an increased
characteristic gas regime)
2 Low W0.07, <0.7 Typical measured flow rate < 70 l/h (otherwise consider
an increased characteristic gas regime)
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
7 Solutions choice
7.1 Recommended gas protection
Having ascertained the characteristic gas situation, as the final part of
the process, the appropriate gas protection should be selected for the
building.
There are a great number of existing designs and component elements
available in the current market (and others being developed constantly);
this document does not seek to remove professional judgement which
should at all times form part of any decision making process; Table 2
and Table 3 however give a guide as to the relative performance of the
various types of designs and systems available today.
Given the combined design gas regime and risk factors, a guidance
value for the required gas protection in the range 0 to 7 should be
obtained from Table 2. Then, a combination of ventilation and/or barrier
systems should be chosen from Table 3 to meet that requirement.
NOTE The guidance value is allocated to reflect the risk associated with
the characteristic gas situation and the combined effectiveness of the
elements in Table 3.
© BSI 2007 • 9
BS 8485:2007
Table 2 Required gas protection by characteristic gas situation and type of building
Characteristic NHBC Required gas protection
gas situation, CS traffic light
Non-managed Public building A) Commercial Industrial buildings B)
property, e.g. buildings
private housing
1 Green 0 0 0 0
2 Amber 1 3 3 2 1 C)
3 Amber 2 4 3 2 2
4 Red 6 D) 5 D) 4 3
5 6 E) 5 4
6 7 6
NOTE Traffic light indications are taken from NHBC Report no.: 10627-R01 (04) [3] and are mainly applicable
to low-rise residential housing. These are for comparative purposes but the boundaries between the traffic light
indications and CS values do not coincide.
A) Public buildings include, for example, managed apartments, schools and hospitals.
B) Industrial buildings are generally open and well ventilated. However, areas such as office pods might require a separate
assessment and may be classified as commercial buildings and require a different scope of gas protection to the main
building.
C) Maximum methane concentration 20% otherwise consider an increase to CS3.
D) Residential building on higher traffic light/CS sites is not recommended unless the type of construction or site
circumstances allow additional levels of protection to be incorporated, e.g. high-performance ventilation or pathway
intervention measures, and an associated sustainable system of management of maintenance of the gas control
system, e.g. in institutional and/or fully serviced contractual situations.
E) Consideration of issues such as ease of evacuation and how false alarms will be handled are needed when completing
the design specification of any protection scheme.
10 • © BSI 2007
BS 8485:2007
© BSI 2007 • 11
BS 8485:2007
pressurization.
Ventilated car park (basement or undercroft) 4 Assumes car park is vented to deal with
car exhaust fumes, designed to Building
Regulations Document F [5] and IStructE
guidance [6].
b) Barriers
Floor slabs
Block and beam floor slab 0 It is good practice to install ventilation in
Reinforced concrete ground bearing floor slab 0.5 all foundation systems to effect pressure
Reinforced concrete ground bearing foundation raft with limited 1.5 relief as a minimum.
service penetrations that are cast into slab Breaches in floor slabs such as joints have
to be effectively sealed against gas
Reinforced concrete cast in situ suspended slab with minimal 1.5
ingress in order to maintain these
service penetrations and water bars around all slab penetrations
performances.
and at joints
Fully tanked basement 2
c) Membranes
Taped and sealed membrane to reasonable levels of 0.5 The performance of membranes is
workmanship/in line with current good practice with heavily dependent on the quality and
validation B), C) design of the installation, resistance to
Proprietary gas resistant membrane to reasonable levels of 1 damage after installation, and the
workmanship/in line with current good practice under integrity of joints.
independent inspection (CQA) B), C)
Proprietary gas resistant membrane installed to reasonable 2
levels of workmanship/in line with current good practice under
CQA with integrity testing and independent validation
d) Monitoring and detection (not applicable to non-managed property, or in isolation)
Intermittent monitoring using hand held equipment 0.5
Permanent monitoring and alarm Installed in the 2 Where fitted, permanent monitoring
system A) underfloor venting/ systems ought to be installed in the
dilution system underfloor venting/dilution system in the
Installed in the 1 first instance but can also be provided
building within the occupied space as a fail safe.
e) Pathway intervention
Pathway intervention — This can consist of site protection
measures for off-site or on-site sources
(see Annex A).
NOTE In practice the choice of materials might well rely on factors such as construction method and the risk
of damage after installation. It is important to ensure that the chosen combination gives an appropriate level of
protection
A) It is possible to test ventilation systems by installing monitoring probes for post installation validation.
B) If a 1 200 g DPM material is to function as a gas barrier it should be installed according to BRE 212 [8]/BRE 414 [9],
being taped and sealed to all penetrations.
C) Polymeric Materials >1 200 g can be used to improve confidence in the barrier. Remember that their gas resistance is
little more than the standard 1 200 g (proportional to thickness) but their physical properties mean that they are more
robust and resistant to site damage.
12 • © BSI 2007
BS 8485:2007
© BSI 2007 • 13
BS 8485:2007
for a range of gas regimes and building sizes. The data is based on
computational fluid dynamics analysis (CFD). The scope of the
original analyses was limited to two sizes of building and limited
ventilation options at the outlets. Various manufacturers have
subsequently commissioned the authors of the report to
undertake further CFD analysis that extends the tables in the
original report.
c) Specific CFD modelling for a particular system or site.
For active ventilation and positive pressurization, the volume of air
flow required to dilute the gas to acceptable levels is estimated using
the guidance in CIRIA Report 149 [13]. It is then a simple matter
of providing a sufficient number of fans to meet the required
capacity (allowing for factors of safety, breakdowns, even air flow, etc.).
Positive pressurization systems also have to provide sufficient air
flow to maintain the pressure immediately below the slab at a level
that is greater than the pressure driving the gas from the ground. All
systems with fans have to be designed to vent passively whenever
possible in the event that the fans stop working (e.g. due to power cuts).
Factors of safety have to be applied to the required ventilation or fan
capacity, depending on the sensitivity of the end use and the robustness
of the conceptual model and data for the site (including desk study,
descriptions of the gas source as well as gas monitoring data). Factors
of safety typically vary from 1 to 3.
14 • © BSI 2007
BS 8485:2007
© BSI 2007 • 15
BS 8485:2007
Y
5.0
4.0
E
3.0 D
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
C
2.0
B
1.0
Table A.1 (taken from PiT [14]) was derived from research based on the
computational fluid dynamic modelling of a range of ventilation media.
There are many factors to be considered in assessing the potential
performance of a passive ventilation system and therefore this table is
to be considered as a guide only and to determine the appropriate
scoring for a chosen media type in Table 3. Specialist advice will
generally be required in designing a suitable passive ventilation system.
Gas regimes A to F do not equate to calculated hazardous gas flow rates
(Qhg) 1 to 6. Column four of Table A.2 gives an indication of the fit
between the PiT gas regimes and the Qhg scale.
16 • © BSI 2007
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
Table A.1 Summary of gas dispersal characteristics of different ventilation media on idealized foundations
Open void space A) Polystyrene shuttering A) Geocomposite 20 mm single size 20 mm single
Methane concentration
Characteristic situation E)
drainage blanket gravel blanket size gravel
blanket with
Equivalent clear void Equivalent clear Equivalent clear void
interleaved
Emission rate D) depth 22 mm depth 100 mm depth 36 mm
pipes at
3 m centres B)
Gas regime
Foundation width C)
% v/v m/s 5m 30 m 5m 30 m 5m 30 m 5m 30 m 5m 30 m 30 m
A 1 0.005 2 Adequate Adequate Adequate Adequate Adequate Adequate Adequate Adequate Adequate Adequate Adequate
B 5 0.005 3 Very good Very good Very good Good Very good Very good Very good Good Good Poor Good
C 5 0.01 4 Very good Very good Very good Good Very good Very good Very good Fair Fair Unsuitable Fair
D 20 0.005 4 Very good Very good Very good Fair Very good Good Good Poor Poor Unsuitable Poor
E 20 0.01 4 Very good Good Good Poor Very good Good Good Unsuitable Poor Unsuitable Unsuitable
F 20 0.05 5 Good Poor Fair Unsuitable Fair Poor Fair Unsuitable Unsuitable Unsuitable Unsuitable
A) For open void space and polystyrene shuttered ventilation layers additional side ventilation provision can improve gas dispersal characteristics.
B) Gas dispersal characteristics based on maximum steady state concentration over 80% area of foundation, pipes interleaved at 3 m centres.
C) Assumes sympathetically detailed underside of foundation.
D) Emission rate values refer to equivalent total gas flow velocity from 50 mm diameter borehole and Peckson [10] assumption.
E) Characteristic situation after CIRIA Report 149 [13].
© BSI 2007
BS 8485:2007
•
17
BS 8485:2007
Table A.2 Comparison of PiT gas regime and CIRIA 665/BS 8485
calculated hazardous gas flow rate by gas screening value in l/hr
Gas regime (PiT [7]) Qhg (CIRIA 665 and BS 8485)
1 < 0.07
A < 0.35
2 < 0.7
B < 1.77
C < 3.5 3 < 3.5
D < 7.1
4 < 15
E < 14.15
5 < 70
F < 70.77
6 > 70
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
18 • © BSI 2007
BS 8485:2007
Table B.1, Table B.2 and Table B.3 also set out some of the common
factors that have to be taken into account when deciding on the level of
risk associated with any development where gas protection measures
are required. Each of these risk variables has to be appraised by the
designer in order to determine the appropriate uncertainty factor to be
applied to a given situation. The designer ought to show that he has
assessed the impact of each of these variables (and any other variables
that are relevant to the site and the proposed development);
consideration of these factors may require the designer to select a
higher gas protection level than that indicated in Table 2.
It is common that the post-construction gas regime will differ from that
measured pre-construction. A number of factors can affect this.
EXAMPLE
If a large area of the site surface is effectively sealed, then gas will be
forced to migrate to escape from other areas of the site (increasing the
emissions in that area post construction compared to the monitoring
data), or indeed, perhaps increase off-site migration.
Such a circumstance might occur if as part of the development:
a) large areas are to be laid to hardstanding;
b) a fully lined and contained SUDs scheme for site drainage is
required; or
c) a large warehouse type building is likely to need gas protection such
as is provided by a positive air blanket (that functions by displacing
the gas away from the underside of the building).
(These are examples, not an exhaustive list.)
© BSI 2007 • 19
BS 8485:2007
20 • © BSI 2007
BS 8485:2007
Table B.3 Variables and common factors that should be considered in the
application of this code of practice – Target variables
Complexity of Suspended floor slab
substructure A) Single level ground bearing floor slab with flat
underside
Single level ground bearing floor slab with
downstanding ground beams
Multi-level ground bearing floor slab
Basement incorporated in structure
Validation of installed Specialist contractor installed, independent
design measures B) inspection and testing by specialist engineer
Specialist contractor installed, independent
inspection by specialist engineer
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
© BSI 2007 • 21
BS 8485:2007
Bibliography
Standards publications
BS 5925, Code of practice for ventilation principles and designing
for natural ventilation
BS 5930, Code of practice for site investigations
Other publications
[1] Model procedures for the management of land contamination
CLR11. 2004 Environment Agency.
[2] AGS Guidelines for Good Practice in Site Investigation.
Association of Geotechnical and Geoenvironmental Specialists.
(http://www.ags.org.uk)
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
22 • © BSI 2007
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
BS 8485:2007
Revisions
British Standards are updated by amendment or revision. Users of British Standards
should make sure that they possess the latest amendments or editions.
It is the constant aim of BSI to improve the quality of our products and services.
We would be grateful if anyone finding an inaccuracy or ambiguity while using this
British Standard would inform the Secretary of the technical committee responsible,
the identity of which can be found on the inside front cover.
Tel: +44 (0)20 8996 9000. Fax: +44 (0)20 8996 7400.
Licensed copy:MOHAMED SALAHUDDIN CONSULT, 10/03/2009, Uncontrolled Copy, © BSI
BSI offers members an individual updating service called PLUS which ensures that
subscribers automatically receive the latest editions of standards.
Buying standards
Orders for all BSI, international and foreign standards publications should be
addressed to Customer Services. Tel: +44 (0)20 8996 9001.
Fax: +44 (0)20 8996 7001. Email: orders@bsi-global.com. Standards are also
available from the BSI website at http://www.bsi-global.com.
In response to orders for international standards, it is BSI policy to supply the BSI
implementation of those that have been published as British Standards, unless
otherwise requested.
Information on standards
BSI provides a wide range of information on national, European and international
standards through its Library and its Technical Help to Exporters Service. Various
BSI electronic information services are also available which give details on all its
products and services. Contact the Information Centre. Tel: +44 (0)20 8996 7111.
Fax: +44 (0)20 8996 7048. Email: info@bsi-global.com.
Subscribing members of BSI are kept up to date with standards developments and
receive substantial discounts on the purchase price of standards. For details of these
and other benefits contact Membership Administration. Tel: +44 (0)20 8996 7002.
Fax: +44 (0)20 8996 7001. Email: membership@bsi-global.com.
Information regarding online access to British Standards via British Standards
Online can be found at http://www.bsi-global.com/bsonline.
Further information about BSI is available on the BSI website at
http://www.bsi-global.com.
Copyright
Copyright subsists in all BSI publications. BSI also holds the copyright, in the UK, of
the publications of the international standardization bodies. Except as permitted
under the Copyright, Designs and Patents Act 1988 no extract may be reproduced,
stored in a retrieval system or transmitted in any form or by any means – electronic,
photocopying, recording or otherwise – without prior written permission from BSI.
This does not preclude the free use, in the course of implementing the standard, of
necessary details such as symbols, and size, type or grade designations. If these
details are to be used for any other purpose than implementation then the prior
written permission of BSI must be obtained.
389 Chiswick High Road Details and advice can be obtained from the Copyright & Licensing Manager.
London Tel: +44 (0)20 8996 7070. Fax: +44 (0)20 8996 7553.
W4 4AL Email: copyright@bsi-global.com.