Professional Documents
Culture Documents
Earned Value Management Explained: Crowdbotics Blog
Earned Value Management Explained: Crowdbotics Blog
Earned Value Management Explained: Crowdbotics Blog
d t di t h it
https://blog.crowdbotics.com/earned-value-management-explained/ d li l f ft 1/14
4/19/2021 Earned Value Management Explained
understanding as to how it can deliver value for your software
Crowdbotics Blog Share this
company.
What is the De nition of Earned Value
Management?
How did Earned Value Management come into existence? What was
the problem that it initially solved? Let's understand the history of
EVM to learn more about it.
This concept in its nascent form dates to the turn of the last century
when it was used in industrial manufacturing. The essential
principle, as conceived of by Frank Gilbreth, was to identify the "one
best way" to accomplish a task. Gilbreth was speci cally focused on
reducing the e ort and fatigue of manual labor, but the process of
tracking di erent work methods within an industrialized workplace
and identifying the optimal approach had applications beyond its
initial use.
NASA th D t t fE
https://blog.crowdbotics.com/earned-value-management-explained/ d th h t 2/14
4/19/2021 Earned Value Management Explained
NASA, the Department of Energy, and other such government
Crowdbotics Blog Share this
agencies.
The construction sector and other real estate-adjacent industries
were known to be early adopters of EVM in the U.S. EVM has now
been an integral component in federal project risk management
since 2005. Even today, the O ce of Management and Budget
prefers using EVM in software projects as a performance
management system.
Planned Value (PV) in EVM means the total estimated costs that
will be incurred by completing the project. Actual Cost (AC) is the
value of actual work done at a particular time in the project. Earned
Value (EV) quanti es the total worth of work done at that particular
moment in the project. EV is computed by multiplying the total
budget and percentage of work done.
ti t th t th t t l t
https://blog.crowdbotics.com/earned-value-management-explained/ ill b $5000 d th ti t k ld 3/14
4/19/2021 Earned Value Management Explained
estimates that the total cost will be $5000 and the time taken would
Crowdbotics Blog Share this
be 2 months. Thus, the PV here is $5000. After a month,
Crowdbotics sends a bill of $2300 to the client after developing 4
modules. This $2300 is the AC of work done in one month. Ideally,
50% of the work amounting to $2500 should have been done by
now, but only 40% ($2000 worth) of work is done so far. Thus, the
EV is 0.40 * $5000 =$2000. Now, a graph is plotted like the one
below for a pictorial representation to answer three main
questions. These questions are:
1. Where are we currently?
The graph below shows the progress of the project at the time of
the EVM analysis.
bt ti th t l t (AC) f
https://blog.crowdbotics.com/earned-value-management-explained/ th d l (EV) f 4/14
4/19/2021 Earned Value Management Explained
subtracting the actual costs (AC) from the earned value (EV) of a
Crowdbotics Blog Share this
project.
Here it is mathematically:
CV = EV - AC
Schedule Variance (SV) tells you how much you have progressed
with the schedule that was set initially. Are you ahead of what was
planned or behind?
Here it is mathematically:
SV = EV - PV
Indexing Performance
Th t id ti
https://blog.crowdbotics.com/earned-value-management-explained/ j t' f i di hi h 5/14
4/19/2021 Earned Value Management Explained
The next considerations are a project's performance indices, which
Crowdbotics Blog Share this
are its cost performance index (CPI) and schedule performance
index (SPI). CPI and SPI signify the CV and SV in proportion to the
scale of work done by far. They are calculated using the following
formulae:
CPI = EV/AC
SPI = EV/ PV
In the example above, CPI is 0.86 and SPI is 0.40. These indices will
help you forecast the current trend of the project and where it will
lead you. This forecasting is done by computing the estimated cost
at completion (EAC) and estimated time at completion (ETC).
The former gure gives you the forecasted nal cost of the project,
and the latter gives you the forecasted number of days to nish the
project. They are calculated as follows:
https://blog.crowdbotics.com/earned-value-management-explained/ 6/14
4/19/2021 Earned Value Management Explained
A id
https://blog.crowdbotics.com/earned-value-management-explained/ tif th l h l i 7/14
4/19/2021 Earned Value Management Explained
As a manager, you can identify the loopholes or pain
Crowdbotics Blog Share this
points in the project which are outside the scope, time,
and cost estimates.
You might think that EVM methodology is only for waterfall projects,
but EVM works equally well with agile-based projects as well. This
approach is referred to as Agile EVM and o ers EVM bene ts for
https://blog.crowdbotics.com/earned-value-management-explained/ 8/14
4/19/2021
pp gEarned Value Management Explained
Crowdbotics
ScrumBlog
using the three main EVM characteristics of cost,Share
time,this
and
scope.
After every sprint, project managers collect the actual data. Then,
the methodology described earlier in this blog is repeated where
PV, SPI, and CPI are calculated to get the estimated number of
iterations needed, total cost, and duration. One problem of
employing EVM in agile is that it requires scope quanti cation,
which makes agile teams apprehensive.
Conclusion
Nakul Shah
Nakul Shah is a Senior Product Manager with experience working
Read More
for startups and enterprises across 10+ countries. He is also an
SME and author on topics like Blockchain, Fintech and Emerging
Tech.
Free Quote:
Estimate cost and timeline for your custom app
First name*
Last name*
Company name*
Email*
Employee Count*
Please Select
Job Title*
Website URL*
Country/Region*
https://blog.crowdbotics.com/earned-value-management-explained/ 10/14
4/19/2021 Earned Value Management Explained
Tell us a little bit about the app you would like to build.
Design Tool*
Method or tool used for creating wireframe, prototype, UX, or visual designs.
Please Select
Design Attachment
Wireframe, prototype, template, sketch, design le, screen diagram, etc. (optional)
Please Select
Phone number
Please Select
Please Select
Start Building
https://blog.crowdbotics.com/earned-value-management-explained/ 11/14
4/19/2021 Earned Value Management Explained
2 replies Blog
Crowdbotics Share this
Are there any other methodologies that you think are helpful in determining cost overruns
of a project?
— Crowdbotics Blog —
Project
Management
RAD STACK
https://blog.crowdbotics.com/earned-value-management-explained/ 12/14
4/19/2021 Earned Value Management Explained
PRODUCT DEVELOPMENT
Project managers and engineering teams need to identify the right way to resume third-
party or internal software development after COVID. Here are a few suggestions.
6 MIN READ
Developer? Try out the Crowdbotics App Builder to quickly sca old and
deploy apps with a variety of popular frameworks.
Connect with Crowdbotics to turn ideas and specs into working code.
Start Building
https://blog.crowdbotics.com/earned-value-management-explained/ 13/14
4/19/2021 Earned Value Management Explained
About Built With Crowdbotics Documentation Discuss App Builder Managed App Development
VERIFIED PARTNER
https://blog.crowdbotics.com/earned-value-management-explained/ 14/14