Schedule of 2poultries Building in Batangas A2
Schedule of 2poultries Building in Batangas A2
First Month
No. Descriptions Section Days
1 2 3 4 5 6 7 1 2 3 4 5 6 7
POULTRY 1
1 Installation of manholes cover
2 Excavation of trench for culverts
Septic tank for
3 Laying of culverts 3 Poultries
4 Construction of 2 open manhole
5 Backfilling & leveling
POULTRY 2
1 Leveling and alignment of I beams
2 Grouting between foundation & I beam
3 Curing
4 Installation Rafters
5 Installation of Purlis
6 Installation of sag rod
7 Installation of cross braces w/ buckles
8 Installation of roofing materials
9 Installation of walling ( long span) Building
10 Installation of walling (short span)