Professional Documents
Culture Documents
Mid Rise Code1 DCR
Mid Rise Code1 DCR
INTRODUCTION 1 4. USE 9
The Eight Principles of Jumeirah Village 1 Section 4.01. Types of Use 9
The Jumeirah Village - Master Plan and Development Code 2 Section 4.02. Use Categories 9
Contents of the Development Code 2 Section 4.03. Conditional Use 9
Section 4.04. Accessory Use or Structure 9
1. GENERAL PROVISIONS 3 Section 4.05. Temporary Use 12
Section 1.01. Title 3
Section 1.02. Authorities 3 5. FORM CODE – MID-RISE LOTS 13
Section 1.03. Purpose & Intent 3 Section 5.01. General 13
Section 1.04. Applicability 3 Section 5.02. Building Configuration and Size 13
Section 1.05. Amendments 3 Section 5.03. Building Setbacks 14
Section 1.06. Measuring System 3 Section 5.04. Urban Design 14
Section 5.05. Architectural Treatments 14
2. REVIEW AUTHORITY 4
Section 2.01. General Authority 4 6. PARKING AND LOADING 17
Section 2.02. Development Code Administrator 4 Section 6.01. Purpose and Type 17
Section 2.03. Development Review Board 4 Section 6.02. General Provisions 17
Section 6.03 Space Requirements 17
3. ZONE 6 Section 6.04. Space and Lot Design 17
Section 3.01. Establishment of Zones 6 Section 6.05. Loading Areas 19
Section 3.02. Official Zoning Map 6
Section 3.03. Interpretation of Boundaries 6
Section 3.04. Uniform Application of Zones 6
dubai, u.a.e. - october 2006 j u m e i r a h v i l l a g e - MI D RI S E d e v e l o p m e n t c o d e
Introduction
introduction
The Eight Principles of Jumeirah Village symmetry through an organized radial pattern and median
streets that end in a large-scale central park. At the same
Jumeirah Village is a community designed to embody a vision
time, the design also allows neighborhoods and open spaces
of peace, harmony, health, and happiness – a community with
to occur in a more natural, pedestrian friendly manner.
the highest standards of quality of life created by capturing
the best characteristics of Arab and Western culture. Overall, Mixed Use
eight principles form the foundation of Jumeirah Village: Actively mixed uses are a part of many of the most dynamic
and successful communities throughout the world. Mixing
Sense of Peace and Community
uses promotes accessibility to major community features
Jumeirah Village promotes an environment that features
such as parks and commercial centers and provides natural
peace and harmony among neighbors. Emphasis is placed
gathering places for residents. Jumeirah Village intertwines
upon creating an atmosphere that promotes friendship,
uses in a manner that builds both economic viability and a
family, healthy interaction and other dynamic traits that
sense of community.
set the neighborhoods of this community apart from other
development. Icons and Focal Points
Landmarks are an important component of the community as
Pedestrian Friendliness
a tool for sense of direction, community recognition, and local
Walking and biking are more than exercise. They are an
pride. The unique towers, the central park, the interconnected
invitation to meet friends, allow children to play, and live life
series of open spaces, the meandering water feature, and
at a slower pace. The design of Jumeirah Village promotes
the town centers are all icons that are unique to Jumeirah
walking, biking and other alternatives through creation of a
Village.
convenient and entertaining atmosphere, including features
such as pedestrian access, landscaping, stores, street Strong Public Space & Private Space
furniture, architectural detail, and open spaces. A home is recognized as a place for privacy throughout Arab
and Western culture. Today, the opportunity for privacy is
Water and Green Space
increasingly more important as a healthy escape from the
Green spaces and water represent a healthy life and
bustle of life. At the same time, however, public spaces
abundance in comparison to the stark beauty of the desert.
are expected to be locations of significant and dynamic
Throughout Arab history, oases have served as attractions
interaction – places for gathering, relaxing, entertaining, and
providing nourishment and focal points for gathering and
shopping. Jumeirah Village offers a broad range of choices
association. Jumeirah Village celebrates the importance
for privacy and proximity to public space. The best of both
of greenery and water in the desert landscape through
worlds is found throughout the community.
development of open spaces and water features that connect
the neighborhoods and Zones of the community. Many of the Health and Happiness
public amenities found in Jumeirah Village including parks, Jumeirah Village - is a living and working environment
sports fields, schools, mosques, and more are strategically that offers superior quality of life, including a healthy and
clustered in the green spaces to create accessible gathering enjoyable living environment. The numerous, interconnected
places reminiscent of the importance of the historic oasis. green spaces and clustered gathering spaces are
intentionally designed to promote a healthy physical lifestyle.
Mix of Symmetry and Natural Form
Neighborhoods are intended to promote social interaction.
Symmetry is a critical component of Islamic art, Arab
architecture and Western urban design. However, many of Jumeirah Village was created by applying these Eight
the most successful communities and spaces in the world Principles throughout the design process. Neighborhoods
have “evolved” through a natural, organic pattern. Jumeirah are designed to be places of interaction and enjoyment that
Village is intentionally designed to capture a sense of are always within easy walking distance of parks, public
J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e - o c t o b e r 2 0 0 6 J UMEIRAH V ILLAGE LL C
introduction
amenities, shopping needs, and friends. The streetscape The Development Code potential parking on the site. In Jumeirah Village, however,
is designed to be attractive, functional and inviting to both The Master Plan is a guide, a detailed layout of spaces and on-street parking is strongly encouraged and is considered
motorists and pedestrians. Jumeirah Village offers an Block Guidelines that provide clues to the detailed design part of meeting parking requirements.
immense number of choices in housing and neighborhoods of Jumeirah Village. The Development Code is a tool for Contents of the Development Code are broken down as
amenities ranging from secluded villas to the bustle of living implementing the Master Plan. It provides the regulatory follows:
in the Town Center. framework that ensures structures and uses are located
A. General Provisions. Introduce the Development Code and
according to plan and that the anticipated high quality of life
provide the purpose, intent and applicability of the Code.
The Jumeirah Village for residents, employees and guests in Jumeirah Village is
Master Plan and Development Code realized. The Development Code is specifically designed to B. Review Authority. Confirms Jumeirah Village LLC as the
carry out several functions: ultimate authority regarding development in Jumeirah
Two documents guide the development of Jumeirah Village
Village and designates representatives responsible for
to ensure that the community reaches its full potential and A. Ensure design that promotes the highest principles of
carrying out the daily duties of administering the Code.
appropriately applies the Eight Principles – The Master Plan general health, welfare and safety for individuals that
and the Development Code. These documents work together live, work or visit the community. C. Zones. Divides the community into areas of common
to span the divide between the vision for Jumeirah Village interest and typology for purposes of regulation.
B. Provide the minimum standards needed to carry out
and the standards necessary to ensure that all is completed the vision established by the Master Plan. The intent of D. Use. Designates permitted uses in each of the zones of
according to plan. the Development Code is to focus, not reign in, creative Jumeirah Village.
The Master Plan freedom. E. Form. Addresses the location, size and design of all
The purpose of the Master Plan is to set the general C. Establish procedures needed for Jumeirah Village structures in the community.
foundation for the physical design of Jumeirah Village. The LLC to successfully carry out the requirements of the F. Parking. Establishes guidelines for provision, location,
Master Plan represents the physical layout of lots, open Development Code. type and design of parking areas.
spaces and amenities throughout the site. The Master Plan D. Provide the tools to make sound decisions regarding the G. Signs. Discusses permitted sign types by purpose,
also includes the overall design strategy that evolved from inevitable evolution of Jumeirah Village. Communities location, size, number, intent, and detail.
the initial Eight Principles for the project. It discusses the must change over time to remain dynamic. However, H. Landscape and Fencing. Acknowledges the benefits of
major features and characteristics that make Jumeirah change does not have to come at the cost of maintaining adding “green spaces” and screening to the community
Village unique, from the broad description of the relationship the Eight Principles that make Jumeirah Village unique. as a means of “softening” the built environment,
between neighborhoods, open spaces, streets, and centers This Code ensures that sufficient information and improving aesthetics, and adding additional opportunities
to more detailed discussion of the appearance of the procedures are available to allow the community, and for recreation.
streetscape and the types of uses expected in the various the tools used to guide development in the community,
community “centers”. The Master Plan establishes the I. Administration and Procedures. Provides the tools and
to change in ways that benefit Jumeirah Village over the
general Circulation Plan for the community and, even here, processes needed to administer the Development Code.
long term.
the Eight Principles have been combined with the need for J. Definitions. Describes the various technical or specific
efficient and safe travel choices. The Master Plan document Contents of the Development Code terms found throughout the Development Code.
is accompanied by two Master Plan Maps – an illustrated K. Application Checklists. Ensure that appropriate and
The Development Code for Jumeirah Village is designed
map that generally depicts the look of a completed project sufficient information is conveyed by the potential
to address a broad range of issues important to carrying
and a digital map that delineates the specific location and applicant to Jumeirah Village LLC when requesting to
out the functions described above and meeting the Eight
coordinates of lots and spaces. develop a site.
Principles that serve as the foundation for the community. The
guidelines address many issues common to all communities,
but once again, they also show an attention to detail unique
to Jumeirah Village. For example, traditional streets are
designed with sufficient width to provide parking but codes
commonly require that a development accommodate all
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e
1. General Provisions
2. Review Authority
review authority
Section 2.01. General Authority 2.01.03. Conformity with Development Code 2.02.03. Staff Duties on Behalf of Development Review Section 2.03. Development Review Board
No employee of Jumeirah Village LLC granted authority by Board
2.01.01. Delegation of Authority this Code may approve or issue a permit for a development In addition to duties described in Section 2.02.02, the 2.03.01. Designation
As stated in Section 1.02.01, Authority of Jumeirah Village application that does not meet the provisions of this Code. Development Code Administrator shall act as staff to the Jumeirah Village LLC shall designate a Development Review
LLC, this section certifies that Jumeirah Village LLC is Any approval or permit issued in conflict with the provisions Development Review Board providing the following services: Board (DRB) for purposes of approving or denying requests
responsible for promoting and control of development of of this Code shall be considered null and void. to vary from the requirements of this Code, amend the Code
A. Accept, review, and recommend actions upon
Jumeirah Village. As a result, Jumeirah Village LLC has the or Zoning Map, or appeal a decision of the Development Code
2.01.04. Final Authority Development Code amendments, Zoning Map
right to approve or deny all applications for development Administrator.
Jumeirah Village LLC reserves the right to final authority on amendments, variances, exceptions, and conditional
within Jumeirah Village. To assist in administration of these
all items related to promotion and control of development uses. 2.03.02. Appointment
duties, Jumeirah Village LLC is authorized to delegate
of Jumeirah Village. All decisions made by Jumeirah Village B. Complete Findings of Fact for each decision reached by Jumeirah Village LLC shall appoint a panel consisting of no
responsibilities, including but not limited to:
LLC, including appeals of decisions made by the Development the Development Review Board. more than five members to serve on the Development Review
A. Daily administration of this Code, the Master Plan for Board. Three members of the DRB shall be regular members.
Code Administrator or Development Review Board shall be C. Respond to the applicant with Findings of Fact.
Jumeirah Village and other plans related to Jumeirah Two additional members shall serve as alternates. Meetings
considered final.
Village. 2.02.04. Additional Duties of the DRB shall occur regularly on a basis that shall not
B. Ability to receive, review, approve, request modification, Section 2.02. Development Code Administrator Additional duties assigned to the Development Code exceed once a month unless approved by the three regular
or deny applications for development. Administrator include: members of the DRB.
2.02.01. Designation
C. Requests or decisions to amend or interpret this Code. A. Conduct Pre-Application Meetings as needed with 2.03.03. Powers & Duties
Jumeirah Village LLC shall designate a Development Code
D. Enforcement of the requirements established by this potential applicants prior to formal submission. As noted in Table 2.01, Roles and Duties, the DRB shall be
Administrator to maintain daily administration of affairs
Code. related to development activity in Jumeirah Village. B. Monitor and enforce the regulations established by this charged with the following activities:
Code. A. Review, approve and deny applications for Variances,
2.01.02. Summary of Review Authority 2.02.02. General Development Application Duties
Jumeirah Village LLC hereby establishes a Jumeirah Village C. Interpret the requirements of this Code. Exceptions and Conditional Uses including the
As noted in Table 2.01, Roles and Duties, the Development
Development Code Administrator and a Development Review D. Prepare and amend any forms and application establishment of Findings of Fact.
Code Administrator shall accept, review, request
Board (DRB) for the purpose of administering the majority modification, approve, or deny the following development information to be utilized in the development review and B. Approve or deny proposed amendments to the
of activity related to this Code. Table 2.01, Roles and Duties, applications based upon the requirements established by this approval process. Development Code or the Zoning Map as requested by an
summarizes the purpose of each entity. Code: applicant, Jumeirah Village LLC staff, the Development
Code Administrator, or the DRB.
A. Concept Plan
C. Hear appeal of any decision made by the Development
B. Site Plan
Code Administrator.
C. Building Permit
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e
RE V IE W AUTHORIT Y
Table 2.01, Jumeirah Village LLC Development Code Administrator Development Review Board (DRB)
Roles and Duties
Role Final authority and administrator of Responsible for daily administration of Responsible for approval or denial of items
responsibilities related to implementation the Development Code including the requiring possible variation or alteration of
and amendment of this Development designated authority to make administrative this Code. Appeals actions taken by the
Code. Delegates duties as necessary and decisions. Develops a report of review and Development Code Administrator.
hears appeals of any actions taken by the recommendation regarding items sent to the
Development Review Board. Development Review Board.
Administrative Actions
Concept Plan Responsible for Approval
Site Plan Hears appeals of DRB decisions or Hears appeals of Administrator’s decisions
Building Permit Denial
Amendments & Exceptions
Code Amendment
Zoning Map Amendment Submits review and recommendations
Responsible for Approval or
Variance Hears appeals of DRB decisions to DRB, completes DRB findings report,
Denial with Findings of Fact
Exception and responds to applicant
Conditional Use
Other Duties
Accepts Notice of Intent Questionnaire
Conducts Pre-Application Meeting
Administers and Accepts Applications for
Development
Reviews Applications for Completeness Hears appeals of DRB decisions Responsible Party Hears appeals of Administrator’s decisions
Develops Reports to the DRB and Jumeirah
Village LLC
Enforces Development Code
Interprets Development Code
Appointment and
Approves Consultants for Service Accepts applications and maintains register --
Pre-Qualification of Consultants
J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
3. Zones
Zones
Zones
Table 3.01,
General
Zone
Information
Description • Lowest density • Low density residential • Variety of Medium • High density units in 3 • High density, mixed-use • Low density, commercial • Large open spaces
residential areas offer use offers a compromise density residential building configurations and heights: units that create a series of retail located within designed to provide
a suburban feel with between suburban single surrounded by other Mid- Gateway Tower, Boulevard dynamic, urban cores for the large median of the recreation, gathering
proximity to urban family villas and multi- Rises and flex units. Tower and Pre-sold Tower. Jumeirah Village. “triangle” portion of the opportunities and civic
services. family living. • Structures are medium • Multifamily skyscrapers • Multi-unit skyscrapers site and within each of the services within walking
• Structures are single • Structures are flexible in to high range in height, of varying heights with of varying heights with “circle” districts. distance.
family, detached homes use - allowing single family multifamily buildings with attached an above/below an urban “podium” and • Structures are limited • Includes Village Centers
surrounded by a private attached townhomes an attached carpark. ground carpark. an attached above/below height and serve a portion as defined in Block
yard. with limited front and rear • Open spaces are • Open spaces are ground carpark. of the commercial retail Guidelines.
• Mix of uses is minimal yards, as well as apartment incidental with the incidental with the • Open spaces may needs of the project. • Structures are limited
with commercial activity flats. exception of optional roof exception of optional roof include plazas, urban • The formal green spaces height and complimentary
limited to home offices. • Mix of uses is minimal gardens. gardens. greens and roof gardens. of the median surround to the open space.
• Located primarily in with commercial activity • Use for Mid-Rise G+4 • Located along major • Primarily a location for this portion of the site with • Primarily functions
southern “triangle” portion limited to home offices. is primarily residential roadway connecting Town office use, although may additional open space as active and passive
of the site and far right • Located throughout the with ground floor retail Center within the site and be a mix of residential, desirable, but optional. recreation space, including
corner of the “circle.” site and creatively used to activity possible. Mix use surrounding arterials. office, hotel and retail. • Located within easy a number of water
surround range of medium is allowed for G+10 & • Use is primarily • Located in three specific access of the majority of features. Institutional
and high density activities. G+16 with retail possible residential, but maybe a areas of the project. the “triangle” portion of uses are permitted by
on Ground & First Floors mix of residential, retail (on • Allows hotel or office the site, particularly by right, as well as limited
and Commercial on First, Ground & First Floor), and automobile. neighborhood commercial
above retail.
Second & Third Floors. commercial (on Second & activity.
Most institutional uses are Third Floors). • Open space connects
permitted by right. virtually all of Jumeirah
• For Presold Towers,
• Located throughout commercial use is Village..
the “circle” portion of the permitted.
site along and within the
major roadways and in
the “triangle” portion of
the site adjacent to tower
parcels.
Function
Live High High High High High None None
Work Low Low Medium Medium High Medium Low
Shop None None Low Medium High High Low
Play Medium Medium Medium Low Low Low High
J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
Zones
Figure 3.01,
Zoning Map
“Triangle” Side
“Circle” Side
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e
4. Use
use
Section 4.01. Types of Use D. Number and character of employees. Jumeirah Village LLC may place conditions upon approval of A. Open storage of loaded and unloaded vehicles.
E. Hours of operation. a Conditional Use Permit to reduce or mitigate impacts upon B. Open storage of materials, supplies or equipment.
Use categories are listed in Tables 4.01a and 4.01b. The
surrounding uses.
following serve as a key to the Land Use Tables and indicate F. Building and site arrangement. C. Outdoor display for sale of items such as automobiles,
treatment for each use according to Zone. G. Vehicles used and parking requirements. 4.03.03. Transferability furniture, appliances or other large-scale materials.
Approval of a Conditional Use is not transferable to new D. Raising, breeding, or keeping of dogs, cats, birds or other
4.01.01. Permitted Uses H. Number of vehicle trips generated.
tenants or operators. animals for sale, feeding or slaughter.
A “P” indicates that a specific use is permitted by right within I. Required signage.
the given Zone. Such uses must meet all other appropriate
J. Advertisement of use. Section 4.04. Accessory Use or Structure 4.04.04 Home Office
requirements of this Code. A home office is permissible as a use in given Zones, as noted
K. Likely impact on surrounding properties. 4.04.01. Criteria
4.01.02. Conditional Uses in Tables 4.01a and 4.01b, if it meets the following criteria:
L. Ability to operate independently of other activities on a A use or structure shall be considered an Accessory Use or
A “C” indicates that a use is permitted provided that the A. The home office is clearly incidental to the residential
site. Accessory Structure if it meets the following criteria:
project appropriately responds to additional criteria. use of the dwelling.
Conditional uses must meet all other appropriate A. The use or structure is subordinate to or serves the
Section 4.03. Conditional Use primary use or principal structure.
B. Business connected to the home office is conducted
requirements of this Code. entirely within a residential structure.
4.03.01. Criteria for Approval B. The use is subordinate in area, extent or purpose to the
4.01.03. Accessory Uses C. No outside storage of any kind is related to the home
Approval of a use in a given Zone is conditional if the use can primary use.
An “A” indicates the use as accessory to the primary use on office.
be made compatible assuming specific criteria have been C. The use is located on the same lot as the primary use.
a given site. An Accessory Use is permitted by right assuming D. The residential character of the dwelling and the lot
met to address negative impacts upon the surrounding area.
that additional requirements established in Section 4.04, D. The use is included in calculation of maximum lot
Following are variables for consideration of approval of a are not altered in any way to account for a home office,
Accessory Use or Structure, are met. coverage.
Conditional Use: including additional parking, placement of a business
4.01.04. Uses Not Allowed 4.04.02 Permitted Accessory Uses related sign, or display of wares in a manner as to be
A. Conformity and compatibility with the approved Master
An “-“ indicates that a particular use is not permitted within a Following are permitted Accessory Uses and Accessory visible to the outside.
Plan for Jumeirah Village.
given Zone. Structures in Jumeirah Village: E. Deliveries by commercial vehicles occur only between
B. The proposed Conditional Use will not adversely impact
A. Home Office and Caretakers quarters as noted in Tables 8am and 6pm.
the surrounding area or the overall development of
Section 4.02. Use Categories 4.01a and 4.01b, as well as 4.04.04, Home Office of this
Jumeirah Village. F. The home office creates no disturbing or offensive noise,
4.02.01. Classification Development Code. vibration, smoke, dust, odor, heat, glare, unhealthy or
C. The location, size, intensity, and accessibility of the use
Use categories classify land uses and activities based B. Storage structures not exceeding 10 percent of the unsightly condition, traffic, or parking problem.
will not adversely impact the marketability of surrounding
upon a similar function, product or physical characteristics. uses or reduce the anticipated standard of living. maximum lot coverage and maintaining compatibility of G. The home office shall not result in the off-street or on-
Characteristics include the type and amount of activity, the scale, materials and design with the principal structure. street parking of more than two vehicles at any one time
D. The size, floor, area, mass, and general appearance
type of customers or residents, how goods or services are C. Commercial or Institutional uses such as cafes or not owned by members of the occupant family.
of the proposed structure are to be compatible with
sold or delivered, likely impact on surrounding properties, and mosques for the exclusive use of employees associated
surrounding structures. H. The business conducted within the home office does not
site conditions. with commercial or office use. involve retail sales or services.
E. Adjacent streets and utilities have sufficient capacity to
4.02.02. Determination of Use meet infrastructure requirements of the Use. D. Solar panels and similar features, awnings, canopies,
In the event that a use is not listed or classification is carports, and other amenities attached or directly related
F. Access to the site is acceptable to Jumeirah Village LLC.
otherwise required, Jumeirah Village LLC shall classify the to the primary structure.
use as appropriate. Following are criteria for determining G. Adequate parking will be available and in accordance
E. Trash or refuge storage and enclosures.
classification: with criteria established by this Code.
F. Radio, television or other telecommunications antennas.
A. Actual or Anticipated characteristics of the activity. H. Impacts such as night lighting and noise have been
successfully addressed. G. Temporary uses associated with construction sites.
B. Approximate size of site area or floor space.
4.03.02. Conditions 4.04.03 Prohibited Accessory Uses
C. Amounts of sales and customer type generated.
The following uses are prohibited in Jumeirah Village:
10 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
use
Table 4.01a,
Permitted Land
Uses: Residential
& Institutional
Residential
Single Family Villa P - - - - - -
Townhome - P - - - - -
Multifamily Apartment - - P P P - -
Home Office A A A A A - -
Caretaker Dwelling A A - - - - -
Cultural/Recreation
Park or Open Space P P P P P P P
Recreation Center C C C C C C P
Play Area P P P P P P P
Sports Fields C C - - C - P
Institutional
School C C - - P P P
Mosque P P P P P P P
Library/Cultural Center C - P - P P P
Medical Facility - - P P P P P
Hospital - - C C P - -
Civil Defence - - P - P P P
Fire Station - - P - P P P
Police Station - - P - P P P
Daycare/Nursery C - P - P P P
Municipality Services - - P - P P P
Post Office - - P - P P P
Carpark Structure - - P P P P P
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 11
use
Table 4.01b,
Permitted Land
Uses: Commercial,
Utility & Industrial
Commercial
Office, General - - C C P P -
Eating Establishments
Indoor Restaurant - - C P P P P
Outdoor Cafe’ - - C P P P P
Entertainment
Indoor Entertainment - - - P P P C
Outdoor Entertainment - - - P P P C
Convenience Grocery - - C P P P P
General Retail - - C P P P P
Temporary Vendor - - - C P P P
Serviced Apartments - - P P P P -
Hotel - - - C P - -
Boutique Hotel - - C C P - -
Service Establishments
General Sales - - - C P P -
Personal Services - - C C P P -
Repair Service - - - - C C -
Gas Station - - - - - P -
Utility and Communication
Public Utility - - C C C C C
Transmission Station - - C C C C C
Waste Related Services - - - - C C C
Industrial - - - - - - -
12 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
Us e
f o r m c o d e – MI D RI S E l o t s
Table 5.02,
Building
Configuration
& Size
entrance should always be facing the primary street and C. The average floor plate shall comprise of gross areas
any secondary entrance may front along secondary streets. including but not limited to all living spaces, walls,
Setbacks shall be provided at the street, alley and paseo service and core areas.
edges.
5.02.04. Building Height
5.02.02. Maximum Built Up Area A. The maximum height of various Mid-Rise structures shall
Figure 5.01,
The total gross buildable area - not including parking be as per the Table 5.02 Building Configuration & Size.
Mid-Rise and Boulevard Mid-Rise Buildings in the foreground
structures, basements, balconies, and rooftop mechanical B. The calculation of the number of stories shall begin at
enclosures - will be set as per the FARs specified in Table ground level and include the ground floor, mezzanines, or
5.02 Building Configuration and Size. This area will be any levels commonly considered a story. Penthouses for
Section 5.01. General 5.01.03. Subdivision of Property calculated to the exterior of all wall enclosures and will mechanical equipment and basements that are not more
5.01.01. Applicability Subject to the approval of Jumeirah Village (L.L.C), land in include all service areas and elevator shafts and shall than 1m above grade are not included.
Design requirements established in Section 5.0, Form shall be the Flex and Town Centre plots in Jumeirah Village may be exclude substations and all service shafts. The table above
C. Items not considered in calculation of height shall
applicable to all sites and structures in the Boulevard Mid- subdivided if each of the lots created by the subdivision also specifies maximum allowable FAR for any ground floor
include architectural treatments, antennas, parapets,
Rise and Mid-Rise Zones unless specifically exempted by this meets all requirements of this code for the zone in which retail use within the buildings.
spires, domes and other such features to be approved by
Code. they are located. Land subdivision of other plot types is not
5.02.03. Average Floor Plate Jumeirah Village LLC.
permitted.
5.01.02. Relationship to Eight Principles and Master Plan A. The average floor plate area for buildings on various D. The floor-to-floor dimension of each story shall be a
Development requirements regarding urban form are Section 5.02. Building Configuration and Size Mid-Rise lots is specifed in Table 5.02 Building minimum of 3m and a maximum of 5m. Any area of
incorporated into this Code as a means of implementing Configuration & Size. occupancy over 30 sqm shall be counted as a story.
design criteria established in the Jumeirah Village Master 5.02.01. Building Elements
B. The average floor plate area of all buildings will be
Plan, ensuring a high quality of life and minimizing the Each type of mid-rise development shall comply with
calculated by dividing the total buildable area by the total
opportunity for adverse impacts on the functionality of the the configuration as stipulated in Table 5.02 Building
number of floors.
community. Configuration & Size. The primary facade with main
14 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
f o r m c o d e – MI D RI S E l o t s
f o r m c o d e – MI D RI S E l o t s
front on a minimum of 80% of the length of lot line within Figure 5.09,
Figure 5.06, 2-4m of the property line. Mid-Rise 3 Lot & Building View
Mid-Rise 3 Typical Site Plan
5.03.02. Shared Parcel Edges
A. In the case of shared side and rear parcel lines, the
lower stories of the structure below the required setback,
may be built up to the property line.
5.03.03. Upper Story Setback
A. If buildings are built to their maximum height, the setback
requirements from Table 5.02 Building Configuration
& Size will apply to the street, paseo or alley edges of
building. The minimum setback for upper-most floors
from builidng line shall be at least 3m. This setback shall
be utilized as a balcony, with trellis and loggia treatments
wherever possible.
5.04.02. Transparency
A. Transparency shall constitute glass with less than 30
percent reflectance. No mirror or highly colored glass is
permitted.
B. The percent of glazing of the façade shall be a minimum
of 20% on the front and rear elevations.
Section 5.05. Architectural Treatments in which it is determined by Jumeirah Village LLC that roof-mounted and screened from sight from public space
safety may be compromised. and other buildings within suitable enclosure areas.
5.05.01. Horizontal/Vertical Articulation If screening areas are mounted atop roofs of lower
D. Roof lighting shall be permissible following approval by
A. No building shall extend greater than 20m horizontally portions of a building, care should be taken to minimize
Jumeirah Village LLC.
without a discernible vertical offset or change in the visual impact from higher floors.
elevation treatment. 5.05.06. Balconies
B. With the exception of parapets along facades and
A. Balconies may be counted as part of the multi-family
5.05.02. Mix of Permitted Materials feature accents such as domes and trellises, rooftops
open space requirement. There is no requirement that all
A. In order to create unity at the street level, at least 50% shall be flat.
or even any balconies be provided.
of the non-glazed area of the facade shall be covered in
limestone. The other materials utilized to cover facades B. Balconies should be well integrated into the façade
shall be compatible in color and texture with limestone composition, and may not appear as boxes that protrude
(such as stucco, cast stone or tile). from the side of the building. Devices that help integrate
balconies include: partially or fully recessing the balcony
5.05.03. Screening of Mechanical Equipment and Parking into the façade, placing the balcony at an inside corner
A. Mechanical equipment, to the extent possible should of the building, and placing the balcony on the roof of a
be placed on the roof of any structure. Mechanical lower floor where the building steps back.
equipment located on a roof shall be screened through
C . Balconies are meant to be fully or partially exterior
development of a “top” for the structure.
places, not a bonus room that does not count towards
B. Mechanical equipment that must be located below the the allowed floor area of the building. To protect this
roof and car park structures should be located to the side and the views from other units, balconies may not be
or rear of a structure and designed to be architecturally glassed-in or have opaque wall surfaces except as
compatible with the remainder of the structure including allowed in this section.
incorporation of appropriate materials to assist in
D. Openwork structures (such as trellises) and plantings
screening.
are encouraged, but must not block more than 30% of
5.05.04. Color the façade area they occupy on any side that protrudes
The color palette selected by applicant shall be generally beyond the building face.
compatible with limestone as well as the colors of E. The following strictures apply to balconies:
surrounding development, with the rear and side of the
1. Balconies may extend up to 2m from the building
primary structure completed in a color compatible with the
face.
front façade.
2. Balconies may protrude into a setback or public
5.05.05. Lighting right-of-way up to 1m.
A. Lighting designed to illuminate any or all of a site shall
3. Balconies may be fully enclosed up to 1.1m above
be fully concealed to avoid direct visibility from a street
floor height (i.e. railing height.)
right-of-way and shall be designed to avoid unreasonable
encroachment of light upon surrounding sites. 4. Opaque walls above 1.1m are allowed only when
balconies of different units are physically joined
B. Commercial parking, loading and staging areas shall
together. In this case the opaque wall may not be
be expected to incorporate lighting during evening
higher than 2m above floor height
operation.
C. Lighting shall be provided at all entry and exit points 5.05.07. Roofscape
of structures as well as locations throughout the site A. Any mechanicals on the exterior, such as air handling
units and communications antennae / dishes shall be
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 17
Table 6.01,
General Parking
Requirements
Type of Parking
On Street (visitors only) P P P P P P P
Driveway/Carpark P P - - - - -
Carpark Structure - - P P P P P
Open Lot - - - - - P P
Added Requirements
Permitted Height (in - - Mid Rise 1 & 2 (3 levels) 4 4 2 2
stories not including ground Mid Rise 3 & 4 (1 level)
level)
Parking Limitations - - parking to be located no parking permitted no parking permitted - -
to rear of site on ground floor along on ground floor along
primary street primary street
Visibility of Parking visible from local street visible from access not visible from not visible from access point visible screened, but visible screened, but visible
street/alley primary street primary street from primary street from primary street from primary street
Location of Vehicle Access local street alley access street/alley access street/alley designated rear of block access street access street
(see Design Principles)
Location of Loading - - access street/alley access street/alley designated rear of block access street access street
Visibility of Loading - - screened from alley screened from alley screened from rear primary street primary street
of block
Landscaped Deck - - Yes Yes Yes Yes -
(see Section 8)
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 19
ID L
7 TAL
TH
3
Cultural/Recreation
Park or Open Space TBD
Recreation Center TBD
3T
A
Play Area TBD
LL ,
EN
Sports Fields TBD
GT
H
Institutional
School 1 per classroom
1 per 45 sq meter of administration area
1 bus parking space per 3 classes
Mosque TBD
Library/Cultural Center 1 per 60 sq. meters
!ISLE 7IDTH
Medical Facility 1 per 60 sq. meters
Fire Station TBD
0ARKING
Daycare/Nursery 1 per 60 sq. meters
!NGLE
Municipality Services 1 per 30 sq. meters /VERALL 7IDTH
Post Office 1 per 30 sq. meters
Commercial
Office, General 1 per 50 sq. meters + 10% for visitors
Eating Establishments 1 per 25 sq. meters
Parking Angle (in degrees) Parallel 45 60 75 90
Entertainment 1 per 5 seats
Stall Width (in meters) 2.7 2.7 2.7 2.7 2.5
Retail & Service 1 per 25 sq. meters of leasable space
Stall Length (in meters) 7 7 7 7 5.0/ 5.5
Hotel/Boutique Hotel 1 per 5 rooms
Aisle Width (in meters) 4 3.75 4.5 6 6
1 for each hotel room containing kitchen
Access Driveway Width (in meters) 6 6 6 6 6
1 per 2 hotel suits
Overall Width (in meters) 9 16.5 18.1 18.75 17/ 18
1 for each flat upto 150 sq meters floor area Turning radius (in meters) 4 4 4 4 4
2 for each flat over 150 sq meters floor area
Staff 1 per 2 employees
Restaurants 1 per 45 sq. meters of restaurant area
Utility/Communication
Public Utility 1 per 60 sq. meters of gross floor area
7. Signs
signs
S IGN S
Section 7.01. General
Table 7.01,
All signs erected, altered, displayed, or relocated in Jumeirah
Village shall be constructed, maintained and removed Signs by Zone
according to the standards established by this Code.
signs
Table 7.02,
Sign Standards Total Permitted Sign Area Maximum Number Sign Type
Maximum Artificial
Other Conditions Time Limit for Removal
by Purpose Height of Sign Lighting
Permanent Signs
Location or Tenant 1.5 sq. meter per linear meter of plot Minimum 3 square meters of total sign area reserved for Within 60 days from date that
Identification frontage (excepting tower sign) As approved by Jumeirah Canopy canopy height each ground floor business business ceases operation at
Village LLC the site of the sign
As approved by Jumeirah Projecting 4 meters internal or
Village LLC external
As approved by Jumeirah Wall 3 meters internal or
Village LLC external
1 per plot Tower 2 meters below internal or 4 sq. meter per linear meter of building frontage, not to
top of upper external exceed 200 sq. meters
shaft
Directional/Informational 0.1% of lot area As approved by Jumeirah As approved No advertising message permitted
Village LLC Pedestal 3.5 meters by Jumeirah
Wall 2.5 meters Village LLC
Advertisement 3 sq. meter Window 3.0 meters none --
Temporary Signs
Real Estate 1 sq. meter in Villa and Townhome Zones & 1 per street frontage Pedestal, Wall or 2 meters -- Advertise only the site on which sign is located On or before closing date of sale
0.5% of lot area in other Zones up to 4 sq. Window
meters
Special Event or Sale minimum of 1 sq. meter or 0.5% of lot area 2 per street frontage Pedestal, Wall or 3 meters -- Include only the name, date, time and content of event 14 days prior and 2 days after
up to 3 sq. meters Window the sale or event
Contractor Advertisement 1 sq. meter in Villa and Townhome Zones 1 per lot Ground, Pedastal, 4 meters front light Advertise only information related to the consultants 10 days after issuance of
& 0.5% of lot area in other Zones up to 10 Wall, or Window external licensed to work on the project including name, address, Certificate of Occupancy
sq. meters phone number, and internet web site. Sign to be sufficiently
durable to remain in a high quality condition through its use
on location.
Future Facility Advertisement 1 sq. meter in Villa and Townhome Zones & 1 per street frontage Ground, Pedastal, 4 meters front light Advertise only information related to the facilities and 10 days after issuance of
0.1% of lot area in other Zones up to 6 sq. Wall, or Window external amenities to be located on the site including uses, size and Certificate of Occupancy
meters date of availability. May advertise a project contact for
additional information including an address, phone number,
and internet web site. Sign to be sufficiently durable
to remain in a high quality condition through its use on
location.
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 23
signs
S IGN S
J. Is Portable, except temporary A-frame signs. Section 7.07. Language 7.08.03. Computation of Height Figure 7.02,
K. Contains strings of light not permanently mounted to a The height of a sign shall be computed as the distance from General Sign Measurements
The content of all signs shall be displayed in both Arabic and
rigid background. ground level to the top of the highest attached component
English, with equivalent translations of all sign content.
of the sign unless otherwise stated in Table 7.02, Signs
L. Is Inflatable and tethered to balloons greater than 50cm
Section 7.08. Dimensions Standards by Purpose.
in diameter.
M. Is an electronic message center in fixed or traveling 7.08.01. Computation of Area of Individual Signs 7.08.04. Computation of Maximum Total Permitted Sign Area
mode. A. The area of a sign shall be computed as the entire and Maximum Number of Signs
advertising area of the sign, including any framing or The permitted sum of the area of all individual signs and the
Section 7.05. Lighting trim used to differentiate a sign face from the structure total number of permitted signs shall be computed based on
against which a sign face is placed. standards identified in Table 7.02, Sign Standards by Purpose.
Sign lighting shall be arranged and maintained so that the
source is not directly visible from a public right-of-way or B. Where a sign consists of individual letters, words or Section 7.09. Temporary Signs
adjacent property. Artificial lighting is allowed as permitted in symbols attached to a surface, building, canopy, awning,
Table 7.02, Sign Standards by Purpose. Specific signs may be located in Jumeirah Village on a
or wall, the sign area shall be the area of the smallest
temporary basis. Temporary signs shall be required to meet
rectangle which completely encompasses all letters,
Section 7.06. Maintenance words or symbols and accompanying background of a
the sign area, maximum number, sign type, maximum height,
Each applicant that receives approval for a sign in Jumeirah color different than the natural color of the wall. Where
lighting and time limit requirements established in Table 7.02, wid
Sign Standards by Purpose. No site plan will be approved
th
Village shall be responsible for maintaining such sign in a such sign includes multiple words, each word located in C
unless all proposed temporary signs conform to the standards A
secure and safe condition. If Jumeirah Village LLC is of the the same plane shall be computed separately.
length
F
stated in Table 7.03. Permitted temporary signs include those E
opinion that a sign is not secure, safe or in good state of
7.08.02. Computation of Area of Multi-faced Signs n
repair or maintenance, such sign shall be considered to be in
addressing:
o sig unt
a violation of this Code and enforcement proceedings shall be
The area for a sign with more than one face shall be A. Real estate. tw s c o
e
computed by adding together the area of all sign faces
fac ne
height
commenced. B. A special event or sale, including A-frame signs.
visible from any one point. Two identical sign faces shall be o
0A
RK I
C. Contractor advertisement.
as
computed asNGa single face under the following conditions:
D. Future facility advertisement. ry
A. Sign faces are placed back to back so that both faces
B ake
cannot be viewed from any point at the same time. b a
Al ara
K
B. Sign faces are substantially similar. arab Al K
aT
a
C. Sign faces are part of the same sign structure.ilor
le
Sa s.
h
3D
24 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
l a n dsc a p e a n d f e n c i n g
Section 8.01. General proposed landscape development, irrigation system and 8.02.05 Village Centers within the Open Space Zone D. Each roof garden shall have at least one water feature
fences. The Landscape Plan may be combined with other A required courtyard or plaza within the Open Space Zone for every 2,500 square meters of pavement. Each water
8.01.01. Purpose plans provided all proposed landscaping is adequately shall have a minimum of 75 percent paved area. At least feature shall be at least 1 square meter in area.
Landscaping and fencing regulations are established as detailed on the plan. 50 percent of the paved area shall be shaded by buildings,
part of this Code to encourage pleasant and attractive trellises or shade trees. Section 8.04. Fencing
surroundings and to contribute to the relief of heat, noise, Section 8.02. Special Requirements by Zone
dust and glare through the proper placement of plants and 8.04.01. Required Fences
Section 8.03. Paseos and Roof Gardens
fences and to provide for the needs of security and privacy. 8.02.01. Town Center and Tower Zone Fences shall be required as appropriate within each Zone as
There are no special landscaping requirements in the Town In keeping with the Eight Principles guiding the design of indicated in Table 8.01, Landscape and Fencing Standards.
8.01.02. General Standards Center and Tower Zones other than roof garden requirements. Jumeirah Village, paseos and roof gardens are hereby
A. Each lot in the Villa Zone or Townhome Zone shall include
Table 8.01, Landscape and Fencing Standards provides incorporated into the community as a means of providing
8.02.02. Neighborhood Retail Zone a perimeter fence along the boundaries of the lot.
a general list of landscape and fencing requirements additional green space and recreational amenities.
associated with this Code. A. Vegetation utilized to meet the Open Lot landscaping B. Fences between properties in the Villa and Townhome
requirement shall not be considered as all or part of the 8.03.01. Paseos Zones shall consist of a single, shared fence along the
8.01.03. Irrigation and Maintenance open space requirement. Each paseo shall be located in the Townhome Zone and property line.
A. Required landscape areas shall be provided with a fixed designed to provide both paved and landscaped areas in a
B. Open space is intended to be largely urban in nature and C. Fences, including foundations, shall be placed entirely
and permanent irrigation system for planted areas, small, private court.
shall include 75 percent paved area. At least 50 percent inside the lot or parcel to which they belong except in the
protected by adequate back flow prevention, designed A. Between 50 to 75 percent of the interior ground plane of
of the paved area shall be shaded by buildings, trellises instance of a single, shared fence along a property line.
and installed in accordance with the following general a paseo shall be paved. The remaining area shall include
or shade trees. D. Fences shall be constructed of durable materials that
provisions: a vegetative ground cover or stone mulch.
8.02.03. Mid-Rise Apartment Zone are compatible with buildings on the same lot in terms
1. Water conservation shall be accomplished in B. A minimum of 50 percent of the paved area shall be
A. For each required Mid-Rise Apartment open space as of materials, finish, color and appearance. No fences of
manually operated (hose-bib) system by the covered in brick, stamped concrete, stone, unit pavers or
described in Section 5.13, the following shall apply: wood, plastic, or chain link shall be allowed.
installation of flow limiting devices. other type of detailed, pedestrian scale paving material.
1. Between 40 and 70 percent of the passive recreation E. Fences shall be a uniform height of 2 meters, except as
2. Applicable codes shall be used for the design and C. A minimum of 8 shade trees shall be planted and
areas shall be covered with a mix of paving described in Section 8.04.02.
installation of automatic control systems. maintained in a healthy growing condition in each paseo.
materials including concrete, brick, block, stone, 8.04.02. Fence Types
B. In all Zones, required landscaped areas shall be D. Each Paseo shall have a minimum of one small scale
or pavers and a minimum of 50 percent of the A fence may be classified as one of the following:
permanently maintained including the proper pruning, water feature.
paved area shall be shaded using a combination of
weeding and removal of litter, fertilizing and replacement A. Solid Fence. A solid fence shall be constructed of
buildings, trellises, vines, and shade trees. 8.03.02. Roof gardens.
of plants when necessary. concrete block and stucco and have no openings larger
2. Each required open space shall have at least one Roof gardens shall be required or encouraged in accordance than 100 cm in diameter or width or 300 cm tall. Solid
C. To minimize problems created by blowing sand and dust
water feature that covers a minimum of 1 square with Table 8.02, Roof Gardens, and shall consist of a mix of fences may have a decorative cap of which no more than
all ground planes in the exterior areas of parcels shall be
meter of area. paving, shade, water features, trees and shrubs as follows: 50 percent of the top may be 100 cm or less above or
treated so that there is no bare ground. Pavement, stone
mulch or groundcovers are acceptable means of treating B. Front yard open areas shall include a minimum of one A. Roof gardens shall be between 50 and 85 percent paved. below the required uniform height.
the earth. shade tree for every 8 meters of open frontage. B. A minimum of 50 percent of the paved area shall be B. Half Fence. A semi-solid fence shall have a solid lower
8.02.04 Villa and Townhome Zones covered in brick, stamped concrete, stone, unit pavers or half constructed of concrete block and stucco, and upper
8.01.04. Safety
Each lot in the Villa Zone shall have at least 3 trees in the other type of detailed, pedestrian scale paving material. half that is of open design, in which a physical separation
No landscaping shall be permitted that endangers health or
front yard area, at least one of which shall be a shade tree. At least 50 percent of the paved area shall be shaded shall be maintained between the two sides of the fence
public safety by creating a traffic or fire hazard, obstructing
Each lot in the Townhome Zone shall have at least one shade with shade trees or vines on trellises. but the visual connection between the two sides shall
vision, or detracts from the use of surrounding property.
tree in the front yard. C. Unpaved areas shall be covered in plant material or remain. Alternately, a full vertical open section may be
8.01.05. Landscape Plan Requirement stone mulch. used, as long as the open design areas constitute at least
As part of any application for Concept Plan and Site Plan 1/3 of the total length of the fence, and no solid section is
approval, a Landscape Plan shall be submitted showing the greater than 3 meters long.
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 25
l a n dsc a p e a n d f e n c i n g
l a n dsc a p e a n d f e n c i n g
Table 8.02,
Roof Gardens
a d m i n i s t r at i o n a n d p r o c e d u r e s
Figure 9.02, Section 9.03. Concept Plan D. The Development Code Administrator reserves the right Figure 9.03,
Pre-Application Review Process to approve a Concept Plan with conditions, assuming Concept Plan Review Process
9.03.01. Submission of Materials that such conditions serve to bring the project into
The applicant shall submit to Jumeirah Village LLC two sets of compliance with this Code.
all design materials required in the Application Checklists as
E. If approval is conditional, the applicant may request a
well as the Concept Plan Application.
Development Intent
meeting with the Development Code Administrator to
A. Generally, the Concept Plan shall conceptually show to Concept Plan
Application discuss the conditions and request reconsideration. Application and
Submitted scale property boundaries, approximate location and Following further review, the Development Code Materials Submitted
dimensions of all structures, setbacks, location and Administrator shall notify the applicant of revisions, if
general information regarding signs, parking areas, any, to the final action.
entryways, topography, north orientation, a description of
Pre-Application Pre-Application
general bulk requirements, landscaping and schematic 9.03.03. Time
Meeting Stage Meeting Stage
floor plans, and elevations of at least three sides of A. The Development Code Administrator shall approve or
Review for all structures. Specific requirements are provided in deny a Concept Plan within 10 working days of receipt Review for
Completeness Application Checklists. of the application and determination of completeness. Completeness
Notification of approval or denial shall be made within
B. An additional CAD file of the Concept Plan may be
5 working days of final action, for a total of 15 working
submitted as a supplement to required materials. If
days.
Concept Plan submitted, the CAD file should be in a format that is Concept Plan
Stage acceptable to Jumeirah Village LLC, including file format, B. Upon approval, the applicant shall have no more than Stage
(Optional) (Optional)
Yes separation of design elements into layers, and clean line 3 months to submit a Site Plan application. Following 3
Pre-Application months, a Concept Plan shall be considered expired. An Application Review
Meeting Conducted work.
extension of time may be granted by Jumeirah Village
C. A spreadsheet summary of all development data, in
LLC upon request.
compliance with the requirements of this Code (such as Yes
lot area, built up area and parking provision). C. If approval is conditional, the applicant shall be deemed
Site Plan to have agreed with all conditions unless, within 15 Site Plan
Stage Is a Concept Plan
9.03.02. Plan Review Process working days, the applicant requests a meeting with the
Stage
Is More Information
No Needed? A. The approval process shall follow the steps highlighted in Development Code Administrator to review the decision. Needed?
Figure 9.03, Concept Plan Review Process and discussed
D. Within 15 working days of meeting the applicant to
throughout Section 9, Administration and Procedures. No
discuss the conditional approval, the Development Code
B. The Development Code Administrator shall review the Administrator shall notify the applicant of revisions, if
application in its ability to meet the vision of the Jumeirah any, to the final action.
Building Permit Building Permit Is the Application
Village Master Plan and the requirements of this Code. Yes
Stage Stage Approved?
If all requirements are met, the Development Code Section 9.04. Site Plan No
Administrator shall approve the application. If additional Yes with
information is needed, the Administrator shall request 9.04.01. Submission of Materials Conditions
additional information. A. The applicant shall submit to Jumeirah Village LLC
two sets of all design materials required in Application
C. The Development Code Administrator shall notify the Letter of
Checklists as well as the Site Plan Application. Rejection
applicant of final action, including approval or denial of
the application. One set of the plans marked as approved B. Generally, the Site Plan shall accurately show to scale
or denied shall be accompanied by a letter and returned property boundaries, location and dimensions of all
to the applicant while the second set shall be similarly structures, all building wall elevations and setbacks,
marked and retained by Jumeirah Village LLC. parking areas, entryways, topography, north orientation,
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 29
a d m i n i s t r at i o n a n d p r o c e d u r e s
a d m i n i s t r at i o n a n d p r o c e d u r e s
accompanied by approval of all additional applications Notification of approval or denial shall be made within Figure 9.05,
and studies, including requirements for Variance, 5 working days of final action, for a total of 20 working Building Permit Review Process
Exception or Conditional Use by the DRB. days.
C. A CAD file of the Site Plan must be submitted as a B. Upon approval, the applicant shall have no more than 3
component of required materials. The CAD file should be months to utilize an approved Building Permit. Following
in a format that is acceptable to Jumeirah Village LLC, 3 months, if the applicant has not initiated construction
Building Permit
including file format, separation of design elements into or is otherwise unable to prove progress, the Building Application and
layers, and clean line work. Permit shall be considered expired. An extension of time Materials Submitted
may be granted by Jumeirah Village LLC upon request.
9.05.02. Minor Modifications to Approved Site Plan
The applicant may be permitted to make minor modifications
Section 9.06. Variance
to the approved Site Plan prior to Building Permit application.
All said modifications should be noted for review by the 9.06.01. Submission of Materials
Generally, the application shall include all materials required Review for
Development Code Administrator. The Development Code Completeness and
Administrator reserves the right to determine that proposed to indicate the requested variance. If submitted as part of the Modifications
changes are beyond “minor modifications” and reject such Development Plan process, materials submitted for Site Plan
changes. review will largely be sufficient.
Pre-Application
9.05.03. Plan Review Process 9.06.02. General Criteria Meeting Stage
A. The approval process shall follow the steps highlighted The Development Review Board may issue a variance from
in Figure 9.05, Building Permit Review Process and the requirements of the Development Code if such action is
not contrary to the interest of residents, investors, employees, Application Review
discussed throughout Section 9, Administration and
Procedures. and guests of Jumeirah Village. The Development Review
Board must also find that, due to special conditions, literal
B. The Development Code Administrator shall conduct final Yes
enforcement of the Development Code would result in undue Concept Plan
review the application in its ability to meet the vision of Stage
and unnecessary hardship based upon the following criteria:
the Jumeirah Village Master Plan and the requirements (Optional)
of this Code. If all requirements are met, the Development A. Extraordinary conditions regarding the specific land Is More Information
involved are such that strict enforcement of this Code Needed?
Code Administrator shall approve the application. If
additional information is needed, the Administrator shall would deprive the applicant of reasonable use of the
land. No
request additional information.
C. The Development Code Administrator shall notify the B. The Variance would not be detrimental to the health, Site Plan
applicant of final action, including approval or denial of welfare, safety, morals, order, convenience, or prosperity Stage Have all Additional
of surrounding residents, investors, employees, and Approvals been
the application. One set of the plans marked as approved Obtained? Letter of
or denied shall be accompanied by a letter and returned guests of Jumeirah Village. No Rejection
to the applicant while the second set shall be similarly C. The conditions are unique to this site and do not apply to Yes
marked and retained by Jumeirah Village LLC. other locations found in the same Zone. No
D. Upon receipt of an approved Building Permit, the D. The extraordinary conditions have not been created as a
Building Permit Is the Application
applicant may begin construction. result of actions by the applicant. Stage Approved?
Building
9.05.04. Time E. The Variance would be consistent with the spirit and Yes Permit
A. The Development Code Administrator shall approve or intent of the Jumeirah Village Master Plan and this Code. Granted
deny a Building Permit within 15 working days of receipt F. Condition of the site and enforcement of this Code would
of the application and determination of completeness. prohibit or unreasonably restrict use of the land.
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 31
a d m i n i s t r at i o n a n d p r o c e d u r e s
a d m i n i s t r at i o n a n d p r o c e d u r e s
support the recommendation. Section 9.08. Conditional Use B. The Development Review Board shall take final action C. The proposed amendment is consistent with the Master
C. The Development Review Board shall consider the on the application for Conditional Use within 15 working Plan and will not adversely impact the mobility and
9.08.01. Submission of Materials days of receiving the report from the Development Code infrastructure systems of Jumeirah Village.
recommendation of the Development Code Administrator
Generally, the application shall include all materials required Administrator. Notification of approval or denial shall be
and determine final action, including approval or denial 9.09.03. Amendment Process
to indicate the requested conditional use. If submitted as part made within 5 working days of final action, for a total of
of the application and specific findings of fact. A. The Development Code Administrator shall complete
of the Development Plan process, materials submitted for Site 20 working days.
D. The Development Code Administrator shall notify the Plan review will largely be sufficient. a report to the Development Review Board including
applicant in writing of final action, including approval or C. Upon approval of a building permit, the applicant shall an overview of the request for amendment, including a
denial of the application. 9.08.02. General Criteria have no more than 3 months to utilize an approved recommendation regarding the proposed amendment
The Development Review Board may issue approval of a Conditional Use. Following 3 months, if the applicant and potential impacts.
E. The Development Review Board reserves the right to
Conditional Use if the proposed project meets the criteria has not initiated construction or is otherwise unable to
approve an Exception with conditions, safeguards or B. The Development Review Board shall consider the
established in Section 4.3, Conditional Use. prove progress, the Conditional Use shall be considered
restrictions as needed to address any adverse impacts recommendation of the Development Code Administrator
expired. An extension of time may be granted by
resulting from the Variance. 9.08.03. Conditional Use Process and determine to approve, reject or modify the proposed
Jumeirah Village LLC upon request.
A. The approval process shall follow the steps highlighted amendment.
9.07.04. Time
in Figure 9.06, Development Review Board Process and 9.08.05. Runs with the Use C. If the request to amend the Development Code was
A. The Development Code Administrator shall submit
discussed throughout Section 9, Administration and Unless otherwise specified in the approval by the DRB, a submitted by an applicant for Development Plan
a report to the Development Review Board within
Procedures. Conditional Use applies only to the specific use or project for approval, the Development Code Administrator shall
15 working days of receipt of the application and
B. The Development Code Administrator shall complete which it is granted. No new use or project shall be permitted notify the applicant in writing of final action, including
determination of completeness.
a report to the Development Review Board including to utilize the exception without prior approval by the DRB. approval or denial of the amendment.
B. The Development Review Board shall take final action
an overview of the request for Conditional Use, a
on the application for Exception within 15 working days
recommendation of approval or denial, and proposed Section 9.09. Development Code Amendment 9.09.04. Time
of receiving the report from the Development Code Upon approval, an amendment to the Development shall
findings of fact to support the recommendation. 9.09.01. Request for Amendment
Administrator. Notification of approval or denial shall be take place immediately upon final action by the Development
C. The Development Review Board shall consider the A Development Code Amendment may be requested by
made within 5 working days of final action, for a total of Review Board.
recommendation of the Development Code Administrator an applicant seeking Development Plan approval, the
20 working days.
and determine final action, including approval or denial Development Code Administrator, the Development Review Section 9.10. Zoning Map Amendment
C. Upon approval of a building permit, the applicant shall
of the application and specific findings of fact. Board, or Jumeirah Village LLC. The authority to approve
have no more than 3 months to utilize an approved 9.10.01. Request for Amendment
D. The Development Code Administrator shall notify the an amendment to this Code is granted to the DRB, however,
Exception. Following 3 months, if the applicant has not A Zoning Map Amendment may be requested by an applicant
applicant in writing of final action, including approval or Jumeirah Village LLC remains the final authority and may
initiated construction or is otherwise unable to prove seeking Development Plan approval, the Development Code
denial of the application. choose to amend the Code without DRB approval.
progress, the Exception shall be considered expired. An Administrator, the Development Review Board, or Jumeirah
extension of time may be granted by Jumeirah Village E. The Development Review Board reserves the right 9.09.02. General Criteria Village LLC. The authority to approve an amendment to Zoning
LLC upon request. to approve a Conditional Use with added conditions, The Development Review Board may amend the Development Map related to this Code is granted to the DRB, however,
safeguards or restrictions as needed to address any Code if the following criteria are met: Jumeirah Village LLC remains the final authority and may
9.07.05. Runs with the Use
adverse impacts resulting from the Variance. A. The proposed amendment is not detrimental to the choose to amend the Zoning Map without DRB approval.
Unless otherwise specified in the approval by the DRB, an
9.08.04. Time health, welfare, safety, morals, order, convenience,
exception applies only to the specific use or project for which 9.10.02. General Criteria
A. The Development Code Administrator shall submit or prosperity of surrounding residents, investors,
it is granted. No new use or project shall be permitted to The Development Review Board may amend the Zoning Map
a report to the Development Review Board within employees, and guests of Jumeirah Village.
utilize the exception without prior approval by the DRB. if the following criteria are met:
15 working days of receipt of the application and B. The proposed exception will provide an equal or greater
A. The proposed amendment is beneficial to the orderly,
determination of completeness. means of meeting the purposes of this Code than current
efficient and economic development of Jumeirah Village
requirements.
and will enhance or protect the health, welfare, safety,
morals, order, convenience, or prosperity of surrounding
residents, investors, employees, and guests of the
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 33
a d m i n i s t r at i o n a n d p r o c e d u r e s
10. Definitions
D EFINITION S
definitions
Abutting: A common border with or being separated from Buildable Area: That portion of a lot upon which a building, Development Plan: A combination of applications and Façade: The exterior walls of a building exposed to public
such common border only by a roadway, easement or right- structure, pavement, or other improvements may be placed submissions to be submitted to Jumeirah Village LLC that are view or that wall viewed by persons not within the building.
of-way. after designation of areas such as front, rear and side yards. necessary to gain approval for project construction..
Feature: Fixtures, components or appurtenances attached
Access: The place or way by which pedestrians and vehicles Building Permit: An authorization granted by Jumeirah Development Review Board: Entity selected by Jumeirah to, contiguous to or otherwise related to a building, structure
have a safe and usable ingress and egress to a property or Village LLC certifying that the design of a proposed structure Village LLC to be responsible for approval or denial of items or property including, without limitation, materials, overlays,
use. An unobstructed way or means of approach to private or development to be erected on a designated lot complies requiring possible variation or alteration of this Code. moldings, sculptures, fountains, light fixtures, windows, and
entry to or exit from a property. with all relevant provisions applicable to this Code. The permit monuments.
Zone: A geographic area within which specific development
allows building construction to commence.
Access Driveway: The area between the traveled portion of regulations assigned by this Code shall apply. Fence: A construction, not considered a structure, which is
a road and a parking lot used by motor vehicles for access to Building, Primary: A building within which is conducted the designed for screening or enclosing. Landscaping screens of
Zoning Map: An official map that identifies Zones that are
and from a car park, but does not include an aisle. principal use permitted on the lot, as provided by this Code. a height of over 1 meter shall be considered a fence whereas
subject to the specific use and development regulations of
random plantings of any height shall not be considered a
Accessory Use: A use customarily incidental to and related to Car Park: Land used to park motor vehicles. this Code.
fence.
a principal use established on the same lot.
Carpark Structure: a building or structure consisting of more Driveway: An access to a required off-street parking facility
Findings of Fact: Statement of facts upon which a decision by
Addition: An extension or increase in floor area or height of a than one level and used to temporarily store motor vehicles. or an off-street loading area.
the Development Review Board has been reached.
building or structure.
Change of Use: Any use which differs from the previous use Dwelling: A building used as a self-contained residence that
Floor Area: The total horizontal area of all floors of a building
Adjacent: Abutting, directly connected to, or bordering. of a building or land. must include a kitchen sink, food preparation facilities, a bath
measured from the exterior surface of the outside walls,
or shower, and a closet pan and washbasin.
Applicant: The person, party or corporation applying for Conditional Use: A use which has certain characteristics including all floors below ground level but exclusive of vent
approval or permission; normally understood to be the owner, which may be detrimental to the surrounding area, but which Dwelling Unit: One or more habitable rooms constituting a shafts and courts.
leaseholder or developer of the lot. may be permitted within a Zone with designated mitigation self-contained unit with a separate entrance and used or
Floor Area Ratio (FAR): The ratio used to control the size of
measures. intended to be used for living and sleeping purposes.
Building: A permanently located structure having a room a building in relation to the size of its lot. FAR is expressed
supported by walls or columns but excluding any courtyard Construction Plans: The maps, drawings and specifications Dwelling, Multiple Unit: A building divided into two or more as a ratio (such as 1.5 to 1) by which the area of the lot is
such structure may have provided, however, that no form of indicating the proposed location and design of improvements dwelling units, each of which is occupied or intended to be compared with the total allowable gross floor area of the
fabric, tent or vehicle shall be considered a building. to be installed. occupied as a permanent home or residence. Also known as building or buildings, excluding parking and nonhabitable
an Apartment Structure. areas along the exterior of the structure such as balconies
Building, Accessory: A building devoted to an accessory Courtyard: A landscaped, outdoor open space surrounded by
and mechanical equipment. Stairs, elevators and other
use or structure that is complementary to the primary use or walls or fences or other materials utilized to establish a sense Easement: A grant of one or more of the property rights by the
service areas located withing the structure are included in
structure. of boundary. property owner to and/or for use by the public, a corporation,
the FAR calculation.
or another person or entity.
Building Height: The vertical distance measured of a Density: The number of dwelling units per unit of land.
Frontages: Configuration of the front façade of a structure
structure measured in number of stories beginning at the Egress: An exit.
Development: The construction, reconstruction, conversion, along, at minimum, the first two floors, including the ground
average elevation of the finished grade at the front of the
erection, alteration, relocation, or enlargement of any building Environment: The physical factors of the surroundings of floor.
building to the highest story of the structure. Penthouse,
or structure; any mining, excavation or landfill; and any land human beings including the land, water, atmosphere, climate,
mechanical equipment and architectural features that Grade: The elevation of the surface of the ground at any point
disturbance in preparation for any of the above. sound, odors, tastes, the biological factors of animals and
comprise the “top” of the structure shall not be considered in on a site.
plants and the social factor of aesthetics.
the overall structure height. Development Code Administrator: Individual designated
Grade, Existing: The elevation of the surface of the existing
by Jumeirah Village LLC to be responsible for daily Existing Use: The lawful use of a building, lot or structure at
Build-To Line: The line parallel to the front lot line upon which undisturbed ground at any point on a site.
administration of the Development Code. the time of the enactment of these regulations.
the edge of a building located closest to the street must be
Grade, Finished Floor: The final elevation of the ground
located. Development Intent Questionnaire: Application to be filled Exception: Permission to depart from the design standards in
surface after man-made alterations, such as grading,
out by a potential applicant as the initiating step in the the ordinance for reasons as described in Section 9.07 of this
grubbing, filling, or excavating, have been made on the
Development Plan approval process. Code.
ground surface.
dubai, u.a.e. - october 2006 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e 35
definitions
D EFINITION S
Guest House: An accessory building for the housing of Lot: A piece, parcel, or plot of land occupied by or to be Parking, Off-Street: An off-street parking space consists of Setback, Side: A setback extending the full width of the lot in
temporary guests, not containing a kitchen and not being occupied by one principal building, its accessory buildings a space adequate for parking an automobile with room for the area between a side lot line and a side building line.
rented or leased. and frontage on a street. opening doors on both sides together with properly related
Sign: Any device designed to inform or attract the attention
access to a public street, including maneuvering room.
Height, Building: The vertical distance from grade to average Lot Area: The total extent of surface, measured in a horizontal of a person not on the premises on which the sign is located.
height of the highest roof structure. plane, within the lot lines of a lot. Paseo: A public walk or boulevard designed exclusively for It means any structure, wall, natural object, or other device
use of pedestrians and including limited amenities as urban used for visual communication which is visible from any
Home Office: A conditional, accessory use permitted in Lot Coverage: The percentage of the area of a lot or parcel of
open spaces. street or means of access and is used to advertise or direct
specific Zones that allows operation of small business in a land, which is occupied by buildings or structures.
attention to an activity, product, place, person, or business.
home providing that impacts are mitigated and a conditional Permitted Uses: Any use allowed in a Zone by right.
Lot Frontage: That portion of a lot which abuts a road.
use permit issued. Sign, Awning: A sign that is mounted, painted or attached to
Plant Materials: Living trees, shrubs, vines, ground covers,
Lot Line: Any line bounding a lot as herein defined. an awning, canopy or marquee.
Hotel: A building offering temporary accommodations for sod, and flowering annuals, biennials and perennials adapted
eight (8) or more guests which may provide as accessory Lot Line, Front: A line separating an interior lot from a street. to the environment of Dubai Sign, Flashing: A sign having a conspicuous and intermittent
uses restaurants, meeting rooms, and recreation facilities. In the case of a corner lot, the orientation of existing or variation in the illumination.
Plaza: An urban open space that is surrounded by streets and
proposed development shall be used to determine which lot
Illuminated: A sign utilizing an artificial or a reflective light structures, largely paved and possibly including landscaping, Sign, Illuminated: Any sign designed to emit or brightly reflect
line shall be considered the front.
source. public art, seating or other features. artificial light.
Lot Line, Rear: A lot line which is opposite and most distant
Impervious Cover: Any hard-surfaced, man-made area Public Facilities: Services or facilities provided by Sign, Ground: A sign which is less than 1.5 meters from the
from the front lot line. In the case of an irregular lot, the
that does not readily absorb or retain water, including but government or government agencies for the benefit of the ground or is supported by a sign structure that is placed on or
rear lot line shall be an assumed line parallel to and at the
not limited to building roofs, parking and driveway areas, general public and to which the public will have access. anchored in the ground and is independent of any building or
maximum distance from the front lot line.
graveled areas, sidewalks and paved recreation areas. other structure.
Remodeling: The refashioning or alteration (whether
Lot Line, Side: Any lot boundary line not a front lot line or a
Improvement: Any building, structure, place, fence, gate, structural or not) of a building or structure without its Sign, Pedestal: A sign that is mounted on one or more
rear lot line.
landscaping, tree, wall, car park, or other object constituting established use being changed. freestanding poles or other support so that the bottom edge
a physical feature which is not a natural feature. Lot Width: The width of a lot at the minimum building setback of the sign face is more than 0.5 meters from contact with a
Right-of-Way: A strip of land acquired by reservation,
line. solid base or the ground. Also sometimes known as a “pole
Ingress: An entry. dedication or condemnation and intended to be occupied by
sign.”
Master Plan: The Jumeirah Village Master Plan. a road, crosswalk, sidewalk, railroad, electric transmission
Intersection: The crossing of two (2) or more roads at grade.
lines, oil or gas pipeline, water line, sanitary or storm sewer, Sign, Projecting: A sign that is partially or wholly dependent
Native Plant: Any species that is indigenous within the local
Landscaping: The treatment and maintenance of a property and other uses. upon a building for support and that projects more than 30
region.
or yard area with a combination of vegetation (ground cover, centimeters from such building.
Screening: A method of visually obscuring nearby structures
plants, shrubs, or trees), natural elements (brick, rocks, or Noise: Any undesirable audible sound.
or land uses (car park, outdoor storage) from another with Sign, Temporary: A sign or advertising display constructed of
water) and other natural or decorative features (walkways,
Occupied: Arranged, designed, built, altered, converted, the use of one or a combination of fencing, walls, dense cloth, canvas, fabric, wood or other light material intended to
fences, pools, fountains, or benches).
rented, leased, occupied or intended to be occupied. vegetation, or berms. be displayed for a short period of time.
Landscape Plan: A plan submitted as part of a package
Open Lot: An area of open land other than a road, used or Setback: A line established by development control Sign, Tower: A large scale sign that is mounted near the top
for Development Plan approval indicating the proposed
intended to be used to provide space for the parking or regulations, generally parallel with and measured from the of a tower that is generally used as a means of identifying an
landscape development, irrigation system and fences.
storage of motor vehicles, including parking spaces, loading front property line, defining the limits of a lot in which no important tenant or the name of a facility.
Loading Space, Off-street: Space logically and conveniently spaces, maneuvering aisles, and other areas providing building, accessory building or structure may be located
Sign, Wall: Any sign posted or painted in suspended from or
located for bulk pickups and deliveries, scaled to delivery access to parking or loading spaces. above the ground.
otherwise affixed to the wall of any building or structure in an
vehicles expected to be used, and accessible to such
Setback, Rear: A setback extending the full width of the lot in essentially flat position or with the exposed face of the sign in
vehicles when required off-street parking spaces are filled.
the area between the rear lot line and the rear building line. a plane approximately parallel to the plane of such wall.
36 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
D EFINITION S
definitions
Sign, Window: Any sign that is placed inside a window,
upon the window, or upon the window pane or glass, and
is intended to be visible from the exterior of the window.
Merchandise displays shall not be considered a window sign.
Yard, Front: The area from one side lot line to the other side
lot line and between the primary structure and the street on
which the lot fronts. On a corner lot (lots abutting on two or
more streets at their intersections), the front yard shall face
the shortest street dimension of the lot.
Application Checklists
a p p l i c at i o n c h e ck l i s t s
APPLI C ATION C HE C K LI S T S
Development Intent Questionnaire Contents Master Form Contents
o General Applicant Information o Concept General requirements: o Project Type
Applicant information to include: Discussion of the concept for the project in as much A. 2 copies of all materials Indicate the type of project expected to be developed
1. Name detail as needed or possible to aid in discussion during B. Drawings clearly labeled in the lower right hand corner according to:
the Pre-Application Meeting. Illustrations or concept 23. Type of Structure (Villa, Townhome, Mid-Rise, Tower,
2. Contact information (address, telephone, fax, email) C. Drawings to be folded to A4 size with labels clearly
sketches, if available, should be submitted with the low scale retail, public or civic)
3. Expatriate Status visible
Development Intent Questionnaire.
24. Type of Activities (Residential, Entertainment,
o Sponsor Information o General Applicant Information
o Anticipated Project Needs Restaurant, Hotel, General Retail, Office, Service,
If applicant is an expatriate, sponsor information is Applicant information to include:
11. Indication of desired location in Jumeirah Village as Recreation, Education, Institutional, Other)
required, including: well as anticipated land requirements 15. Name
25. If one or more of uses is expected to be a hotel, the
4. Name of Agent/Sponsor 12. Project Development Services such as architecture, 16. Contact information (address, telephone, fax, email) number of units, staff and food outlets should be
5. Contact Information for Agent/Sponsor (address, landscape architecture, engineering, site design, or 17. Expatriate Status provided.
telephone, fax, email) other 18. Development Application Tracking Number o Concept
o Construction Information 13. Financial Services Discussion of the concept for the project as it has
o Sponsor Information
Determine the type of construction activity to be carried If applicant is an expatriate, sponsor information is evolved through the Pre-Application and Development
out such as: required, including: Plan process.
o Time of Anticipated Construction and Completion
6. New Construction (of primary structure, accessory Estimated timeline for project to commence as well as 19. Name of Agent/Sponsor o Certifications
structure, parking, signs, or other amenities) time of completion. Key dates throughout the process, if Indication of the seal and certification of all architects,
20. Contact Information for Agent/Sponsor (address,
7. Redevelopment or Alteration (of primary structure, known, should also be included. telephone, fax, email) engineers and other allied professionals involved
accessory structure, parking, signs, or other with the project as licensed and registered to work in
amenities) o Action Requested Jumeirah Village and certifying the authenticity, quality
Actions may include Approval for Concept Plan, Site and preparation of submitted documents.
o Project Type Plan, Building Permit, Variance, Exception, Conditional
Determine the type of project expected to be developed Use, Development Code Text Amendment, or Zoning Map
according to: Amendment
8. Type of Structure (Villa, Townhome, Mid-Rise, Tower,
o Construction Information
low scale retail, public or civic)
Indicate the type of construction activity to be carried out
9. Type of Activities (Residential, Entertainment, such as:
Restaurant, Hotel, General Retail, Office, Service,
21. New Construction (of primary structure, accessory
Recreation, Education, Institutional, Other)
structure, parking, signs, or other amenities)
10. If one or more of uses is expected to be a hotel, the
22. Redevelopment or Alteration (of primary structure,
number of units, staff and food outlets should be
accessory structure, parking, signs, or other
provided.
amenities)
38 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
APPLI C ATION C HE C K LI S T S
a p p l i c at i o n c h e ck l i s t s
Concept Plan Checklist
o Master Application Form o Notation of materials to be used on site including type, color, texture, transparency, and location
o Design Statement o Floor and roof plans (scale of 1:200) indicating each roof and floor, proposed uses, roof gardens, penthouses and
The applicant discussing the impact of the project on Jumeirah Village. and the methods used to meet the vision of the location of mechanical equipment
Master Plan and meet the Eight Principles guiding community design o Calculations of Floor Area Ratio and Maximum Lot Coverage
o Documentation o Conceptual Parking and Loading Plan (scale of 1:200)
Table of architects, engineers, contractors and other allied professionals to be working on the project and certification that o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
they have been licensed and registered by Jumeirah Village LLC
o Calculations indicating the total number of parking spaces anticipated for the project, the number of on-street spaces
o Layout Plan (Scale of 1:1,000) adjacent to the project, and number of bicycle units supported
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date o Site plan and elevations as needed to indicate conceptual design of parking area including number of floors (if needed)
o Location of lot in relation to Jumeirah Village, adjacent streets and surrounding development below and above ground, parking and lane dimensions, location of access, screening techniques employed and details
o Zone in which project and surrounding sites are located to ensure compatibility with the structure and site design
o Location and design of loading areas
o Site Plan (Scale of 1:200)
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date o Space for vehicle stacking, if needed
o Site dimensions, lot description and reference coordinates o Conceptual Master Sign Plan (scale of 1:200)
o Street pavement lines o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
o Build-to line and setbacks o Calculations indicating the amount of sign space and type of permitted signs available to the project
o Location of proposed primary and accessory buildings o Anticipated location, dimensions, design, and type of signs to be utilized throughout the site in relationship to lot lines,
setbacks, structures, amenities, and the streetscape
o Location and measure of parking area, type of parking and points of access
o Location of services and facilities such as refuse containers and complimentary fencing/screening o Conceptual Master Landscape Plan (scale of 1:200)
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
o Existing features and proposed alterations to structures or other features of the site
o Calculations of required landscaping and fencing
o Existing and proposed site contours
o Site Plan indicating the anticipated location, materials and type of landscape and fencing treatment, including roof
o Conceptual Architectural Details gardens, plazas, courtyards, and open spaces
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
o If fencing is required, the type of fencing that is to be employed, including materials and location
o Perspective or elevation renderings clearly showing the proposed style, appearance and form of all buildings and
improvements o Service Requirement
Estimated infrastructural requirements to support staff, utilities and facilities
o Description of techniques used to meet Form standards of the Development Code (including bulk, articulation and
differentiation) o Estimated Irrigation Needs
o Elevations (scale of 1:200) of a minimum of 3 building faces for each structure including delineation of podium, shaft An estimate in liters of the total peak daily irrigation water requirements for all proposed plantings based upon the
(lower, middle and upper sections) and top Conceptual Landscape Plan, including an estimate for grass, if any
APPLI C ATION C HE C K LI S T S
Site Plan Checklist
o Master Application Form o Detailed Architectural Details
o Design Statement o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
The applicant discussing the impact of the project on Jumeirah Village and the methods used to meet the vision of the o Perspective or elevation renderings clearly showing the proposed style, appearance and form of all buildings and
Master Plan and meet the Eight Principles guiding community design improvements
o Documentation o Detailed Description of techniques used to meet Form standards of the Development Code (including bulk, articulation
Table of architects, engineers, contractors and other allied professionals to be working on the project and certification that and differentiation)
they have been licensed and registered by Jumeirah Village LLC o Detailed plans of each floor of primary and accessory structures including all development, improvements or
alterations. Roof plans shall be include and accessory structures shall include carpark structures and serve facilities
o Layout Plan
such as refuse areas. All indoor and outdoor spaces shall be clearly delineated, including roof gardens and other
If the project required a Concept Plan, then the Layout Plan for the Site Plan approval shall be the same with changes
required spaces.
incorporated from the Concept Plan process
o Detailed elevations (scale of 1:100) of all building faces for each structure including delineation of podium, shaft (lower,
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
middle and upper sections) and top
o Location of lot in relation to Jumeirah Village , adjacent streets and surrounding development
o Two or more sections (scale of 1:100) drawn at right angles through each structure and indicating internal and
o Zone in which project and surrounding sites are located external floor levels, window sill heights, parapet heights, penthouses, roof gardens, mechanical equipement, and the
o Site Plan (Scale of 1:200) relationship to surrounding structures
If the project required a Concept Plan, then the Site Plan shall be the same with changes incorporated from the Concept o Detailed drawings shall include location of fences, walls, parking areas, signs, landscaping and lighting for purposes of
Plan process context and review
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date o Samples of materials to be used on site including type, color, texture, transparency, and location
o Site dimensions, lot description and reference coordinates o Calculations of Total Floor Area, Floor Area Ratio and Maximum Lot Coverage
o Street pavement lines o Detailed Parking Plan (scale 1:100)
o Build-to line and setbacks o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
o Location of proposed primary and accessory buildings o Calculations indicating the total number of parking spaces anticipated for the project, the number of on-street spaces
o Location and measure of parking area, type of parking and points of access adjacent to the project, and number of bicycle units supported
o Location of services and facilities such as refuse containers and complimentary fencing/screening o Site plan and elevations as needed to indicate detailed design of parking area including number of floors (if needed)
below and above ground, parking and lane dimensions, location of access, screening techniques employed and details
o Existing features and proposed alterations to structures or other features of the site
to ensure compatibility with the structure and site design
o Existing and proposed site contours
o Location and design of loading areas
o Grading and Drainage Plan (scale of 1:200) o Space for vehicle stacking, if needed
A site plan and two cross-sections through the site in each main direction indicating existing and finished levels with areas
of cut and fill emphasized in shading. Drainage flow on site plan must be shown to an approved stormwater inlet or to an o Detailed Master Sign Plan (scale 1:100)
access way that leads to a street o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
o Calculations indicating the amount of sign space and type of permitted signs available to the project
o Precise location, dimensions, design, and type of signs to be utilized throughout the site in relationship to lot lines,
setbacks, structures, amenities, and the streetscape
o A single elevation depicting each permanent sign
40 J u m e i r a h V i l l a g e - MI D RI S E D e v e l o p m e n t C o d e october 2006 J UMEIRAH V ILLAGE LL C
APPLI C ATION C HE C K LI S T S
a p p l i c at i o n c h e ck l i s t s
o Detailed Master Landscaped Plan (scale of 1:100)
o Plan Title, Scale, North Arrow, Project Name, Address of Site, Applicant Name, Date
o Calculations of required landscaping and fencing
o Schedule of plants and materials to be incorporated into the project including name, quantity and reference to the
Landscape Master Plan
o Site plan and section detail of location of landscape treatments, including trees, shrubs, ground cover and lawns
o Location and section detail of hard surface materials, water features and fencing to be located on the project site
o Irrigation Calculations
o Irrigation water demand calculations relating to the proposed plantings shown and described in the Landscape Master
Plan, including the peak daily plant water consumption as indicated in liters and calculated at the peak season of July
o Monthly projected irrigation water consumption figures covering the effect of leaching and other off-season practices
o Irrigation site plan (scale of 1:200) indicating the location and capacity of the irrigation water storage tanks, tank
connections, and details of the distribution system.
o A timetable for timing in relationship to irrigation of landscaping at maturity
o Refuse Plan
Calculation of anticipated refuse to be accumulated as well as provisions made for storage and disposal
o Construction Schedule
o Proposed time schedule for completion of the project as initiated upon receiving an approved Building Permit
o Management plan describing the organization of work to be completed on the project in coordination with the provided
time schedule, including plans for onsite supervisory personnel