Professional Documents
Culture Documents
Building Cracks and Repair MRK
Building Cracks and Repair MRK
A PROJECT REPORT
Submitted By
B.MORISHNATH (311518103016)
A.RATHEESH KUMAR (311518103028)
K.KARTHIK (311518103012)
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
NOVEMBER 2021
ii
BONAFIDE CERTIFICATE
SINGNATURE SINGNATURE
Dr.L.RAMAJEYEM Mr.S.SARAVANAN,M.E,
M.E., Ph.D, F.I.E., F.I.V., C.Eng. (Ind). SUPERVISOR
Dean & Head of the department Assistant Professor
ACKNOWLEDGEMENT
An endeavor over a long period can be successfully only with the advice and
support of many well-wishers. We take the opportunity to express our gratitude and
appreciation to all of them.
The project has been successfully completed due to the blessing showered on us by
god. We thank the almighty for giving physical and mental stamina to complete the
project.
Our sincere thanks to our Internal guide Asst prof. Mr.S.SARAVANAN for giving
us valuable suggestions at all stages of our project.
Most importantly, we liked to thank all our staff members, family, classmates who
helped us in every possible way and guiding us in the completion of project.
iv
ABSTRACT
Building cracks are most common type of problem in any type of building. So, it is
important to understand the cause and the measures to be taken for prevention. Due
to some faulty steps during construction and some unavoidable reasons, different
type of cracks start to appear on various structural and non- structural parts of the
beam to increase the stiffness and the strength. A total of 8 concrete cubes were
constructed with the same material using the same mix and water-cement ratio.
Structural cracks are the one whose inherent cause lies in either in incorrect design,
or faulty construction or overloading and are the one which can endanger the safety
of a given structure. On the other hand, the non-structural cracks are the one which
deformation, creep, chemical reaction, or reason related to the foundation soil such
mostly due to internally induced stresses in building materials and these generally
do not directly result in structural weakening. In this study, we will discuss about
types of cracks, causes of cracking and preventive measures to be taken along with
the methods for repair of cracks using epoxy injection and retrofitting method.
v
சுருக்கம்
அல் லது குடிவயற் றம் அல் லது தகடயற் ற தாவரங் கள் வ ான் ற
காரணங் களால் அடி ் கட வதாற் றம் பகாண்டகவ.
கட்டகம ்பு அல் லாத விரிசல் கள் ப ரும் ாலும் கட்டுமான ்
ப ாருட்களில் உள் ள உள் தூண்ட ் ட்ட அழுத்தங் களால்
ஏற் டுகின் றன, வமலும் இகவ ப ாதுவாக கட்டகம ்பு
லவீனமகடவதில் வநரடியாக விகளவதில் கல. இந்த
ஆய் வில் , எவ ாக்சி ஊசி மற் றும் பரட்வராஃபிட்டிங் முகறகய ்
யன் டுத்தி விரிசல் ககள சரிபசய் யும் முகறகளுடன் ,
விரிசல் களின் வகககள் , விரிசல் ஏற் டுவதற் கான
காரணங் கள் மற் றும் தடு ்பு நடவடிக்கககள் ற் றி
விவாதி ் வ ாம் .
vii
VISION
To develop technical man power by facing challenges in
emerging technologies through excellence in education, research and
scientific training with socio-economic involvement.
MISSION
1. Transcending, disseminating and integrating knowledge of
engineering, science and technology.
2. Developing and innovating in applications through interdisciplinary
research and development projects in collaboration with
stakeholders.
3. Acting as problem solvers by acquiring relevant skills required for
a wide range of career challenges.
4. Creating opportunities in a collaborative and sustainable
environment and encouraging students and staff to achieve the
best.
viii
TABLE OF CONTENT
ABSTRACT(ENGLISH) iv
ABSTRACT(TAMIL) v
LIST OF FIGURES xi
LIST OF TABLES xiii
LIST OF ABBREVIATIONS AND SYMBOLS
1 INTRODUCTION 1
1.1 CRACK 1
1.2 CRACK CATEGORIZATION 1
1.3 CAUSE OF CRACKS 2
1.4 PREVENTION OF CRACKS 9
1.5 METHOD FOR REPAIR OF CRACKS 11
2 LITERATURE REVIEW 16
2.1 INTRODUCTION 16
2.2 CASE STUDY 20
3 METHODOLOGY 25
3.1 DETAILED METHODOLOGY 25
3.1.1 Literature Review 26
3.1.4 Curing 26
Retrofitting Methods 27
4 EXPERIMENTAL INVESTIGATIONS 28
4.1 GENERAL 28
4.2 MATERIAL INVESTIGATION 28
4.2.1 Cement 28
4.2.1.1 specific Gravity of Cement 29
4.2.2 Fine Aggregate 29
4.2.2.1 Physical Properties of The FineAggregate. 29
4.2.2.2 Specific Gravity Test and Water Absorption Test. 29
4.2.3 Water 31
4.2.4 Coarse Aggregate 31
4.2.4.1 Physical Properties of The Coarse Aggregate 31
4.2.4.2 Specific Gravity Test and Water Absorption Test 31
4.2.5 Epoxy 33
4.2.5.1 Manufacturing Process of Epoxy 33
4.2.5.2 Mix Proportion 34
4.2.5.3 Concreting 34
4.2.5.4 Casting 35
4.2.5.5 Curing 35
4.2.5.6 Upv Testing 36
5 RESULT AND DISCUSSION 37
5.1 UPV TESTING 38
5.2 CRACK FORMATION 39
5.3 REPAIRING OF CRACKS USING EPOXY
INJECTION 39
5.4 UPV TESTING AFTER REPAIRING OF CRACKS 41
x
LIST OF FIGURES
FIGURE. DESCRIPTION PAGE.
NO NO
LIST OF TABLE
CHAPTER 1
INTRODUCTION
1.1 CRACK
Cracks in a building are of common occurrence. The first and most common reason
of crack development is the stress component exceeding its strength component
which can be associated to the externally applied loads (forces) such as dead, live,
wind or seismic loads, or foundation settlement or stresses developed internally due
to thermal movements, moisture changes and/or chemical action,etc.
Most buildings crack at some time during their service life. The appearance of
cracks is a symptom of distress within the structure of the building.
According to IS: 456 2000, the surface width of crack should not exceed 0.3mm
in members where cracking is not harmful and does not have any serious adverse
effects upon the preservation of reinforcing steel, nor upon the durability of the
structures. In the members where cracking in tensile zone is harmful either because
they are exposed to moisture or in contact of soil or ground water, an upper limit of
0.2mm is suggested for maximum width of crack. For particularly aggressive
environment such as the ‘severe’ category, the assessed surface width of crack
should not in generally exceed 0.1mm. Cracking in reinforced concrete structures
of various types can be divided into two main groups:
A.Non-structural Cracks
These type of crack occur mostly due to internally induced stresses in building
material and normally do not endanger safety but may look unsightly, create
impression of faulty work or give feeling of instability. Crack on wall, parapet wall,
driveway are called non-structural cracks.
B.Structural Cracks
Most of the building materials having pores in their structure in the form of
intermolecular (ex. concrete, mortar, bricks etc) expand on absorbing moisture and
shrink on drying. These movements are reversible. Initial shrinkage is partly
irreversible and occurs in all building materials which are cement/lime based e.g
concrete, mortar, masonry etc.
3
B. Thermal Movement
C. Elastic Deformation
4 56
Fig. 1.3 Vertical Cracks and Diagonal Cracks
D. Movement due to Creep
8
Fig.1.6 Cracks at the Corner of a Building Due to Foundation Settlement
Fig.1.7 (a) Cracking of a Compound Wall Due to Growing Roots Under the
Foundation
459
Fig. 1.7 (b) (i) Cracks due to under growing tree roots
1.4 PREVENTION OF CRACKS
1) Select materials having small moisture movement eg bricks, lime stones, marble
etc
2) Plan for less richer cement content, larger size of aggregates and less water
content.
9
3) Porus aggregates (from sand stone, clinker etc) prone for high shrinkage
1) Dark coloured and rough textured materials on exteriors have lower reflectivity
and react more for thermal expansions
2) Plan for a layer of adequate thickness of good reflective surface over concrete
roof slabs to minimize these cracks
3) Slip joint should be introduced between slab and its supporting wall or the some
length from the supporting wall or the slab should bear only on part width of the
wall
4) Mortar for parapet masonry should be 1cement: 1 lime: 6 sand
1) Do not provide brickwork over a flexural RCC member (beam or slab) before
removal of centering and allow a time interval of at least 2 weeks between removal
of centering and construction of partition or panel wall over it.
2) When brick masonry is to be laid abutting an RCC column, defer brickwork as
much as possible.
10
3) When RCC and brickwork occur in combination and are to be plastered over,
allow sufficient time (at least one month) to RCC and brickwork to undero initial
shrinkage and creep before taking up plaster work.
4) A panel walls in RCC framed structures: (i) as far as possible, all framework
should be completed before taking up masonry work of cladding and partitions
which should be started from top storey downward. (ii) Provide horizontal
movement joint between the top of brick panel and soffit of beams.
5) Partitions supported on floor slab or beam :( i) Provide upward camber in
floor slab/beam so as to counteract deflection. (ii) Defer construction of partitions
and plaster work as much as possible (iii) Provide horizontal expansion joints
between the top of masonry and soffit of beam/slab, filling the gaps with some
mastic compound.
E. To Prevent cracks due to Foundation Movement and Settlement of Soil
3) Slip / expansion joints to ensure that new construction is not bonded with the old
construction and the two parts (Old and new) are separated right from bottom to the
top. When plastering the new work a deep groove should be formed separating the
new work from the old.
For cracks of width of micro-cracks less than 0.2mm, it is the most simple technique
used and to apply brush polymer or to apply elastomeric sealant on the surface in
order to prevent moisture content, carbon dioxide and other harmful materials. But
the main drawback is that it belongs to repair only shallow surfaces and not deep
cracks and cracks not suitable to water pressure.
11
D. Crack Stitching
Stitching involves drilling holes on both sides of the crack and grouting in U shaped
metal units with short legs (staples or stitching dogs) that span the crack. Stitching
may be used when tensile strength must be re-established across major cracks. The
stitching procedure consists of drilling holes on both sides of the crack, cleaning
the holes, and anchoring the legs of the staples in the holes, with either a non-shrink
grout or an epoxy resin-based bonding system.
E. Gravity filling
Low viscosity monomers and resins can be used to seal cracks with surface widths
of 0.001 to 0.08 in.by gravity filling. High molecular weight methacrylates,
urethanes, and some low viscosity epoxies have been used successfully.
F. Dry packing
H. Retrofitting
Retrofitting is the method of modifying or repairing something after it has been
manufactured. Retrofitting of Building work includes changing or repairing the
structure system of a building after its construction and occupation. This work
result in increased safety and durability of the structure.
Retrofitting, refers to inadequate reliability or owner for higher reliability of the
bearing structure, component part and its related to enhance, local replacement or
adjustment measures such as its internal force, to make it with the current design
specification and the owner required safety, durability and applicability
CHAPTER 2
LITERATURE REVIEW
2.1 INTRODUCTION
Literature study for the project provides the reference details about the work, from
the papers further experimental study can be carried out to explore the
disadvantages to the advantage over the project. Here some of the literatures been
collected and studied thoroughly to understand the project concept and queries from
various journals were discussed below.
Structural Cracks are a common occurrence in all types of buildings. To ensure the
longevity of the structure, engineers are often required to look into their causes and
carry out suitable repairs and remedial measures. For repairs and remedies to be
effective, it is essential that the engineer should have a proper understanding of
various causes of occurrence of cracks. For investigating the causes it is necessary
to observe carefully the location, shape, size, depth, behavior and other
characteristics of the cracks, and to collect information about specifications of the
job and time of construction. It is also necessary for the engineer to keep track of
when the cracks first came to notice. This paper talks about how visual inspection
of cracks can be helpful in order to identify and categorize them with respect to
various parameters by taking case study of an institutional building.
A large number of investigations has been devoted to the problem of the formation
and the development of a crack during brittle fracture of solids. The first of these
was the well-known work of Griffith [l] de-voted to the determination of the critical
length of a crack at a given load, i.e. the length of a crack at which it begins to
widen catastrophic-ally. Assuming an elliptical form of a crack forming in an
infinite body subjected to an infinitely homogeneous tension, Griffith obtained an
ex-pression for the critical length of a crack as that corresponding to the total.of the
full increase in energy (equal to the sum of the surface energy plus the elastic
energy released due to the formation of the crack). In recent years, in connection
with the numerous technical applica-tions regarding the problem of cracks, the
number of investigations has increased, among the first of which we ought to name
the works of Orowan and Irwin, general izing and refining Griffith’s theory. A
bibliography and a short &urn6 of these works can be found in the recent works
of Orowan [ 2 f , Irwin [ 3 1 , and Bueckner [ 4 1. The development of cracks in
brittle materials can be depicted in the following fashion. In the material there are
a large number of micro-cracks. Upon an increase in load in a given spot of the
body, a stress is reached sufficient for the development of the micro-crack existing
at that spot to a certain size. The beginning of the development of the micro-crack
is determined by some condition, because in view of the fact that usually the size
of the micro-crack is small in ComParison with the characteristic linear dimension
of the stress change, the state of stress in the surrounding area of the micro-crack
can be represented in accord-ance with Griffith’s scheme in the form of a uniform
infinite tension.
19
The effectiveness of a technique for the repair of reinforced concrete beam column
connections, damaged due to cyclic loading, is experimentally investigated. The
applied technique is mainly based on the use of thin epoxy resin infused under
pressure into the crack system of the damaged joint body. Special attention is given
to the examination of the repair efficiency with reference to the shear reinforcement
of the joint. To achieve this purpose, the test program included 17 exterior
connection specimens covering all commonly used joint reinforcing practices.
Specimens were initially subjected to increasing full cyclic imposed deformation
until the cycle maximum load decreased to 40% of the yield load level measured
in the first cycle. After repair, all specimens were retested in the same way.
Conclusions concerning the effectiveness of the applied repair technique, based on
maximum cycle toads, loading stiffness, and hysteretic energy absorption
capabilities of the tested specimens, are drawn and commented upon. Remarks
concerning the influence of different design reinforcement arrangements on the
behaviour of the joints are also included. The examined repair technique can be
considered to be satisfactory, since all repaired joints exhibited equal or higher
response load values and loading stiffness compared to the virgin ones, and tended
to undergo more full loading cycles without a significant loss strength.
building having started in 2014, most of the structure already have started
showing deep cracks at various locations all across the building which will lead
to the decrease in the durability of structure. Most of the structures in the building
are composite structures where columns are of structural steel slabs being RCC.
This combination has led to occurrence of cracks at all the major juncture points
of steel and concrete. The use of improper design mix, Improper curing along
with many other reasons has led to different structural and Non- structural cracks.
For the cracks all the prominent cracks were identified and classified on its
possible causes. Subsequently remedial measures for each of those cracks have
been identified and listed. In the month of nov 2021, the main building and as
well as all the internal rooms were inspected carefully and each type of cracks
were photographed and recorded for further observations. The cracks have been
categorized on the basis of
CHAPTER 3
METHODOLOGY
3.1 DETAILED METHODOLOGY
The following flowchart represents the detailed methodology of the experimental process of the
repairing the cracked cube using epoxy injection method and retrofitting method.
Literature Review
Curing process
UPV testing
Literature study is the reference study related to the project, from the journal papers reference
remarks were taken to do experimental study of the project. With collection of literatures the first
part of the project work starts
After the detailed theoretical study about the project selection, availability and collection of
materials is done in an economical manner. Materials such easily available cement, coarse
aggregate, fine aggregate, and reinforcement mesh is gathered.
With the reference in Indian standard method (IS10262-2009) the design mix for M20 grade
concrete is been calculated.
3.1.4 Curing
Curing is the maintaining of an adequate moisture content and temperature in concrete at early
ages. So, that it can develop properties the mixture was designed to achieve placement and
finishing so that the concrete may develop the desired strength and durability.
An ultrasonic pulse velocity (UPV) test is an in-situ, nondestructive test to check the quality of
concrete and natural rocks. In this test, the strength and quality of concrete or rock is assessed by
measuring the velocity of an ultrasonic pulse passing through a concrete structure or natural rock
formation.
27
For the formation of cracks in the concrete, the concrete is placed in the compression machine
and the load is gradually increased until the required crack formation is obtained.
Epoxy injection is an economical method of repairing non-moving cracks in concrete walls, slabs,
columns and piers and is capable of restoring the concrete to its pre-cracked strength.
Retrofit is the process of adding some new features that were not there before. retrofitting is the
construction industry refers to the re-strengthening of the existing structure to make them seismic
resistant. Retrofitting is the economic approach to increase the life span of an existing structure
rather than redeveloping it.
After testing and crack formation, the crack in the concrete is repaired using epoxy injection and
retrofitting method. Then the repaired concrete is tested to check whether the concrete has
regained its existing strength.
28
CHAPTER 4
EXPERIMENTAL INVESTIGATIONS
4.1 GENERAL
This chapter potrays the information regarding the materials such as cement, fine
aggregates,coarse aggregates,water,steel wire and polymer meshes used for making ferrocement
panels and also a simple mix design procedure, the various workability tests conducted on
ferrocement panels mix, the details about the size and the number of specimens casted are
presented elaboratetly.
4.2.1 Cement
Cement is a building material used for making any type of concrete and structures. Among the
various types of cement available in the market,Portland pozzolona cement is used in this work.
This type of cement is manufactured by inter-grinding well burnt OPC clinker with gypsum and
pozzolanic materials like fly ash or silicious earths. The table below shows the physical properties
of cement.
Table.4.1 Physical properties of cement
S.NO PROPERTY VALUE
1 Standard consistency 29.5%
2 Initial setting time 30 minutes
3 Final setting time 6 hours
4 Specific gravity 2.90
29
4.2.3 Water
Water should be free from oils, acids, alkalies, vegetables or any other organic impurities. Soft
water also produces weaker concrete. Water has two function in a concrete mix. First it reacts
chemically with the cement to form the cement paste in which the inert aggregates are held in
suspension until the cement paste has harderned . Secondly,it serves as a lubricant in the mixture
of fine aggregate and cement.
Specific gravity for an aggregate is defined as the ratio of the weight of a given volume of sample
to the weight of equal volume of water at the same temperature.Specific gravity of coarse
aggregate is generally requires for mix design calculation. Table gives the specific gravity of fine
aggregate.
32
4.2.5 Epoxy
crack as narrow as 0.05 mm can be bonded by the injection of epoxy. Non-moving, dry cracks
were repaired by first sealing the face of the crack with a gel and then injecting epoxy resin into
the crack by following the procedure as laid down by the manufacturer.
Epoxy resins are created by mixing BPA and epichlorohydrin (ECH), which are then reacted so
as to create the basic monomer unit of epoxy resin called BADGE or DGEBA. The properties of
the cured epoxy resins are determined by a chemical process called curing or hardening. It involves
mixing the resin with (poly)amines, aminoamides, phenolic compounds or other reactive
substances. This curingprocess will determine many properties of the cured epoxy resin, like, its
adhesion to other materials, durability, resistance and versatility. The ratios of BPA and ECH
alsocontribute to determine the epoxy’s final properties.
Residual BPA content: Epoxy can be used either in solid (SsER) or liquid (LER) form depending
on the applications. Thus, the amount of unreacted BPA in final applications would also depend
on the type of epoxy resin used. Although lots of factors indicate that the values usually are much
lower, according to literature LER can contain a maximum of 10 ppm of residual (unreacted) BPA.
For SsER the maximum amount is 65 ppm of BPA. This analysis assumed the highest estimate
for both type of epoxy resins; hence the final amount of residual epoxy per step of the life cycle
of epoxy resin is likely to be lower in reality. Unreacted BPA could potentially leave the epoxy
matrix and enter the environment but there are no available scientific studies specifying in what
quantities and how it would be further degraded in the environment.
4.2.5.3 Concreting
The throughly mixed concrete is poured carefully and slowly without causing much disturbances.
The concrete is filled in smaller or thinner layers and is agitated with the help of vibrating tables
to avoid the void formation.
Fig.4.1 concreting
35
4.2.5.4 Casting
The mixed concrete is poured in the 15X15X15 CM mould for the formation of the cube structure
and is agitated with the help of tamping rod for vibration to avoid the void formation.
4.2.5.5 Curing
As previously mentioned, the amount of water included in the concrete mix is usually enough
for the initial hydration of the cement. However, the water that is not immediately used up in the
chemical reaction can evaporate, particularly in hot climates, leaving insufficient water for the
complete hydration of the cement. This continuing hydration, which takes place over a long
period of time leads to the increase in strength already mentioned. It is therefore important to
reduce the water loss due to the sun, wind and heat of hydration. Providing the best conditions
continued strength gain is known as 'curing. The strength of un-cured concrete can be only 50%
of that of concrete properly cured for 14 days. Rapid drying of fresh concrete can cause shrinkage
cracks. The 8 specimens required been casted and kept for curing in water for about 28
days(4cubes) and 14 days(4cubes) till attaining the age of for testing.
36
CHAPTER 5
RESULT AND DISCUSSION
The crack is cleaned using the wire brush to allow the epoxy to bond to sound concrete for placing
the paste over epoxy. Under pressure of injection these materials may lift and cause a leak. If the
surface coating is covering the crack, it may be necessary to route out the opening of the crack in
a "V" shape using a grinder in order to get past the surface contamination.
After repairing the cracks, the cube is again tested using ultrasonic pulse velocity machine to
check its quality and strength, therefore the result is predicted to be the same before the crack
formation and after repairing it.
Rebound hammer test is done to find out the compressive strength of concrete by using rebound
hammer as per IS: 13311 (Part 2) - 1992. The underlying principle of the rebound hammer test
is: The rebound of an elastic mass depends on the hardness of the surface against which its mass
strikes. When the plunger of the rebound hammer is pressed against the surface of the concrete,
the Spring-controlled mass rebounds and the extent of such a rebound depends upon the surface
hardness of the concrete. The surface hardness and therefore the rebound is taken to be related to
the compressive strength of the concrete.
42
Retrofitting work includes changing or repairing the structure system of a building after its
construction and occupation. This work result in increased safety and durability of the structure.
Retrofitting of structural members is carried out to regain the strength of deteriorated structural
concrete elements. The strength deficiency of concrete structural members can be due to poor
workmanship, design errors, and deterioration due to the aggression of harmful agents.
In this method the 15x15x15 cm cube were made to get cracked using the compression machine
and the cracked cube placed inside the 20x20x20 cm mould and the concrete of M20 grade is
poured into the mould consist of a 15x15x15cm cube, thus making the cube packed with concrete
for 2.5cm cover on all the sides.
44
21.5
21
20.5
(compressive strength)
20
19.5
19
Epoxy injection
18.5 Retrofitting
18
17.5
17
16.5
14 days 14 days 28 days 28 days
(age of testing)
CHAPTER 6
CONCLUSION
This study gives insight to types of cracks, causes of cracks and prevention of cracks and also
about the various methods to get them repaired especially using epoxy injection method and
Retrofitting method. Various techniques for treatment of cracks are discussed in this study and
from results it is clear that the regaining strength in epoxy injection method is many times efficient
than retrofitting method. And also, not all type of crack requires same level of consideration. The
probable causes of crack can be controlled if proper consideration is given to construction material
and technique to be used. In case of existing cracks, after detailed study and analysis of crack
parameters, most appropriate method of correction should be adopted for effective and efficient
repair of crack.
47
REFERENCES
[1] Rajveer Singh Narwaria, Archana Tiwari, “Development of cracks in concrete, preventive
measures and treatment methods: A review” .International Research Journal of Engineering and
Technology (IRJET), Volume: 03 Issue: 09, pp.671-677, Sep -2016
[2] Rishabh Pathak, Deepak Rastogi, “Case Study on Cracks in Public Buildings and their
Remedies”, International Journal of Science and Research
[3] Prasad S. Barve, Dr. Lalit S. Thakur, Ruchi P. Barve, Jaimin K. Shah, Neha P. Patel,
“Detection and sizing study of Cracks: a Case study”, International Journal of Advance Research
in Engineering,Science & Technology(IJAREST), Volume 2, Issue 8, pp.84-91, August-
2015
[4] Grishma Thagunna,”Building cracks – Causes and Remedies”, International Journal of
Advanced Structures and Geotechnical Engineering ISSN 2319- 5347, Vol. 04, No. 01, pp.16-
20, January 2015
[5] SP 25-1984: “Handbook on Causes and Prevention of Cracks in Buildings”
[6] IS 456-2000: “Indian Standard Plain and Reinforced concrete - Code of
Practice”
[8] ACI Committee 224 (2007) Causes, evaluation, and repairs of cracks in concrete structures
(224.1R-07). American Concrete Institute, Farmington Hills,
[9] ACI Committee 546R-96 (1996) Concrete repair guide. American Concrete Institute,
Michigan
[10] ACI Committee E706 (2003) Structural crack repair by epoxy injection (ACI RAP bulletin
1). American Concrete Institute, Farmington Hills, p 5
48
Course Outcomes
Gain knowledge of the civil engineering field and gain knowledge and be up to date with the
C410.2
latest technology.
Program Outcome:
5. Modern tool usage: Create, select, and apply appropriate techniques, resources, and
modern engineering and IT tools including prediction and modeling to complex
engineering activities with an understanding of the limitations.
6. The engineer and society: Apply reasoning informed by the contextual knowledge to
assess societal, health, safety, legal and cultural issues and the consequent
responsibilities relevant to the professional engineering practice.
7. Environment and sustainability: Understand the impact of the professional
engineering solutions in societal and environmental contexts, and demonstrate the
knowledge of, and need for sustainable development.
8. Ethics: Apply ethical principles and commit to professional ethics and responsibilities
and norms of the engineering practice.
9. Individual and team work: Function effectively as an individual and as a member or
leader in diverse teams, and in multidisciplinary settings.
10. Communication: Communicate effectively on complex engineering activities with the
engineering community and with society at large, such as, being able to comprehend
and write effective reports and design documentation, make effective presentations, and
give and receive clear instructions.
11. Project management and finance: Demonstrate knowledge and understanding of the
engineering management principles and apply these to one's own work, as a member
and leader in a team, to manage projects and in multidisciplinary environments.
12. Life-long learning: Recognize the need for and have the preparation and ability to
engage in independent and lifelong learning in the broadest context of technological
change.
PSO1: Able to apply the engineering fundamentals to analyze and design various Civil
Engineering Structures.
PSO2: Catering to the changing industrial needs and adapting green concepts for different
applications.
PSO3: Understand the civil engineering solutions in the social context.
50
CO-PO Mapping
CO PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C410.1
C410.2
C410.3
AVERAGE
CO-PSO Mapping
C410.1
C410.2
C410.3
AVERAGE