SUMADHURA INFRACON PVT.

LTD Format No: SIPL/QAQC/MS/25


Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
1.Health & Safety
The following personal protective equipments shall be used
a) Helmet
1.1 b) Hand gloves Safety Induction record Safety Er/Site Er
c) Dust mask
d) Safety goggles
2. Equipment & tools
The following equipment/machinery shall be used
a) Angle grinder with grinding wheel
c) Batch box, GI/MS sheet or tray, Gamla, Showel,
2.1 Tools inspection format Safety Er, Site Er, QC Er.
d) Mason trowel, Tube level, Spirit level, Plumb bob
e) Straight edge, Nylon thread, rubber hammer, chisel
f) Scaffolding with platform, ladder, LDPE sheets
3.Materials
The following materials & tools shall be used
Approved list of
a) Granite, marble, Vito - Resin, hardener, Tinx - Resin,
3.1 materials, Approved list QC Er.
b) M.Sand/River sand, Cement, Araldite, 06mm down size
of vendors
aggregates
4 Material inspection & storage
Granite, marble, Cement & sand being purchased for
Material inward register
4.1 plastering work must be inspected as per Inspection Test Plan QC Er., Store Incharge
& Test reports
(ITP) and reports generated before unloading
All materials entering site premises shall be unloaded only
Material inward register
5.1 after QC check & stamping QC PASSED seal on the Delivery QC Er., Store Incharge
& Test reports
Challan.
All corresponding QC checks as laid in Inspection/Material test
Plan (ITP/MTP) must be conducted & records must be
Material inward register
6.1 maintained for the same. All material delivery must be QC Er.
& Test reports
captured in QC & Store material inward register as per
supplier wise & type wise
Granite, marble, Sand, cement, construction chemical storage
Store Incharge, QC Er.,
7.1 conditions must fulfill requirements as laid down in material Material storage plan
Project Manager
storage instruction/plan.
A Granite works - Staircase & Lift Lobby/granite flooring
5.1 Prerequisite
Tiling works inside flats, door frame & shutter fixing activities
must be completed prior to staricase & lobby flooring. 01m Tiling, Door frame &
5.1.1 Site Er., QC Er.
level mark from FFL must be available in staircase midlanding, shutter checklist
landing & lift lobby.
For stories above G+4, firewall shall be constructed from
basement to stilt bifurcating the access into 02, making two
5.1.2 - PM, VP/AVP
passages in each stairway such that, One from top floors to
stilt & other from stilt to basements
Bull marking for Staircase must be started from Basement
such that FFL in Staircase basement, Stilt & G.F shall be higher
5.1.3 - PM
in level than basement/stilt/G.F parkings which would enable
free movement of residents after installation of fire door

Page 1 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
Also consideration has to be given for FFL of each floor lift
5.1.4 lobby as it is mandatory, that FFL of lift lobby shall be lower in - PM
level than adjacent flats by minimum 05 to 12mm
Any difficulty in achieving above two steps shall be discussed
& sorted out before proceeding with granite flooring. QC
5.1.5 - PM
Dept. shall be kept in communication regarding decisions
fianlised by site management
Mock up shall be done to finalise pattern on Lift lobby.
Wastage factor shall be considered while finalising pattern,
5.1.6 Mail Communication PM, QC Er.
whether to proceed with plain single granite shade or with
borders & two or more patterns etc.,
FFL inside staircase at basement, stilt must be compared with
FFL outside staircase i.e car parking. And FFL inside staircase
5.1.7 must be higher in level than at car parking. This is required - PM
because fire door has to open towards car parking & there
shall be no obstruction during movement of people. This
aspect
FFL haslobby
of lift to beatconsidered
basement &shall
anybe
difficulties,
higher in same shallthan
elevation be
adjacent car parking area. Check for the same in Architectural
5.1.8 dwg. If not shown in dwg, generally provide 1/2' level - PM
difference by doing block work. Ramp shall be provided at
appropriate location for access to lift by differently abled
people.mortar sedimentation deposited due to plastering
Loose
activities shall be scraped off with special hacking bit as shown
beside. Bit with pointed ends must not be used. Level
5.1.9 difference (high) if any found out in mother slab itself shall be Site Er, QC Er.
brought to required level by forming cake pieces with cutting
wheel & chipped off with low frequency chipping machine
HILTI TE -7C
Obtain clearance from MEP engineer for lift lobby areas, Granite & Marble
5.1.10 Site Er., MEP Er.
before proceeding with button mark provision flooring & dadoing -
5.2 Work procedure checklist
Provide button mark in 1:3 cement mortar with base
measurement as 4"x4" & top 3"x3" at maximum spacing of 6
Granite & Marble
feet. Record button mark thickness obtained in each lift lobby
5.2.1 flooring & dadoing - Supervisor
& staircase landing, midlanding and attached as enclosure in
checklist
checklist. Avg. button level mark more than 25mm shall be
recorded in cost of poor quality.
For G+04 story buildings & for buildings which has got OTS,
adjacent to lift lobby, where there is possibility of rain spatter,
necessary slope has to be provided to drain off rain spatter.
Drain spots must be identified during button mark provision
5.2.2 -do- Site Er.
itself & button marks provided accordingly in slope.
Subsequently mortar bedding shall also be laid in slope. But
drain spot location shall be selected such that mortar bedding
thickness shall not exceed 40mm at any location
Offer inspection to QC Er. & obtain clearance for surface
preparation. Surface must be free from debris, foreign
5.2.3 -do- Site Er, QC Er.
materials, loose mortar deposits etc. Apply air blower to
blow off minute loose particles. Clearance shall be given per

Page 2 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
After bull mark provision, individual floor to floor
measurement for staircase must be taken to make Riser
pieces. Do not cut Riser pieces as standard measurement.
5.2.4 -do- Site Er.
Instead individual floor clear height available must be divided
by number of risers & the resulting dimension must be
considered for riser piece height
Similarly, individual floor measurements must be taken for Lift
lobby, staricase midlanding & landing prior to making of
5.2.5 -do- Site Er.
granite cut slabs. Standard measurements must not be
adopted
Tread length shall be half inch excess than existing plaster
finish & from riser granite piece, so as to make half bull nose
5.2.6 edge finish or any other edge finish as shown in Fig 5,6 & 7, -do- Site Er.
whereas Riser length shall be same as that of actual dimension
matching with plaster finish surface of steps.
Anti skid provision shall be made in all Tread pieces by making
03 grooves each of 05mm in width & 02mm in depth. 01st
5.2.7 -do- Site Er.
groove shall start at 50mm from bull nose edge, 02nd at
20mm from 01st & 03rd at 15mm from 02nd. Workmanship
Both Riser & Tread pieces must be cut in level platform/base.
After making Anti skid groovess, half bull nose or 1/2" or 3/4"
bevel finishing (refer fig 5) shall be done with a series of
5.2.8 -do- Supervisor
polishing wheel grits numbering from 0 to 6 by wet polishing.
Dry polishing must not be done, as original apperance of
granite is lost & white patch pattern would be visible after dry
polishing.
Staircase skirting pieces of 100mm high must be made ready
either by 45 degree cut or 90 degree cut, but considering
5.2.9 shape of Edge finish of Tread, such that Tread piece fits -do- Supervisor
properly in the shape carved out in skirting. 1/2" or 3/4" bevel
edge finish shall be done with 7 layer wet polishing
Shift required amount of cement & sand materials in bags &
5.2.10 -do- Supervisor
store in adjacent flat or adjacent area whichever is feasible
Just prior to start of work in each floor, once again apply air
5.2.11 blower to blow off loose particles, prewet the substrate & -do- Supervisor
apply cement slurry in 1(cement):2(water) ratio.
Using standard batch box, weigh 6 parts of sand & 1 part of
5.2.12 cement. Dump in proposed work area & mix dry ingredients -do- Supervisor
uniformly. Add required amount of water & again mix
Granite slabs shall be dry matched in the yard under day light
5.2.13 and then cut to exact size required & numbered in -do- Site Er.
sequence/continuous pattern and laid at site exactly in same
manner.
Place granite slabs for setting out in sequence, one by one
over the entire lobby & enusre finish level of all panels is in
5.2.14 same level (as there may be difference in thickness of granite -do- Supervisor
slabs). When any mismatch in FFL is observed, remove such
panels & scrape off/apply mortar mix to make levels even.
Check even level of slabs with 2m spirit level

Page 3 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
Once mortar is leveled to slope or flat & modified matching
granite slab thickness as per requirement, remove one panel
at a time & apply cement slurry in 1(cement):2(water) & make
grooves with trowel at every 05 to 08 cm distance, adequately
5.2.15 -do- Supervisor
which aids absorption of cement slurry into mortar &
expulsion of entrapped air, so as to ensure proper adhesion
with granite slab. Similary repeat the process for all granite
slab and complete the lobby.
For installing borders mark the location from wall surface in
already laid granite slabs 3"/4" as approved & cut the portion
5.2.16 with cutting machine. Remove & place appropriate border -do- Supervisor
pieces of same dimension, once again make grooves and apply
cement slurry. Then tamp with rubber hammer & finish to
level.
At junctions like door openings where there is level difference
5.2.17 -do- Site Er.
between lobby & adjacent flat, aluminium L angle shall be
fixed
Similarly staircase granite laying shall also be completed. Gap
5.2.18 at interface of riser & tread shall be filled with adequate -do- Supervisor
mortar to ensure no voids. Hollow sound must not be found
Once Riser & Tread laying is complete, start fixig skirting with
respect to plumb & alignment. First fix two end pieces in
alignment, followed by fixing of intermediate pieces. Use rich
cement mix for securing the skirting pieces.Skirting packing
5.2.19 shall be done with cement mortar of 1:4 ratio or tile adhesive -do- Supervisor
whichever is convenient as per site situation. Take care to
finish off the skirting packing & wall plaster above to match &
wipe off excess mortar. Skirting shall project equally
throughout the length of wall.
Care shall be taken to ensure that zero level exists in Treads. If
5.2.20 required outward slope of 01/02mm could be provided in -do- Site Er.
Treads, but reverse slope must not exist at any condition.
Offer inspection to QC Er. & obtain clearance for each floor
just prior to commencement of curing. He shall check hollow
5.2.21 -do- Site Er., QC Er.
sound in staircase & lobby, Riser plumb, Tread levels, skirting
alignment & levels, surface eveness among granite slabs in
Ensure curing to all areas including skirting for a minimum
5.2.22 -do- Supervisor
period of 07 days.
B Granite works - Lift wall, feature wall & planter box granite
5.3 cladding
Prerequisite
Sampling, one or two as decided by site management shall be
done & offer inspection to VP/AVP. Upon approval
5.3.1 Mail Communication PM, QC Er.
corresponding Granite stone shall be ordered for
procurement. QC Er. shall intimate HO about sampling, for
reference.
Granite slabs on reaching site premises, must be inspected as Material inward register
5.3.2 QC Er., Store Incharge
per ITP & reports generated & Test reports

Page 4 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
5.4 Work procedure
Granite slabs shall be cut as per approved pattern & design
(chamfer, half bull nose etc., Refer fig 5,6 & 7) and done with
Granite & Marble
07 layers of wet polishing. 45 degree cuts of different slabs
5.4.1 flooring & dadoing - Supervisor, Site Er.
must be in straight line when positioned on proposed
checklist
feature/lift/planter wall. Edge/corners must not be broken.
Proper measurement & Workmanship must be ensured to
achieve
No wherethis.
sharp edge of granite must exist in the whole setup,
in particular at corners. If "L" shaped corner is approved,
5.4.2 edges of both granite pieces coming in contact must be -do- Supervisor
slightly buffed to get rid off sharp edge. Not only "V" shaped
corner, same is applicable for any type of corner finish.
Wall/planter box cladding stones shall be done with special
treatment on the rear side for enhanced bonding with
substrate. Apply a layer of Araldite (bonding agent) followed
by spraying of 06mm downsize chips over Araldite as shown in
5.4.3 -do- Site Er.
fig 1 & leave it undisturbed for 48 hrs. Though this surface
treatment is preferred for both floor & wall, it is mandatory to
do this for wall cladding & for flooring it is up to site
management whether to provide or not.

Fig 1

Opening for service provisions like Lift Electricity distribution


boxes shall be cut to proper shape & dimensions later (after
5.4.4 fixing). DB cover shall be fixed in flush with granite surface -do- Site Er.
after installation. Electrical engineer must be discussed to
mitigate any difficulties

Once granite pieces are ready, same shall be fixed in position


maintaining verticality & alignment between different granite
5.4.5 slabs, secured with rich cement mix as required maintaining a -do- Supervisor
gap of about half inch between substrate and granite, in order
to fill/pack with cement mortar slurry or tile adhesive.

Page 5 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
Offer inspection to QC Er. for each/group of lift/feature
wall/planter box according to site condition & obtain
5.4.6 clearance for correctness of plumb, alignment of different -do- Site Er, QC Er.
granite pieces, straightnes of 45 deg cuts, surface finish on
polished edges, unbroken corners etc.,
After QC clearance, seal all the voids at boundary of granite
pieces with cement mortar of 1:6 ratio like 45 degree cut in
plastering to alignment, followed by prewetting & pouring of
5.4.7 cement mortar slurry of 1:5 ratio mixed with required amount -do- Supervisor
of water to bring required flow consistency. The mix shall be
agitated frequently & just prior to pouring so as to prevent
settlement of sand at bottom in the container which it is
stored.
Alternatively, tile adhesive or cement mortar paste could be
used instead of cement mortar slurry, depending on site
management decision. In this method temporary securing of
granite slabs in position with rich cement mix is not required.
5.4.8 Adhesive or cement mortar paste could be applied on rear -do- Supervisor
side, placed over substrage & malleted with rubber hammer.
But in this method few drawbacks exist. Like plumb, alignment
out of slabs after fixing, hollow sound etc., So method
mentioned in 5.4.7 is more appropriate
If method mentioned in 5.4.8 is followed, offer QC inspection
just prior to commencement of curing. QC Er. shall check
5.4.9 -do- Site Er., QC Er.
verticality, alignment of granite slabs with one another,
straightnes of 45 deg cuts, surface finish on polished edges,
unbroken
For plantercorners etc., groove is provided to seperate
boxes where
horizontal & vertical members, a tile piece of 2/3" in width
5.4.10 shall be fixed on top of vertical member to maintain straight -do- Site Er.
line & neat finish on grooves before proceeding with fixing of
horizontal member. Refer picture below.

Fig 3

Fig 2
Fig 2 shows tile piece fixing above vertial member @ groove location before fixing of horizontal granite piece. Fig 3
shows finished groove surface after fixing of horizontal granite piece

Page 6 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
C Granite coping - wall

Propsed masony wall receiving granite coping (swimming pool


wall, parapet wall, planter walls if any) shall be done with
02/03" thick coping concrete with MSA 12mm in 1:2:4 ratio
using proper shutter arrangements, such that after stripping Granite counter & coping
5.5.1 Supervisor
concrete does not slide. Shutters provided for coping must not - checklist
be removed before 01 hr. Also dry cement shall not be spread
over coping concrete to avoid it from sliding after stripping.
Do not use straight edge as shutter for coping concrete.

5.5.2 Ensure curing to coping concrete for a minimum period of 07 -do- Site Er, QC Er.
days.
Plastering on proposed wall receiving coping shall be
5.5.3 terminated atleast 01" below proposed granite finish, so as to Wall plastering checklist Site Er.
aid proper packing of mortar

Granite coping pieces shall be fabricated to proper dimension


with slight buffing on each & every corner. Special clamp as
Granite counter & coping
5.5.4 shown in picture below shall be tightened over two granite Site Er.
- checklist
pieces for proper adhesion of add on fragments at border.
Araldite resin & hardener shall be used to join granite pieces

Fig 4

Fabricated granite strips shall be placed over 01" thick cement


Granite counter & coping
5.5.5 mortar mix of 1:6 ratio for particular stretch in level. Use spirit Supervisor
- checklist
level to ensure adjacent strips are being placed in level with
one another.
Remove strips one at a time & pour cement slurry 1:2 ratio
over the mortar & cut it trowel at different locations for
5.5.6 -do- Supervisor
penetration of slurry with mortar & bonding with granite.
Then place the granite & strike with rubber hammer for
proper
Likewisecompaction.
repeat the process for all granite strips & each time
ensure adjacent strips are again placed in level with one
another. When particular stretch is complete pack the gap
5.5.7 -do- -do-
below at interface of granite & plaster cut to perfection
manually without disturbing the setup. Scrape off excess
mortar & match the finish in level with plastered surface.
Offer inspection to QC Er. for a particluar stretch. He shall
check alignment & level of granite coping, uniformity of mild
5.5.8 -do- Site Er, QC Er.
buffing at corners & edge finish, hollow sound, proper
packing at bottom side of coping, surface finish at interface

Page 7 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
5.5.9 Ensure curing to the whole area for a minimum period of 07 -do- Supervisor
D days
Ledge wall coping & Wash basin counter
Ledge wall coping could be done in two types. Type 1: Single
granite piece with 1/2" bull nosing, 1/2" or 3/4" bevel, straight Granite counter & coping
5.6.1 PM, Site Er.
edge finish or Type 2: Square Eased or Miter Edge as shown - checklist
below.

Fig 6

Fig 5 Fig 7
Sampling shall be done adopting any of the above 06 options
5.6.2 & approval shall be taken from VP/AVP. Site QC shall keep -do- PM, QC Er.
informed the HO regarding approved type & pattern
As mentiond in earlier procedures, each & every granite piece
shall be slightly buffed at corners to avoid sharp edges & cut
to exact dimensions & in right angle wherever applicable.
5.6.3 -do- Supevisor
Special tools as shown in Fig 4 shall be used depending upon
type of finish adopted & as applicable. 06 layers of wet
polishing shall be done to all edges
Ledge wall granite coping shall be fixed with cement mortar of
1:6 ratio & cement slurry of 1:2 ratio as described in above
5.6.4 mentioned procedures or tile/stone adhesive could be used. -do- -do-
Care to be taken to see that no gap exist between wall dado &
ledge wall coping & level to be maintained.
For wash basin counter opening, do not use templates
provided by manufacturers as shape & size may differ from
template & real fitting. Use real sanitary wash basin fitting &
make a template at site itself. Similarly hole for sink
cock/basin mixer shall be made after finalization of sink cock
5.6.5 -do- PM, Site Er.
to be provided. Inappropriate location of sink cock hole &
inappropriate size of spout pipe may result in inconvenience
to users, when waterflow is very close to granite edge. This
aspect must be considered during selection of sink cock for
wash basin.
For wash basin counter fixing, groove shall be formed in wall
dado upto 01" deep & width same as that of granite thickness.
5.6.6 Prior to groove cut outline shall be marked in dado with red -do- Supervisor
oxide. Care to be taken to ensure same level at two extreme
corners of groove

Page 8 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
Insert granite wash basin couner inside the groove
maintaining even level throughout & ensure the counter is
5.6.7 -do- -do-
stable as it would be free hanging till GI brackets provision
during basin fixation.
Offer inspection to QC Er. & obtain clearance for each flat.
He shall check right angle & level of ledge wall coping,
5.6.8 projection from ledge wall dado, gap between wall dado & -do- Site Er, QC Er.
coping etc., Again for wash basin level check, stability,
distance of sink cock hole, edge polish finish, uniformity of
edge
Duringfinish
handover stage, interface of wall dado & granite wash
basin counter shall be filled with Clear Silicone sealant to avoid
5.6.9 -do- Site Er.
percolation of water from the joint. Uniform application must
be ensured along the length of counter
E Kitchen granite platform
Based upon the customization by customers, flat list shall be
prepared which needs to be fixed with kitchen counter granite
platform at 34" from FFL (top lvl) after fixing of Kitchen wall
dado during handover stage. Width shall be 24" & bottom of
granite slab shall be provided with drip groove of 03x03 mm at
25mm from edge of platform. MS brackets painted in black Granite counter & coping
5.7.1 Site Er.
shall be used as supports. Generally 50x50x05mm angle could - checklist
be used at 750mm spacing with anchor bolts. Or else
appropriate size & spacing required site specific shall be
decided doing sampling as per site management decision. In
both methods, care to be taken to ensure stability & no
sagging of supports due to weight of granite slab
Offer inspection to QC Er. & obtain clearance for each flat.
5.7.2 He shall check dimension, level, height of platform. Size & -do- Site Er, QC Er.
uniformity of drip grooves, spacing & rigidity of bracket
supportsflooring & wall cladding
F Marble
5.8 Prerequisite & Surface preparartion
All measures as given in clause 5.1 shall be taken due care, Granite & Marble
5.8.1 Site Er, QC Er., Supervisor
similar to that of granite flooring flooring & dadoing -
5.9 Work procedure checklist
Procedure mentioned in 5.1.9, 5.1.10 & 5.2 shall be followed Granite & Marble
5.9.1 Site Er, QC Er., Supervisor
whichever applicable flooring & dadoing -
Place marble slabs for setting out in sequence, one by one checklist
over the entire lobby & enusre finish level of all panels is in
5.9.2 same level (as there may be difference in thickness of marble -do- Supervisor
slabs). When any mismatch in FFL is observed, remove such
panels & scrape off/apply mortar mix to make levels even.
Care to be taken while handling marble slabs, as they are
brittle in nature. Just before placing/setting & taking out , do
not remove the protective wrapping on the rear side of
5.9.3 -do- Supervisor
marble completely. Instead protective wrapping shall be
removed at localised spots, thereby minimising the tendency
to break while handling. Refer Fig. 8

Page 9 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility

Fig 8

Once mortar is leveled to slope or flat & modified matching


marble slab thickness as per requirement, remove one panel
at a time & apply white cement slurry in 1(cement):2(water) &
make grooves at every 05 to 08 cm distance, adequately
5.9.4 -do- Supervisor
which aids absorption of cement slurry into mortar &
expulsion of entrapped air, so as to ensure proper adhesion
with marble slab. Similary repeat the process for all marble
slab and complete the area.
Once flooring is laid, joint between marble stones, broken
edges, cracks etc., shall be filled with suitable colored Resin
5.9.5 -do- Supervisor
mixed with hardener & accelerator. similarly entire marble
surface area must also be applied with admixed resin for
protection
For skirting,till time of
before polishing
cutting to required size, entire marble slab
shall be placed in leveled platform & done with 07 layers of
wet polishing. Use appropriate Resin mixed with hardener &
5.9.6 accelerator in required proportion during polishing. Apply -do- Supervisor
glazing agent after 07 layer of polishing. Then cut skirting
piece 100mm high & fix in required area. Use white cement
for rich mix & mortar used for skirting fixing & packing
respectively.
Edge finishing for skirting shall be of appoved type as shown in
fig 5. Same shall be done with hand cutting machine with good
5.9.7 workmanship and again wet polishing to edges shall be done -do- Supervisor
with polishing stones numbering from 0 to 6 & applied with
glaze coat
Offer inspection to QC Er. prior to polishing & applying Resin
5.9.8 for marble joints. He shall check for level, pattern match for -do- Site Er, QC Er.
floor. Alignment, verticality for skirting pieces etc.,
Before commencing polishing to marble floors, access shall be
blocked along periphery. Contamination with sand, dirt,
foreign materials must be avoided, because even a small sand
5.9.9 particle could spoil the polishing process & final finish. -do- Supervisor
Polishing with stones numbering from 0 to 3 is called rough
polishing & with number from 4 to 6 is called smooth
polishing.

Page 10 of 11
SUMADHURA INFRACON PVT. LTD Format No: SIPL/QAQC/MS/25
Method statement Rev No: 0
Granite & marble works Date:
S.No. Description Records Responsibility
Resin compound must be applied for each layer of polishing &
also over chipped/cracked/scratched surface found during the
5.9.10 -do- Electrical Er.
polishing process. After 07 layers of polishing, glaze coat shall
be applied
Offer inspection to QC Er. for final finish acceptance. He shall
5.9.11 check for adequacy of glazed surface, cracks, odd spots etc., -do- Site Er, QC Er.
Any defects found in unacceptable limits, marble rework
shall be done as mentioned in 5.3 & 5.4 shall be followed
All procedures
5.9.12 whichever applicable, in case of Marble cladding except for -do- Electrical Er.
few deviations as mentioned below.
First is polishing of Marble stones before cutting into desired
shapes for fixing. Secondly, step 5.4.7 must be followed, not
5.9.13 -do- Electrical Er.
5.4.8. Third, precaution as shown in Fig 8. Fourth extra care in
handling as Marble is very brittle in nature.
Above laid down procedure, if any needs compromise, same
shall be discussed with Project Director and approval has to be Site Instruction register
5.9.14 PM, QC Er.
obtained through site instruction register. Copy of same shall & mail communication
be attached to checklist & intimated to HO.
Prepared by
Reviewed by Approved by

S.Suresh Kumar Bubesh Kumar Babu Bharat kumar Kandukuri


Head - QA/QC COO - Technical Director - Operations

Page 11 of 11