Professional Documents
Culture Documents
Revreschedule HUBT With
Revreschedule HUBT With
S M
1 1 START 28.8 wks Wed 10/27/21 Mon 5/16/22 RM5754949.00 58% RM316283.10
2 1.1 LETTER OF ACCEPTANCE 0 wks Mon 11/22/21 Mon 11/22/21 RM0.00 0% RM0.00
3 1.2 PRELIMINARIES 26 wks Wed 10/27/21 Tue 4/26/22 RM315264.00 98% RM298264.00
4 1.2.1 SITE SURVEY & SETTING O 1 wk Wed 10/27/21 Tue 11/02/21 RM10000.00 100% RM10000.00 2
UT
5 1.2.2 INSURANCES / PERFORMAN 1 wk Wed 10/27/21 Tue 11/02/21 RM5764.00 100% RM5764.00 2
CE BOND
6 1.2.3 WORK PROGRAMME 1 wk Wed 10/27/21 Tue 11/02/21 RM10000.00 100% RM10000.00 2
7 1.2.4 CONTRACTOR'S OFFICE 1 wk Wed 10/27/21 Tue 11/02/21 RM0.00 100% RM0.00 2
8 1.2.5 SITE ITEM FOR S.O 1 wk Wed 10/27/21 Tue 11/02/21 RM10000.00 100% RM10000.00 2
9 1.2.6 SITE STAFF 26 wks Wed 10/27/21 Tue 4/26/22 RM40000.00 100% RM40000.00 2
10 1.2.7 SITE SECURITY 26 wks Wed 10/27/21 Tue 4/26/22 RM20000.00 100% RM20000.00 2
11 1.2.8 OFFICE & STORAGE 25 wks Wed 11/03/21 Tue 4/26/22 RM20000.00 100% RM20000.00 2FS+5 days
12 1.2.9 SITE CABIN FOR S.O 26 wks Wed 10/27/21 Tue 4/26/22 RM10000.00 100% RM10000.00 2
13 1.2.10 WATER & POWER 26 wks Wed 10/27/21 Tue 4/26/22 RM30000.00 100% RM30000.00 2
14 1.2.11 OTHER RECURRING PRELIM 26 wks Wed 10/27/21 Tue 4/26/22 RM142500.00 100% RM142500.00 2
INARIES
15 1.2.12 AS-BUILT DRAWING 2 wks Wed 4/13/22 Tue 4/26/22 RM10000.00 0% RM0.00 13FF
16 1.2.13 CLEANING AFTER COMPLET 2 wks Wed 4/13/22 Tue 4/26/22 RM7000.00 0% RM0.00 13FF
ION
17 1.3 BUILDING WORKS 16.8 wks Wed 11/03/21 Mon 2/28/22 RM800287.00 3% RM2968.60
18 1.3.1 UPGRADING OF FLOOR ELE 5.3 wks Wed 11/03/21 Thu 12/09/21 RM194600.00 17% RM1650.00
MENT
Page 1
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
19 1.3.1.1 HACK EXISTING FLOOR 1 wk Wed 11/03/21 Thu 11/25/21 RM3300.00 50% RM1650.00 4
20 1.3.1.2 NEW FLOOR CONSTRUCT 2 wks Thu 11/25/21 Thu 12/09/21 RM191300.00 0% RM0.00 19
ION INCL. FINISHES
21 1.3.2 SCUPPER DRAIN & GREASE 3 wks Tue 11/23/21 Mon 12/13/21 RM19636.00 0% RM0.00
TRAP @ WASHING & DEBO
NING AREA
22 1.3.2.1 HACK EXISTING FLOOR 1 wk Tue 11/23/21 Mon 11/29/21 RM3120.00 0% RM0.00 19SS
23 1.3.2.2 SCUPPER DRAIN CONSTR 2 wks Tue 11/30/21 Mon 12/13/21 RM16516.00 0% RM0.00 22
UCTION INCL. GREASE TR
AP
26 1.3.5 FLAKE ICE MACHINE PLATFO 1 wk Tue 12/07/21 Mon 12/13/21 RM5383.00 0% RM0.00 24
RM
27 1.3.6 DEMOLISH EXISTING PLINTH 1 wk Wed 11/03/21 Fri 11/26/21 RM3000.00 20% RM600.00 19SS
28 1.3.7 WALL & DOOR 7.8 wks Wed 11/03/21 Mon 12/27/21 RM13734.00 3% RM718.60
29 1.3.7.1 DEMOLISH EXISTING BRIC 1 wk Wed 11/03/21 Fri 11/26/21 RM3593.00 20% RM718.60 19SS
KWALL/PARTITION
30 1.3.7.2 DISMANTLE EXISTING DO 1 wk Tue 11/23/21 Mon 11/29/21 RM1320.00 0% RM0.00 19SS
ORS
Page 2
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
31 1.3.7.3 HACK EXISTING WALL FO 1 wk Tue 11/30/21 Mon 12/06/21 RM1702.00 0% RM0.00 30
R DOOR OPENING
32 1.3.7.4 MAKE GOOD EXISTING DO 1 wk Tue 12/07/21 Mon 12/13/21 RM6447.00 0% RM0.00 31
OR & FRAME
33 1.3.7.5 PAINTING TO WALL 2 wks Tue 12/14/21 Mon 12/27/21 RM672.00 0% RM0.00 32
34 1.3.8 SUPPLY & INSTALL SLIDING 2 wks Tue 12/28/21 Mon 1/10/22 RM374720.00 0% RM0.00 33
DOOR
35 1.3.9 SUPPLY & INSTALL STRIP C 1 wk Tue 1/11/22 Mon 1/17/22 RM34010.00 0% RM0.00 34
URTAIN
37 1.3.10.1 SUPPLY & INSTALL NEW 2 wks Tue 12/28/21 Mon 1/10/22 RM1500.00 0% RM0.00 34SS
WINDOWS
38 1.3.10.2 MAKE GOOD & CLEAN EX 1 wk Tue 1/11/22 Mon 1/17/22 RM5000.00 0% RM0.00 35SS
ISTING WINDOWS
39 1.3.11 SUPPLY & INSTALL THERM 1 wk Tue 12/07/21 Mon 12/13/21 RM13104.00 0% RM0.00 25SS
AL REFLECTIVE UNDERLAY
40 1.3.12 INTERNAL CEILING FINISHE 4.2 wks Mon 11/29/21 Mon 12/27/21 RM84560.00 0% RM0.00
41 1.3.12.1 S TAKE DOWN, MAKE GOO 1 wk Mon 11/29/21 Fri 12/03/21 RM600.00 0% RM0.00 29
D EXISTING CEILING PAN
ELS
Page 3
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
42 1.3.12.2 SUPPLY & INSTALL NEW 3 wks Mon 12/06/21 Fri 12/24/21 RM1960.00 0% RM0.00 41
CEILING BOARD PANELS
43 1.3.12.3 MAKE GOOD EXISTING RO 3 wks Tue 12/07/21 Mon 12/27/21 RM82000.00 0% RM0.00 31
OF
44 1.3.13 WALL FINISHES 3 wks Tue 1/18/22 Mon 2/07/22 RM22145.00 0% RM0.00
45 1.3.13.1 CLEAN WALL FINISHES U 1 wk Tue 1/18/22 Mon 1/24/22 RM17145.00 0% RM0.00 38
SING WATER JET
46 1.3.13.2 MAKE GOOD EXISTING W 2 wks Tue 1/25/22 Mon 2/07/22 RM5000.00 0% RM0.00 45
ALL TILES
47 1.3.14 SUPPLY & INSTALL SANITAR 1 wk Tue 2/08/22 Mon 2/14/22 RM12000.00 0% RM0.00 46
Y FITTINGS
48 1.3.15 SUPPLY & INSTALL WORKIN 1 wk Tue 2/15/22 Mon 2/21/22 RM12750.00 0% RM0.00 47
G TABLE
50 1.4 EXTERNAL WORKS 16.8 wks Wed 11/03/21 Mon 2/28/22 RM137330.00 7% RM8700.00
51 1.4.1 SITE CLEARANCE 1 wk Wed 11/03/21 Tue 11/09/21 RM5700.00 100% RM5700.00 4
52 1.4.2 DEMOLITION WORKS 4.8 wks Wed 11/10/21 Mon 12/13/21 RM8000.00 25% RM3000.00
53 1.4.2.1 DEMOLISH EXISTING BUIL 2 wks Wed 11/10/21 Mon 11/29/21 RM6000.00 50% RM3000.00 51
DING
54 1.4.2.2 REMOVE EXISTING PREM 2 wks Tue 11/30/21 Mon 12/13/21 RM2000.00 0% RM0.00 53
IX & ROAD KERB
Page 4
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
55 1.4.3 NEW PAVEMENT 6 wks Tue 12/14/21 Mon 1/24/22 RM41250.00 0% RM0.00
56 1.4.3.1 EXCAVATE FOR ROAD 1 wk Tue 12/14/21 Mon 12/20/21 RM2400.00 0% RM0.00 54
58 1.4.3.3 N
SUB-BASE 0.5 wks Tue 12/28/21 Thu 12/30/21 RM5400.00 0% RM0.00 57
59 1.4.3.4 ROADBASE 0.5 wks Thu 12/30/21 Mon 1/03/22 RM9150.00 0% RM0.00 58
60 1.4.3.5 PRIME COAT 0.5 wks Tue 1/04/22 Thu 1/06/22 RM1200.00 0% RM0.00 59
61 1.4.3.6 TACK COAT 0.5 wks Thu 1/06/22 Mon 1/10/22 RM1200.00 0% RM0.00 60
64 1.4.4 SUPPLY & LAY ROAD KERB 2 wks Tue 1/25/22 Mon 2/07/22 RM5910.00 0% RM0.00 63
65 1.4.5 SUPPLY & INSTALL TRUCK W 1 wk Tue 2/08/22 Mon 2/14/22 RM522.00 0% RM0.00 64
HEEL & STOPPER
66 1.4.6 ROAD MARKINGS & FURNITU 2 wks Tue 2/15/22 Mon 2/28/22 RM11948.00 0% RM0.00 65
RE
67 1.4.7 RUBBISH COLLECTION ARE 4 wks Tue 11/30/21 Mon 12/27/21 RM21000.00 0% RM0.00
68 1.4.7.1 A CONSTRUCTION OF RUBB 3 wks Tue 11/30/21 Mon 12/20/21 RM15000.00 0% RM0.00 53
ISH COLLECTION AREA
69 1.4.7.2 SUPPLY & INSTALL GARB 1 wk Tue 12/21/21 Mon 12/27/21 RM6000.00 0% RM0.00 68
AGE BIN
70 1.4.8 GUARD HOUSE 3 wks Tue 12/21/21 Mon 1/10/22 RM6000.00 0% RM0.00 68
72 1.4.10 COMPACT SUB 2 wks Tue 1/11/22 Mon 1/24/22 RM30000.00 0% RM0.00 70
Page 5
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
74 1.5 WASTE WATER TREATMENT P 12 wks Tue 12/14/21 Mon 3/07/22 RM218882.00 0% RM0.00
LANT
75 1.5.1 SEWERAGE WORKS 6 wks Tue 12/14/21 Mon 1/24/22 RM43382.00 0% RM0.00
76 1.5.1.1 CUT & MAKE GOOD EXIST 1 wk Tue 12/14/21 Mon 12/20/21 RM1500.00 0% RM0.00 54
ING PREMIX
77 1.5.1.2 EXCAVATE TRENCH & PIT 1 wk Tue 12/21/21 Mon 12/27/21 RM770.00 0% RM0.00 76
78 1.5.1.3 LAY SEWERAGE PIPE 2 wks Tue 12/28/21 Mon 1/10/22 RM11700.00 0% RM0.00 77
79 1.5.1.4 SUPPLY & INSTALL MANH 2 wks Tue 1/11/22 Mon 1/24/22 RM29412.00 0% RM0.00 78
OLE INCL. PUMP
80 1.5.2 SEWERAGE TREATMENT PL 5 wks Tue 1/25/22 Mon 2/28/22 RM175500.00 0% RM0.00
ANT
81 1.5.2.1 DESIGN & CONSTRUCT S 3 wks Tue 1/25/22 Mon 2/14/22 RM70000.00 0% RM0.00 79
TP
82 1.5.2.2 CONNECTION WITH SEW 1 wk Tue 2/15/22 Mon 2/21/22 RM92500.00 0% RM0.00 81
ERAGE
83 1.5.2.3 TESTING & COMISSIONIN 1 wk Tue 2/22/22 Mon 2/28/22 RM13000.00 0% RM0.00 82
84 1.5.3 G
MISCELLANEOUS 1 wk Tue 3/01/22 Mon 3/07/22 RM0.00 0% RM0.00 83
85 1.6 PROCESSING & STORAGE SY 2 wks Tue 3/01/22 Mon 3/14/22 RM3792448.00 0% RM0.00
STEM
86 1.6.1 PROCESSING & STORAGE S 1 wk Tue 3/01/22 Mon 3/07/22 RM0.00 0% RM0.00 17
YSTEM
Page 6
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
91 1.6.6 FLAKE ICE MACHINE 1 wk Tue 3/08/22 Mon 3/14/22 RM145362.00 0% RM0.00 86
93 1.6.8 AUTOMATIC FISH DEBONIN 2 wks Tue 3/01/22 Mon 3/14/22 RM184000.00 0% RM0.00
G MACHINE
94 1.6.8.1 SUPPLY, DELIVER & INSTA 1 wk Tue 3/01/22 Mon 3/07/22 RM179000.00 0% RM0.00 17
LL FISH DEBONING MACH
INE
95 1.6.8.2 TESTING & COMISSIONIN 1 wk Tue 3/08/22 Mon 3/14/22 RM5000.00 0% RM0.00 94
96 1.7 G
MECHANICAL WORKS 10 wks Tue 3/01/22 Mon 5/09/22 RM267643.00 1% RM6350.50
97 1.7.1 COLD WATER SYSTEM 6 wks Tue 3/08/22 Mon 4/18/22 RM75400.00 0% RM0.00
98 1.7.1.1 SUPPLY & INSTALL SUCTIO 1 wk Tue 3/08/22 Mon 3/14/22 RM5300.00 0% RM0.00 74
N TANK
99 1.7.1.2 PIPING WORKS 3 wks Tue 3/15/22 Mon 4/04/22 RM65660.00 0% RM0.00 98
100 1.7.1.3 SUPPLY & INSTALL WATE 1 wk Tue 4/05/22 Mon 4/11/22 RM1440.00 0% RM0.00 99
R TANK
101 1.7.1.4 TESTING & COMISSIONIN 1 wk Tue 4/12/22 Mon 4/18/22 RM3000.00 0% RM0.00 100
102 1.7.2 G
SANITARY PLUMBING 4.5 wks Wed 3/02/22 Fri 4/01/22 RM63505.00 8% RM6350.50
103 1.7.2.1 PIPING WORKS 3 wks Wed 3/02/22 Fri 3/25/22 RM63505.00 10% RM6350.50 74
104 1.7.2.2 TESTING & COMISSIONIN 1 wk Fri 3/25/22 Fri 4/01/22 RM0.00 0% RM0.00 103
105 1.7.3 G
SANITARY FITTINGS 3 wks Fri 4/01/22 Fri 4/22/22 RM1065.00 0% RM0.00
Page 7
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
106 1.7.3.1 SUPPLY & INSTALL SANIT 2 wks Fri 4/01/22 Fri 4/15/22 RM65.00 0% RM0.00 102
ARY FITTINGS
107 1.7.3.2 TESTING & COMISSIONIN 1 wk Fri 4/15/22 Fri 4/22/22 RM1000.00 0% RM0.00 106
109 1.7.4.1 HOSE REEL SYSTEM 1 wk Tue 3/01/22 Mon 3/07/22 RM33720.00 0% RM0.00 17
110 1.7.4.2 HOSE REEL PUMPSET SY 2 wks Tue 3/08/22 Mon 3/21/22 RM16050.00 0% RM0.00 109
STEM
111 1.7.4.3 FIRE ALARM PANEL 2 wks Tue 3/22/22 Mon 4/04/22 RM9000.00 0% RM0.00 110
112 1.7.4.4 PORTABLE FIRE EXTINGU 1 wk Tue 4/05/22 Mon 4/11/22 RM17600.00 0% RM0.00 111
ISHER
113 1.7.4.5 LABELLING & PAINTING 1 wk Tue 4/12/22 Mon 4/18/22 RM3000.00 0% RM0.00 112
114 1.7.4.6 TESTING & COMISSIONIN 1 wk Tue 4/19/22 Mon 4/25/22 RM2000.00 0% RM0.00 113
116 1.7.5.1 SUPPLY & INSTALL SPLIT U 1 wk Tue 4/26/22 Mon 5/02/22 RM44303.00 0% RM0.00 108
NIT AIR CONDITIONER
117 1.7.5.2 TESTING & COMISSIONIN 1 wk Tue 5/03/22 Mon 5/09/22 RM2000.00 0% RM0.00 116
118 1.8 G
ELECTRICAL WORKS 10 wks Tue 3/01/22 Mon 5/09/22 RM203095.00 0% RM0.00
119 1.8.1 MAIN SWITCH BOARD / DIST 1 wk Tue 3/01/22 Mon 3/07/22 RM33000.00 0% RM0.00 17
RIBUTION BOARD
120 1.8.2 CABLES 3 wks Tue 3/08/22 Mon 3/28/22 RM75000.00 0% RM0.00 119
121 1.8.3 LIGHTING 2 wks Tue 3/29/22 Mon 4/11/22 RM64075.00 0% RM0.00 120
Page 8
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21
S M
122 1.8.4 EARTHING SYSTEM 1 wk Tue 4/12/22 Mon 4/18/22 RM8500.00 0% RM0.00 121
123 1.8.5 TNB 2 wks Tue 4/19/22 Mon 5/02/22 RM22520.00 0% RM0.00 122
124 1.8.6 TESTING & COMISSIONING 1 wk Tue 5/03/22 Mon 5/09/22 RM0.00 0% RM0.00 123
125 1.9 PROVISIONAL SUM 1 wk Tue 5/10/22 Mon 5/16/22 RM20000.00 0% RM0.00
126 1.9.1 SIGNAGES 1 wk Tue 5/10/22 Mon 5/16/22 RM10000.00 0% RM0.00 118
127 1.9.2 RE-STRENGTHENING EXIST 1 wk Tue 5/10/22 Mon 5/16/22 RM10000.00 0% RM0.00 118
ING STRUCTURE
Page 9
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
22.11
Page 10
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 11
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 12
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 13
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 14
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 15
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 16
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 17
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Page 18