ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

1 1 START 28.8 wks Wed 10/27/21 Mon 5/16/22 RM5754949.00 58% RM316283.10

2 1.1 LETTER OF ACCEPTANCE 0 wks Mon 11/22/21 Mon 11/22/21 RM0.00 0% RM0.00

3 1.2 PRELIMINARIES 26 wks Wed 10/27/21 Tue 4/26/22 RM315264.00 98% RM298264.00

4 1.2.1 SITE SURVEY & SETTING O 1 wk Wed 10/27/21 Tue 11/02/21 RM10000.00 100% RM10000.00 2
UT

5 1.2.2 INSURANCES / PERFORMAN 1 wk Wed 10/27/21 Tue 11/02/21 RM5764.00 100% RM5764.00 2
CE BOND

6 1.2.3 WORK PROGRAMME 1 wk Wed 10/27/21 Tue 11/02/21 RM10000.00 100% RM10000.00 2

7 1.2.4 CONTRACTOR'S OFFICE 1 wk Wed 10/27/21 Tue 11/02/21 RM0.00 100% RM0.00 2

8 1.2.5 SITE ITEM FOR S.O 1 wk Wed 10/27/21 Tue 11/02/21 RM10000.00 100% RM10000.00 2

9 1.2.6 SITE STAFF 26 wks Wed 10/27/21 Tue 4/26/22 RM40000.00 100% RM40000.00 2

10 1.2.7 SITE SECURITY 26 wks Wed 10/27/21 Tue 4/26/22 RM20000.00 100% RM20000.00 2

11 1.2.8 OFFICE & STORAGE 25 wks Wed 11/03/21 Tue 4/26/22 RM20000.00 100% RM20000.00 2FS+5 days

12 1.2.9 SITE CABIN FOR S.O 26 wks Wed 10/27/21 Tue 4/26/22 RM10000.00 100% RM10000.00 2

13 1.2.10 WATER & POWER 26 wks Wed 10/27/21 Tue 4/26/22 RM30000.00 100% RM30000.00 2

14 1.2.11 OTHER RECURRING PRELIM 26 wks Wed 10/27/21 Tue 4/26/22 RM142500.00 100% RM142500.00 2
INARIES

15 1.2.12 AS-BUILT DRAWING 2 wks Wed 4/13/22 Tue 4/26/22 RM10000.00 0% RM0.00 13FF

16 1.2.13 CLEANING AFTER COMPLET 2 wks Wed 4/13/22 Tue 4/26/22 RM7000.00 0% RM0.00 13FF
ION

17 1.3 BUILDING WORKS 16.8 wks Wed 11/03/21 Mon 2/28/22 RM800287.00 3% RM2968.60

18 1.3.1 UPGRADING OF FLOOR ELE 5.3 wks Wed 11/03/21 Thu 12/09/21 RM194600.00 17% RM1650.00
MENT

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

19 1.3.1.1 HACK EXISTING FLOOR 1 wk Wed 11/03/21 Thu 11/25/21 RM3300.00 50% RM1650.00 4

20 1.3.1.2 NEW FLOOR CONSTRUCT 2 wks Thu 11/25/21 Thu 12/09/21 RM191300.00 0% RM0.00 19
ION INCL. FINISHES

21 1.3.2 SCUPPER DRAIN & GREASE 3 wks Tue 11/23/21 Mon 12/13/21 RM19636.00 0% RM0.00
TRAP @ WASHING & DEBO
NING AREA

22 1.3.2.1 HACK EXISTING FLOOR 1 wk Tue 11/23/21 Mon 11/29/21 RM3120.00 0% RM0.00 19SS

23 1.3.2.2 SCUPPER DRAIN CONSTR 2 wks Tue 11/30/21 Mon 12/13/21 RM16516.00 0% RM0.00 22
UCTION INCL. GREASE TR
AP

24 1.3.3 FOOTBATH 1 wk Tue 11/30/21 Mon 12/06/21 RM1095.00 0% RM0.00 22

25 1.3.4 REINFORCED CONCRETE R 1 wk Tue 12/07/21 Mon 12/13/21 RM3050.00 0% RM0.00 24


AMP

26 1.3.5 FLAKE ICE MACHINE PLATFO 1 wk Tue 12/07/21 Mon 12/13/21 RM5383.00 0% RM0.00 24
RM

27 1.3.6 DEMOLISH EXISTING PLINTH 1 wk Wed 11/03/21 Fri 11/26/21 RM3000.00 20% RM600.00 19SS

28 1.3.7 WALL & DOOR 7.8 wks Wed 11/03/21 Mon 12/27/21 RM13734.00 3% RM718.60

29 1.3.7.1 DEMOLISH EXISTING BRIC 1 wk Wed 11/03/21 Fri 11/26/21 RM3593.00 20% RM718.60 19SS
KWALL/PARTITION

30 1.3.7.2 DISMANTLE EXISTING DO 1 wk Tue 11/23/21 Mon 11/29/21 RM1320.00 0% RM0.00 19SS
ORS

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

31 1.3.7.3 HACK EXISTING WALL FO 1 wk Tue 11/30/21 Mon 12/06/21 RM1702.00 0% RM0.00 30
R DOOR OPENING

32 1.3.7.4 MAKE GOOD EXISTING DO 1 wk Tue 12/07/21 Mon 12/13/21 RM6447.00 0% RM0.00 31
OR & FRAME

33 1.3.7.5 PAINTING TO WALL 2 wks Tue 12/14/21 Mon 12/27/21 RM672.00 0% RM0.00 32

34 1.3.8 SUPPLY & INSTALL SLIDING 2 wks Tue 12/28/21 Mon 1/10/22 RM374720.00 0% RM0.00 33
DOOR

35 1.3.9 SUPPLY & INSTALL STRIP C 1 wk Tue 1/11/22 Mon 1/17/22 RM34010.00 0% RM0.00 34
URTAIN

36 1.3.10 WINDOWS 3 wks Tue 12/28/21 Mon 1/17/22 RM6500.00 0% RM0.00

37 1.3.10.1 SUPPLY & INSTALL NEW 2 wks Tue 12/28/21 Mon 1/10/22 RM1500.00 0% RM0.00 34SS
WINDOWS

38 1.3.10.2 MAKE GOOD & CLEAN EX 1 wk Tue 1/11/22 Mon 1/17/22 RM5000.00 0% RM0.00 35SS
ISTING WINDOWS

39 1.3.11 SUPPLY & INSTALL THERM 1 wk Tue 12/07/21 Mon 12/13/21 RM13104.00 0% RM0.00 25SS
AL REFLECTIVE UNDERLAY

40 1.3.12 INTERNAL CEILING FINISHE 4.2 wks Mon 11/29/21 Mon 12/27/21 RM84560.00 0% RM0.00

41 1.3.12.1 S TAKE DOWN, MAKE GOO 1 wk Mon 11/29/21 Fri 12/03/21 RM600.00 0% RM0.00 29
D EXISTING CEILING PAN
ELS

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

42 1.3.12.2 SUPPLY & INSTALL NEW 3 wks Mon 12/06/21 Fri 12/24/21 RM1960.00 0% RM0.00 41
CEILING BOARD PANELS

43 1.3.12.3 MAKE GOOD EXISTING RO 3 wks Tue 12/07/21 Mon 12/27/21 RM82000.00 0% RM0.00 31
OF

44 1.3.13 WALL FINISHES 3 wks Tue 1/18/22 Mon 2/07/22 RM22145.00 0% RM0.00

45 1.3.13.1 CLEAN WALL FINISHES U 1 wk Tue 1/18/22 Mon 1/24/22 RM17145.00 0% RM0.00 38
SING WATER JET

46 1.3.13.2 MAKE GOOD EXISTING W 2 wks Tue 1/25/22 Mon 2/07/22 RM5000.00 0% RM0.00 45
ALL TILES

47 1.3.14 SUPPLY & INSTALL SANITAR 1 wk Tue 2/08/22 Mon 2/14/22 RM12000.00 0% RM0.00 46
Y FITTINGS

48 1.3.15 SUPPLY & INSTALL WORKIN 1 wk Tue 2/15/22 Mon 2/21/22 RM12750.00 0% RM0.00 47
G TABLE

49 1.3.16 MISCELLANEOUS 1 wk Tue 2/22/22 Mon 2/28/22 RM0.00 0% RM0.00 48

50 1.4 EXTERNAL WORKS 16.8 wks Wed 11/03/21 Mon 2/28/22 RM137330.00 7% RM8700.00

51 1.4.1 SITE CLEARANCE 1 wk Wed 11/03/21 Tue 11/09/21 RM5700.00 100% RM5700.00 4

52 1.4.2 DEMOLITION WORKS 4.8 wks Wed 11/10/21 Mon 12/13/21 RM8000.00 25% RM3000.00

53 1.4.2.1 DEMOLISH EXISTING BUIL 2 wks Wed 11/10/21 Mon 11/29/21 RM6000.00 50% RM3000.00 51
DING

54 1.4.2.2 REMOVE EXISTING PREM 2 wks Tue 11/30/21 Mon 12/13/21 RM2000.00 0% RM0.00 53
IX & ROAD KERB

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

55 1.4.3 NEW PAVEMENT 6 wks Tue 12/14/21 Mon 1/24/22 RM41250.00 0% RM0.00

56 1.4.3.1 EXCAVATE FOR ROAD 1 wk Tue 12/14/21 Mon 12/20/21 RM2400.00 0% RM0.00 54

57 1.4.3.2 SUBGRADE PREPARATIO 1 wk Tue 12/21/21 Mon 12/27/21 RM3000.00 0% RM0.00 56

58 1.4.3.3 N
SUB-BASE 0.5 wks Tue 12/28/21 Thu 12/30/21 RM5400.00 0% RM0.00 57

59 1.4.3.4 ROADBASE 0.5 wks Thu 12/30/21 Mon 1/03/22 RM9150.00 0% RM0.00 58

60 1.4.3.5 PRIME COAT 0.5 wks Tue 1/04/22 Thu 1/06/22 RM1200.00 0% RM0.00 59

61 1.4.3.6 TACK COAT 0.5 wks Thu 1/06/22 Mon 1/10/22 RM1200.00 0% RM0.00 60

62 1.4.3.7 BINDER COURSE 1 wk Tue 1/11/22 Mon 1/17/22 RM10050.00 0% RM0.00 61

63 1.4.3.8 WEARING COURSE 1 wk Tue 1/18/22 Mon 1/24/22 RM8850.00 0% RM0.00 62

64 1.4.4 SUPPLY & LAY ROAD KERB 2 wks Tue 1/25/22 Mon 2/07/22 RM5910.00 0% RM0.00 63

65 1.4.5 SUPPLY & INSTALL TRUCK W 1 wk Tue 2/08/22 Mon 2/14/22 RM522.00 0% RM0.00 64
HEEL & STOPPER

66 1.4.6 ROAD MARKINGS & FURNITU 2 wks Tue 2/15/22 Mon 2/28/22 RM11948.00 0% RM0.00 65
RE

67 1.4.7 RUBBISH COLLECTION ARE 4 wks Tue 11/30/21 Mon 12/27/21 RM21000.00 0% RM0.00

68 1.4.7.1 A CONSTRUCTION OF RUBB 3 wks Tue 11/30/21 Mon 12/20/21 RM15000.00 0% RM0.00 53
ISH COLLECTION AREA

69 1.4.7.2 SUPPLY & INSTALL GARB 1 wk Tue 12/21/21 Mon 12/27/21 RM6000.00 0% RM0.00 68
AGE BIN

70 1.4.8 GUARD HOUSE 3 wks Tue 12/21/21 Mon 1/10/22 RM6000.00 0% RM0.00 68

71 1.4.9 MOBILE TOILET 1 wk Tue 12/28/21 Mon 1/03/22 RM7000.00 0% RM0.00 69

72 1.4.10 COMPACT SUB 2 wks Tue 1/11/22 Mon 1/24/22 RM30000.00 0% RM0.00 70

73 1.4.11 MISCELLANEOUS 1 wk Tue 1/04/22 Mon 1/10/22 RM0.00 0% RM0.00 71

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 5
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

74 1.5 WASTE WATER TREATMENT P 12 wks Tue 12/14/21 Mon 3/07/22 RM218882.00 0% RM0.00
LANT

75 1.5.1 SEWERAGE WORKS 6 wks Tue 12/14/21 Mon 1/24/22 RM43382.00 0% RM0.00

76 1.5.1.1 CUT & MAKE GOOD EXIST 1 wk Tue 12/14/21 Mon 12/20/21 RM1500.00 0% RM0.00 54
ING PREMIX

77 1.5.1.2 EXCAVATE TRENCH & PIT 1 wk Tue 12/21/21 Mon 12/27/21 RM770.00 0% RM0.00 76

78 1.5.1.3 LAY SEWERAGE PIPE 2 wks Tue 12/28/21 Mon 1/10/22 RM11700.00 0% RM0.00 77

79 1.5.1.4 SUPPLY & INSTALL MANH 2 wks Tue 1/11/22 Mon 1/24/22 RM29412.00 0% RM0.00 78
OLE INCL. PUMP

80 1.5.2 SEWERAGE TREATMENT PL 5 wks Tue 1/25/22 Mon 2/28/22 RM175500.00 0% RM0.00
ANT

81 1.5.2.1 DESIGN & CONSTRUCT S 3 wks Tue 1/25/22 Mon 2/14/22 RM70000.00 0% RM0.00 79
TP

82 1.5.2.2 CONNECTION WITH SEW 1 wk Tue 2/15/22 Mon 2/21/22 RM92500.00 0% RM0.00 81
ERAGE

83 1.5.2.3 TESTING & COMISSIONIN 1 wk Tue 2/22/22 Mon 2/28/22 RM13000.00 0% RM0.00 82

84 1.5.3 G
MISCELLANEOUS 1 wk Tue 3/01/22 Mon 3/07/22 RM0.00 0% RM0.00 83

85 1.6 PROCESSING & STORAGE SY 2 wks Tue 3/01/22 Mon 3/14/22 RM3792448.00 0% RM0.00
STEM

86 1.6.1 PROCESSING & STORAGE S 1 wk Tue 3/01/22 Mon 3/07/22 RM0.00 0% RM0.00 17
YSTEM

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 6
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

87 1.6.2 FREEZER ROOM 1 wk Tue 3/08/22 Mon 3/14/22 RM1249740.00 0% RM0.00 86

88 1.6.3 BLAST FREEZER 1 wk Tue 3/08/22 Mon 3/14/22 RM367324.00 0% RM0.00 86

89 1.6.4 ANTE ROOM 1 wk Tue 3/08/22 Mon 3/14/22 RM373010.00 0% RM0.00 86

90 1.6.5 PROCESSING AREA 1 wk Tue 3/08/22 Mon 3/14/22 RM1400940.00 0% RM0.00 86

91 1.6.6 FLAKE ICE MACHINE 1 wk Tue 3/08/22 Mon 3/14/22 RM145362.00 0% RM0.00 86

92 1.6.7 RACKING SYSTEM 1 wk Tue 3/08/22 Mon 3/14/22 RM72072.00 0% RM0.00 86

93 1.6.8 AUTOMATIC FISH DEBONIN 2 wks Tue 3/01/22 Mon 3/14/22 RM184000.00 0% RM0.00
G MACHINE

94 1.6.8.1 SUPPLY, DELIVER & INSTA 1 wk Tue 3/01/22 Mon 3/07/22 RM179000.00 0% RM0.00 17
LL FISH DEBONING MACH
INE

95 1.6.8.2 TESTING & COMISSIONIN 1 wk Tue 3/08/22 Mon 3/14/22 RM5000.00 0% RM0.00 94

96 1.7 G
MECHANICAL WORKS 10 wks Tue 3/01/22 Mon 5/09/22 RM267643.00 1% RM6350.50

97 1.7.1 COLD WATER SYSTEM 6 wks Tue 3/08/22 Mon 4/18/22 RM75400.00 0% RM0.00

98 1.7.1.1 SUPPLY & INSTALL SUCTIO 1 wk Tue 3/08/22 Mon 3/14/22 RM5300.00 0% RM0.00 74
N TANK

99 1.7.1.2 PIPING WORKS 3 wks Tue 3/15/22 Mon 4/04/22 RM65660.00 0% RM0.00 98

100 1.7.1.3 SUPPLY & INSTALL WATE 1 wk Tue 4/05/22 Mon 4/11/22 RM1440.00 0% RM0.00 99
R TANK

101 1.7.1.4 TESTING & COMISSIONIN 1 wk Tue 4/12/22 Mon 4/18/22 RM3000.00 0% RM0.00 100

102 1.7.2 G
SANITARY PLUMBING 4.5 wks Wed 3/02/22 Fri 4/01/22 RM63505.00 8% RM6350.50

103 1.7.2.1 PIPING WORKS 3 wks Wed 3/02/22 Fri 3/25/22 RM63505.00 10% RM6350.50 74

104 1.7.2.2 TESTING & COMISSIONIN 1 wk Fri 3/25/22 Fri 4/01/22 RM0.00 0% RM0.00 103

105 1.7.3 G
SANITARY FITTINGS 3 wks Fri 4/01/22 Fri 4/22/22 RM1065.00 0% RM0.00

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 7
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

106 1.7.3.1 SUPPLY & INSTALL SANIT 2 wks Fri 4/01/22 Fri 4/15/22 RM65.00 0% RM0.00 102
ARY FITTINGS

107 1.7.3.2 TESTING & COMISSIONIN 1 wk Fri 4/15/22 Fri 4/22/22 RM1000.00 0% RM0.00 106

108 1.7.4 G FIGHTING SYSTEM


FIRE 8 wks Tue 3/01/22 Mon 4/25/22 RM81370.00 0% RM0.00

109 1.7.4.1 HOSE REEL SYSTEM 1 wk Tue 3/01/22 Mon 3/07/22 RM33720.00 0% RM0.00 17

110 1.7.4.2 HOSE REEL PUMPSET SY 2 wks Tue 3/08/22 Mon 3/21/22 RM16050.00 0% RM0.00 109
STEM

111 1.7.4.3 FIRE ALARM PANEL 2 wks Tue 3/22/22 Mon 4/04/22 RM9000.00 0% RM0.00 110

112 1.7.4.4 PORTABLE FIRE EXTINGU 1 wk Tue 4/05/22 Mon 4/11/22 RM17600.00 0% RM0.00 111
ISHER

113 1.7.4.5 LABELLING & PAINTING 1 wk Tue 4/12/22 Mon 4/18/22 RM3000.00 0% RM0.00 112

114 1.7.4.6 TESTING & COMISSIONIN 1 wk Tue 4/19/22 Mon 4/25/22 RM2000.00 0% RM0.00 113

115 1.7.5 G CONDITIONING & MECH


AIR 2 wks Tue 4/26/22 Mon 5/09/22 RM46303.00 0% RM0.00
ANICAL VENTILATION SYST
EM

116 1.7.5.1 SUPPLY & INSTALL SPLIT U 1 wk Tue 4/26/22 Mon 5/02/22 RM44303.00 0% RM0.00 108
NIT AIR CONDITIONER

117 1.7.5.2 TESTING & COMISSIONIN 1 wk Tue 5/03/22 Mon 5/09/22 RM2000.00 0% RM0.00 116

118 1.8 G
ELECTRICAL WORKS 10 wks Tue 3/01/22 Mon 5/09/22 RM203095.00 0% RM0.00

119 1.8.1 MAIN SWITCH BOARD / DIST 1 wk Tue 3/01/22 Mon 3/07/22 RM33000.00 0% RM0.00 17
RIBUTION BOARD

120 1.8.2 CABLES 3 wks Tue 3/08/22 Mon 3/28/22 RM75000.00 0% RM0.00 119

121 1.8.3 LIGHTING 2 wks Tue 3/29/22 Mon 4/11/22 RM64075.00 0% RM0.00 120

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 8
ID WBS Task Name Duration Start Finish Cost % Complete Actual Cost Predecessors Oct 31, '21

S M

122 1.8.4 EARTHING SYSTEM 1 wk Tue 4/12/22 Mon 4/18/22 RM8500.00 0% RM0.00 121

123 1.8.5 TNB 2 wks Tue 4/19/22 Mon 5/02/22 RM22520.00 0% RM0.00 122

124 1.8.6 TESTING & COMISSIONING 1 wk Tue 5/03/22 Mon 5/09/22 RM0.00 0% RM0.00 123

125 1.9 PROVISIONAL SUM 1 wk Tue 5/10/22 Mon 5/16/22 RM20000.00 0% RM0.00

126 1.9.1 SIGNAGES 1 wk Tue 5/10/22 Mon 5/16/22 RM10000.00 0% RM0.00 118

127 1.9.2 RE-STRENGTHENING EXIST 1 wk Tue 5/10/22 Mon 5/16/22 RM10000.00 0% RM0.00 118
ING STRUCTURE

128 2 FINISH 0 wks Mon 5/16/22 Mon 5/16/22 RM0.00 0% RM0.00 1

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 9
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

22.11

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 10
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 11
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 12
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 13
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 14
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 15
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 16
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 17
Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: HUB IKAN BESUT-with amount RSplit External Tasks Inactive Summary Manual Summary Deadline
3
Date: 11/21/2021 10:34 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 18

You might also like