Civil4M Solutions LLP

Forum Project
RCC Column Works

Building Area : Date :

Reference Drawings : Location:

Sr. Particulars Yes / No / Remarks


No. N.A.

Reinforcement
1 Column main bars are as per drawing
2 All Links spacing as per drawing
3 All rings provided with 135o bend inside (confinement)
4 Covers provided as per drawing
5 Joggles with correct slope (Max 1in 6) with extra stirrup
6 Master ring provided above top level of concrete
(app.1meter)
7 Overlap provided for column bars in central zone
8 Staggering of bars done at overlapping
Shuttering
1 Approved formwork drawings available on site.
2 Size and diagonals of column as per drawing.
3 Plumb, Right angle and alignment checked
4 Gap sealing done at starter level and for all sides
5 Spacing of horizontal runners(chavi) as per drawing.
6 Spacing of vertical Wailers(Patti) as per drawing.
7 Horizontal wailers flush with vertical runners
8 Tie rod provided as per drawing
9 Sufficient cross bracing provided to support the column
10 Shikanja spacing is as per drawing
11 Independent platform erected for casting
12 Top level of concrete marked from inside

Conclusion by Civil4M Representative - Activities Are Satisfactory / Not satisfactory

Contractor's Representative Civil4M Representative

Signature Signature