I amMr.Vishal R.Shende Roll No. 03 a student of
Third year of Department of Civil Engineering , humbly
completed this microproject in Subject Design of steel and RCC structure
(DSR) work from the time to time as described in this report by
ourown skill and study between the period from 2021- 2022.
As per instructions and Guidance of Mr.JAYANT
SAHARE and that, Ihave not copedi the report
or it's any apprecabe part from any other iterative contravention
of thrilling academcethcs.ii
Date:-
Sign
Name:-................................
..............
Part–A
Micro-ProjectProposal
Title of Micro-Project
TYPES OF FORM WORK USE FOR RCC STRUCTURE SATSITES
• Aims of the Micro-Project:
Prepare a report on types of form work use for RCC structure satsites.
3.0ProposedMethodology:
At the first step we got our topic of design of steel and RCC structures to
Preparereport on types of formwork use for RCC structures at sites. Then we discussed with our
subjectteacher about the collection of data required for project, source of data, preparation
ofreport etc.
For our micro-project thenwe will discuss about topic inour group and
distributeourworkamongallgroupmembers.Wewillsearchfortypesofformwork usefor
RCCstructures at sites and then we will show our collected data to subject teacher after that
wewillprepareareport.
4.0 Action Plan
Part– B
Micro-ProjectReport
TitleofMicro-Project
TYPESOFFORMWORK USEFORRCC STRUCTURESATSITES
• Rationale:-
The use of formwork is very important in the process of construction.
Therearemany types offormworkand thisisnecessarywhenconstructingabuild.Becauseof
formwork,it is easy tomake the different designof building parts suchas stairs,
walls,andfloor.Thereare3typesofformworkdesignsuchastimberformwork,plywoodformwork,
andsteelformwork.
2.0 AimoftheMicro-Project :
PrepareareportontypesofformworkuseforRCCstructuresatsites.
• CourseOutcomesAddressed:-
1) ToacquireknowledgeabouttypesofformworkuseforRCCstructuresatsites.
2) TostudythesuitabilityoftypesofformworkuseforRCCstructuresatsites.
4.0 LiteratureReview
Sr. TitleofBook Author Publication
no.
5.0ActualMethodology Followed:-
AtthefirststepwegotourtopicofdesignofsteelandRCCstructurestoPreparereportontypesoff
ormworkuseforRCCstructuresatsites.Thenwediscussedwithour
subject teacher about the collection of data required for project, source of data,
preparationofreportetc.
For our micro-project thenwe will discuss about topic inour group and distributeour
work among all group members. We will search for types of formwork use for RCCstructures
at sites and then we will show our collected data to subject teacher after that
wewillprepareareport.
INTRODUCTION
FORMWORK
Formwork (shuttering) in concrete construction is used as a mould for
astructure in which fresh concrete is poured only to harden subsequently.
Typesof concrete formwork construction depends on formwork material and
type ofstructuralelement.
Theconstructionofformworktakestimeandinvolvesexpenditureupto20 to
25% of the cost of the structure or even more. Design of these
temporarystructures are made to economic expenditure. The operation of
removing theformworkis knownas stripping.Strippedformworkcanbereused.
Agoodformworkshouldsatisfythefollowingrequirements:
• Itshouldbestrongenoughtowithstandalltypesofdeadandliveloads.
• Itshouldbeaslightaspossible.
• Itshouldrestonfirmbase.
EconomyinFormwork
The following points are to be kept in view to effect economy in the cost
offormwork:
• Theplanofthebuildingshouldimplyminimumnumberofvariations in
thesize of rooms, floor area etc. so as topermitreuse
oftheformworkrepeatedly.
• Design should be perfect to use slender sections only in a
mosteconomicalway.
Construction:TimberFormwork:
requirement:Itshouldbe
• Well-seasoned
• lightinweight
• easilyworkablewithnailswithoutsplitting
• freefromlooseknots
Timberusedforshutteringforexposedconcreteworkshouldhavesmoothandeven
surfaceon allfaceswhichcomeincontactwithconcrete.
TimberFormwork
PlywoodFormwork
• Byuseoflargesizepanelsitispossibletoeffectsavinginthelabourcostof
fixinganddismantling.
• Numberofreusesaremoreascomparedwithtimbershuttering.Foresti
mationpurpose,numberofreuses canbe takenas20to 25.
PlywoodFormwork
SteelFormwork
This consist of panels fabricated out of thin steel plates stiffened along
theedges by small steel angles. The panel units can be held together through
theuse of suitable clamps or bolts and nuts. The panels can be fabricated in
largenumber in any desired modular shape or size. Steel forms are largely used
orcurvedstructures.
SteelFormwork
Steelformscomparedwithtimberformwork:
• Steelformsarestronger,durableandhavelongerlifethantimberform
workandtheirreuses aremoreinnumber.
• Steelformscanbeinstalledanddismantledwithgreatereaseandspeed
.
• Thequalityofexposedconcretesurfacebyusingsteelformsisgoodands
uchsurfacesneednofurthertreatment.
• Steelformworkdoesnotabsorbmoisturefromconcrete.
• Steelformworkdoesnotshrinkorwarp.
ConstructionofConcreteformwork:
Thisnormallyinvolvesthefollowingoperations:
• Proppingandcentring
• Shuttering
• Provisionofcamber
treatmentOrderandMethodofRemovingFor
mwork:
Thesequenceofordersandmethodofremovalofformworkareasfollows:
• Shutteringformingsoffitofslabsshouldberemovednext.
engineeringconstruction.
FORMWORKFORBEAMSANDSLABS
Periodofremovalofformwork
• OutputsoftheMicro-Projects
• WegottheinformationaboutvarioustypesofformworksuseforR.C.C.structures.
• Westudiedthesuitabilityofaboutvarioustypesofformworks.
• SkillDeveloped/LearningoutcomeofthisMicro-Project;-
• Learningskill
• Workingina Team.
• Preparationofreport.
9.0 ApplicationsofthisMicro-Project:-
It is used as a mould for a structure in which fresh concrete is poured
onlytohardensubsequently.
**************
Micro Project Evaluations Sheet
Name of Student :-Vishal. Ratan Shende ENROLLMENT
NO:- 1815970011
1. Relevancetothe
course
2. LiteratureReview/
information collection
3. Completionofthe
targetasperproject
proposal
4. AnalysisofDataand
representation
5. Qualityofprototype/
Model
6. ReportPreparation
(B) Individual presentation/Viva(Coverts overtaken armour of4marks)
7. Presentation
8. Viva
(A) (B)
Process and product Individual Presentation/ Total marks 10th