Specification of The Project: 1.earth Work 1.1site Clearance
Specification of The Project: 1.earth Work 1.1site Clearance
1.Earth work
1.1Site clearance
Removal of bushes & vegetation
Removal of bushes & vegetation
Excavation & Get out Removal of top soil
Excavation in ordinary soil
1.5 Fill
Fill to excavations or to make up level shall be made in suitable material approved by the Engineer and
capable of being compacted. Fill shall be placed in successive stages of not exceeding 20cm and watered
and compacted to approval by the Engineer. Fill shall be measured as equal to the net volume of void to
be filled and shall be understood as including the stockpiling and haulage of material from location of fill.
Classification of fill
Backfill to excavation
Selected excavated fill
Selected borrowed fill
2.Concrete work
Footing
Grade beam
Ground slab
For all of the above use similar description
Grade of concrete C-25
Mix ratio 1:2:3
68
2.1 Lean concrete
Grade C-5
thickness 5cm
3 Stone work
3.1Foundatio wall
B superstructure
1 Concrete work
Column
Floor beam
Tie beam
Floor slab
Roof slab
2.Masonary work
Above grade wall shall mean masonry above ground floor.
Buried wall shall mean masonry in contact with earth on both faces.
Tapering wall shall mean wall built at specified inclination from the vertical.
2.1Brick masonry
Bricks shall be selected for their consistency in dimensions, shapes, angles and strength.
69
2.2 Stone masonry
Stone wall concealed from view or to be left for further finish shall be built in stone sizes of not less than
300mm high per course and 400mm wide per stone.
3. ROOF WORK
Type of roofing
Brand
Gauge or thickness
Supply and construct G-28 well galvanized corrugation sheet of iron of Akaki brand.
4.Floor Finish
Types of floor finishing material
PVC
Ceramics
Size of material
Grade of mortar 1:4
5.Plastering
Thickness of plaster 25mm
Numbers of coats
Grade of mortar 1:3
Location of plaster
Applying three coats of cement mortar plastering in 1:3 ratio internal wall and ceiling.
6.Ceiling
7.Skirting
Terrazzo tile skirting
70
8.Form work
Formwork shall mean temporary support construction for in-situ concrete, designed and
constructed in timber or metal and capable of withstanding the live and dead loads imposed on
it and fully preventing leakage of concrete.
9. Glazing
Glazing beads shall be temporarily fixed to doors, windows and curtain walls. Glass must be clear.
71
CONCLUSION
The project is to analyze the given drawing, prepare take of sheet, bill of quantity and in addition, we
have improved our understanding during the analysis. We have done take off sheet for every
component of the G+2 residential building project. That means take off sheet for concrete works for sub
structure and supper structure, take off sheet for reinforcement bars, masonry works, hard core, site
clearance and earth works.
After we have finished take off preparation, we have computed unit rate analysis for each component of
the building. Finally, we computed their bill of quantity and obtain the total cost the project.
During the analysis, problems we have faced are: in some parts of drawing dimension are not given
clearly, the given dimensions contradict each other in some parts section and elevation drawing.
72
REFFERENCES
BaTCODA
HANDOUT OF QUANTITY SURVEY AND SPECIFICATION
73