Pwps Service Bulletin 96B03 Attachment A-2: Recommended Periodic Maintenance Schedule For Ft8 Units
Pwps Service Bulletin 96B03 Attachment A-2: Recommended Periodic Maintenance Schedule For Ft8 Units
On the bleed muscle air system, pull the two each check
Gas Generator / valves P/N 1081669 & 1081670 (4 total) to check for free
M-GT-04 Annually Annually With Unit Shutdown No 1.50 3.00
Power Turbine operatiion and signs of corrosion. Replace as required.
Change out inlet filter pre-filter elements. Filters should be changed based
As required based on
M-I-02 Inlet Annually With Unit Shutdown Yes 4.00 8.00 on differential pressure and
Diff P
overall condition.
Change out inlet filter secondary filter elements. Filters should be changed based
As required based on
M-I-03 Inlet Bi-annually With Unit Shutdown Yes 6.00 12.00 on differential pressure and
Diff P
overall condition.
Check the inlet plenum ductwork for leakage, water
M-I-04 Inlet buildup or dirt/scale. Clean as required (cleaning is not Semi-Annually Annually With Unit Shutdown No 0.30 0.60
in time estimate).
Inspect inlet fogging system. Pull last chance screens
M-IF-01 Inlet Fogging System from a couple of fogging nozzles to look for blockage. Annually Annually With Unit Shutdown No 1.00 2.00 Only apply time if unit has this
option.
Perform inspection, cleaning and operation check (chip
detector will alarm on control when detector gap is
M-L-01 Lube Oil System bridged by a piece of metal) on three Chip Detectors Bi-monthly Annually With Unit Shutdown Yes 1.00 2.00
(XS601, XS602 & XS603). Reference vendor's manuals.