Professional Documents
Culture Documents
CPM (Critical Path Method) : Activity Immediate Predecessor Duration in Weeks
CPM (Critical Path Method) : Activity Immediate Predecessor Duration in Weeks
CPM (Critical Path Method) : Activity Immediate Predecessor Duration in Weeks
A - 2
Doing effectively and efficiently B - 5
Less wastage C - 4
Prepare use of resources
D B 5
Timely start of a project and
Timely competition of a project then two types:
E A 7
1) CPM F A 3
2) PERT G B 3
H C, D 6
I C, D 2
Project Management J E 5
K F, G, H 4
L F, G, H 3
Network Analysis
M I 12
It is a Technique use to breakdown a complex project’s data into the component parts [events, N J, K 8
activities, duration etc.] and plotting them to show their interdependencies and interrelationship.
1 2
Solution:
1st method like verbally can perform. Longest time duration will be called the critical path. Early event Time
3 4
Late event time
Immediate Duration in Total Free
Predecessor Weeks Floats Floats
Activity Nodes
A 1–2 - 2
B 1–3 - 5
C 1–4 - 4
D 3–4 B 5
E 2–5 A 7
F 2–6 A 3
G 3–6 B 3
H 4–6 C, D 6
I 4–7 C, D 2
J 5–8 E 5
K 6–8 F, G, H 4
Estimation of Critical Path L 6–9 F, G, H 3
M 7–9 I 12
1 – 3 – 4 – 6 – 8 – 9 is the critical path
N 8–9 J, K 8
B – D – H – K – N are critical activities
5 6
Question # 02:
A company manufacturing plant and equipment for chemical processing is in the process of
quoting tender called by public sector undertaking. Help the manager to find the project
completion time to participate in the tender.
Required:
Solution:
7 8
Question # 03: Solution:
A small project has 7 activities and the time in days for each activity is given below:
9 10