Professional Documents
Culture Documents
July Capital Projects 2021
July Capital Projects 2021
July Capital Projects 2021
DBE Participation
Contract Current DBE % of DBE # of DBE Vendors
Construction Participation Value Participation
Contract Value
$ 10,256,000 $ 4,096,695 39% 14
Budget/Cost Information
Current Project Budget Projected Costs Projected Over/Under
$ 13,825,000 $ 12,200,000 ($ 1,625,000)
Schedule Status
Task Planned Adjusted Actual
Design July 2020 --- ---
Procurement October 2020 --- ---
Construction Complete November 2021 December 2021 ---
Move-in December 2021 --- ---
2
Project Status
• Contract executed with General Contractor
• Pre-Construction meeting scheduled
• Anticipate an August Notice to Proceed
3
Project Status
• Finalizing contract with General Contractor
4
Project Status
• Rough-in of MEP systems on 2nd & 3rd floors are underway.
• Existing exterior brick being removed for new windows.
• The first-floor under containment for abatement.
• Auditorium structure removed. Concrete removal underway.
DBE Participation
Contract Value Current DBE % of DBE # of DBE Vendors
Participation Value Participation
$ 26,973,500 $9,395,050 35% Goal 22 Estimated
Budget/Cost Information
Current Budget Projected Costs Projected Over/Under
$ 25,000,000 $ 27,009,000 ($ 2,009,000)
Schedule Status
Task Planned Adjusted Actual
Design Aug 2020 ------- Aug 2020
Procurement Jan-20 to Sep-20 Oct 2020 Oct 2020
Construction Complete Aug 2022 Dec 2022 -------
Move-in Aug 2022 Dec 2022 -------
5
Project Status
6
Project Status
• New Construction:
• Installation of foundation piles complete.
• Forming and pouring of pile caps are underway.
DBE Participation
Contract Value Current DBE % of DBE # of DBE Vendors
Participation Value Participation
$ 31,397,539 $ 11,805,895 36.5% 44
Budget/Cost Information
Current Budget Projected Costs Projected Over/Under
$31,000,000 $31,397,539 ($397,539)
Schedule Status
Task Planned Adjusted Actual
Design July 2020 --- July 2020
Procurement August 2020 --- August 2020
Construction Complete August 2022 October 2022 ---
Move-in August 2022 December 2022 ---
7
• The NOLA PS 2019 Facility Plan identified properties for “disposition” after a rigorous data and
community process. Below is an update on our progress for properties identified for disposition.
• Property Purchases:
• AP Tureaud Purchase Agreement - Presented to the board for approval.
• School First Right of Refusal;
• McDonogh 15 – One school submitted a Letter of Intent; a Purchase Agreement will be presented to
the board in August.
• Valena C. Jones – One school submitted a Letter of Intent; staff are currently verifying financials.
• 4422 General Meyer – No school exercised rights for this facility, exploring multiple options for sale.
• RFP for Real Estate Services: Intent to Award at the July Board meeting.
• Once approved and contract finazlied the District will be able to move forward with sale process for
4422 General Meyer.
12