Punch No. Scope of Contractor Permit Description of Punch Status
Punch No. Scope of Contractor Permit Description of Punch Status
FINAL LAYER PROPER BACKFILLING AND COMPACTION HAS TO BE DONE AND TO BE TESTED. (CIVIL -
4452 SPML : backfilling (SKD), QC General SEA WATER INTAKE - Partial -7) In progress
BACKFILLING HAS TO BE DONE IN M10, M10A, M06A & M06 PEDESTALS NEAR TO MH TYPE 6B-030B
4453 SPML : backfilling (SKD), QC N/A AND TO BE TESTED (CIVIL - SEA WATER INTAKE - Partial -7) Ready for submission
BACK FILLING HAS TO BE DONE AND RFI HAS TO BE ATTACHED. (CIVIL - POST TREATMENT GENERAL -
6225 SPML : backfilling (SKD), QC N/A Partial -25) Ready for submission
PAINT TOUCHUPS HAS TO BE DONE ON THE CHEMICAL SODIUM HYPOCHLORITE UNLOADING AREA
6275 SPML : Painting (AL MAKEENA) Nomac (CIVIL - POST TREATMENT CHEMICAL GENERAL - PARTIAL 27) In progress
PAINT TOUCHUP HAS TO BE DONE ON THE DAMAGED AREAS (CIVIL - DAF GENERAL STREAM 1 -
6705 SPML : Painting (AL MAKEENA) Nomac PARTIAL-8) In progress
BACKFILLING NEAR TO M01 AT GRID 15 HAS TO BE COMPLETED (CIVIL - DMPF GENERAL STREAM 1 -
6826 SPML : backfilling (SKD) Nomac PARTIAL-13) In progress
BACFILLING REPORTS FOR RO CIP, IBC SULPHURIC ACID & RO INLET HAS TO BE ATTACHED (CIVIL - RO
7390 SPML : backfilling (SKD) N/A CIP NEUTRA CHEMICAL GENERAL - PARTIAL-24) Ready for submission
WALL REPAIRS AND TOUCHUP HAS TO BE DONE- BATTERY ROOM (CIVIL - ELECTRICAL BUILDING -
8189 SPML : Painting (AL MAKEENA) Nomac PARTIAL - 40) In progress
FINAL COAT PAINT ON THE WESTSIDE WALL HAS TO BE DONE -LV SWITCHGEAR ROOM STREAM 1
8217 SPML : Painting (AL MAKEENA) (CIVIL - ELECTRICAL BUILDING - PARTIAL - 40) Can't attend
8355 SPML (AL MOAYYED) N/A MASKER KEY HAS TO BE CHECKED IN ALL THE DOORS (CIVIL - ELECTRICAL BUILDING - PARTIAL - 40) Sidem under review
8499 SPML : (KRONOS) EARTHING CABLE SHOULD BE BURIED 600 TO 700 MM BELLOW THE FINAL LEVEL Can't attend
8508 SPML : (KRONOS) N/A OUTDOOR STREET LIGHTING SYSTEM IS NOT COMPLETED FOR STREAM #1 SCOPE Sidem under review
FALSE CEILING HAS TO BE COMPLETED & CORNER GAP TO BE FILLED. (CIVIL - LABORATORY
8558 SPML (ALLIED GULF) N/A BUILDING - PARTIAL - 2) Letter issued
8567 SPML : Painting (AL MAKEENA) N/A EXTERNAL PAINT TOUCHUPS HAS TO BE DONE (CIVIL - LABORATORY BUILDING - PARTIAL - 2) Sidem under review
WALKWAY WORKS HAS TO BE COMPLETED & RFI HAS TO BE ATTACHED. (CIVIL - LABORATORY
8569 SPML : QC Action N/A BUILDING - PARTIAL - 2) Sidem under review
8619 SPML : backfilling (SKD) N/A BACKFILLING HAS TO BE DONE IN ALL CHEMICAL TRENCHES. (CIVIL - UG SLUDGE LINE - PARTIAL - 42) Ready for submission
PAINT TOUCHUPS BELOW THE TRAY SUPPORTS HAS TO BE DONE AT POST TREATMENT AREA
8636 SPML : Painting (AL MAKEENA) Nomac CHEMICAL TRENCH. (CIVIL - UG SLUDGE LINE - PARTIAL - 42) In progress
8676 SPML : (KRONOS) N/A LIGHTING AND LIGHTING PROTECTION NEED TO BE COMPLETED Sidem under review
FLOOR PAINT RECTIFICATIONS HAS TO BE DONE ON THE DAMAGED AREA (CIVIL - RO GENERAL
8743 SPML : Painting (AL MAKEENA) STREAM 1 - PARTIAL - 20) Can't attend
8795 SPML : Painting (AL MAKEENA) PAINTING JOINT MISMATING HAS TO BE CORRECTED (CIVIL - RO GENERAL STREAM 1 - PARTIAL - 20) Can't attend
8798 SPML : QC Action N/A FFL SURVEY RECORD HAS TO BE SUBMITTED (CIVIL - RO GENERAL STREAM 1 - PARTIAL - 20) In progress
BACKFILLING HAS TO BE DONE ON ALL ELECTRICAL MANHOLES AND TRENCHES (CIVIL - CABLE DUCT
8814 SPML : backfilling (SKD) N/A MANHOLES & UG ELECTRICAL DUCT - PARTIAL - 43) Ready for submission
8937 SPML (ALLIED GULF) N/A SMALL GAP BETWEEN WALL AND ROOF NEED TO FILLED In progress
PRECAST FOR INSTALLATION RFI HAS TO BE ATTACHED (SOME FOUNDATION FOUND WITH LEVEL
10209 SPML : QC Action N/A DIFFERENCE ) (PARTIAL-4 LIGHTING (STREET LIGHT + GENERAL AREAS)) Sidem under review
10283 SPML : Painting (AL MAKEENA) Commisioning PAINT TOUCHUP HAS TO BE DONE ON ALL DAMAGED AREAS.(PARTIAL-9,DAF GENERAL STREAM 2) Sidem under review
10317 SPML : QC Action N/A GROUTING TEST REPORTS HAS TO BE ATTACHED (PARTIAL-14, DMPF GENERAL STREAM 2) Sidem under review
10339 SPML : QC Action N/A SLOPE HAS TO BE CHECKED ON THE GUTTER.(PARTIAL-23, RO FLUSHING CIP NEUTRA STREAM 2) Ready for submission
10406 SPML : QC Action N/A DOCUMENT PUNCHES HAS TO BE ADDED. ( PARTIAL-41, DRAINAGE SYSTEMS ) Sidem under review
11728 SPML : QC Action N/A DOCUMENT PUNCHES HAS TO BE ADDED. ( PARTIAL-6, ROAD WORKS & LANDSCAPING ) Sidem under review
11769 SPML : Painting (AL MAKEENA) Nomac CRACKS IN THE GRADE SLAB/PAVEMENT TO BE REPAIRD (RO BLDG. ) In progress
11784 SPML : Painting (AL MAKEENA) Nomac CRACK IN THE GRADE SLAB TO BE RECTIFIED (NEAR SKID 5 WEST SIDE) (RO BLDG. INSIDE ) In progress
11865 SPML (ALLIED GULF) Nomac FENCE TOWER BOLTS ARE NOT FUNCTIONING (ELECT. BLDG. ) In progress
ACCESS AROUND THE ANALYSER (GRADING & LEVELLING TO BE COMPLETED) (METEREING STATION
11902 SPML : backfilling (SKD) General ) In progress
12130 SPML : (KRONOS) N/A LIGHTNING PROTECTION SYSTEM ECC PACKAGE -NOT YET SUBMITTED (ECOD ) Sidem under review
12228 SPML : QC Action N/A DOCUMENT PUNCH TO BE ADDED (CIVIL - GENERAL AREA - PARTIAL - 1) Sidem under review
12229 SPML : QC Action N/A AS BUILT DRAWING NEED TO BE SUBMITTED (CIVIL - GENERAL AREA - PARTIAL - 1) Ready for submission
12270 SPML : QC Action N/A DOCUMENT PUNCHES HAS TO BE ADDED (CIVIL - R&I 1.0 - PARTIAL -44) Sidem under review