Download as pdf or txt
Download as pdf or txt
You are on page 1of 113

Training Material on Construction Contract Management

Training Material On

Construction Contract Management

Organized & delivered


By

Zewdu Tefera Worke

Engineering Contracts Lawyer


December, 2018

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 1
Training Material on Construction Contract Management

Training Material On

Construction Contract Management

………………………………………………………………………………………

Table of Contents
 Introduction & Objectives
 Conceptual Background
 Construction: Concept & Scope
 Contract: Concept & Categories
 Contract & Construction Contract: Formation
 Contract & Construction Contract: Effects
 Standard Conditions of Construction Contract
 Construction Contract Management
 Parties & their Legal Status
 Scope of their Deal
 Contract Documents
 Obligations of the Contractor
 Obligations of the Employer
 Risk Sharing Obligations
 Security Management

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 2
Training Material on Construction Contract Management

Training Program On

Construction Contract Management

Trainer: Zewdu Tefera Worke


……………………………………………………………………………………………………………

Item Description Time Implemented by


(Day 1) Tuesday, December 11/18, 2018
Morning
Training Overview 9:00-9: 30am The Trainer
Construction: Concept & Categories 9:30-10: 30am The Trainer
Tea Break 10:30-11: 00 am
Contract: Concept & Categories 11:00-11:30am
Contract & Construction Contract: 11:30-12: 30 pm The Trainer
Formation
Afternoon
Contract & Construction Contract: 2:00-3;30pm The Trainer
Formation
Tea Break 3:30-4: 00pm
Contract & Construction Contract: 3:45-5:00 pm The Trainer
Formation
(Day 2) Wednesday, December 12/19, 2018
Morning
Standard Conditions of Construction 9:00-10:30am The Trainer
Contract:
Tea Break 10:30-11:00am
Contract & Construction Contract: 11:00-12:30 pm The Trainer
Effects
Afternoon
Construction Contract Management: 2:00-3:30 pm The Trainer
Background
Tea Break 3:30-4:00 pm
Construction Contract Management: 4:00-5:00 pm The Trainer
Contractor’s Obligations
(Day 3) Thursday, December 13/20, 2018
Morning
Construction Contract Management: 9:00-10:30 am The Trainer
Contractor’s Obligations
Tea Break 10:30-11:00am
Construction Contract Management: 11:00-12:30 pm The Trainer
Contractor’s Obligations
Afternoon
Construction Contract Management: 2:00-3:30 pm The Trainer
Employer’s Obligations
Tea Break 3:30-4:00 pm
Construction Contract Management: 4:00-5:00 pm The Trainer
Employer’s Obligations
(Day 4) Friday, December 14/21, 2018
Morning
Construction Contract Management: 9:00-10:30 am The Trainer
Employer’s Obligations
Tea Break 10;30-11:00am

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 3
Training Material on Construction Contract Management

Construction Contract Management: 11:00-12:30 pm The Trainer


Employer’s Obligations
Afternoon
Construction Contract Management: 2:00-3:30 pm The Trainer
Risk Management
Tea Break 3:30-4:00 pm
Construction Contract Management: 4:00-4:30pm The Trainer
Security Management
Reflections 4:30-5:00pm The Trainees & the Trainer

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 4
Training Material on Construction Contract Management

I. Introduction & Objectives

Introduction to the Training

The scope of the training shall encompass, based on design-bid-build delivery sub-system, the
following four interrelated areas: viz., construction & contract; contract & construction contract;
standard conditions of construction contract; and construction contract management;

As related to construction the concept & its scope shall be explored; As related to contract, the
concept & categories of same shall be addressed;

As related to contract & construction contract, the training shall cover the process how contract is
formed in general & construction contract in particular. The training shall also identify & address
the effects of contracts in general & the effects of construction contract in particular;

As related to standard conditions of construction contract, the training shall cover the need for &
the use of general standard conditions of contract for construction projects; the level of general
standard conditions of construction contract and the particular attention to be given in the process
of the preparation of a particular conditions of construction contract for a given construction
project;

As related to construction contract management, the training shall address the concept & scope of
construction contract management; identify the contracting parties to a given construction contract
& their legal status; the scope of their deal and where the scope of their deal recorded viz.,
identification of the construction contract documents. The contract documents so identified form
the foundation for construction contract management. Respective & common obligations (viz., risk
management) of the contracting parties, viz., the employer & the contractor, shall also be identified
& discussed. Security management (based on security instruments originating from the financial
market) shall also be addressed.

Role of the Engineer in construction contract management process shall also be addressed briefly.

Construction contract management process characterized by two key features: in using standard
conditions of construction contracts (as foundation for the said management) & in engaging the
Engineer (the consultant) (in terms of its management process).

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 5
Training Material on Construction Contract Management

Objectives of the Training

At the end of the training, the trainees be able:

 to define the concept of construction & identify its scope;


 to define the concept of contract & identify its categories;
 to define & understand the concept, elements & effects of contracts in general;
 to define & understand the formation & effects of construction contract;
 to identify & understand the need, level, structure & content of general standard &
particular conditions of construction contract;
 to define & understand the concept, scope & process of construction contract management;
and to identify the critical contractual stakeholders therein (viz., the employer & the
contractor) including their status, scope of their deal & their respective & common
obligations;
 to understand the indispensable role of the Engineer in the construction contract
management process;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 6
Training Material on Construction Contract Management

Construction Contract & Law: Overview

………………………………………………………………………………………

The Formula
………………………………………………………………………………………………………………

D
KP and/or LP: ROLE
V…?
(Developed by: Zewdu Tefera Worke, Engineering Contracts Lawyer)

………………………………………………………………………………………………………

The Legend
L: Law

K: Contract

P: Persons

and/or: cumulative with/alternatively (K and/or L)

D: Delivery

R: Relationship

O: Obligation

L: Liability

E: Enforcement

V: Variability (context) of all the above concepts (viz., LKPDROLE);

…………………………………………………………………………………………………………………………………………………………………

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 7
Training Material on Construction Contract Management

The Application

LV: Law…?

KV: Contract…?

PV: Persons…?

DV: Delivery…?

RV: Relationship…?

OV: Obligation…?

LV: Liability…?

EV: Enforcement…?

V: Variability (context) of all the above concepts….?;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 8
Training Material on Construction Contract Management

II. Construction: Concept & Scope


 Concept

 In the fields of architecture & civil engineering, construction is a process that


consists of the building or assembling of infrastructure.
 Construction is undertaken to create a physical infrastructure through a
construction process;
 In the Ethiopian legal system, definition is given to works and also for
construction itself;
 According to Article 2 (3) of Proclamation No. 649/2009 i.e. the Ethiopian
Federal Government Procurement & Property Administration
Proclamation, works is defined as follows.
 Works mean all work associated with the construction, reconstruction,
upgrading, demolition, repair or renovation of a building, road, or structure,
as well as services incidental to works, if the value of those services does not
exceed that of the works themselves…;
 According to Article 2 (9) of the Ethiopian Building Proclamation (Proc. No.
624/2009) construction, from building perspective, has been defined, as
follows: construction means the construction of a new building or the
modification of an existing building or alteration of its use.
 According to Article 2 (5) of the Construction Industry Registration draft
Proclamation, construction has been defined as follows: Construction means
a provisions of a combination of goods & services carried out under or over
ground for the development, extension or installation or repair,
maintenance, renewal, renovation, alteration, excavation, dismantling or
demolition of a fixed asset including building & engineering infrastructure;
 According to Art. 3244 of the Civil Code: work from public works
perspective has been defined as follows: A contract of public works is a
contract whereby a person, the contractor, binds himself in favour of an
administrative authority to construct, maintain or repair a public work in
consideration of a price.

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 9
Training Material on Construction Contract Management

 Such works could be building or (civil) engineering work;


 Categories
 Two categories of construction projects could be identified: viz.,
 construction projects related to physical facility development; and
 construction projects related to process facility development;
 Core Difference:
 Physical facility construction projects, if completed, are service-oriented;
and
 Process facility construction projects, if completed, are product-oriented;
 Type of Projects: twofold
 physical facility: Physical facility construction projects may include:
infrastructures (works and/or structures) related to building, dam & road;
 process facility; Process facility construction projects may include: works
related to industrial (manufacturing) plant; power generation plant; water
treatment plant; waste water treatment plant;
 Implications:
 The categorization of construction projects in to physical facility & process
facility may result, at least, the following implications:
 project scope: to have standalone physical facility development construction
project; or to have integrated physical facility development construction
project with a defined process plant development project;
 conditions of contract: the choice as to the applicable standard conditions
of construction contract is different if the construction project were:
 standalone: merely for standalone (building or engineering) or
 integrated; both for integrated (building and/or engineering with
process facility) construction project:
 professionals configuration: the configuration of the required professions
& therewith professionals within the construction project structure is

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 10
Training Material on Construction Contract Management

different; relatively limited/less in the standalone & more intense/more in the


integrated (with process facility) type of construction project;
 management complexity: the level of construction project management
complexity of the said construction projects is different: it is relatively less
complex in the standalone and more complex in the integrated type of
construction project;
 The training shall thus focuses merely on the standalone physical facility
development type of construction project related to building or engineering
type;
III. Contract & Construction Contract
 Contract: Definition

 According to Article 1675 of the Civil Code: A contract is an agreement


whereby two or more persons as between themselves create, vary or
extinguish obligations of a proprietary nature.
 All contracts are agreements but not all agreements are contracts;
 Concept
 That the contract is an agreement;
 The agreement is to be made between two or more persons (like the employer
& the contractor);
 That the agreement is binding between such two or more persons; this
concept is related to the doctrine of privity of contract; persons outside of
such contractual relationship are called third parties and are not party to
such contract; like the Engineer under the construction contract; like the
sub-contractor under the main construction contract;
 The agreement is to create, vary & extinguish (terminate) obligations;
 The agreement is to create obligations; obligations on the employer &
obligations on the contractor;
 That the nature of obligations is proprietary (financial/economic); like
construction;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 11
Training Material on Construction Contract Management

 The construction contract clearly fulfils all the elements given to the
definition of contract;
 Categories; Application
 Categories of contract are of threefold: viz., works contract; services
contract; and contract related to supply of goods;
 The principle of the general law of obligations (originating like from contract
under Book IV: Art. 1675-2026) shall also apply to special type of contracts
(see Book V of the Civil Code: Art. 2266-3346) like the construction contract;
 see Article 1676 cum 3131-3206 cum 3244-3296 (Public Works Contract);
for public construction contract like water or road or building construction
projects; and
 see 1676 cum 2610-2631 (Contract of Work & labour); 3019-3040 (for
Building projects) cum 2610-2631 of the Civil Code; for private construction
contracts;
 Contract & Construction Contract: Formation
 Background
 The formation of any type of contract including construction contract shall
consider the following four ingredients or legal elements: viz.,
 capacity: capacity of contracting parties;
 consent: consent of contracting parties;
 object: object of the contract; and
 form: form of contract, if any;
 Determination of the capacity of contracting parties is not the subject to be
dealt with under the law of obligations or contract; it is the subject to be
treated by other applicable laws (public law & private law regimes);
 Capacity, consent & object are always cumulative for any type of contract;
whereas, form is only required where the law specifically prescribes or
requires;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 12
Training Material on Construction Contract Management

 Capacity:
 see the Civil Code Article 1678 (a) cum all possible relevant laws; like
 Art. 394 of the Civil Code cum Proc. No. 1097/2018; the State is a person
including its organs (viz., legislative; executive; and judiciary);
 Proc. No. 25/1992 cum the specific regulative legal instrument; as related to
federal public enterprises;
 Proc. No. 686/2010 cum Proc. No. 1097/2018 (Ministry of Trade &
Industry); cum the Law of Agency Art. 2179-2265 of the Civil Code; the
Law for Authentication & Registration of Documents see Proc. No.
922/2015;
 The legal concept of capacity presupposes the existence of persons;
 Categories: Persons are of two types:
 natural persons: viz., human beings;
 legal persons: are of three types again:
 public institutions; like ministries; bureaus; public enterprises;
 corporate entities like share companies or private limited companies;
public enterprise shall also be considered as corporate entities;
 voluntary organizations like non-governmental organizations
(NGOs); associations; and so forth
 The relevant persons to a construction contract are: employer &
contractor;
 Natural persons (i.e., human beings) acquire their existence by birth;
 Whereas, legal persons acquire their legal existence or personality by
different legal instruments depending on whether they are public institutions
or private entities or voluntary organizations;
 Public institutions acquire their legal existence or personality by legislation
or by regulation;
 legislative instruments: see Proc. No. 1097/2018 for Ministries cum
Article 394 ff of the Civil Code;
 regulative legal instruments: like for public enterprises or public
share companies or public universities;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 13
Training Material on Construction Contract Management

 Private entities (to become contractors) (like private limited companies or


share companies) acquire their legal existence or personality by registration;
see Proc. No. 686/2010 cum 1097/2018;
 The legal capacity of public institutions (to serve as employers emanates
from their formative legal instrument;
 The legal capacity of private entities (to serve as contractors) emanates not
from the registration itself but from their formative & operative document,
which is contractual in nature, and which provides the required legal
capacity & empowerment (for example to the general manager of such
company) to act in the name & on behalf of the company; like to negotiate &
to enter in to contract; like water or road or building construction contract;
 Thus legal capacity emanates from two sources: from the law & from the
contract;
 Agents acquire their derivative legal capacity from contract; this lead us to
the concept of the law of agency; see Article 2179-2265 of the Civil Code cum
Proc. No. 922/2015;
 Implications
 Having the required legal capacity results to enter in to legal transactions
and as related to construction it may have the following implications, as well;
 bid purchase: to purchase & participate in the construction project bid;
 bid submission: to sign on the tender document (i.e., the bid);
 negotiation: to negotiate on the planned (draft) construction contract, if the
bidder found to be successful in the tender evaluation process;
 contract signing: to sign the final construction contract documents with the
employer;
 contract performance: to perform the construction contract by the contractor
or on behalf of the contractor;
 instruction: to receive instruction from the Engineer;
 payment: to receive payment from the employer;
 suspension: to take suspension of the works measure by the contractor;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 14
Training Material on Construction Contract Management

 notice: to receive notice of termination from the employer & to give notice of
termination to the employer;
 claims submission; to submit construction claims to the Engineer on behalf of
the contractor;
 dispute initiation; to initiate a dispute resolution proceeding in the name & on
behalf of the employer or the contractor;
 representation; to represent the contractor in the disputes forums (like
arbitration, litigation…) & in their respective proceedings;
 enforcement: to demand the enforcement of the benefit of court judgment or
arbitral award through enforcement proceeding;
 appeal: to initiate an appeal proceeding at the court of law, if an award not
final & binding;
 set aside; to initiate an award set aside proceeding at the court of law;
 Consent:
 Consent concerns exchange of the planned deal between the future
contracting parties: viz., in terms of offer & acceptance;
 Exchange of offer & acceptance is regulated by the following possible laws:
the law of contract; the law of procurement (in case of public contract);
and/or the applicable international legal instrument (agreement: bilateral or
multilateral);
 see the Civil Code Article 1678 (a) cum 1679 -1710 cum 3134-3146 cum Proc.
No. 649/2009 cum the Federal Procurement Directive (2002 E.C);
 Consent is a freely declared will of the contracting persons (parties) & it
shows an intention to be bound by such will so declared;
 Consent is divided in to two: viz., offer & acceptance;
 Consent is the very foundation for contractual/consensual (or promissory)
relationship;
 The exchange of offer & acceptance, as related to construction contract, is
governed by the procurement procedure to be followed (as per the law of
procurement) and as per the law of contract;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 15
Training Material on Construction Contract Management

 The process of exchange of offer & acceptance may resemble as follows:


 invitation for bids: the employer issues publicly (as a matter of
transparency requirement) invitation for bids;
 bid purchase: eligible & interested bidders (future contractors)
purchase the bid document;
 bid submission: bidders, based on the instruction to bidders,
prepare their bid & submit same to the employer;
 bid opening: the employer receives & officially opens the bids
submitted & so received
 bid evaluation: the employer evaluates the bids so received;
 award: the employer awards the contract to the winner (who
becomes the future contractor under the construction contract, if
completed);
 acceptance: based on its award decision, the employer writes to the
successful bidder a letter of acceptance;

 pre-contract negotiation: following such letter of acceptance, (pre-


contract) negotiation may be undertaken between the employer & the
future contractor;
 contract signing: following successful pre-contract negotiation, all
construction contract documents have to be signed between and by
the employer & the selected contractor;
 contract approval: sometimes an approval from some defined
regulatory and/or financing institution may be required for the signed
contract to be effective; see Article 3134 cum 3143-3145 of the Civil
Code;
 see also Clause 8.1 cum 16.2 (i) of the MDB-FIDIC (2006) which gives
a contractual right to the contractor to terminate the contract if the
conditions for the effectiveness of the contract were not fulfilled up to
180 days;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 16
Training Material on Construction Contract Management

 offer; The bid submitted by the bidder contractor constitutes an offer,


whereas the decision of the award together with the letter of acceptance
constitutes an acceptance;
 acceptance; The letter of acceptance may not by itself constitutes a contract
specially as related to public construction contracts;
 Object:
 object of contract creates a nexus/bridge between the law & construction;
 see the Civil Code Article 1678 (b) cum 1711-1718 cum the signed
construction contract;
 Object of contract basically gives us the respective obligations of the
contracting parties under a given contract;
 From the construction industry perspective, the doctrine of object of contract
has to be seen from the following three critical considerations; namely.,
 subject matter: from the specific type of construction project
perspective building and/or engineering;
 purpose of the project; the purpose of the specific subject matter
project so selected under building and/or engineering; and
 delivery system: from the concept of delivery system perspective
(viz., the selected delivery sub-system);
 subject matter of the contract:
 by object of contract it means the definition of the subject matter of the
contract under consideration;
 as related to construction contract is it related to: building
construction? or engineering (like water project related)
construction? building and/or engineering construction integrated
with industrial/process plant (like dam construction with water
treatment plant) construction?
 purpose of the project;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 17
Training Material on Construction Contract Management

 by purpose of the project it means the specifically selected


construction project type from the given subject matter: like building
and/or engineering project;
 from engineering related projects like water related projects: dam
construction or water transmission line construction or water
distribution network construction and so forth;
 each specific water related project has its own purpose: therefore,
each specific type of construction project differs in terms of its design
content & the construction process from one another;
 this determines the specific foundation for the respective obligations
of the contracting parties;
 delivery sub-system:
 the specific delivery sub-system so selected determines at least the
following three issues: scope of obligation; scope of risk allocation;
and liability dimension;
 scope of obligation: the specific project delivery sub-system so
selected for the project (subject matter then purpose) under
consideration shall determine the scope of the respective obligations of
the contracting parties; (viz., as related to design, construction,
operation and/or payment);
 risk allocation: the delivery sub-system so selected also determines
the risk allocation scheme of the contract under consideration
towards the contracting parties; (viz., as related to design,
construction, operation and/or payment);
 liability dimension: the delivery sub-system so selected shall also
determine the dimension of liability followed under the contract
towards the contracting parties; (design liability, operation liability
and/or construction liability;)
 respective obligations:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 18
Training Material on Construction Contract Management

 the subject matter so selected; the specific purpose from such subject
matter so selected; and the delivery sub-system so decided; provide
the basis for the allocation of the respective obligations of the
contracting parties under a given construction contract;
 Object of contract, in terms of its respective obligation perspective, as
related to building and/or engineering construction, and based on design-bid-
build delivery sub-system, for example, has two dimensions: promise &
consideration;
 promise dimension: the contractor promises to execute & complete and
remedy defects in the construction works (like the water related
project); and
 consideration dimension: the employer undertakes to pay the contract
price to the contractor;
 promise dimension; the employer promises also to appoint the
Engineer & notify the contractor; to handover the construction site
possession & access thereto to the contractor; to deliver the
design/drawing to the contractor; to take over the works, if
completed from the contractor; and so forth
 Object of contract has to be sufficiently defined, possible & legal;
 Therefore, object of contract has three requirements from the law of contract
perspective: viz.,
 sufficiency requirement;
 legality/morality requirement; and
 possibility requirement;
 The sufficient definition of the respective obligations of the employer & of the
contractor shall thus be done through all possible construction contract
documents under consideration;
 It thus includes but not limited to the following contract documents:
 the Letter of Acceptance;
 the Bid (submitted by the contractor initially as a bidder);
 the Special Conditions of Contract;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 19
Training Material on Construction Contract Management

 the General Standard Conditions of Construction Contract;


 the Technical Specifications;
 the Drawing;
 the Bill of Quantities;
 These contract documents form the required contractual & legal foundation
for construction contract management;
 Form:
 form concerns about recording of the deal between the contracting parties;
 see the Civil Code Article 1678 (c) cum 1719-1730 cum other applicable
laws;
 The issue of form is related to whether or not a given contract is to be made
in writing or otherwise, namely, orally/verbally;
 Unless the law requires, a contract could be made in writing or verbally;
 As per Article 1724 of the Civil Code, the law specifically requires that
contract to be made with government (like in case of public works contract)
shall be made in writing; see 1678 (c) cum 1724;
 This is fundamentally important in case of public construction contract like
dam or road or building construction projects; see Article 3131-3206
(administrative contract) cum 3244-3296 (contract of public works);
 If the construction contract is to be made in writing as a matter of public
policy, there are two options to make;
 tailor-made: to prepare a detailed tailor-made construction contract;
or
 standard: to use a suitable standard conditions of construction
contract (i.e., based on the chosen delivery sub-system);
 The construction industry, in Ethiopia, uses standard conditions of
construction contract;
 see the discussion on standard conditions of construction contract as one of
the basic features of construction contract & its management;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 20
Training Material on Construction Contract Management

 All contract documents so made an integral part thereof have to be signed


by the employer and the contractor, witnessed by witnesses and respectively
sealed & delivered;
 Such signed construction contract documents become the foundation for
construction contract management;
IV. Standard Conditions of Construction Contract
 Purpose
 The whole purpose of standard conditions of construction contract is to
sufficiently define the respective contractual obligations of the contracting
parties to the construction contract viz., the employer & the contractor;
 see Article 1678 (b) of the Civil Code;
 Standard conditions of construction contracts are thus the means:
 obligations & rights: to define the content & structure of the
respective obligations & rights of the contracting parties to the
construction contract;
 liabilities & remedial rights: to define the respective liabilities &
remedial rights of the contracting parties under the construction
contract; and
 risk allocation: to identify & to allocate & distribute respective
risks to such contracting parties;
 Importance
 It is virtually unthinkable about the management of a modern construction
project and its contract without using standard conditions of construction
contract;
 The legitimate reasons could be of the following;
 Proven documents: standard conditions of construction contract
are tested through time & experience in the construction industry.
 Standard communication: standard conditions of construction
contract provide a common means of communication to the
stakeholders of the construction industry: to the employer; to the

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 21
Training Material on Construction Contract Management

contractor; to the Engineer; to the Sub-contractors; to the


regulators; to the financiers; to the construction dispute resolution
professionals (experienced in ADR or otherwise); to the insurance
companies; to the banks; and so forth.
 Norm: standard conditions of construction contract provide a useful
construction industry-wide norm as related to construction project
management processes & practices;
 Risk: standard conditions of construction contract provide also a
formidable ground for the identification, assessment & management
of construction related risks inherent in the construction process
especially by the contractor and also by the construction risk insurers.
 Efficiency: standard conditions of construction contract save time,
cost & energy comparing to preparing a tailor-made conditions of
construction contract for each & every construction project every
time;
 Framework: general standard conditions of construction contract
provide a framework or basis for the concretization of general
conditions of contract as related to:
o the actual project under consideration (viz., the subject matter
of the contract);
o based on the specific subject matter of the project provide &
regulate the purpose of such construction project;
o actual location of the project (rural vs. urban setting);
o actual contracting parties (structuring respective obligations);
through special conditions of contract (based on the delivery
sub-system so selected);
 Source
 The following three institutions are identified as sources for the development
of standard conditions of construction contract; viz.,
 governmental (regulatory) institution;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 22
Training Material on Construction Contract Management

 financial institution; and


 professional institution;
 governmental institution;
 like the current Public Procurement Property Administration Agency
(PPA for short);
 financial institutions;
 like the World Bank; the African Development Bank or the African
Development Fund;…like as related to MDB;
 professional institutions;
 like the FIDIC; the ICE (Institute of Civil Engineers in the UK…);
 In Ethiopia, there was/is a practice to use all types of standard conditions of
construction contract;
 Level
 Standard conditions of construction contract could be prepared at
international or local level;
 Therefore, in the construction industry, we may have the following standard
conditions of construction contract based on their level;
 international: international standard conditions of construction
contract; and
 local: local standard conditions of construction contract;
 In Ethiopia there was & there is a practice to use all such levels or types of
standard conditions of construction contract;
 International Standard Conditions of Construction Contract:
 Background
 Among the international standard conditions of construction contract, the
one prepared & issued by FIDIC is prominent in the international
construction industry including in Ethiopia;
 FIDIC is a French abbreviation which stands for: Federation Internationale
Des Ingenieurs-Conseils;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 23
Training Material on Construction Contract Management

 It is an international association of national consulting engineers


associations;
 FIDIC has been established in 1913 by five European countries in Europe; It
headquartered in Lausanne, Switzerland;
 Since 1957, FIDIC prepared & issued standard conditions of construction
contract & related publication as related to:
 civil engineering works;
 electro-mechanical engineering works; and
 consulting engineering services;
 Its relevant standard conditions of contract are identified simply by their
particular color; For example:
 Red Book: The Red Book being dedicated to Civil Engineering
Works;
 Yellow Book: Yellow Book being dedicated (historically) to Electro-
mechanical Engineering Works;
 White Book: White Book being dedicated to Consulting Engineering
Services since 1990;
 FIDIC Standard Conditions of Construction Contract
 FIDIC has prepared & issued the following editions of the Red Book;
 First Edition; 1957;
 Second Edition; 1969;
 Third Edition; 1977;
 Fourth Edition; 1987; Fourth Edition (a supplement) Summer 1992;
Fourth Edition (further amendment) November, 1996;
 New Red Book
 FIDIC has also prepared & issued in 1999 the New Red Book;
 These conditions of construction contract have no any resemblance in
structure & content with the former FIDIC editions (1957-1987);
 Based on the 1999 FIDIC New Red Book all relevant international
financial institutions have agreed to issue a common (harmonized)
standard conditions of construction contract in 2006;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 24
Training Material on Construction Contract Management

 It is called MDB-FIDIC standard conditions of construction contract


(also known as Pink Book);
 Its full & formal designation reads as follows; The Conditions of
Contract for Building and Engineering Works Designed by the
Employer: Multilateral Development Banks (MDB) Harmonized
Edition, March, 2006-FIDIC New Red Book;
 MDB-FIDIC has also its 2010 second edition or version;
 The focus of the training shall be on MDB-FIDIC (2006) standard conditions
of construction contract & the PPA 2011, as the case may be;
 Features
 MDB-FIDIC (2006) has the following basic features;
 works: it clearly shows to apply both for building & engineering
works;
 delivery system: it follows a design-bid-build project delivery sub-
system;
 payment system: it follows ad measurement (based on quantities)
payment system;
 Engineer: the role of the Engineer is clearly provided;
 dispute method: it contains settlement & judgmental (both dispute
board & arbitration) dispute resolution methods;
 DB Agreement; in case of dispute board, it contains a form of
agreement to be signed by the three parties: the employer; the
contractor & the members of the said dispute board;
 Structure & Content
 MDB-FIDIC contains the following twenty major clauses & sub-divided
further in to 147 sub-clauses;
 Clause 1: General Provisions
 Clause 2: The Employer
 Clause 3: The Engineer
 Clause 4: The Contractor
 Clause 5: Nominated Subcontractors

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 25
Training Material on Construction Contract Management

 Clause 6: Staff & Labor


 Clause 7: Plant, Materials & Workmanship
 Clause 8: Commencement, Delays & Suspension
 Clause 9: Tests on Completion
 Clause 10: Employer’s Taking Over
 Clause 11: Defects Liability
 Clause 12: Measurement and Evaluation
 Clause 13: Variations & Adjustments
 Clause 14: Contract Price & Payment
 Clause 15: Termination by Employer
 Clause 16: Suspension & Termination by Contractor
 Clause 17: Risk & Responsibility
 Clause 18: Insurance
 Clause 19: Force Majeure
 Clause 20: Claims, Disputes & Arbitration
 Local Standard Conditions of Construction Contract:
 Background
 The use of local standard conditions of contract in Ethiopia, up to recent
times, seems to be based on adaptation from international standard
conditions of construction contract notably that of FIIDC;
 This is evident from the following “local” standard conditions of construction
contracts; viz.,
 The 1959 MoUDH General Conditions of Construction Contract;
(developed or adopted & issued by Ministry of Urban Development &
Housing);
 The 1987 BaTCoDA Standard Conditions of Contract for
Construction of Civil Work Projects; (developed or adopted & issued
by Building and Transport Construction Authority);
 The 1994 MoWUD Conditions of Contract for Construction Works
(1994); developed or adopted by Ministry of Works and Urban
Development;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 26
Training Material on Construction Contract Management

 These standard conditions of contracts were based on the respective FIDIC


Red Book versions;
 The PPA Standard Conditions of Construction Contract
 It is for the first time in the history of the Ethiopian construction
industry that an attempt was made to develop & issue a local
standard conditions of construction contract including the full
standard bidding documents in 2006;
 This was done by such government institution known as PPA: the
Public Procurement Agency (as per its initial formative legislative
instrument i.e., Proc. No. 430/2005); and
 now formally known as PPPAA: Public Procurement & Property
Administration Agency (as per the new re-establishment legislative
instrument i.e., Proc. No. 649/2009);
 Features
 Delivery system: The PPA standard conditions of construction contract are
based on Design-Bid-Build project delivery sub-system;
 Payment system: The type of contract could be based on BOQ, in which case
it becomes measurement based; or based on Activities Schedule, in which
case it becomes lump sum;
 The payment system adopted in case of ad-measurement is obviously BOQ
based;
 the Engineer: The role of the engineer is clearly recognized;
 Nature of contract: The PPA standard conditions of construction contract are
expressly qualified as an administrative contract; See Article 3132 (a) of the
Civil Code, which provides for the legal regulation of public construction
contract; see Article 1675 cum Article 3131-3206 cum Article 3244-3296
(Contract of Public Works) like public water project construction;
 dispute method: The dispute resolution methods adopted were adjudication
and then arbitration; NB: the PPA 2011 has not provided such kind of
dispute resolution methods except for specific institutions which has a clear
legal power to settle construction disputes out of court;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 27
Training Material on Construction Contract Management

 Special Conditions of Construction Contract


 Background
 The general standard conditions of construction contract works in line with
the special conditions of construction contract;
 The purpose of the special conditions of construction contract thus being to
augment & concertize the operation of the general standard conditions of
construction contract as related to the actual contracting parties & the
specific project under consideration;
 The scope of concretization of the general conditions of construction contract
through the special conditions of contract may encompass the following
points but not limited to: issues like related;
 to the contracting parties;
 to the subject matter of the project;
 to the type thus purpose of the construction project;
 to the location of the project selected;
 to the payment & type of currency;
 to the applicable law;
 to dispute resolution system & method;
 to any terms of the contract said to be concretized through the special
conditions of contract as required by or stated under the general
conditions of construction contract & the contract policy of the
project owner (i.e., the future employer);
 This concretization is to be done during tender document preparation stage
but before issuing the tender documents (also known as tender dossier) to the
bidders;
 Process
 The concretization process of the general conditions of contract to the special
conditions of contract may take the following different forms; add; replace;
amend; delete; and not applicable;
 Addition:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 28
Training Material on Construction Contract Management

 Addition may come in to picture in to the following two ways: within


or without
 Addition within the existing clauses of the general conditions of
contract; or
 Addition without or beyond the existing clauses of the general
conditions of contract; the new clause number continues where the
general conditions of contract ends;
 The term to be used being: Add the following …
 Replacement
 This is done to do away with the effect of the existing clause within the
general conditions of contract (by deletion) and to replace it by a new
terms of contract;
 The term to be used being: Delete & Replace…
 Amendment
 This is done to modify the effects of the existing clause of the general
conditions of contract by the new one introduced through the special
conditions of contract;
 The term to be used being: Amend…
 Deletion
 Deletion may come in to picture in to the following two ways: to delete
& to replace or to delete it altogether;
 In case of “to delete & to replace” the effect of the existing clause in
the general conditions of contract has been deleted but replaced with
new terms (deal);
 In case of “only to delete” the effect of the existing clause of the
general conditions of contract has been altogether removed from the
terms of the contract and therewith the deal;
 The term to use: delete & replace; or delete the following clause;
 Not Applicable;
 This is done to do away with the effects of the general conditions of
contract in the terms of the contract

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 29
Training Material on Construction Contract Management

 It has a declaratory effect and does away the effects of the terms of the
general conditions of contract declared “not applicable” from the
subsequent deal between the future contracting parties ;
 The term to use being: Not applicable…
 In this regard, it is strongly advised to follow the relevant Guide prepared
by the respective owner institutions, local or international, of the general
standard conditions of construction contract;
 It requires also specific training;
 Skill & Caution
 contract drafting skill: Ensuring the compatible reading between the
general conditions of contract & the special conditions of contract requires
contract drafting skill;
 technical staff: The knowledge and/or information primarily being within
the hands/minds of the technical staff in charge of preparing the standard
bidding document including the special conditions of contract;
 construction lawyer: The first task could be done by the technical staff
(knowledgeable project engineers); the final draft special conditions of
contract has to be reviewed by a specialized lawyer, if any, for consistency
purpose with a view to importing the required:
 contract policy of the employer;
 financial interest of the financial institution; and/or
 regulatory requirements of the regulatory body;
to such special conditions of contract;
 cross reference: Ensuring consistency with respect to incorporating the
contract policy or financial interest or regulatory requirements of the
employer or financial institution or regulatory body, respectively, requires
undertaking careful clause by clause cross-reference between the general
conditions of contract & the special conditions of contract;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 30
Training Material on Construction Contract Management

 clarification (bidders): From the future contractor side (as bidder), if


there is any inconsistency in this regard, it may be a ground to request
clarification from the project owner;
 claims and/or disputes: Lack of consistency may invite discrepancy or
ambiguity during the performance stage of the contract, which may pave
the way for construction claim, and, if not settled well also lead to
construction disputes;
 professional care: Therefore, utmost professional care has to be taken with
a view to prepare a clear, complete & consistent conditions of contract; this
may also apply to the other standard bidding documents;
 Such caution may also help to have smooth contract management and in
preventing or minimizing construction claims to arise;
 deal conformance: Now the construction contract is ready for its
management process: viz., ensuring conformance to the recorded deal (viz.,
the signed contract & the applicable law);
 Contract & Construction Contract: Effects
 Background
 see the Civil Code: Article 1731 cum 1952 cum 1678 (b) cum 1711-1718 cum
Art. 3131-3206 cum 3244-3296 plus
 the actually signed construction contract documents;
 The issue of effect of contract deals with the following two broad issues:
 parties: parties to the contract; and
 deal: content & scope of their deal;
 Contracting Parties
 The issue of parties to the contract is related to the doctrine of privity of
contract; i.e., contract brings (relative) effects only to the parties to such
contract; namely., on the employer & on the contractor;
 Outsiders, legally known as third parties, in principle, are excluded from the
contract to get neither benefit nor burden;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 31
Training Material on Construction Contract Management

 There may be some exceptions to such rule as provided under Article 1731
(1) cum Article 1952 ff of the Civil Code (Third Parties);
 The Engineer is a third party say to the specific project related construction
contract signed between the employer & the contractor;
 The sub-contractor is a third party to such given construction contract
signed between the main contractor & the employer;
 The employer is a third party to such construction sub-contract signed
between the main contractor & the said sub-contractor;
 The contractor is a third party to the consulting services agreement signed
between the employer (as a client) & the Engineer (as a consultant or the
Engineer under a given construction contract);
 Scope of the Deal
 The scope of the deal of the contracting parties (like the employer & the
contractor under a given construction contract) encompasses the following
two broad areas:
 It encompasses: K & L
 the signed construction contract (K); and
 the applicable law (L);
 the contract:
 the terms of the signed construction contract itself, established based
on the principle of freedom of contract & sufficiency requirement
provides the formidable ground for the deal of the contracting
parties; viz., the employer & the contractor;
 see Article 1678 (b)) cum 1711-1718;
 the applicable law: shall or may come to apply to the specific construction
contract in two distinct ways; viz., in terms of
 express terms of the law; and
 implied terms of the law;
 express terms of the law: public policy (regulatory) role of the law

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 32
Training Material on Construction Contract Management

 the express terms of the mandatory provisions of the law shall apply
to the (construction) contract, as a matter of public policy & legality
requirement and they automatically become the deal between the
contracting parties; see Article 1678 (b) cum 1731 (2);
 implied terms of the law: gap filling (facilitative) role of the law
 the implied terms of the law apply to the construction contract where
the parties to the construction contract fail to determine the terms of
their deal based on the principle of autonomy of parties & freedom of
contract;
 This is evident from the reading of Article 1731 (2) & (3) of the Civil Code;
 The issue of applicable law to the contract thus comes from here:
 express terms: either to mandatorily regulate the behavior or
obligations of the contracting parties as a matter of public policy (see
Article 1678 (b) cum 1711-1718); and/or
 implied terms: to fill the gap, through such implied terms of the
law in the contract, where the parties fail to exercise their freedom
of contract to fix their deal; (illustration: see Article 2619; 3174 as to
time);
 Effectiveness:
 In construction contract, the issue of effectiveness of contract might
also be considered where the parties to such contract include some
defined pre-conditions in the signed contract for its effectiveness;
 Illustration: see Clause 8.1 of the MDB-FIDIC; pre-conditions like
effecting advance payment; making financial arrangement; handing
over of the site & access thereto;
 Illustration: see also Article 3144 cum 3143-3145 the Civil Code as
related to possible (further) approval requirement after signing of the
construction contract under consideration;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 33
Training Material on Construction Contract Management

 Scope of Effects of Contract


 The issue of effects of contract encompasses, from the law of contract
perspective, the following four areas: viz.,
 interpretation of contract;
 performance of contract;
 variation of contract;
 non-performance of contract;
 The four issues have been provided for & governed under Article 1732-1805
of the Civil Code;
 Interpretation of Contract:
 see Article 1732-1739 of the Civil Code cum other applicable laws cum the
signed construction contract;
 purpose:
 the objective of contract interpretation is to reach to the true meaning
of the terms of the contract document; and
 then to determine who bears the benefit or burden from the result of
such interpretation process;
 Rules of contract interpretation have been provided under the Civil Code;
 The first rule of interpretation states:
 no interpretation in case of clear contract terms;
 The other important rule of interpretation being:
 in case of doubt the benefit of doubt goes to the debtor; this is true in
case of interpreting standard conditions of construction contract; the
benefit of doubt goes to the contractor since it is not the one who
prepares such construction contract documents;
 also called contra proferentum rule;
 From institutional perspective, two types of interpretation may be identified:
 formal interpretation; and
 informal interpretation;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 34
Training Material on Construction Contract Management

 Formal interpretation
 formal interpretation is undertaken;
 by the judge at the court of law; and
 by the arbitrator at the arbitral tribunal;
 the Courts:
 The reason being that the courts are judicial institutions both
constitutionally & legally empowered to do interpretation of law; and
 in case of disputes related to contract to interpret the contract (like
construction contract) as well;
 arbitration tribunals:
 The arbitrator is the one who legally empowered to give its award
based on the principle of law;
 this task necessarily requires to interpret both the law and the
underlined (construction) contract to settle the dispute; see Article
3325 ff of the Civil Code;
 The difference between such two institutions, the court & arbitration, being
that:
 the court being the creation of the law;
 whereas arbitration, specially as related to construction, being the
creation of agreement (contract) (i.e., agreement to arbitrate);
 Informal interpretation
 Informal interpretation may be undertaken;
 by the contracting parties themselves; during their claims or disputes
negotiation process or otherwise;
 by the Engineer; through providing clarification (as related to
ambiguity or discrepancy or contradiction) & instruction; during its
claims consultation; claims determination or decision process or
contract administration or project supervision or otherwise;
 by the Adjudicator/DRE; during its dispute resolution process with a
view to give its decision or recommendation;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 35
Training Material on Construction Contract Management

 The construction contract document also contains some rules of


interpretation in the relevant contract documents such as:
 in the Contract Agreement, if completed; in terms of establishing the
hierarchy of construction contract documents & the rule of
interpretation to be followed in case of ambiguity or discrepancy
between and/or among such contract documents listed;
 in the General Conditions of Contract; in the definition part of same;
for example, see MDB-FIDIC (2006) under Clause 1, has defined
certain terms and/or phrases grouped under the following categories;
viz..
 The Contract;
 Parties & Persons;
 Dates, Tests, Periods & Completion;
 Money & Payments;
 Works & Goods; and
 Other Definitions; like Contractor’s Documents; Country;
Employer’s Equipment; Force Majeure; Laws; Performance
Security; Site; Unforeseeable; and Variation;
 in the Special Conditions of Contract; in the definition part of same;
 in the other part of the construction contract documents; like under
the BOQ; the Drawing; the Technical Specification;
 Performance of Contract:
 see the Civil Code: Article 1740-1762 cum 3131-3206 cum 3244-3296 plus the
signed construction contract documents;
 By performance of construction contract it means to discharge the respective
contractual obligations of the employer & the contractor (like the Enterprise)
as per the signed construction contract;
 Performance of construction contract has the following two dimensions;
 promise dimension; and
 consideration dimension;
 Promise dimension may relate to the contractor & to the employer;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 36
Training Material on Construction Contract Management

 to the contractor; generally, in terms of its contractual obligation as


related to execution & completion of works and remedying of defects
therein;
 to the employer; in terms of its obligation related to appointment of the
Engineer; design; site handover; takeover of the works if completed;
…;
 Consideration dimension being related to the employer; viz.,
 as related to its payment obligation;
 The level of detail & complexity of contract performance by the employer &
the contractor, with respect to their respective contractual obligation, is
provided & regulated by their relevant construction contract documents; re:
1678 (b) sufficiency requirement is crucial here!
 The whole purpose of construction contract management process & goal is
thus to achieve the realization of the performance of say the water works
construction project by ensuring the discharge of the respective contractual
obligations of contracting parties, viz., the employer & the contractor (like
the Enterprise);
 Construction contract management thus means ensuring conformance to
their deal;
 Variation of Contract:
 see the Civil Code Article 1675 cum 1763-1770 cum 3131-3206 cum 3244-
3296 plus the signed construction contract documents;
 Variation may have two dimensions within the construction contract context:
 textual variation; meant variation of the terms of the contract; and
 physical variation; meant variation in the works;
 Textual Variation:
 Contracting parties, as they are free to create their contractual terms,
they are also free to vary same;
 This type of variation is called textual variation as provided &
regulated under Article 1675 cum 1763-1770 of the Civil Code;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 37
Training Material on Construction Contract Management

 This type of variation is mostly effected through supplementary


agreement as related to construction projects (or Addendum);
 Variation in the Works:
 Variation in the works is the second type of variation which has
nothing to do with changes in the terms of the contract but the works;
 This type of variation is effected during the performance period of the
construction contract through the variation order issued by the
Engineer;
 Each & every variation in the works does not need any textual
variation in the management of construction contract;
 The cumulative effect of variation in the works (as provided under the
construction contract) may trigger a textual variation, however;
 Variation in the works recognized, legally, as changes in the work
(see Article 2625) or alteration to the works (Article 3031-3034 ) in the
field of private construction contract;
 This concept is crucial in terms of scope management under a given
construction contract; see Clause 13 of MDB-FIDIC (2006); see
Clause 15 of the PPA (2011);
 Non-Performance of Contract:
 see Article 1771-1805 cum 3131-3206 cum 3244-3296 under the Civil Code
plus the signed construction contract documents;
 Non-performance of contract results in the failure to perform or discharge the
underlined contractual obligation assumed by that specific contracting party,
either the employer or the contractor, under the relevant signed construction
contract;
 If the contracting party responsible for such performance obligation fails
(then becomes the defaulting contracting party),
 remedial right: the other contracting party (the non-defaulting party)
is entitled to some form of remedial right; and

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 38
Training Material on Construction Contract Management

 liability: such defaulting contracting party is becoming liable for such


remedial right towards the other contracting party (the non-
defaulting party);
 Non-performance thus brings with it the following four interrelated issues;
 obligation: who was responsible for what (obligation dimension);
 liability: what results from non-performance against whom (liability
dimension);
 remedial right: who is to be entitled to benefit from enforcement of
such liability (remedial rights dimension);
 quantum of remedial right: to what extent he (the one who benefits
from) is entitled to such remedial rights; (quantum of liability
dimension); illustration: how many days of EOT; and how much
additional payment;
 Obligation Dimension
 Who was responsible for what provides the contracting party
responsible for a defined type of performance or obligation;
 From this perspective, we may have two dimensions: promise &
consideration dimensions;
 The promise dimension may relate to the contractor or the employer,
as the case may be;
 The promise dimension as related to the contractor expressed in
terms of its execution, completion & remedying defects obligation;
therefore, it is said to be that the contractor (like the Enterprise) was
contractually under obligation for execution & completion of the
works; and remedying defects in the works;
 The promise dimension as related to the employer may be related to
its obligation like as to design or site handover or takeover obligation;
therefore it is said to be that the employer was contractually under
obligation for design or site handover or takeover;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 39
Training Material on Construction Contract Management

 The consideration dimension being related to the employer; as related


to its payment obligation; therefore it is said to be that the employer
was contractually under obligation for payment;
 Therefore, the contractor (like the Enterprise) as related to execution
of the works, and the employer as related to say design or site or
takeover and payment is their respective obligations;
 Liability Dimension
 The failure to discharge or to perform such respective contractual
obligations by the employer or the contractor (like the Enterprise)
brings with it a liability against the employer or the contractor(like
the Enterprise), as the case may be;
 towards the other party, i.e., the employer towards the contractor
(like the Enterprise); or the contractor (like the Enterprise) towards
the employer;
 Remedial Right Dimension
 Therefore, the employer or the contractor (like the Enterprise), as the
case may be, is the one to benefit from the enforcement of such
liability against the contractor or the employer, respectively;
 Remedial right may emanate from the applicable law or from the
signed construction contract;
 The legal remedial rights as provided under the Civil Code, may take
the following three forms; viz., specific performance; cancellation of
contract; and general damages;
 The contractual remedial rights could take the following three forms:
viz., time or cost or both time and cost; and others like suspension of
works or termination of contract;
 Quantum of Remedial Right Dimension
 Liability as specified in terms of specific remedial rights has quantum
dimension specially as related to time and/or cost;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 40
Training Material on Construction Contract Management

 Quantum may be expressed as follows: how many days of extension of


time to be granted to the contractor; how much cost (viz., in terms of
additional payment) to be given to the contractor;
 This is evident in case of construction claims & dispute management;
V. Construction Contract Management
 Contracting Parties & their Status
 The contracting parties to the signed construction contract are:
 the employer; and
 the contractor;
 Such signed construction contract only binds, in principle, the employer &
the contractor; see Article 1675 cum 1731 (1) cum 1952 of the Civil Code;
 The following are not party to the construction contract signed between the
employer & the (main) contractor: for example, the Engineer; the Sub-
contractors (nominated & domestic);
 The Employer:
 initiator: The employer is the one who initiates the idea or plan of a
construction project under consideration;
 financer: the employer is the financer of the project; save the role of
international financial institutions in providing the necessary financial input
to the project in terms of loan or grant or aid;
 owner: the employer is the owner of the physical facility up on its
completion; save in certain circumstances where the executing agency & the
final operator of the project being different;
 independent: the employer is independent:
 legal autonomy: the employer enjoys legal autonomy (based on
formative legal instruments in case of public employers;); it has its
own legal personality different & independent from the contractor,
the engineer or any other persons);
 organizational autonomy: the employer enjoys organizational
autonomy; having its own structural set up;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 41
Training Material on Construction Contract Management

 financial autonomy: the employer enjoys financial autonomy; in


terms of its source, cost structure & management of same;
 management autonomy: the employer enjoys management
autonomy; to run its business and/or project based on its own
structure, system & resources including its human capital;
 professional: the employer may or may not be a professional;
 That is why the employer engages a consultant in various phases of the
construction process/project:
 project study services:
o to get project study services (project planning; reconnaissance
study; pre-feasibility study; feasibility studies; environmental
studies (impact, risk & mitigation measures related); socio-
economic studies; compensation and/or resettlement action
plan (RAP) studies;) as related to some defined construction
project say building; engineering; and/or industrial;
 delivery system;
o to get a recommendation & advice on the choice of appropriate
project delivery sub-system & their range of implications as
related to the contemplated construction project;
 design services:
o to get the complete/detail design or otherwise of the
construction project under consideration based on the delivery
sub-system selected & decided;
 bidding documentation:
o to get a complete standard bidding documents ready for
invitation for bids based on the delivery sub-system selected &
decided;
 procurement services:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 42
Training Material on Construction Contract Management

o to get a procurement assistance services with a view to select a


qualified contractor based on the recommendation of the
consultant;
 project supervision services:
o to get project supervision services from the consultant;
 contract administration services:
o to get construction contract administration services from the
consultant;
 In case of public institutions, as employers, there is an issue of legal
substitution of the former employer by the new employer;
 See the definition given to Employer; under Sub-Clause 1.1.2.2: MDB-FIDIC
(2006);
 The Contractor;
 The legal status of the contractor is different from the employer;
 Two issues are important here: viz.,
 the contractor’s independence status; and
 its professional status;
 independent status:
 the contractor, based on the doctrine of independent contractor, is
independent from the employer; see Article 2616 (1) of the Civil
Code;
 This legal status of the contractor brings with it the following
threefold autonomies, viz., legal, organizational and financial
autonomy;
 legal autonomy:
 the contractor enjoys legal autonomy; it has its own legal personality
(based on its formative legal instrument viz., regulation) different &
independent from the employer; the engineer or any other person;
 organizational autonomy:
 the contractor (like the Enterprise) enjoys organizational autonomy;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 43
Training Material on Construction Contract Management

 it has its own structural set up but subject to project requirement, if


any;
 financial autonomy:
 the contractor enjoys financial autonomy; in terms of its source, cost
structure & management of same;
 Implications
 being independent & professional brings with it important legal &
contractual obligations & liability:
 legally & contractually: to be liable for his own acts, defaults or
neglects & of its sub-contractors acts, defaults or neglects towards the
employer & third parties; and
 legally & contractually: as to its obligation & liability in terms of its
design method related, if any; and construction method related;
 professional Status:
 the contractor is a professional; it knows what, when and how to do
in terms of its contractual & technical obligations under a given
construction contract;
 the contractor performs its contractual obligation as it wishes & by
complying the rules of its profession; see 2616 (1) of the Civil Code;
 The professional status of the contractor brings with it the following
threefold autonomies viz., management autonomy; schedule
autonomy; and method autonomy;
 management autonomy:
 the contractor enjoys management autonomy; to manage the
construction project as he wishes; see Article 2616 (1) of the Civil
Code;
 schedule autonomy:
 the contractor enjoys schedule/program autonomy since he knows
what (activities), when (sequencing) to do;
 method autonomy;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 44
Training Material on Construction Contract Management

 the contractor enjoys method autonomy since he knows how to do it;

 Limitations
 There are two limitations on the professional freedom (autonomy) of
the contractor: viz., regulatory limitation; and contractual limitation;
 regulatory limitation;
o this limitation comes or originates from the rules & practice of
the contractor’s respective profession; water or building or
road or otherwise;
o this limitation aims to protect public interest; see Article 2616
(1) of the Civil Code;
 contractual limitation:
o this limitation comes or originates from the construction
contract under consideration as related to the order of the
client (the employer) as agreed by the contractor as the time of
the making of the contract
o this limitation aims to protect the legitimate interests of the
specific employer under consideration;
o The contractor may not follow the orders of the client (i.e., the
employer) except in so far as it has agreed, at the time of
contract, to comply therewith;
o The construction contract thus provides the ground for such
order by the employer through the Engineer (viz., the
supervision consultant); like variation order; suspension
order; order as related to quality assurance; and so forth;
o see 2616 (1) & 2616 (2) of the Civil Code;
 In case there is a change of the contractor during contract performance, its
institutional successor, if any, may continue as contractor; see Clause 1.1.2.3:
MDB-FIDIC;
 there are various reasons for the contractor to be changed by another;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 45
Training Material on Construction Contract Management

 Contract Documents
 Construction contract (like water works or dam or building or road
construction contract) may contain the following five categories of contract
documents: viz.,
 the legal part;
 the technical part;
 the commercial part;
 the technological part, if any; and
 the dispute resolution part (re: arbitration clause);
 The legal part: may include the following contract documents:
 the Form of Agreement , if completed;
 the Letter of Acceptance;
 the Minutes of Pre-contract Negotiation Meeting, if any;
 the Bid (including any Appendixes thereto, if any);
 the Special Conditions of Construction Contract;
 the General Standard Conditions of Construction Contract;
 other identified contract documents, if any;
 The technical part: may include the following contract documents:
 scope: the Technical Specifications; the Drawing; the Bill of Quantities;
 The Technical Specifications: which provides the textual
description of the project & which specifies the quality parameters of
the works (in terms of its workmanship; construction materials;
construction equipments (plant);) under the construction contract;
defines how the project to be done (i.e., method));
 The Drawing: which describes graphically the works under the
construction contract; defines what to be done; provides ground for
measurement of works;
 The Bill of Quantities: identifies the scope of works, in terms of
those quantities, and provides the basis for valuation of quantities

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 46
Training Material on Construction Contract Management

(based on the drawing: measured) to be executed; it is both a technical


& financial document;
 The commercial part:
 The commercial part of the contract may include the following contract
documents (i.e., commercial security instruments originating from & issued
by banks or insurance companies including insurance policies):
 security instruments like: for security management
 Advance Re-payment Guarantee/Bond;
 Performance Bond /Guarantee;
 Retention Money Bond/ Guarantee; and
 other security instruments, if any;
 These documents are the basis for our discussion as related to security
management;
 insurance policies like: for risk management
 Insurance for Works;
 Insurance for Personnel;
 Insurance for Plant & Equipment;
 Insurance as related to Third Part Liability; and
 other insurance policies, if any;
 The technological part:
 may include process related documents as related to electro-
mechanical part of the (water) works, if any;
 like for elevation works in building projects;
 like signaling, communication, electrical, mechanical works in railway
construction projects;
 The dispute resolution part:
 it is basically related to an arbitration clause in a given construction
contract, if any;
 an arbitration clause, even though it is already part of the main
construction contract document (under the general and/or special

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 47
Training Material on Construction Contract Management

conditions of contract, if any) it is legally a separate contract


document based on the doctrine of separability or severability of such
arbitration clause from the underlined construction contract;
 see for example, Clause 20.6 MDB-FIDIC (2006);
 see Clause 26.6: Disputes Settlement PPA 2011 (viz., arbitration) if
applicable;
 The type, size and/or complexity of the construction project may have its own
legitimate impact on the scope of the relevant contract documents;
 Scope & Basis
 Under this part of the training, the main & respective obligations of the
contractor & of the employer have been presented;
 As to the obligations of the contractor, it may include the following:
 Completion Obligation;
 Quality Related Obligation;
 Time Related Obligation;
 Scope Related Obligation;
 Cost Related Obligation;
 Safety Related Obligation; and
 Risk Sharing Obligation;
 As to the obligations of the employer, it may include the following:
 Engineer Related Obligation;
 Design Related Obligation;
 Site Related Obligation;
 Takeover Related Obligation;
 Payment Related Obligation; and
 Risk Sharing Obligation;
 As common obligation of the contractor and of the employer, cost & risk
related obligations shall also be discussed separately;
 Security management issues shall also be discussed as related to the
commercial part of the construction contract;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 48
Training Material on Construction Contract Management

 The discussion is mainly based on MDB-FIDIC international Standard


Conditions of Construction Contract, March, 2006;
 Some cross references may also be made to the relevant clauses of PPA 2011;
 Some cross references may also be made to the relevant applicable laws like
the Civil Code or otherwise;
1.1 Obligations of the Contractor
 Background
 The contractor may have different obligations under a construction contract;
 The following are some of the fundamental obligations of the contractor
under the construction contract;
 These are:
 completion obligation;
 quality related obligation;
 time related obligation;
 scope related obligation;
 cost related obligation; and
 safety related obligation;
 These issue areas are the basis for construction contract management;
 Completion Management
 Basic Obligation
 see Clause 4.1 cum 7.6 cum 8.2 (a) (b) cum 9.1 cum 13.1 cum 11.1 cum 17.4
cum 19.7 cum MDB-FIDIC;
 see Clause 34: General Obligations (of the Contractor) PPA 2011;
 The basic obligation of the contractor under the construction contract shall
read:
 to execute the works;
 to complete the woks; and
 to remedy defects in such works;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 49
Training Material on Construction Contract Management

 The contractor undertakes such obligation by itself & through others: viz.,
through sub-contractors (domestic vs. nominated) sub-contract arrangement,
if nay;
 Such completion obligation of the contractor encompasses two time
dimensions: viz.,
 performance period; and
 defects liability period;
 During performance period, the contractor is under such contractual
obligation to:
 to execute, to complete & to remedy defects in the works within the
time agreed;
 to execute the whole of the Works in accordance with the Contract up
to Take Over of the Works by the employer;
 to undertake tests on completion;
 see Clause 4.1 cum Clause 8.2; Clause 13; Clause 9; Clause 10 MDB-FIDIC;
 During defects liability period, the contractor is under such contractual
obligation to:
 execute outstanding works; and
 to remedy defects & damages in the works;
 see Clause 11.1 MDB-FIDIC;
 Extent of Completion Obligation
 The scope of completion obligation of the contractor under such contract
may include to undertake the following:
 to execute & complete the original scope of work & to remedy
defects in such original scope of work; see Clause 4.1 cum Clause 10
MDB-FIDIC;
 to execute variations orders; see Clause 13.1 MDB-FIDIC;
 to rectify losses or damages to the works arising out of the
Employer’s Risks; see Clause 17. 4 MDB-FIDIC;
 to execute remedial or urgent works; see Clause 7.6 MDB-FIDIC;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 50
Training Material on Construction Contract Management

 to carry out works to achieve tests on completion for the purpose of


Taking Over; see Clause 9.1 cum Clause 8.2 (a) cum 8.2 (b); MDB-
FIDIC
 Specially passing tests on completion is a critical obligation which
may have serious contractual consequences against the contractor;
see Clause 9.4 MDB-FIDIC;
 Completion obligation of the contractor thus related to time; scope; and
quality parameters of the contract/the project;
 Excuses from Completion Obligation
 The contractor may be excused from its completion obligation on the
following contractual and/or legal grounds;
 The grounds may generally relate to:
 impossibility; legal and/or physical impossibility;
 risk; as related to the employer risk under the contract;
 suspension; by the employer or the contractor;
 termination; by the employer or the contractor;
 impossibility:
 due to legal or physical impossibility;
 see Clause 19. 7 MDB-FIDIC;
 see Clause 18 PPA 2011 (Force Majeure);
 see also Article 1678 (b) (i.e., possibility of obligation legal
requirement;) cum 1715 (1) cum 1792-1794 (Force Majeure) of the
Civil Code;
 risks:
 in case of the occurrence of the Employer’s Risks;
 see Clause 17. 3 MDB-FIDIC;
 suspension:
 in case of suspension of the Works by the Employer;
 see Clause 8.8 MDB-FIDIC;
 suspension:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 51
Training Material on Construction Contract Management

 in case of legitimate suspension of the Works by the Contractor as


related to payment; see Clause 16.1 MDB-FIDIC;
 termination:
 in case of termination of the Contract by the Contractor due to the
default of the Employer as related to payment;
 see Clause 16.2 MDB-FIDIC;
 termination:
 in case of termination of the Contract by the Employer for its
convenience;
 see Clause 15.5 MDB-FIDIC;
 see also Clause 21.2 (O) of the PPA 2011;
 see also the concept of employer’s termination of contract for its
convenience under Article 3180 of the Civil Code;
 termination:
 in case of termination of the Contract for the whole of the Works due
to prolonged suspension caused by the Employer; see Clause 8.11
MDB-FIDIC;
 termination:
 in case of optional termination of the Contract by the Contractor or
by the Employer due to prevention of performance by force majeure;
see Clause 19.6 MDB-FIDIC; see also the legal concept & scope of
force majeure under Article 1792-1794 of the Civil Code;
 under such circumstances the contractor is not in contractual and/or legal
position to complete the project under consideration;
 Role of Sub-contractors
 see Article 1675 cum 1731 cum 1952 cum 3201-3206 of the Civil Code;
 see Clause 4.4 MDB-FIDIC for domestic sub-contracting;
 see Clause 14 PPA (2011) for domestic sub-contracting;
 see Clause 5 MDB-FIDIC for nominated sub-contracting;
 see also Clause 4.1 as related to domestic sub-contracting;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 52
Training Material on Construction Contract Management

 Engagement of sub-contractors considered to be part of the broad


completion obligation of the contractor;
 Sub-contractors are of two types: domestic & nominated sub-contractors;
 The very reason for the engagement of sub-contractors may be divided in to
three:
 work load reduction;
 specialty input; and
 public policy requirement;
 Domestic sub-contractors are engaged by the main contractor with a view to
reduce the work load from the contractor (see Clause 4.4 of MDB-FIDIC)
and Clause 14 PPA 2011;
 Nominated sub-contractors are nominated by the employer (either before or
after the selection of the main contractor) due to the special services or input
or otherwise of such nominated sub-contractor (see Clause 5 MDB-FIDIC);
 The engagement of small & medium enterprises in the construction project
may be considered due to public policy reason with a view to create
employment opportunity & capacity building;
 If there is any formal contract created between such sub-contractors & the
main contractor, the legal & contractual relationship is created only between
the main contractor and such sub-contractor;
 There are however some fundamental differences between the legal status of
the domestic sub-contractor & that of nominated sub-contractor;
 The underlined difference lies in the bargaining power of such (nominated)
sub-contractor; no bargaining power in case of domestic sub-contractors;
whereas, full of bargaining power in case of nominated sub-contractors;
 For example, in case of domestic sub-contractors, the main contractor is
required to execute, complete & remedy defects in the works through such
sub-contractor;
 In this case, the contractor acts as follows vis-a-vis the sub-contractor:
 as the main contractor (for the sub-contract purpose);
 as the employer (for payment channeling purpose); and

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 53
Training Material on Construction Contract Management

 as the engineer (for instruction channeling purpose);


 The main contractor is contractually liable for the execution & completion of
the project, also by such sub-contractor, towards the employer;
 This requires serious coordination effort by the main contractor so that the
sub-contractor has been duly selected in due time; duly mobilized; duly
progressed i.e., executed; and duly completed the project;
 The project linkage between the main contract & such sub-contract is
created through:
 the back-to-back application of the main contract to the sub-contract:
this is done by direct reference of the relevant main contract
documents in the sub-contract excluding price information; or
 by preparing a stand-alone or full-fledged construction sub-contract;
 Construction Sub-construct management requires its own training;
 Quality Management
 MDB; see Clause 7 (Plant, Materials & Workmanship) cum Clause 4.9
(Quality Assurance System) cum Clause 9 (Test on Completion cum Clause
11.4 (Tests After Completion); other relevant parts of the MDB-FIDIC;
 PPA: see Clause 37 (Control & Supervision of the Works); Clause 80 (Origin
& Quality of Works & Materials); Clause 81 (Inspection & Testing); Clause
82 (Rejection); 85 (Tests on Completion) of PPA 2011;
 see the Technical Specifications of the project under consideration;
 see also the applicable laws regulating the quality of construction materials;
re: quality infrastructure;
 see Article 3282 (for public projects) or Article 3039 (for private projects) of
the Civil Code; re: legal warranty of construction for 10 years after its final
completion & delivery;
 Scope of Obligation
 One of the pillars of construction project is executing the works as per the
quality parameters or requirements specified in the contract;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 54
Training Material on Construction Contract Management

 The quality performance obligation of the contractor is related to those


quality parameters specified in the contract in terms of materials, plant &
workmanship;
 in case of Plant; see Clause 7.1 (a) MDB-FIDIC;
 in case of Materials; see Clause 7.1 (c) MDB-FIDIC;
 in case of Workmanship; see Clause 7.1 (b) cum Clause 6.1 MDB-FIDIC;
 The quality performance obligation of the contractor has been specified in
detail in the Technical Specification;
 Deviation from the quality parameters by the contractor may lead to the
issue of defects in construction;
 Defects may relate to workmanship; material; equipment; design; or sub-
surface or geological factor of the project site;
 Defect, Time & Liability Dimension
 Defect as related to the severity of its impact could be:
 structural defect or
 functional defect;
 Defect as related to construction may encompass two relevant time horizons:
 contractual period; and
 legal period;
 The contractual horizon as related to defect is related to:
 performance period; and
 defects liability period;
 In case of performance period, the defect being identified, notified &
remedied; the Engineer has direct power to ensure quality through various
measures: inspecting; testing; retesting by ordering demolishing & re-work
and so forth;
 Up on completion of the project, tests on completion has to be undertaken by
the contractor; the Engineer, under the contract, has broad power to ensure
the quality of works; see Clause 9 of MDB-FIDIC; and Clause 85 of the PPA
2011; like requiring multiple retesting & reduction of the contract price; or

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 55
Training Material on Construction Contract Management

requiring multiple retesting & rejection of the works; demolishing &


reconstruction of the works;
 During the defects liability period remedial works are going to be executed
based on the snag list and/or on those defects found & recorded during such
period for which the contractor is responsible under the contract;
 Performance period & defects liability period are separated by the issuance
of takeover certificate by the Engineer;
 The contractual period & the legal period (which constitutes the warranty
period) separated by the issuance of defects liability certificate or final
acceptance or taking of possession of the works by the employer;
 Those defects which were apparent, visible & remedied during the contract
period (viz., during performance & defects liability period) are called patent
defects;
 Those defects which were not visible during such contract period are called
latent defects; for such type of construction defects the contractor shall be
legally liable provided those defects were related to construction;
 The liability of the contractor for such latent defects could be for 10 years;
see Article 3282 of the Civil Code; as related to public construction contracts;
like water works construction; see Article 3039 as related to private
construction contract;
 the liability of the contractor is called decennial liability;
 Excuse from Quality Obligation
 There is no excuse for defective performance or failure to achieve quality
parameters of the works;
 Consider the issue of variation order as related to the concept of detrimental
variation;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 56
Training Material on Construction Contract Management

 Time Management
 Background
 MDB-FIDIC (2006):
 see Clause 8: Commencement Date, Delay & Suspension
 see Clause 8.1: Commencement Date
 see Clause 8.2: Time for Completion
 see Clause 8.3: Program
 see Clause 8.4: cum
 see Clause 8.5 cum
 see Clause 8.8 cum
 see Clause 8.9 cum
 see Clause 8.11 cum
 see Clause 8.2 cum
 see Clause 8.6 cum Rate of Progress
 see Clause 9 : Tests on Completion
 PPA 2011:
 see Clause 41 (Program of Implementation of Tasks); cum
 see Clause 71 (Commencement of Works); cum
 see Clause 72 (Period of Execution of Works); cum
 see Clause 73 (Extension of Intended Completion Date); cum
 see Clause 74 (Compensation Events for Allowing Time Extensions);
cum
 see Clause 75 (Acceleration) cum
 see Clause 27 (Liquidated Damages);
 Civil Code:
 see Article 1675 cum 1731 cum 3174 (Time);
 see Article 1675 cum 1731 cum 2619 (Time);
 Other Applicable Laws
 Rest & Holidays related laws; re: Program related;
 Protocols, if they were helpful…

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 57
Training Material on Construction Contract Management

 see also The Society of Construction Law Delay & Disruption Protocol
UK; October 2002; (First Edition)
 see also The Society of Construction Law Delay & Disruption Protocol
UK; February 2017 (Second Edition);
 Time related obligation of the contractor is the most complex and thus
difficult issue in the field of construction contract management;
 Time obligation of the contractor should be specific; i.e., there must be clear
commencement date & clear completion date; based on these dates Program
is also required;
 If there is clear commencement date & completion date, the Program may
help;
 Is the program part of the contract document then? Should it be either? If so
how does it help? What are the factors to be considered to prepare the
program (structure)?
 What is the basis for time management then? The program or such clear
commencement date & completion date or both?
 What is the basis for delay claims then? What about the basis for disruption
claims? Are they (delay & disruption claims) the same or different?
 How the delay claims of the contractor are assessed? How about the delay
damages claims of the employer is to be assessed? Do they share same
principle or are they different?
 Scope of Time Obligation
 The timely completion i.e., on completion date, if any, of the project by the
contractor may depend on multitude of factors contributed both by the
contractor itself and of the employer including the Engineer and so forth;
 The issues are discussed in relation to:
 mobilization;
 commencement;
 progress;
 completion; and
 tests on completion;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 58
Training Material on Construction Contract Management

 These factors show that the completion of the project on such completion
date, if any, interwoven by the series of contractual obligations to be
discharged by the contractor; by the employer and/or the Engineer; and to
be free from external risk factors;
 mobilization: timely & effective mobilization by the contractor ;
 site: providing site & access thereto by the employer;
 advance: effecting mobilization advance, if agreed, by the employer;
 notice: effecting notice to proceed, if required under the contract, by
the Engineer; for the Contractor to duly mobilize & commence
works;
 commencement: commencement of the Works, if there is clear cut
commencement date or otherwise; see Clause 8.1 MDB-FIDIC;
 progress: proceeding with the progress of the works: see Clause 8.1
cum Clause 8.6 (Rate of Progress) MDB-FIDIC;
 this is related to the following situations; like
 effective project management on the part of the contractor in terms of
organizing & deploying all the required resources to the project;
 achieving the planned production and productivity on the part of the
contractor;
 issuing the required working drawings (from time to time) on the part
of the Engineer;
 securing the required site & access thereto (from time to time) on the
part of the employer;
 approving variations in due time on the part of the Engineer;
 certifying payments in due time by the Engineer;
 effecting payment on time on the part of the employer;
 progress: the Engineer may instruct the contractor to accelerate the progress
of the Works, for which the Contractor is not responsible under the
Contract; see Clause 8.6 MDB-FIDIC
 completion: completing the works or section thereof on the originally agreed
or subsequently varied completion date, if any; see Clause 8.2 MDB-FIDIC;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 59
Training Material on Construction Contract Management

consider also the effects of delay and/or disruption by the employer, third
parties and/or the Engineer & other grounds;
 tests: for the works to be declared completed they have to pass Tests on
Completion: please, also consider the possible contractual obligation of the
employer in doing some of the required tests on completion by itself and/or
providing some input to the contractor to undertake the tests on completion;
see Clause 9 MDB-FIDIC;
 Excuse from Time Related Obligation
 The following grounds may serve as excusable grounds for the non-
completion of the project by the contractor on the originally agreed
completion date or subsequently varied completion date; viz.,
 extension:
 due to extension of time for completion; see Clause 8.4 MDB-FIDIC;
 delay;
 due to delays caused by authorities; see Clause 8.5 MDB-FIDIC;
 suspension:
 due to suspension of work by the Engineer & its consequences;
 see Clause 8.8 cum 8.9 MDB-FIDIC;
 suspension:
 due to prolonged suspension as related to the suspension order
instructed by the Engineer; provided the performance of the Works
has been resumed after such prolonged suspension;
 see Clause 8.11 MDB-FIDIC;
 see Clause 20 (Suspension): PPA 2011;
 suspension:
 due to suspension & deceleration of the Works by the Contractor due
to payment problems;
 see Clause 16.1 (h) MDB-FIDIC;
 delay:
 due to delay in issuing drawings or instructions by the Engineer;
 see Clause 1.9 (a) MDB-FIDIC;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 60
Training Material on Construction Contract Management

 delay:
 due to initial delay caused by the employer in providing possession of
Site & access thereto;
 see Clause 2.1 (a) MDB-FIDIC;
 see Clause 74: Compensation Events for Allowing Time Extension;
PPA 2011;
 setting out:
 due to setting out;
 see Clause 4.7 (a) MDB-FIDIC;
 see Clause 49 (Setting out of the Works); PPA 2011;
 unforeseeable factors:
 due to unforeseeable physical conditions;
 see Clause 4.12 (a) MDB-FIDIC;
 fossils:
 delay encountered by the Contractor due to the discovery & reporting
of Fossils;
 see Clause 4.24 (a) MDB-FIDIC;
 see Clause 51: Discoveries; PPA 2011;
 testing:
 due to testing as instructed by the Engineer or for which the employer
is responsible under the Contract;
 see Clause 7.4 (a) MDB-FIDIC;
 see Clause 81 (Inspection & Testing) PPA 2011;
 interference:
 due to interference with the Tests on Completion by the Employer;
 see Clause 10.3 (a) MDB-FIDIC;
 legislation:
 due to adjustment for changes in legislation;
 see Clause 13.7 (a) MDB-FIDIC;
 see also Clause 16 of the PPA 2011: Changes in Law & Regulations;
 risks:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 61
Training Material on Construction Contract Management

 due to consequences of Employer’s Risks;


 see Clause 17.4 (a) MDB-FIDIC;
 see Clause 18: Force Majeure; PPA 2011;
 see also Civil Code Art. 1792-1794: Force majeure;
 Remedies:
 The contractor may be entitled to secure time or cost or both in case the
contractor itself were not liable for the delay caused; see the above MDB-
FIDIC & PPA clauses for excuses to the contractor;
 The employer may also be entitled to delay damages if the contractor were
liable for the delay caused; see Clause 8.7 MDB-FIDIC;
 completion date:
 Such liabilities of the contractor or of the employer may work as
related to time related obligation of the contractor should there be a
clear commencement date, and clear completion date originally
agreed or as subsequently varied;
 time at large:
 if there were no clear commencement date and/or completion date,
the time for completion may become at large and the contractor will
then be entitled to complete the project within a reasonable time;
 see Article 1731 cum 3174 of the Civil Code; (consider also the issue of
implied terms of the law to the contract);
 if time becomes at large, the employer may no longer be entitled to collect
delay damages (under MDB-FIDIC) or deduct liquidated damages (under
PPA) from the contractor;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 62
Training Material on Construction Contract Management

 Scope Management
 Background
 MDB-FIDIC (2006)
 see Clause 1.1.6.9 definition & scope of variation;
 see Clause 1.1.5.4; definition for Permanent Works;
 see Clause 13.1 related to instructed variation;
 see Clause 13.2 related to approved variation ; cum
 see also Clause 4.1 (a) (b) & (c); (viz., value engineering);
 PPA 2011
 see Clause 15: Modifications by Change Orders;
 Civil Code
 see Article 1675 cum 1763 cum 1767 of the Civil Code (contract
variation);
 see also Article 3031-3033 of the Civil Code; re: to refuse alterations;
 see also Article 3034 of the Civil Code related to approved variation;
 Concept
 In construction contract, scope is basically related to the broad concept of
variation, viz., variation in the works;
 Variation means as per Clause 1.1.6.9 of MDB-FIDIC any change to the
works, which is instructed or approved as variation under Clause 13;
 works mean the permanent works (see Clause 1.1.5.4 MDB-FIDIC); like the
water works project;
 The changes to the permanent works may result in the following way:
 changes to the quality & other characteristics;
 changes to the level, positions and/or dimensions of any item of work;
 omission of any work it is to be carried out by others;
 any additional work, plant, materials or services necessary for the
permanent works including any associated tests on completion,
boreholes and other testing and exploratory works;
 changes to the sequence or timing of the execution of works;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 63
Training Material on Construction Contract Management

 Causes
 The causes which may trigger variation during construction could be
diverse;
 The following are merely illustrative:
 inadequate briefing from the employer side to the designers;
 inconsistent & late instruction from the employer/engineer;
 incomplete design;
 lack of meticulous planning at the design stage;
 poor planning of a project;
 using typical design for all geographical locations;
 lack of coordination of specialists under design work;
 late clarification of complex details;
 Types
 There are different criterion to categorize types of variation;
 Based on the definition given above (as per MDB-FIDIC), two types of
variations are identified: viz., instructed variation & approved variation;
 FIDIC 4th (1987) plus PPA both the 2006 & 2011 versions have no room for
approved variation;
 Instructed Variation
 Causes
 Under instructed variation, the variation order or instruction is coming from
the employer through the Engineer;
 The actual causes which trigger instructed variation may be of the following:
 employer: change of requirement by the employer;
 engineer: design change and/or instruction(s) by the engineer;
 contractor; like unavailability of the required construction material
and/or machinery in the market;
 regulatory body: change in regulatory requirements (say as related to
the water works project) by the government;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 64
Training Material on Construction Contract Management

 stakeholder: request from or pressure by the community/ultimate


beneficiary (like in case of changing the road alignment or dam site or
dam safety zone or aquifer location and/or ground water site radius
or pipe laying route/alignment (as related to transmission and/or
distribution network) or otherwise);
 nature: like change in ground conditions in terms of geological and/or
hydrological excluding climatic conditions;
 Procedure
 see Clause 13.1 MDB-FIDIC (2006); Variation;
 see Clause 15 PPA (2011) Modification;
 see also Article 3031-3032 of the Civil Code cum Article 3033; Alteration;
 The employer has the right to vary the works & this is done through the
order or instruction of the Engineer;
 The contractor has a contractual obligation to accept & execute variation
orders, as part of its overall obligation to complete the works;
 The overall procedure may seem as follows: instruction; confirmation;
proposal; agreement/determination; execution;
 Instruction: The Engineer instructs the contractor to do the variation;
the instruction should be in writing;
 Confirmation: If the instruction were oral it has to be subsequently be
confirmed by the contractor in writing;
 Proposal: The contractor proposes how to execute the variation in
terms of time, cost and/or method;
 Agreement/Determination: There must be agreement between the
contracting parties (employer & contractor; the Engineer expected to
play its consultative role here) or determination by the Engineer as to
the effects of such variation (i.e., on time & cost and/or method);
 Execution: The contractor proceeds to execute the works as varied;
 If there were no agreement between the contracting parties on the effects of
variation (time and/or cost), the contractor may have variation related
claims;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 65
Training Material on Construction Contract Management

 As part of variation procedure between instruction of the engineer and


before the contractor’s confirmation & making proposal, the contractor has
a contractual right to refuse variation on the following two grounds: see
Clause 13.1 MDB-FIDIC:
 goods related: the contractor cannot readily obtain the goods required
for variation; or
 level of impact: such variation triggers a substantial change in the
sequence or progress of the works;
 The Engineer has to consider and determine on such refusal of the contractor
under the contract; see Clause 3.5 MDB-FIDIC;
 see also Article 3033 of the Civil Code; re: Contractor Refusing Alterations
(in the works);
 Effects
 Variation may bring the following two major effects: time & cost;
 It may bring from the contractor side not only time & cost, but also method
change & disruption;
 This may have its own implications on the variation related claims of the
contractor;
 Approved Variation
 see Clause 13.2 MDB-FIDIC (2006); Value Engineering;
 see also Article 3034 of the Civil Code;
 Approved variation is basically related to the broad concept of value
engineering;
 It means that the contractor proposes to trigger variation which brings value
to the works & to the employer, to the project and to itself;
 Such proposal may include design change; then the contractor becomes a
designer for the permanent works; see also Clause 4.1 (a) (b) & (c) MDB-
FIDIC (2006);
 The fundamental objective of the proposed & thus approved variation being
to bring value to the project;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 66
Training Material on Construction Contract Management

 This is expressed in terms of the following concrete values:


 time: completion time acceleration;
 cost: reduction of cost;
 quality: improvement in quality;
 efficiency: improving the efficiency of the completed works (like in
terms of operation & maintenance cost);
 The procedure is almost the same except that this time the initiation for
variation comes from the contractor side;
 The net benefit accrued will then be shared, equally, between the employer &
the contractor less costs of the contractor to research & develop the
proposal;
 Safety Management
 MDB-FIDIC (2006)
 see Clause 4.1: Method of Construction;
 see Clause 4.18: Protection of the Environment;
 see Clause 6: Staff & Labour;
 see Clause 4.16 (Transport of Goods);
 PPA 2011
 see Clause 45: Health & Safety on Sites;
 see Clause 46: Safeguarding Adjust Properties;
 see Clause 47: Interference with Traffic;
 see Clause 48: Cables & Conduits ;
 Other Applicable laws
 see Proc. No. 377/1996: the Labour Law of Ethiopia;
 see Proc. No. 624/2009 Ethiopian Building Proclamation;
 see Regulation No. 243/2011: Ethiopian Building Regulation;
 see also all Ethiopian Building Codes;
 see Proc. No. 464/2005: Power & Telecommunications Network
Proclamation (re: safety);
 see Proc. No. 299/2002: the Law of Environmental Impact
Assessment;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 67
Training Material on Construction Contract Management

 see Proc. No. 300/2002: the Law on (integrated) Environmental


Pollution Control;
 see also applicable ILO Conventions; ILO Protocols; and so forth;
 see also UN Conventions on climate change;
 Civil Code
 see Article 2027-2161 of the Civil Code: Extra-contractual Liability;
 The other important obligation of the contractor is related to safety;
 The concept of safety has to be understood very broadly;
 It may relate to the safety of the following ecologies: to
 the natural environment;
 the heritage environment;
 the human environment;
 the built-environment; and
 the utilities environment;
 Natural Environment;
 The natural environment may include both the bio-sphere (plants, animals &
micro-organisms) & the physical environment (water, soil & air);
 Such obligation of the contractor embedded into two broad environmental
objectives: viz., to ensure sustainable development & to ensure
environmental safety (by preventing environmental pollution);
 The obligation of the contractor is both contractual & legal: it is contractual
as per Clause 4.18 of MDB-FIDIC; it is legal as per all the applicable laws of
Ethiopia enacted for the protection of the natural environment;
 If the water works construction project were subject to environmental
impact assessment (indeed it is), the first obligation rests with the employer
(as proponent of the project) to undertake such environmental impact
studies with a view to secure environmental clearance for the project under
consideration from the competent federal or regional regulatory institutions;
 The contractual & legal obligation of the contractor, in this regard, being
thus to implement the mitigation measures developed & approved in such

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 68
Training Material on Construction Contract Management

EIA document including based on such environmental management plan, if


any;
 The protection of the heritage (historical & cultural) environment, as the
legacy of the past generation, is part of such EIA study & approval process;
 Human Environment
 The human environment may have three dimensions:
 the labor & staff of the contractor or contractor’s personnel as
defined; see Clause 1.1.2.7 cum Clause 4 cum 6.7 MDB-FIDIC; the
employer personnel; see as defined; see Clause 1.1.2.6 cum 18.3 MDB-
FIDIC;
 the general public; see the relevant applicable laws;
 the end user of the completed project;
 The safety obligation of the contractor as to its staff & labor (its personnel
broadly) is both contractual & legal; see the contract of employment cum the
applicable laws & regulations; for its own staff & labour; and contractual as
related to its sub-contractors; see Clause 4 MDB-FIDIC;
 The safety obligation of the contractor as to the employer’ s personnel is
contractual; see Clause 1.1.2.6 cum Clause 18.3 MDB-FIDIC;
 The safety obligation of the contractor towards the general public is legal;
the Civil Code shall apply as related to its extra-contractual liability; see
Article 2027-2161 of the Civil Code; plus see also Proc. No. 624/2009 as
related to building projects;
 Built-Environment
 The built-environment may encompass the following six dimensions:
 the permanent water works under construction by the contractor;
 any neighboring structure or work proximate to the water works
project under construction;
 any road or bridge or any other work or structure off the project site;
 the property of the contractor on site intended for the execution of the
permanent works (i.e., the construction materials &
equipments/plant);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 69
Training Material on Construction Contract Management

 the property of the employer brought to the project site for the
execution & completion of the permanent works;
 the property of other persons;
 Ensuring safety to the permanent works under construction is the clear
contractual obligation of the contractor; see Clause 4.8 cum Clause 18.2
MDB-FIDIC;
 Ensuring safety to the neighboring structures, if any, is the legal obligation
of the contractor, as well; see Civil Code Article 2027 ff cum Building Proc.
No. 624/2009;
 Ensuring safety of the road & bridges and any other work or structure (in
the country) is the contractual & legal obligation of the contractor;
 see Clause 4.14, 4.15 cum 4.16 MDB-FIDIC cum Civil Code Article 2027 ff
cum Building Proc. No. 624/2009;
 Ensuring safety to its property & the property of the employer is mainly
contractual but also legal;
 Ensuring the safety of the property of other persons is mainly legal but also
contractual;
 see Clause 18.3 MDB-FIDIC; and Article 2027 ff of the Civil Code;
 Utilities Environment
 Public utilities may have the following four dimensions:
 water supply network;
 waste water network;
 electric power network;
 telecommunications network;
 Ensuring safety to such utility lines is the legal obligation of the contractor;
 The employer is also expected during planning & design phase to secure
complete & adequate information (like benchmarks) as to their location &
specific alignment and to give due consideration in the design document;
 The following applicable laws may apply to establish the legal liability of the
contractor and/or the employer:
 Power & Telecommunications networks:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 70
Training Material on Construction Contract Management

 see Proc. No. 464/2005 cum the Civil Code Article 2027 ff cum Proc.
No. 624/2009 (Ethiopian Building Proclamation) cum Reg. No.
243/2011 (building regulation);
 Water supply networks and/or any hydraulic structure & waste water
networks:
 see Proc. No. 10/1995 (issued by the Addis Ababa City Government)
cum Civil Code Article 2027 ff cum Proc. No. 624/2009 (Ethiopian
Building Proclamation) cum Reg. No. 243/2011 (Ethiopian Building
Regulation);
 The construction method statement meant for ensuring safety & serves as
risk management tool at the construction project site;
 see Clause 4.1 MDB-FIDIC: the contractor is expected to ensure the safety of
its construction operations!
1.2 Obligations of the Employer
 Background
 The employer shall have many obligations under like the water works
construction contract;
 The obligation of the employer has two dimensions: consideration & promise
dimensions:
 The consideration dimension relates to its payment obligation whereas other
obligations of the employer are its promise obligation;
 The duly performance of such obligations are thus formidable ground for the
successful mobilization, commencement, execution & completion of the water
works construction project under consideration;
 The following are some of the fundamental obligations of the employer under
the construction contract:
 appointing the Engineer; NB: Key consideration for the Corporation
as supervision consultant;
 payment of the contract price;
 design related obligations;
 site related obligations;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 71
Training Material on Construction Contract Management

 takeover related obligations;


 Appointment of the Engineer
 see Clause 3.1-3.5 MDB-FIDIC; cum the Engineer
 see Clause 1.2 (n) MDB-FIDIC cum the Site
 see Clause 12 cum Clause 14 MDB-FIDIC cum the Measurement & Payment
 see Clause 12: Engineer & Engineer Representative; of PPA 2011;
 see also the applicable laws; like Article 1675 cum 2632-2638 cum 2610-2631
of the Civil Code as related to the contract between the engineer & the
client;;
 see also the applicable laws; like Article 2632-2638 cum 2179-2265 (Law of
Agency) of the Civil Code as related to the role of the consultant;
 see all the applicable laws: Article 2632 (3) cum all relevant special laws as
related to the role of the consultants;
 The modern construction project management necessarily requires the role
of the Engineer;
 This is very true specially in case of design-bid-build project delivery sub-
system;
 For the Engineer to play its agent & professional role, the employer is
required under the construction contract to appoint such Engineer;
 The Engineer, in effect, is required for the following purposes:
 for continuous design & design related function;
 for project supervision;
 for contract administration; and
 for claims determination;
 The non-appointment of the Engineer by the employer will endanger the
smooth mobilization, commencement, completion and remedying of the
works and the certification of payment to the contractor;
 This may lead to delay in construction; delay or non-payment in the
construction process for which the contractor being entitled to claim under
the contract;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 72
Training Material on Construction Contract Management

 The Engineer discharges its expected professional and managerial functions


directly by itself, through assistants and/or by securing specific approvals
from the employer;
 The action of the Engineer which requires the prior specific approval from
the employer shall be specified in the special conditions of contract;
 The following are some of the actions which require the approval of the
employer as provided under the general conditions of contract; viz.,
 claim related: extension of time and/or additional cost;
 variation related: instructed variation;
 variation related; approved variation;
 currencies related: on the extent of applicable currencies;
 The Engineer shall discharge its duties within a given time scale;
 The contractor is bound to comply with the instructions of the Engineer;
 Design Management
 Background
 Design is one of the critical inputs to the construction process;
 Even if during the design phase the design for such construction project has
been prepared, the employer still need continuous design and/or design
related services from a professional;
 that professional is now the Engineer as supervision consultant;
 During construction phase, therefore, we have to identify the contractual role
& liability of the employer, the designer & the contractor as related to
design;
 The Employer
 Under design-bid-build project delivery sub-system, it is certain that the
design is done through a professional designer;
 It becomes thus the contractual matter between the design professional & the
client (now the employer under the construction contract);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 73
Training Material on Construction Contract Management

 Since there is no contractual relationship between the designer & the


contractor, the contractual obligation for design vis-à-vis the contractor rests
with the employer;
 Therefore, the employer is obliged under the construction contract, through
the Engineer, to provide design information & instruction;
 Should there be any failure in providing such design information or working
drawing, it is the contractual obligation thus liability of the employer to pay
for the consequences like in case of delay in issuing drawings to the
contractor; see Clause 1.9 MDB-FIDIC;
 The Engineer
 The Engineer, as supervision consultant, continues its design & design
related obligation under its contract agreement with the client;
 The Engineer serves as the source of design information, clarification in this
regard;
 The obligation of the employer towards the contractor as related to design
information & clarification remains with the employer;
 The Engineer is professionally liable for design error and/or omission under
the applicable law based on the principle of skill & care and professional
diligence then; if that diligence not achieved becomes the ground for
professional negligence;
 see Article 2636 cum 2031 of the Civil Code;
 The Contractor
 The contractor, in terms of its legal status, is a professional;
 Its design related obligation of the contractor may be seen from two
perspectives: temporary & permanent works;
 Temporary Works:
 The first & obvious design obligation of the contractor comes as
related to temporary works;
 the contractor is responsible for the design & construction of
temporary works including its adequacy;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 74
Training Material on Construction Contract Management

 see Clause 1.1.5.7 MDB-FIDIC;


 Permanent Works:
 During construction phase, the contractor may have certain design
related obligations & therewith possible design liability as related to
permanent works; see Clause 1.1.5.4 MDB-FIDIC
 This could be revealed in the following three instances: viz., as related
to: partial design; and substantial design; duty to notify design error;
 Partial Design: Clause 4.1 MDB-FIDIC
 if the contractor is required under the contract, it may design part of
the permanent works;
 in such a case, the contractor shall become liable for such design
based on the principle of design liability fit for its reasonable purpose
intended; see Clause 4.1 (c) MDB-FIDIC
 Fitness for purpose design liability is the highest level of design
liability as opposed to design liability based on skill & care and
diligence;
 Substantial Design: Clause 13.2 MDB-FIDIC
 The contractor may propose, by its own initiative or otherwise, and
the Engineer may approve the design of the contractor under the
concept of value engineering;
 In such a case, the contractor shall become liable for such design to fit
for its reasonable purpose intended; see Clause 13.2 (b) cum 4.1 (a)-
(d) MDB-FIDIC;
 Fitness for reasonable purpose design liability is the highest level of
design liability standard as opposed to design liability based on skill &
care and diligence; 13.2 cum 4.1(c);
 see also Article 2622 (Warranty against Defects i.e., as related to
works) cum
 see also Article 2287-2300; 2332; 2344-2346 of the Civil Code as
related to private construction contract; which provisions regulating

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 75
Training Material on Construction Contract Management

the “fitness for reasonable purpose” legal requirement for the works
like road or dam or building;
 Duty to Notify Problems in Design or Specification
 MDB-FIDIC has no specific clause regulating this possible obligation
of the contractor;
 FIDIC 4th incorporates such clear contractual obligation; see Clause
8.1 (Contractor’s General Responsibilities);
 part of the sub-clause reads, as follows;
 The Contractor shall give prompt notice to the Engineer, with a copy
to the Employer, of any error, omission, fault or other defect in the
design of or Specification (see Sub-clause 1.1 (b) (ii) for the Works(see
Sub-clause 1.1 (f) (i) (ii));) (i.e., Permanent Works i.e., the road or
bridge) which he (i.e., the Contractor as defined under sub-clause 1.1
(a) (ii)) discovers when reviewing the Contract (see Sub-clause 1.1 (b)
(i) or executing the Works (see sub-clause 1.1 (f) (i) (ii)); (Emphasis
added);
 Site Related Obligation & Management
 see Clause 1.1.6.7 Site cum 2.1 Right of Access to the Site; Clause 8.3:
Program; Clause 8 Extension of Time; MDB-FIDIC;
 see Sub-clause 1.2 (ee) Site cum Clause 31: Access to the Site; Clause 41:
Program of Implementation of Tasks; Clause 74: Compensation Events for
Allowing Time Extensions Clause 77: Early Warning; PPA 2011;
 see all relevant applicable laws; like
 Proc. No. 1/1995 the FDRE Constitution;
 the Civil Code Article 1460-1488 Expropriation Proceeding;
 the federal Rural Land Administration related Laws; like Proc. No.
455/2005; Proc. No. 456/2005; and
 the respective regional states rural land administration laws;
 the Urban Land Administration related Laws; see Proc. No.
721/2011;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 76
Training Material on Construction Contract Management

 see the respective urban setting master plan or structure plan or local
development plan; and the respective zoning or planning laws of each &
every urban setting & urban administration;
 see the Rural & Urban Land acquisition & compensation related Laws;
regulations; directives; and guidelines; Proc. No. 456/2005 cum Reg. No.
135/2007; re: as related to farmers (as to their land, plants); pastoralists;
urban dwellers (as to land, houses, fences); utilities; and so forth
 the employer may require to undertake a socio-economic study including a
Resettlement Action Plan (RAP) to fully address all these complex issues;
 Background
 The most critical aspect of construction project management issues is related
to providing the required possession site and access thereto by the employer
to the contractor;
 Providing the site to the contractor is mainly dependent on the contractor’s
program;
 Based on such program and based on the nature of the project, the site is to
be provided to the contractor at once or from time to time;
 To acquire all relevant site for the project under consideration, there are
some defined legal requirements to be fulfilled by the employer unless the
project is legally exempted from to undergo such legal requirements;
 Concept
 Site is defined (see Clause 1.1.6.7) as the places where the permanent works
are to be executed, including storage and working areas, and to which Plant
& Materials are to be delivered, any other places as may be specified in the
Contract as forming part of the Site;
 The scope of site could be too broad; it may thus include the following for the
purpose indicated;
 site for the permanent work itself and access thereto; say for the dam;
groundwater development; pipe installation/laying (transmission
and/or distribution); other hydraulic structures; building; road;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 77
Training Material on Construction Contract Management

 site for camp establishment and access thereto;


 site for temporary works; like detour…; re: access road;
 site for quarry development and access thereto;
 site for storage and access thereto; for construction plant, materials
including some specified goods like explosives, consumables…;
 site for dumping construction debris (i.e., for cart away) and access
thereto;
 site for any other project related purposes and access thereto;
 Site by itself may not serve its purpose unless there is a right to access to the
designated project site;
 The site so provided to the contractor will remain, contractually, within the
possession right of the contractor; nobody is allowed to enter in to the site
without the permission or prior approval of the contractor except for those
employer’s personnel designated under the contract;
 The contractor is required under the contract to return back the site upon
completion of the project and/or the termination of the contract;
 Legal Requirements
 In Ethiopia both rural & urban land is a public property since 1975;
 There are rural & urban land management laws based on the FDRE
Constitution;
 Some defined legal requirements may be important for the acquisition of
land (site in its broadest sense) unless there is a legal exemption there from:
 following planning & zoning requirements, if applicable for the
project; see Clause 1.13 cum 2.2 MDB-FIDIC
 following land acquisition procedure, if applicable for the project;
 effecting some payment as related to (rural and/or urban) land
acquisition, if any, if applicable; and
 payment of compensation for the properties situated within the
project site/land, if applicable for the project;
 These are regulated respectively by rural & urban land management laws
and payment of compensation as related thereto;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 78
Training Material on Construction Contract Management

 All obligations as related to site acquisition of land has to be complied with


by the employer in due time;
 Site Related Problems
 Site, as defined, is a physical pre-requisite and a critical input to the
construction project; see Clause 8.1 cum 2.1 MDB-FIDIC;
 The legal obligation of the employer has to be discharged before the actual
construction implementation begins i.e., during project planning, study &
design phases;
 Site plus access thereto is required for the following purposes during project
implementation period like under the road construction contract:
 to mobilize the project; like for project camp establishment;
 to commence the project; for the permanent & temporary works;
 to progress with the project; for the temporary, permanent works
plus for quarry site and so forth;
 to complete the project;
 If the employer, based on the contractor’s program, if any, fails to provide
the site & access thereto, the project may suffer delay for which the employer
is contractually liable to compensate the contractor in terms of time and cost
plus profit; see Clause 2.1 MDB-FIDIC;
 Takeover Management
 see & consider the various clauses of the MDB-FIDIC as related to Take
Over & the provisions of the Civil Code as related to Acceptance of Works;
plus the PPA 2011;
 that is the contractual and/or legal ground for takeover management;
 MDB-FIDIC 2006
 see Clause 1.1.3.5 definition of Takeover Certificate; cum
 see Clause 4.1 (d) (re: as-built documents) cum ;
 see Clause 4.21 Progress Reports cum
 see Clause 4.23 Contractor’s Operations on Site cum
 see Clause 6.10 Records of Contractor’s Personnel & Equipment cum

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 79
Training Material on Construction Contract Management

 see Clause 8.2 (b) Time for Completion cum


 see Clause 8.4 Extension of Time for Completion; cum
 see Clause 8.7 Delay Damages; cum
 see Clause 1.1.3.4 (re: definition of Tests on Completion) cum 9.4 (c)
(Failure to Pass Tests on Completion) cum
 see Clause 10.1 (Taking Over of Works & Sections) cum
 see Clause 10.2 (Taking Over of Parts of the Works) cum
 see Clause 10.3 (Interference with Tests on Completion)cum
 see Clause 10.4 (Surfaces Requiring Reinstatement) cum
 see Clause 11.1 Completion of Outstanding Work & Remedying
Defects cum
 see Clause 11.3 (Extension of Defects Notification Period) cum
 see Clause 13.1 (Right to Vary) cum
 see Clause 14.2 (Advance Payment re: fate of the advance payment
not fully repaid up on the issuance of the Taking Over Certificate)
cum see also Article 3271 of the Civil Code (settlement vs.
installment);
 see Clause 14.4 (Schedule of Payments re: last paragraph related to
Taking Over Certificate) cum
 see Clause 14.6 (Issue of Interim Payment Certificate) (re: TOC its
correlation with minimum level of works executed for IPC purpose)
cum
 see Clause 14.9 (Payment of Retention Money) (re: effects of TOC;)
cum
 see Clause 14.10 (Statement at Completion) (re: effects of issuing
TOC) cum
 see Clause 14.14 (Cessation of Employer’s Liability) (re: effects of
issuing TOC as related to preserving the payment rights of the
contractor for works executed after issuing the TOC & final payment
certificate) cum

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 80
Training Material on Construction Contract Management

 see Clause 17.2 (Contractor’s Care of the Works) cum i.e., the
Permanent Works see Clause 1.1.5.4 (re: effects of issuing TOC &
cessation of contractor’s obligation to take care of the Works) re: the
CPA has to be considered here; cum
 see Clause 17.7 (Use of Employer’s Accommodation/Facilities) (re:
effects of issuing TOC on the obligation of the contractor as to such
facilities) cum
 see Clause 18.2 (Insurance for Works & Contractor’s Equipment); re:
effects of issuing TOC on the cessation of the contractual obligation
of the contractor to insure against such assets;
 PPA 2011
 see Clause 84: General Principles (for Acceptance)
 see Clause 85: Tests on Completion
 see Clause 86: Partial Acceptance
 see Clause 87: Provisional Acceptance
 see Clause 88: Defects liability
 see Clause 89; Final Acceptance
 see also Clause 58.8 Performance Security (re: discharging the security to
the contractor);
 see also Clause 61.3: Retention Money (re: release of the retention money);
 see Clause 65: Final Statement of Account (re: following final acceptance
preparing final accounts by the contractor cum Clause 89);
 Civil Code
 see Article 3274-3281 (Acceptance of Works); re: related to public
construction contract;
 see also Art. 2002: Means of Evidence; re: presumptive takeover;
 Background
 One of the fundamental obligation of the employer under the construction
contract is to take over (accept) the permanent works (the Project) from the
contractor;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 81
Training Material on Construction Contract Management

 There are however certain pre-conditions to be fulfilled on the part of the


contractor and the Engineer for takeover of the permanent works by the
employer;
 Takeover of the works also bring some important contractual & legal effects
as between the employer & the contractor;
 Concept & Types
 Takeover of the permanent works by the employer, based on scope, may take
two forms; see Clause 10.1 cum 10.2 MDB-FIDIC;
 sectional takeover, if any; or
 whole work takeover;
 Takeover of the permanent works by the employer may take, based on time,
two forms:
 provisional (acceptance) takeover (effected through issuing TOC by
the Engineer); see Clause 10 MDB-FIDIC; and
 final takeover (acceptance) (effected through issuance of DLC by the
Engineer); see Clause 11 MDB-FIDIC;
 As per the applicable law, provisional acceptance is a joint ascertainment of
the works made immediately after completion of the works; see Article 3274
of the Civil Code;
 As per the applicable law, final acceptance is the act whereby the employer
definitively appropriate the works after having ascertained that the
contractor has performed his obligations in its entirety;
 see Article 3279 of the Civil Code; Final Acceptance
 Takeover of permanent works, based on its legitimacy, may take two forms:
viz.,
 actual takeover (based on issued TOC); or
 presumptive takeover (based on non-issuance of TOC); see Clause
10.1 (final paragraph for presumptive takeover) MDB-FIDIC;
 Takeover is to be effected through a formal document known as a Taking
Over Certificate to be issued by the Engineer to the contractor;
 see Clause 1.1.3.5 MDB-FIDIC;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 82
Training Material on Construction Contract Management

 Pre-conditions
 For the permanent works to be taken over by the employer the following pre-
conditions have to be fulfilled; viz.,
 completion: in terms of scope, the works have to be completed; see
Clause 10.1 MDB-FIDIC
 as-built documents: the contractor shall submit as-built documents for
the tests to be undertaken;
 tests: the works have to pass tests on completion; see Clause 9.1
through Clause 9.3; MDB-FIDIC;
 request: the contractor has to request for the issuance of the taking
over of the works; and see Clause 10.1 MDB-FIDIC;
 determination/presumption: the Engineer determined that the works
are completed & passed their tests on completion & thus issued
Taking over Certificate to the contractor or the contract takes
presumption in favor of issuance of such certificate; see Clause 10.1
MDB-FIDIC
 The contractor has to complete the works in accordance with the contract;
see Clause 8.2;
 The extent of completion may not be absolute; it suffices to be substantial or
reach to the level of practical completion, which is subjective to be
determined by the Engineer, however;
 Tests on completion have to be passed by the works as defined in the
contract; retesting may also be required;
 The contractor has to request for takeover of the works by the employer
upon the issuance of taking over certificate by the Engineer; it is the
obligation of the employer to take over the works;
 The Engineer determines, based on the request of the contractor, whether or
not the works have been completed & the required tests on completion have
been passed by the works;
 The scope of takeover of the works by the employer may relate to the whole
of the works or section thereof;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 83
Training Material on Construction Contract Management

 If all such pre-conditions have been fulfilled, the works are to required,
actually, to be taken over by the employer or the contract takes a presumption
in favor of takeover of the works by the employer;
 Takeover
 Takeover of the works, in whole or in part, shall be effected through Taking
Over Certificate or by such presumption;
 Then the employer said legally has taken over the works;
 Effects
 The following legal and/or contractual effects shall result from due to actual
or presumptive takeover or otherwise thereof; viz.,
 risk: It shifts the risk as related to the works from the contractor to the
employer; see MDB-FIDIC Clause 17.2; see also Clause 17.7 as related to
contractor’s obligation with respect to employer’s accommodations or
facilities for which the contractor being obliged to take responsibility up to
the issuance of the takeover certificate;
 insurance: up on issuance of the taking over certificate the contractor’s
obligation to insure the following shall cease; the Permanent Works; the
contractor’s Plant; Materials & Contractor’s Documents; see Clause 18.2
MDB-FIDIC;
 defects liability: It marks the commencement of defects liability period or (so
called maintenance period) or defects notification period, within which time
frame the contractor being obliged to remedy defects in the works;
 retention: It triggers the release of half of the retention money to the
contractor; see Clause 14.9 2 MDB-FIDIC;
 balance retention; the issuance of the defects liability period after the defects
notification period shall trigger the release of the balance of the retention
money to the contractor; provided that where there was no retention security
arrangement; see Clause 14.9 2 MDB-FIDIC;
 retention security; It may trigger the deposit of retention money security (for
the balance 50%) by the contractor; see Clause 14.9 MDB-FIDIC;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 84
Training Material on Construction Contract Management

 site clearance; the contractor is required to clear the site up on issuance of


such certificate; see Clause 10.4 MDB-FIDIC;
 delay damages: the issuance of taking over certificate shall cease the
assessment of delay damages against the contractor, if any or may result the
reduction of same; see Clause 10.2 MDB-FIDIC;
 variation: the issuance of taking over certificate marks the time for not
issuing any variation order by the Engineer to the contractor; see Clause 13.1
MDB-FIDIC;
 advance payment; if the advance payment has not been repaid before the
issuance of Taking over certificate, the whole of the balance then
outstanding, if any, shall become due to the employer; see Clause 14.2 MDB-
FIDIC cum Article 3271 of the Civil Code;
 statement at completion; (after 84 days) of the issuance of the Taking over
Certificate shall trigger the submission of statement at completion by the
contractor; see Clause 14.10 cum 14.14 MDB-FIDIC;
 operation: the provisional acceptance triggers the use (operation) of the
works as completed by the employer;
 defects liability; the final takeover of the works releases the contractor to
remedy defects; Article 3281of the Civil Code;
 legal warranty; the final takeover or possession of the works triggers the
commencement of the legal warranty period for the works as related to
construction; see Article 3282 of the Civil Code; as related to public
construction contract like road construction;
 Takeover Related Problems
 Problems with respect to takeover may originate from the following three
sources;
 from the contractor;
 from the employer; and
 from the Engineer;
 From the contractor: see Clause 9.4

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 85
Training Material on Construction Contract Management

 Contractor related problems as related to takeover may come from


failure to pass tests on completion including repeated tests on
completion of the works;
 If the works fail to pass tests (plus repeated tests) on completion the
following alternative but serious contractual consequences may result;
see Clause 9.4 MDB-FIDIC; namely;
 ordering further retesting;
 rejection of the works in whole or in part; and
 reducing the contract price by issuing takeover certificate;
 From the Employer: see Clause 10.1 MDB-FIDIC
 The other problem as related to takeover is refusal on the part of the
employer to take over the works;
 this problem has been resolved contractually through presumptive
takeover;
 From the Engineer: see Clause 10.1 MDB-FIDIC
 The problem as related to takeover may come from the Engineer in
rejecting the issuance of the takeover certificate;
 This problem may be encountered by the contractor where the
Engineer takes a position viz., either the works are not completed in
accordance with the contract or to its satisfaction or the works are not
completed substantially;
 This problem has been resolved contractually through presumptive
takeover;
 Payment Management
 contractual and/or legal information;
 MDB-FIDIC 2006
 see Clause 1.1.1.9 Bill of Quantities; re: definition cum
 see Clause 12 Measurement & Evaluation “valuation?” cum
 see Clause 1.1.4.1 Accepted Contract Amount cum
 see Clause 1.1.4.2 Contract Price cum; re: definition
 see Clause 1.1.4.9 Payment Certificate; re: definition cum

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 86
Training Material on Construction Contract Management

 see Clause 1.1.4.7 Interim Payment Certificate; re: definition cum


 see Clause 14 Contract Price & Payment;
 see Clause 14.2: Advance Payment;
 see Clause 14.3: Interim Payment;
 see Clause 1.1.4.4 Final Payment Certificate; re: definition cum
 see Clause 1.1.4.6 Foreign Currency;
 see Clause 1.1.4.8 Local Currency; re: definition cum
 see Clause 15.4 Payment After Termination;
 PPA 2011
 see Clause 32: Payment cum
 see Clause 59: General principles (re: payment) cum
 see Clause 60: Advance Payment cum
 see Clause 61: Retention Monies cum
 see Clause 62: Price Adjustment cum
 see Clause 63: Valuation of Works cum
 see Clause 64: Interim Payment cum
 see Clause 65: Final Statement of Account
 see Clause 66: Direct payment to Sub-contractors
 see Clause 67: Delayed Payments cum
 see Clause 68: Payments to Third Parties cum
 see Clause 69: Claims for Additional Payment
 Civil Code
 see Article 1678 (b) cum 3261-3273 Payment of Price;
 see also Article 2623; as related to the doctrine of entire contract;
 Other Laws
 see also the specific fiscal year (federal) budget law;
 see the specific fiscal year (regional) budget law;
 see the specific fiscal year (city administration) budget law;
 see the (federal) financial administration laws (like Proc. No.
648/2009) plus its amendments;
 see the (regional) financial administration laws;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 87
Training Material on Construction Contract Management

 see the financial administration laws of a given city administration;


like the City of Addis Ababa;
 see the (federal) procurement laws (see Proc. No. 649/2009) &
procurement directives;
 see the (regional) procurement laws & procurement directives, if any;
 see specific relevant legal instrument ratifying finance (like loan or
aid) from international (bilateral or multilateral) source; and consider
their various legal implications on the Project;
 Background
 One of the fundamental obligations of the employer is payment obligation;
 This obligation provides us the consideration dimension of a construction
contract; see Article 1678 (b) of the Civil Code;
 Payment could be in cash or in kind;
 Payment in cash is the usual way of remunerating the contractor under the
construction contract; see Article 1678 (b) cum 3244 of the Civil Code;
 As per the applicable law, as related to private contracts, the employer is
obliged to pay to the contractor if the contractor completes the whole of the
works or section thereof and if the employer accepts such work, in whole or
in part; see Article 2623 of the Civil Code;
 Completion of the works & acceptance of such works are, therefore, the pre-
conditions for payment or for the contractor to have a mature right to
payment;
 This is related to the broad concept or doctrine of entire contract;
 In the modern construction contract there are different ways of determining
the pricing mechanism under the contract: viz., quantity based; lump sum;
or cost plus;
 Types
 MDB-FIDIC identifies the following three types of payments; viz.,
 advance payment;
 interim payment; and

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 88
Training Material on Construction Contract Management

 final payment;
 Advance Payment
 see Clause 14.2 MDB-FIDIC;
 see also Article 3271 of the Civil Code
 paid by the employer to the contractor against the submission of an
unconditional bank guarantee by the contractor;
 deducted from each and every interim payment certificate till its full
repayment;
 its purpose being for project mobilization;
 its management may be left totally to the contractor or may be
subjected to joint management both by the employer & the
contractor;
 Interim Payment
 see Clause 12 (Measurement & Evaluation) cum 14.3 ff (Payment of
the Contract Price) MDB-FIDIC;
 see Clause 59-69 PPA (2011); Payments to the Contractor
 see also Article 3269 & 3270 of the Civil Code; re: Payment
 the interim payment certificate reflects the quantities so executed
under the contract by the contractor;
 the certificate is subjected to measurement (based on the Drawing) &
valuation process based on quantities jointly recorded on site (related
to the BOQ); see Clause 12 MDB-FIDIC; and quality (against the
specification;)
 the certificate is prepared & processed monthly provided the agreed
threshold has been met which has to be stated in the special conditions
of contract (or Contract Data);
 the certificate may be subjected to possible corrections by the
Engineer;
 the certificate is not considered as approval of the works done; that is
left to the final payment certificate;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 89
Training Material on Construction Contract Management

 Final Payment
 see Clause 14.11 ff MDB-FIDIC cum
 see Clause 65 of the PPA (2011);
 see also Article 3272 & 3273 of the Civil Code;
 the preparation of final payment certificate shall follow the format &
procedure acceptable to the Engineer;
 Purpose: if such certificate has been prepared & executed, it settles
all the financial balance between the employer & the contractor;
 Purpose: such certificate considered as declaration of the final
approval of the works & satisfaction of the Engineer;
 Therefore, both the employer & the contractor have to include any
payment and/or that they may request or demand (claim) from the
other in such certificate;
 The failure to include such financial requests (in terms of payment
and/or claim) may lead to the loss (waiver) of such financial right
under the contract due to the finality of such certificate;
 Effects: such certificate thus may have the following legal effects;
o On the contractor: waiver of its financial right not duly
included in such certificate;
o On the employer: waiver of its financial right not duly included
in such certificate;
o On the Engineer: loss of contractual power under the contract
between the employer & the contractor (called ex officio
effect);
 There may be some exceptions to the finality of such final payment
certificate: like fraud or double payment; or work executed by the
contractor after issuance of the final payment certificate;
 interim payment & disputes: due to disputes related to such final
payment certificate, the Engineer is required to issue an interim
payment certificate for sums agreed between the employer & the
contractor; the balance under the final payment certificate being

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 90
Training Material on Construction Contract Management

subjected to dispute resolution process; see Clause 14.11 MDB-


FIDIC;
 Payment Related Problems
 Payment related problems may originate from three sources:
 from late certification or partial certification (i.e., as related to
measurement related problems) by the Engineer;
 from late or non-payment by the employer and other grounds;
 from lack of financing arrangement or disbursement under the loan
or aid;
 To maintain & improve the cash flow of the contractor, discharging the
payment obligation of the employer is so critical;
 If there is any delay in payment or non-payment at all, the contractor may
have certain less critical and critical remedial rights against the employer
under the contract;
 Such less critical remedial right may include demanding interest or financing
charges for late payment from the employer; see Clause 14.8 MDB-FIDIC;
 see also Clause 67 of the PPA (2011); delayed payments
 Critical remedial rights available to the contractor may include the
following; viz.,
 deceleration or reduction of the progress of the works by the
contractor; see Clause 16.1 MDB-FIDIC;
 suspension of the works by the contractor; see Clause 16.1 MDB-
FIDIC; and if the contractor resumes work after suspension the
employer is required to entitle the contractor extension of time and
additional cost plus profit; see Clause 16.1
 termination of the contract by the contractor; see Clause 16.2 MDB-
FIDIC;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 91
Training Material on Construction Contract Management

Common Obligations:
Cost Related Obligations & Management
 the following contractual clauses & legal provisions provide the basis for cost management;
 MDB-FIDIC 2006
 see Clause 1.1.4.1: Accepted Contract Amount re: definition
 see Clause 1.1.4.2: Contract Price re: definition
 see Clause 1.1.4.3; Cost: re: definition
 see Clause 2.5 Employer’s Claims;
 see Clause 4.10; Site Data;
 see Clause 4.11; Sufficiency of Accepted Contract Amount;
 see Clause 4.12; Unforeseeable Ground Conditions);
 see Clause 13.1; Variation (re: instructed variation);
 see Clause 13.7 Adjustment for Changes in Legislation;
 see Clause 13.8 Adjustment for Changes in Cost;
 see 4.11 Sufficiency of Accepted Contract Amount;
 see Clause 14.1; The Contract Price; re: as related to IPCs;
 PPA 2011
 see Clause 16: Changes in Laws & Regulations (re: no cost adjustment in
principle;)
 see Clause 62: Price Adjustment (subject to stated conditions);
 see Clause 69: Claims for Additional Payments
 Civil Code
 see Article 3261-3273 Payment of Price;
 see Article 3183-3189 Unforeseen Circumstances;
 see Article 3190-3193 Act of Government; cum Article 1767 (re: variation of
contract; re; contract with public administration;);
 Background
 One of the project performance criterion will be completion of the project
within the budget allocated;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 92
Training Material on Construction Contract Management

 The project cost may relate to everything from its capital cost to its operation
& maintenance cost;
 All relevant factors during the various phases of the project may contribute
also to the cost effectiveness or otherwise (i.e., cost overrun) of the project;
 During tendering phase, for example, the cost estimate to be done by the
future contractor has to consider the following cost relevant factors: see
Clause 4.10 Site Data; 4.11 Sufficiency of Accepted Contract Amount MDB-
FIDIC;
 source: sub-contractor’s quotation; quantity takeoffs; and
construction procedure;
 caution: knowledge on the current market prices information (for
materials; labor; equipment; consumables;) is essential;
 caution: pre-bid site visit for bid estimate is necessary to see problems
ahead of time which may have possible cost implications;
 Otherwise, the accepted contract amount deemed to include all costs of the
contractor under the contract; see : see Clause 4.10 (Site Data); 4.11
(Sufficiency of Accepted Contract Amount) MDB-FIDIC;
 Concept
 The concept of cost as defined in the contract document (MDB) reads;
 cost means all expenditure reasonably incurred or to be incurred by the
contractor whether on or off the site, including overhead & similar charges,
but does not include profit;
 Causes for Cost Overrun
 Conceptually, as related to the construction phase, cost overrun means the
difference between the accepted contract amount & the final contract price;
 The final contract price includes all allowable adjustments (see Clause
1.1.4.2: (Contract Price) cum Clause 14.1 (a) MDB) that the project has
experienced during its implementation phase;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 93
Training Material on Construction Contract Management

 The following may be taken as factors to contribute to the cost overrun of the
construction project during construction phase to determine the final
contract price: viz., market; nature; government; parties;
 market driven factors (inflation); as related to labor, material and/or
equipment;
 nature driven or act of God factors: adverse or unforeseen grounds
condition or other events of forces of nature;
 act of government factor; like change in legislation; regulatory
requirement change;
 contracting party driven factors: two factors: viz., variation & claims;
 The contract price said to include all tax obligation of the contractor; see
Clause 14.1 (b) MDB-FIDIC;
 Due to its nature quantity-based contract may not have certain or fixed
contract price from the beginning, as related to quantities;
 Categories of Cost
 Based on the definition given to cost, the following two categories of cost
emerge; direct & indirect
 Direct cost means the category of cost which represents the cost of the core
permanent or physical works comprising the following;
 material cost;
 labor cost;
 machine/plant cost; and
 sub-contractors cost (to the main contractor);
 Indirect cost means costs other than direct cost which include the following;
viz., overhead costs & risk costs
 overhead costs: project on site costs & project head office (off site)
costs;
 risk costs: corporate taxes; risk allowances & insurance related costs;
 Implications
 The definition of cost & categorization of same in to direct & indirect may
bring the following implications: contractual & legal;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 94
Training Material on Construction Contract Management

 Contractual implications:
 delay claims: to determine the type & assessment of the extent of costs
recoverable from the employer by the contractor as related to its
delay claims; it may cover both the idle costs of the contractor as
related to direct & indirect costs;
 disruption claims: to determine the type & assessment of the extent of
costs recoverable from the employer by the contractor; disruption
claim may only cover the direct cost and from this only idle labor &
equipment cost, as related to loss of productivity of such resources;
 profit claim: unless specifically provided under the contract, profit
claim is excluded from the definition of cost; see for example the
following MDB clauses which entitle the contractor to profit claim:
 Legal implications:
 quantum duty: even if the contractor may be entitled to recover some
costs from the employer, it is legally obliged to minimize the extent of
damage;
 see Article 1802 of the Civil Code; this legal obligation applies in all
other relevant types contractor’s claims;
Common Obligations:
Risk Sharing Obligations & Management
 the following contractual clauses from the MDB-FIDIC & provisions from the Civil Code
may show the sole assumption of risk or sharing of risk by the contracting parties;
 MDB-FIDIC 2006
 see Clause 3.1 Engineer’s Duties & Authority cum
 see Clause 4.10 Site Data cum
 see Clause 4.13 Rights of Way & Facilities cum
 see Clause 4.19 Electricity, Water & Gas cum
 see Clause 4.20 Employer’s Equipment & Free-Issue-Materials cum
 see Clause 8.6 (Rate of Progress) MDB-FIDIC cum
 see Clause 9.2 Delayed Tests cum
 see Clause 11.2 Cost of Remedying Defects cum

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 95
Training Material on Construction Contract Management

 see Clause 11.6 Further Tests cum


 see Clause 15.4 Payment After Termination cum
 see Clause 17.2 Contractor’s Risks cum
 see Clause 17.3 Employer’s Risks cum
 see Clause 17.4 Consequences of Employer’s Risks cum
 see Clause 17.5 Intellectual & Industrial Property Rights cum
 see Clause 17.6 Limitation of Liability cum
 see Clause 18.2 Insurance for Works & Contractor’s Equipment cum
 see Clause 18.3 Insurance against Injury to Persons & Damage to Property
cum
 see Clause 19.6 Optional Termination, Payment & Release;
 PPA 2011
 see Clause 16: Changes in Laws & Regulations
 see Clause 18: Force Majeure
 see Clause 27: Liquidated Damages (re: direct deduction of such damages by
the employer);
 see Clause 31: Access to the Site
 see Clause 40: Insurance to be Taken by the Contractor
 see Clause 43: Sufficiency of Bid Prices
 see Clause 44: Exceptional Risks
 see Clause : 49: Setting-out the Works
 see Clause : 67: Delayed Payments
 Civil Code
 see Article 1792-1794: Force Majeure
 see Article 3177: no sanction against the public employer if no payment
effected by same;
 see Article 3183-3189 Unforeseen Circumstances; cum
 see Article 3190-3193 Act of Government; cum
 see Article 1767: re: variation of contract; contract with public
administration;);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 96
Training Material on Construction Contract Management

 Commercial Code
 see the Commercial Code; Insurance: Article 654-712;
 Background
 Construction project is a risk-prone venture;
 At different phases of the construction project, there are different types of
risks;
 Risk is defined as a combination of the probability, or frequency, of
occurrence of a defined hazard and the magnitude of the consequences of the
occurrence.
 Hazard is a situation that could occur during the life time of a product,
system or plant that has the potential for human injury, damage to property,
damage to the environment, or economic loss.
 The following are some of the basic principles/standards for the allocation of
risk:
 They are related to: fault, foresee ability, management & incentive.
 the fault standard: cost & time impacts of risks caused (or not avoided)
through the fault of a party should be borne by that party;
 the foresee-ability standard: he who is best able to foresee the risk is
allocated that risk;
 the management standard: he who is best able to control and manage
the risk is allocated that risk;
 the incentive standard: risks should be placed on the party most in
need of incentive (presumably already in the ability) to prevent &
control them;
 The risk management involves the following steps: risk identification; risk
assessment; risk response; risk management plan; and risk monitoring &
control;
 Risk: Contractual Allocation
 The very purpose of construction contract document being allocation of risk
to the contracting parties i.e., to the employer or to the contractor;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 97
Training Material on Construction Contract Management

 Such risk allocation could be express and/or implied;


 The non-balanced risk allocation under the construction contract may
generate construction claims and then disputes;
 There are two broad categories of risks in construction contract. These are:
 risks that lead to death, bodily injury and/or physical loss or damage;
and
 risks that lead to economic loss and/or time loss;
 Risks that lead to death, bodily injury and/or physical loss or damage may
arise due to defective design, defective material, defective workmanship, Acts
of God, fire, human error, and failure to take adequate precaution;
 Such types of risks may or may not be insurable by the insurance market;
 Risks that lead to economic loss and/or time loss involve the following;
 late possession of the site;
 delay in receipt of information necessary for timely construction;
 changes in design; and
 variations to the original contract;
 Such risks are characterized as resulting from default in the obligations
specified in the contract and as augmented by the applicable law;
 On the employer side the following may lead to economic loss or time loss
risks:
 delay in performance and cost overrun;
 defective design by or on behalf of the Engineer;
 non-performance; like delay in payment;
 Such risks may not be insurable by the insurance market, however;
 On the contractor side the following may lead to economic loss or time loss
risks:
 Delay in performance; resulting in payment of liquidated damages by
the contractor; see Clause 8 MDB-FIDIC;
 additional costs; due to various reasons; inefficiency or otherwise;
 defects; patent defects (to be remedied during performance like
rework & during defects correction period) or latent defects (i.e., after

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 98
Training Material on Construction Contract Management

issuance of defects liability certificate to be regulated by the


applicable law; see Article 3282 of the Civil Code) for public
construction contract like road;
 non-performance; due to various reasons as provided under Clause 15
MDB-FIDIC; and also under the applicable law; legal remedies are
provided under the applicable law like specific performance or
general damages or cancellation of contract; performance bond could
be the remedy for the employer;
 Such risks may not be insurable by the insurance market, however;
 Employer’s Risks
 The risks under Clause 17.3 MDB-FIDIC are the risks of the employer;
 Such risks may or may not be insurable by the insurance market;
 Contractor’s Risks
 the following are the risks of the contractor; viz., risks; under MDB-FIDIC
 related to works under construction; see Clause 18.2
 related to contractor’s equipment; see Clause 18.2
 related to the property of the employer; see Clause 18.3
 related to contractor’s personnel; see Clause 18.4
 related to employer’s personnel; see Clause 18.3
 related to the property of third parties; see Clause 18.3
 Such risks could be insurable by the insurance market;
 Insurance
 If ownership of risk has been determined through the contract document, the
contracting party who carries such risk may have an insurable interest to
insure such risk; see Clause 18 (Insurance) MDB-FIDIC;
 However, all risks may or may not be insured against by the insurance
market;
 If the risk is to be insured, the insurer (i.e., the insurance company) & the
insured (say the contractor) enter in to an insurance contract as per the

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 99
Training Material on Construction Contract Management

applicable law (i.e., the Commercial Code) and based on the particular &
relevant insurance policy;
 The following three types of insurance have been identified;
 property insurance; ex. for the contractor’s equipment by the
contractor itself;
 liability insurance; ex. for the property of the employer and/or the
property of the third party by the contractor;
 life insurance; related to life accident and/or sickness;
 The details of which being governed under Article 654-712 of the
Commercial Code;
 Insurance is part of risk management mechanism;
Security Instruments Management
 Background
 The following contractual clauses from the MDB-FIDIC & the PPA including the
provisions from the applicable laws may provide some regulations as to security
related issues;
 MDB-FIDIC 2006
 see Clause 1.1.4.11 Retention Money; re: definition; cum
 see Clause 1.1.6.6 Performance Security; re: definition; cum
 see Clause 4.2 Performance Security; re: form of security (viz., guarantee vs.
bond as per Contract Data) cum
 See Clause 1.1.1.10; re: definition on Contract Data; cum
 see Clause 14.2 Advance Payment cum see also Clause 1.1.1.10 Contract
Data; cum
 see Clause 14.9 Payment of Retention Money; re: after issuance of the TOC
the possibility for the contractor of substituting for the balance of the
retention money (i.e., 50%) by some form of security as provided under the
particular conditions of contract;
 see Clause 18.2 Insurance for Works & Contractor’s Equipment;
 see Clause 18.3 Insurance against Injury to Persons & Damage to Property;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 100
Training Material on Construction Contract Management

 PPA 2011
 see Clause 40 Insurance to be Taken by the Contractor;
 see Clause 58; Performance Security;
 see Clause 61; Retention Monies (guarantee);
 see Article 3271 of the Civil Code; (Sums advanced by the administrative
authorities); against guarantee;
 see the Commercial Code of Ethiopia on Insurance; Article 654-712;
 Civil Code
 see Article 3271 of the Civil Code; Sums advanced by the administrative
authorities); against guarantee;
 see also Article 1920-1951: Surety ship
 Commercial Code
 see Article 654-712 Insurance;
 Concept & Scope
 The concept of security is broad; it may include the following aspects;
 contractual security: different contractual security regimes under the
contract;
 legal security: security under the applicable law; and
 security from the market; based on a given construction contract but
securing & submitting commercial & non-commercial security
instruments notably by the contractor;
 contractual security & legal security are discussed somehow in the other
parts of the training;
 The security from the market is the focus of our training;
 Different securities are required under the construction contract for defined
& different purposes to be secured & submitted by the contractor;
 The following are some of the sources of security from the market;
 performance security; see Clause 4.2 MDB-FIDIC; see also Clause 58
PPA 2011;
 advance re-payment security; see Clause 14.2 MDB-FIDIC; see also
Clause 60.4 PPA 2011;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 101
Training Material on Construction Contract Management

 retention money security; see Clause 14.9 MDB-FIDIC; see also


Clause 61 PPA 2011;
 insurance policy; see Clause 18 MDB-FIDIC; see also Clause 40 PPA
2011;
 The contractor has no contractual right to demand payment security from
the employer except to request the financial arrangement in writing; see
Clause 8.1 (b) (Commencement of Works; re: financial arrangement serves
us here as a pre-conditions for the commencement of the Works) cum Clause
2.4 (Employer’s Financial Arrangement);
 The contractor, however, is obliged under the contract to secure & submit
some defined security instruments for due performance of its obligation
under the contract;
 Among such security instruments performance; advance re-payment; and
retention are some;
 Security Instruments
 Performance, advance re-payment & retention money related securities may
be provided by the banks or insurance companies;
 The term security stands here both for guarantee & bond;
 If they were issued by the banks we call the specific security instrument a
guarantee;
 If they were issued by insurance companies, we call the specific security
instrument a bond;
 From construction contract management perspective, the following are
worth to note:
 the security instruments issued by the banks (viz., the guarantee) are
mostly unconditional or on demand;
 the security instruments issued by the insurance companies (viz., the
bond) are conditional;
 The nature of such two security instruments to be issued by the banks
& insurance companies being non-commercial;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 102
Training Material on Construction Contract Management

 Due to this legal nature, the applicable law governing the enforcement
of such security instruments, viz., both guarantee & bond, is the Civil
Code;
 see Article 1920-1951 (Surety ship);
 Insurance Policies
 Insurance policies may serve as a security to the one who benefits
under such policy;
 Contrary to the above security instruments(namely, guarantee &
bond), insurance policies are commercial in nature, however;
 The applicable law governing their enforcement shall thus be the
Commercial Code of Ethiopia;
 see Article 654-712 (Insurance);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 103
Training Material on Construction Contract Management

Review Questions on
Construction Contract Management
………………………………………………………………………………………
1. What is Contract & Construction Contract?
2. What do you understand by the very concept & scope of construction?
3. What do you understand by the concept of utility/process plant erection project/erection
contract?
4. Why utility/process plant erection projects are excluded from the concept & scope of
construction & construction contract? Is it correct to exclude them? Why or why not?
5. Identify & discuss the structural difference between construction project/contract and
utility/process plant projects & contracts;
6. What is the difference between construction contract and other categories of contracts (viz.,
service contract, supply of goods contract)?
7. Identify & discuss the fundamental parts of construction contract documents?
8. What do you understand by the concept of method of construction?
9. Does method of construction constitute an integral part of construction contract
documents?
10. What do you understand by the concept of construction work program?
11. Describe the elements or structure of construction work program?
12. Does construction work program constitute an integral part construction contract
document?
13. Why we use standard conditions of construction contract for our construction projects?
14. What is the conceptual basis for each & every standard conditions of construction contract?
15. What is the relationship between general standard conditions of construction contract &
conditions of particular application/special conditions of contract?
16. What do you understand by the very concept of construction contract management?
17. Identify & discuss the fundamental contractual obligation of the Employer under a given
construction contract;
18. Identify & discuss the fundamental contractual obligations of a contractor under a given
construction contract;
19. What do you understand by the concept of consultant or the Engineer? (design vs.
supervision consultant);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 104
Training Material on Construction Contract Management

20. Why we need consultants as related to construction projects? like the design consultant or
supervision consultant?
21. Identify & discuss the role of the Engineer (as a supervision consultant) in a given
construction contract;

Exercise Assignment
Pre-contract Negotiation
A certain (public) employer has undertaken a successful tender process and awarded, via a formal
letter of acceptance thereto, a dam (impounding 20 Billion CM raw water) construction project
worth Birr 4 Billion, to a certain public contractor. The project duration would be 500 calendar
days. Before signing the underlined construction contract, both parties decided to hold a pre-
contract negotiation. The respective agendas to be negotiated, as recorded, were of the following.
The delivery sub-system is that of design-bid-build.

Employer’s Agenda

 Program;
 issue of focus: guiding vs. binding program:
 We have reviewed the tender program of the Enterprise;
 we found that the Program is good; we demand the said working program to be
critically reviewed & to become an integral part of the upcoming Dam Construction
Contract;
 Tests on Completion; the tests; insurance; method;
 tests; let us define & specify the tests on completion; Notes; as the public contractor
what are the possible tests on completion to be proposed, if any, on the dam upon its
completion?
 insurance: we demand a specific insurance Policy to guarantee the successful tests
on completion; Notes; as the supervision consultant, do you think that there is an
insurance coverage for such possible risks (viz., failing to pass tests on completion);
 method: if the dam fails to pass specified tests on completion, without prejudice to
our contractual right to reject the dam, let us agree on the method of measurement
(calculation) of the extent of the loss of benefit/value of the dam with a view to

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 105
Training Material on Construction Contract Management

reduce the contract price; as supervision consultant, what do you expect from the
successful bidder to be proposed as method of calculation? Advise the public
employer!
 Threshold for Interim Payment;
 we recommend ETB 20 Million (instead of ETB 10 Million), as a threshold, to
trigger & process every interim payment certificate;
 Performance Security;
 guarantee: without prejudice to the percentage agreed (viz., 10%), we demand
performance bank guarantee instead of performance bond for the due performance
of the Dam Project;
 what do you advise the employer?
 Reduction of Bid Price/Accepted Contract Amount;
 discount: we demand reduction of the Bid Price which is now an accepted contract
amount (viz., Birr 4 Billion) by 5%;
 consider first the feasibility of the agenda;

The Successful Bidder Agenda

 Advance Payment %;
 the project is capital intensive;
 we demand the increase of the advance payment, now 10%, to 20% and to be
distributed equally in terms of our financial requirement (cash flow) both in foreign
& local currency;
 Advance Re-Payment Security;
 guarantee vs. bond:
 to ease our initial financial burden & future cash flow, we demand the advance
repayment security to be in the form of bond instead of guarantee;
 advise the public employer thereon;
 Site Acquisition & Access Plan;
 the plan: to determine the timing & extent of our mobilization, we demand a clear
site possession & access plan from the employer side;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 106
Training Material on Construction Contract Management

 non-encumbrance: we demand also the full encumbrance free and obstruction free
site & its access with a view to avoid any delay;
 advise the public employer thereon;
 Mobilization Period; timing; program; contract effectiveness;
 timing: the proposed mobilization period is 3 months calculated from the signing of
the construction contract; we demand 6 months mobilization period calculated from
the receipt of the full advance payment both in foreign currency (25%) & local
currency (75%);
 mobilization program: our proposed Mobilization Program has already been
submitted for your due consideration;
 contract effectiveness: we thus consider the effecting of the advance payment as a
condition precedent to the effectiveness of the construction contract;
 advise the public employer thereon;
 Project Duration;
 500 vs. 760: we have observed, in the drawing, a gross error as related to the
quantities to be excavated;
 we understand it is very difficult to change the method of construction from
machine-based to blasting;
 therefore, we demand the project duration to be increased to 760 calendar days;
 Notes: no disclosure from all bidders as to such error during bidding;
 advise the public employer thereon;
 Financial Arrangement;
 we demand, in writing, the availability of the finance (approved budget) for the
whole duration of the Project;
 Info: the capital budget for the Project already indicated in the fiscal budget of the
said public institution (the Employer);
 Payment Security;
 as a contractor, we demand from the Employer an unconditional payment
guarantee from a reputable local bank;
 Retention Security;
 bond vs. guarantee:

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 107
Training Material on Construction Contract Management

 we demand to submit a local retention bond, instead of guarantee, for the balance of
our retention money upon the issuance of the taking over certificate;
 advise the public employer thereon;

Discussion Points

 Concept; What we call, conceptually, this kind of negotiation (pre-contract negotiation)


between such future employer & successful bidder?
 Non-negotiability; Is there any non-negotiable agenda raised from the Employer’s
side? Identify & discuss; why it being non-negotiable?
 Non-negotiability: Is there any non-negotiable agenda raised from the Successful
Bidder’s side? Identify & discuss; why it being non-negotiable?
 Employer’s Agenda: What is your position on each negotiable agenda raised by the
Employer?
 Successful Bidder’s Agenda: What is your position on each negotiable agenda raised
by the Successful Bidder?
 Integration with contract; Assume that both negotiating parties have agreed on such
identified & negotiable items; How do you incorporate those negotiated terms within the
underlined dam construction contract?

Pre-contract Claims
The above pre-contract negotiation has been finalized in two-week time. The pre-contract
negotiation result has been signed by both parties in the form of Minutes of Meeting of the Pre-
contract Negotiation. Assume that the said public employer, after finalization of the said pre-
contract negotiation, has refused to enter into a contract with the Enterprise for reasons unknown;

Discussion Points

 Experience: Have you ever encountered such similar circumstances in your professional
career?
 Legitimacy; Is such public employer legitimate to decline to enter in to a contract with
such successful bidder?

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 108
Training Material on Construction Contract Management

 No Legitimacy; If not legitimate, what remedies were available to the successful bidder
against the said employer?
 Remedies: If there were some remedies available to the successful bidder, are such
remedies contractual or legal? Justify

Pre-contract Claims
Assume that the head of the said public employer institution ordered the future Engineer (now the
supervision consultant), in the presence of the Successful Bidder’s General Manager & its all
project staff, to instruct the Successful Bidder to commence execution of the works (say the Dam)
(which is an urgent project) by promising to the Successful Bidder to sign the dam construction
contract after his return from abroad that he is due to depart for some urgent public interest. The
supervision consultant has ordered same in writing. The Successful Bidder has mobilized &
executed some works (say 10%) in a month-time. After his return, the head of the said public
employer has refused to sign the dam construction contract for reasons unknown.

Discussion Points

 Experience: Have you ever encountered such similar circumstances in your professional
career?
 Legitimacy: Is such employer legitimate to refuse to enter in to such construction
contract with the said Successful Bidder?
 No Legitimacy; If not legitimate, what remedies were available to the Successful Bidder
against the said employer?
 Remedies: If there were some remedies available to the Successful Bidder, are such
remedies contractual or legal? Justify

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 109
Training Material on Construction Contract Management

Brief Professional Profile of the Trainer


………………………………………………………………………………………………………
 Name: Zewdu Tefera Worke;
 Date of Birth; February 12, 1957;
 Nationality: Ethiopian;
 Education: LL.B (Ethiopia, 1984 G.C); LL. M (Germany, 1991 G.C);
 Specialization: 1989-1991 G.C
 Building Construction & international Civil Engineering Construction Contracts:
related to physical facility & infrastructure development projects (viz., building;
dam; transport; water & power transmission & distribution works…);
 international Electro-Mechanical Engineering Contracts: related to utility or
process facility/plant development projects (viz., industrial plant; power generation
plant; water treatment plant; waste water treatment plant; groundwater drilling
works & treatment plant;…);
 international Consulting Engineering Agreements: related to: the study; design;
procurement; construction supervision & contract administration of physical
facility & infrastructural development projects; and related to the procurement &
contract management of; the design; fabrication; supply; erection & commissioning
of utility/process plant projects;
 Work Experience: 1984-2007 G.C
 Deputy General Manager (for Business Development): at AAWSA; 2006-2007;
 Legal Advisor: at AAWSA; 1995-2006;
 Chief Legal Advisor: to the Addis Ababa City Manager; 2003-2005;
 Asst. Legal Advisor: at Addis Ababa Water & Sewerage Authority (AAWSA) 1984-
1995;
 Professional Competence: 2007-to date:
 Instructor: Construction Contract & Law Course for postgraduate Students
specializing in Construction (Engineering) Technology & Management at different
public universities mentioned below;
 Instructor; Environmental Policy & Regulation Course for graduate students
specializing in Environmental Engineering;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 110
Training Material on Construction Contract Management

 Advisor; re: master thesis works of graduate students specializing in construction


(engineering) technology & management field at some of the technical departments
of the universities mentioned below;
 Construction Arbitrator; as presiding arbitrator; as co-arbitrator;
 Construction Arbitration Counsel; representing clients (construction companies or
engineering consulting firms) at construction arbitration tribunals;
 Legal Consultant; primarily related to building & engineering construction
including utility or process plant/industrial projects & other relevant fields;
 Trainer: on Construction Law: on Construction Contract Management; already
trained or co-trained all federal courts judges; employers (like the staff of the
Ethiopian Roads Authority;); the management staff & professionals of the Addis
Ababa City Roads Authority; the legal staff of the Commercial Bank of Ethiopia;
consultants (like the staff of the Defense Construction Design Enterprise); Ethiopian
Construction Design & Works Supervision Corporation; contractors (like the staff
of the Defense Construction Enterprise); Oromia Water Works Construction
Enterprise (professionals & management staff);…); consultants like the Ethiopian
Construction Design & Works Supervision Corporation (professionals &
management);
 Trainer: on Construction Claims & Disputes Management; already trained
employers (like the staff of the Ethiopian Roads Authority; the legal professionals of
the Commercial Bank of Ethiopia ;); the management staff & professionals of the
Addis Ababa City Roads Authority; contractors (like the staff of the Defense
Construction Enterprise);…); Oromia Water Works Construction Enterprise
(professionals & management staff);…); consultants like the Ethiopian Construction
Design & Works Supervision Corporation (professionals & management);
 Assistant Professor: at relevant technical departments of the following public universities:
 Construction Contract & Law Course
 Addis Ababa University: Addis Ababa Institute of Technology, School of Civil &
Environmental Engineering (2007-2013);
 Mekelle University: Ethiopian Institute of Technology-Mekelle, School of Civil
Engineering (2012-2018);
 Adama Science & Technology University: School of Engineering; Department of
Civil Engineering (2008-2010 & 2013);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 111
Training Material on Construction Contract Management

 Jimma University: Institute of Technology, School of Civil & Environmental


Engineering, Department of Construction Engineering & Management; (2012-
2013; 2017-2018);
 Jimma University, Institute of Technology, Online Course Delivery (e-learning),
School of Civil & Environmental Engineering, Department of Construction
Engineering & Management in cooperation with Lucy Consulting Engineers PLC
(2017-todate);
 Jimma University, College of Law & Governance, designed & proposed a new
Graduate Program on Construction Law (2017); leading to LL.M (for lawyers);
and leading to M. Sc (for relevant engineers); endorsed by Jimma University
(2017);
 Addis Ababa Science & Technology University, Institute of Architecture & Civil
Engineering, Department of Construction Technology & Management; (2014-
2018);
 Arba Minch University: Institute of Technology, Department of Civil Engineering
(2014-2016);
 Hawassa University: Institute of Technology, School of Civil Engineering & Built-
Environment, Department of Construction Technology & Management (2016-to
date);
 Wollega University: College of Engineering & Technology, Department of
Construction Technology & Management (2016-2017);
 Dire Dawa University, Institute of Technology, Department of Construction
Technology & Management (2018-);
 Environmental Policy & Regulation Course
 Addis Ababa University: Addis Ababa Institute of Technology, School of Chemical
& Bio-Engineering (2009-2016);
 Addis Ababa Science & Technology University: School of Energy Resources &
Environmental Engineering (2012-2013);
 Training Taken:
 International Project Procurement (2001-USA, Washington D.C.); related to the
procurement of Works; Goods; and Services, organized by International Law
Institute (ILI);

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 112
Training Material on Construction Contract Management

 International Commercial Arbitration, organized by International Law Institute


(ILI-African branch) (2002-Uganda, Kampala);
 Water & Sanitation Sector Reform (2004-South Africa, Johannesburg); organized
by the World Bank & African Water Utility Partnership;
 Alternative Dispute Resolution (ADR); construction operation; construction dispute
management system; urban governance; radiation; taxation; international
banking; and other relevant trainings (Ethiopia);
 Contributions
 Design-Build Delivery Sub-system & Some Contractual & Legal Issues from
Ethiopian Perspective (March, 2012, Unpublished);
 Developed a Formula on Construction Contract & Law (2014); (for education,
training & research);
 Developed a Postgraduate Program on Construction Law (2017);
 Public Construction Contracts & Construction Disputes Management System: with
Special Emphasis to Public Interest (April, 2018, Unpublished);
 Membership:
 Member, Ethiopian Construction Technology & Management Professionals
Association;
 Chairperson, Board of Directors, Ethiopian Conciliation & Arbitration Center
(2010-2012);
 Chairperson, Board of Directors, Ethiopian Center for Development (2012-todate);
 Countries Visited:
 Europe: Germany (1988-1992); France (1997 & 2000); Switzerland (1997); Republic
of Ireland (2012, 2013, 2014, 2015 & 2016);
 Africa: Nigeria (1994 & 1995); Benin (1995); Uganda (2002); South Africa (2004);
 North America: United States of America (2001);
 Asia: United Arab Emirates (2013);
 Language Proficiency: Amharic; English; German; listening; writing; speaking very good;
 Professional Designation: Engineering Contracts Lawyer;
 Contact Details: email: zewtefw@gmail.com, Cell phone: +251-921-386052;

Organized & delivered by: Zewdu Tefera Worke, Engineering Contracts Lawyer Page 113

You might also like