Professional Documents
Culture Documents
Client: Job No.: Job Title: Client's Job No.:: Company Name
Client: Job No.: Job Title: Client's Job No.:: Company Name
Client:
Job No.:
Job title:
Client's Job No.:
Title:
1. P& ID(s)
2. Isometric drawing(s)
3. Welding summaries and NDT/PMI reports
4. Line check before hydrostatic
5. Hydrostatic test and chart recorder
6. Calibration equipment certificates
7. Flushing and drying report
8. Punch list
9. Painting report
TEST PACKAGE
TP-01
PROJECT
PG-1:
CLIENT
PG-2:
EQUIPMENT
Recorder:
TAG NAME
Test temperature:
JOB NUMBER
re
su
es
Pr
P ------------------------------- [PSI]
P=Design Pressure
50% P ------------------------------- [PSI]
Job title:
Job No. Test Pack No. Tested date Sheet No. Revision No. Report No.
Line
Items/Description of check Yes No N/A Remarks
No.
Check that all NDT/stress relieving requirement as per specification have been
2
met and recorded and all welded attachments installed
3 Check that correct bolts and gaskets are installed at all mechanical joints
4 Check that all vents and drains are installed (add temporary vents and drains
for testing as required)
5 Check piping for correct schedule and type and ratings of forged steel fitting
Check valve materials, use spec., ref., in piping material specification, tags,
6
and nameplates
10 Check that all pressure connections are installed correctly as per specification
Check for correct direction of flow through check valves, globe valves and
11 control valves
Check all pipe supports are correctly installed, all temporary pipe supports
12 removed and any additional supports fitted
Check that all chain wheels and extended spindles required for specified
13 valves have been installed
Comments:
Signature
Date
PRESSURE TEST CERTIFICATE
Client:
Job title:
Client's Job No.:
Job No. Test Pack No. Tested date Sheet No. Revision No. Report No.
TESTING INFORMATION
Procedure No.: Tem. at start/end of test:
Required test pressure: Actual pressure test:
Test medium: Holding time:
Tesing item: Draining completed:
TESTING INSTRUMENTS
Pressure gauge 1 Pressure gauge 2 Pressure and temperature recorder
Serial no.
Calibration label no.
Due date
LIST OF TESTED ITEMS
# Line No. Sheet No. Rev. No. Spool No. Drawing No. Remarks
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
24
Comments: No leak was observed and all above piping spools found being able to withstand the test pressure.
Date
PUNCH LIST
Client: Test pack No.:
Job title: Report No.:
Line No.: Date:
Page:
Class Clear by Verified by Verified by
No. Desciption Remarks
(A, B, C) (Signature & Date) (Signature & Date) (Signature & Date)
Note: Class A: Clear before hydrotest; Class B: Clear after hydrotest; Class C: Clear during commissioning priod
Witnessed by COMPANY Client Third party
Name
Signature
Date
FLUSHING AND DRYING INSPECTION REPORT
Client: Report No.:
Job title: Inspected date:
Job No.: Sheet No.:
Acceptance Criteria:
No. Line No. Drawing/ Iso No. Revision Remarks
1
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Comments: Flushing and drying out of pipe section after hydrostatic test and before installation on skid.
Signature
FLUSHING AND DRYING INSPECTION REPORT
Client: Report No.:
Job title: Inspected date:
Job No.: Sheet No.:
Acceptance Criteria:
No. Line No. Drawing/ Iso No. Revision Remarks
Date
PAINTING INSPECTION REPORT
Client:
Job title:
Job No. Part No. Serial No. Inspection date Sheet No. Report No.
SURFACE PREPARATION:
Date of blasting: Original condition:
Abrasive type used: Surface standard:
Paint manufacturer: Surface profile:
Time Remarks
Air temperature [AT] (°C)
Relative humidity [RH] (%)
Steel temperature [ST] (°C)
Dewpoint temperature [DP] (°C)
PAINTING:
Painting Painting Coating RH ST DP Batch DFT (µm)
Date description No. (%) (°C) (°C) No. Req. Min. Max. Ave.
1st
2nd
3rd
Date