Professional Documents
Culture Documents
Chapter 6 2021 Revision
Chapter 6 2021 Revision
Chapter 6 2021 Revision
1
Please see section 5.2 for how to define your project’s basis date
2
Please see section 4.1 for how to determine a trend line (trend) price
1
that the existing facility has a design operating rate of 1000 kg/hr of product A and that the
project you are evaluating will result in a design operating rate of 1100 kg/hr of product A. Then
the revenues from product A sales associated with the project would be:
Product A Annual Revenue= (1100-1000) kg/hr*($trend price in 2018)*Op factor. (6.1)
For retrofit projects, the actual operating factor for the facility should be used, if known, instead
of the ideal operating factor used in the facility’s initial design. This information should be
available from existing plant operating data.
Many times a retrofit project is considered that does not increase the production capacity
of any of the products or by-products from the facility. However, such a project may still have a
positive economic impact if it reduces operating costs. There are two common and equally valid
methods to address this circumstance. The first is to simply calculate the incremental decrease in
operating costs and show this as a “credit” under the operating costs category. The second is to
classify incremental operating cost decreases as a revenue. Either method will result in the same
value for the two most important economic measures described in the following sections. For
purposes of consistency, we will always show these as an operating cost credit in this book.
For some retrofit projects, it may be more appropriate to use the actual operating rate
rather than the design operating rate. If the existing process has three or more years of operating
history, you should be able to obtain the average actual operating rate for the facility. This is
important because some projects may appear to be economically worthwhile when calculated
using the design operating rate, but will not actually provide this economic benefit based on the
actual operating history of the process. For example, let us consider a project that will remove a
constraint in the process and increase the design operating production capacity of the facility by
10%. If the existing process has a design operating product A production rate of 1000 kg/hr then
the modified facility would have a design operating product A production rate of 1100 kg/hr. If
we estimate the revenues on a design operating basis, the incremental revenue would be
calculated based on 100 kg/hr * trend price * theoretical operating factor. However, if the
average actual operating production rate is 600 kg/hr, then the incremental revenue would be
zero since the extra capacity of the process is not required. As such, this project would probably
be judged to not be worth doing until such time as the company has found additional market
share for that product that results in the average actual operating rate that is close to the design
operating rate.
6.1.1.1 Fuzzy benefits
Sometimes, especially for retrofit projects, there are benefits from the project that are
difficult or impossible to quantify. The fuzzy benefits method is a technique that can be used to
provide a conservative value for these benefits. Here is the procedure:
1. Qualitatively identify all of the possible benefits that might occur if the project is
implemented
2. Force rank each benefit in order of probable magnitude of the benefit. Keep the top
3-4 benefits and ignore the rest.
3. Determine how each benefit is achieved.
4. Determine how you would quantify that benefit if you had all of the data you needed
to make the calculation.
2
5. Identify what data is missing that is preventing you from quantifying the benefit.
6. For each missing data element, make a reasonable estimate of the value. Use these
estimated to calculate the most probable benefit.
7. Discount the quantitative value of the benefit substantially.
8. Do this for the top 3-4 benefits and then use the sum of these values as revenue or
reduced operating costs for the project.
4
(note: I kept one extra digit beyond the level of uncertainty in the numbers during my
calculations to minimize roundoff errors, but report the final value with the correct number of
significant digits (one certain and one uncertain).
For some retrofit projects, the taxable profit may be a negative value for one or more
years of the project. For example if the project is needed to meet a new environmental
regulation, we conduct an economic analysis of project alternatives in order to determine the
least costly way to meet the regulation. Another example is a project where the gross profit for a
given year (usually year 1) is less than the depreciation value allowable for that year, yielding an
annual taxable profit that is less than zero.
A hypothetical “negative tax” or “tax credit” should be calculated in the same way that
the tax on profits is calculated, as described above. For cases where the annual taxable profit is
less than zero, it is assumed that the rest of the facility is making a profit and that the tax credit
can be applied to the annual taxes of the entire facility to reduce the overall tax burden.
Therefore the profitability calculation should include a value for taxes even when the net profit
for a given year is less than zero.
For example if the gross profit in the previous example is changed from +$15,000 to -
$5,000, the following calculations would be made to determine the net profit in year 1. After
deduction of the allowable value of depreciation of $3,000, the Federal taxable profit is -$8,000.
The Federal tax will then be:
FT= -$8,000*0.21 = -$1,680.
In most states, the taxable profit for state tax calculations, TPS, is the overall taxable profit minus
the Federal tax:
TPS= -$5,000-$1,680 = -$6,680.
If the state tax rate is 7.5% of the state taxable profit, then the state tax is:
ST = -$6,680*0.075= -$500.
The overall year 1 tax:
Tax = FT,1 + ST,1 = (-$1,680) + (-$500) = -$2,180.
The net profit is the gross profit – any non-taxable charges – Tax. In this example:
NP = -$5,000 - $0 – (-$2,180) = -$2,820 -$2,800.
5
section 5.2), reported in currency units at an “evaluation date”. Net present value is a measure of
the productivity of an investment and is the most common economic measure used for grassroots
or major expansion projects. Because the investment is always compared to a hurdle rate, an
NPV value is undefined unless the hurdle used is specified. As such, the correct abbreviation for
this measure is NPV@HR, where HR is replaced by the actual hurdle rate denoted as the
discounting factor percentage (e.g. NPV@20%).
To calculate the NPV@HR, the net profit (cost) for each relevant year (or other time
period) of the project execution schedule and the operational schedule is forecast forward or
discounted backward in time to the evaluation date using the hurdle rate as the discount factor in
the equation:
PVn=NPn/(1+HR)n (6.2)
where: PVn is the value of the net profit in period n discounted by the HR to the
evaluation date; NPn is the undiscounted value of the annual net profit (cost) in
period n, and n represents the number of accounting periods (usually years) since
the evaluation date; HR is the hurdle rate.
The most common evaluation date is the day before the project’s facilities and systems
are completely commissioned. In other words, the first day of full operation after project
completion is typically counted as “year 1, day 1” and the evaluation date is “year 0, day 365.”
When the net profit is calculated annually, the evaluation is dated to year 0 which is the year just
prior to full operation. If the net profit is calculated quarterly (small retrofits), the evaluation is
dated to quarter 0.
For example, to calculate the PV for each year if the project execution schedule is 2
years, the costs in the first year are $1,000,000, the costs in the second year are $1,200,000, the
operational life is 5 years with the following annual profits: years 1-3 = $500,000 per year; year
4=$450,000; year 5 = $550,000, and a hurdle rate is 10%:
Note that the value of n is usually negative for years prior to the evaluation date, which are the
years when costs are incurred for project execution. Note also that the evaluation date does not
usually correspond to the basis date of the analysis. The basis date, represents the time at which
6
the currency of all cash flows is valued while the evaluation date represents the time to which all
cash flows are discounted and is usually the projected date at which the project is put into
service.
This sounds a bit confusing. Why not just use the basis date as the evaluation date? You
can, but then all of your cash flows, both those that occur before the project is finished (which
are typically costs), that is those associated with the project execution schedule, and those that
occur after the project is finished (which are typically net profits or revenues), that is those that
occur during the operational life, will all be discounted to an earlier date. For most people, it is
more intuitive to view the project costs as an investment (hence the term capital investment) that
must be recovered before profits are realized. Using an evaluation date that is set at the date the
project is finished reflects this view.
The net present value is the sum of all of the PV’s from both the project’s execution
schedule years (e.g. PV-1 and PV0) and the project’s operational life years (e.g. PV1 through PV5).
For our example:
NPV@10% = -1,100,000+-1,200,000+455,000+413,000+376,000+342,000 = -$710,000
If the NPV@HR is greater than zero, the project is considered to be economically
worthwhile and if the NPV@HR is less than zero, the project is considered to be not worthwhile.
For our example project, the NPV@10% is less than zero, so the project is not worthwhile from
an economic viewpoint. Notice that if we just summed the undiscounted cash flows, the value
would be +$2,500,000. This illustrates the importance of taking into account the time value of
money, the risk tolerance, and the minimum required profitability when analyzing the project.
The NPV@HR measure incorporates all of these factors into the analysis, yet provides a very
simple means to assess the economic worth of the project.
7
DCFROR is assumed and each of the annual (or other time period) cash flows are discounted
using the DCFROR instead of the HR in equation 6.1. If the NPV calculated is larger than zero,
the next iteration should use a higher value for the DCFROR while if the NPV is less than zero,
the next iteration should use a lower value for the DCFROR.
Returning to the example we used in section 6.2.1. The undiscounted cash flows for the
project execution period were: year -1=-$1,100,000 and year 0 -$1,200,000. The undiscounted
cash flows for the 5 year operational life were: years 1-3=$500,000, year 4=$450,000, year
5=$550,000. We know from the calculation performed in section 6.2.1 that the NVP@10% is
less than zero. Therefore, we know that the DCFROR is less than 10%. For a second guess of
the DCFROR, let’s assume the value is 2%. Then the discounted cash flows would be:
Year Value
-1 -$1,120,000
0 -$1,200,000
1 $ 490,000
2 $ 481,000
3 $ 471,000
4 $ 416,000
5 $ 498,000
NPV@2% = $34,000
Since this value is greater than $0, the DCFROR (HR) of 2% is too low. If we iterate on the
value of the HR, we will find that the HR=2.43% at the point where the NPV@DCFROR=0.
Therefore, the DCFROR for this project is 2.43%.
As can be seen from the paragraphs above, NPV@HR and DCFROR are related. To use
DCFROR to determine if a project is worthwhile, the value of the DCFROR is compared to the
HR. If DCFROR>HR, the project is economically worthwhile and if DCFROR<HR, the project
is not economically worthwhile.
The DCFROR only has meaning when it is a positive value. That is, the NPV@0%>0. A
negative DCFROR can be generated by calculating the discounted rate of loss (DCFROL). This
is done by changing the sign on the annual (or other time period) cash flows. In the example we
used earlier, if the year -1 investment was a -$2,000,000 cash flow instead of -$1,000,000 the
NPV@0%<0. The DCFROL would be calculated by multiplying each annual cash flow by (-1)
and then determining the HR at which the NPV@DCFROL=0. This would yield a DCFROL of
6.9%:
Year Cash Flow PV@HR HR = DCFROL = 6.9%
-1 2000 1871
0 1200 1200
1 -500 -534
2 -500 -571
3 -500 -611
4 -450 -587
8
5 -550 -767
NPV@HR = 0
If all of the cash flow values have the same sign (are either all positive or all negative),
the DCFROR cannot be calculated and is undefined. This is most commonly encountered when
we have a project that must be completed for safety or environmental reasons, where there may
be no incremental revenues, only costs. In this case, all of the annual cash flow values are
negative and the DCFROR is undefined. For these projects a different economic measure must
be used.
9
The undiscounted version of the net present value is known as the cumulative cash value
or more commonly the cumulative cash position (CCP). This is calculated by summing all of the
individual net profits from the cash flow sheet. CCP is a measure of the undiscounted
productivity of the investment.
Another variation of the cumulative cash position is the cumulative cash ratio (CCR).
This is calculated as shown in equation 6.3:
n
∑ NPi
1
CCR= 0 (6.3)
∑ NP j
m
where: NPi = net profit in year i; NPj = net profit in year j; n = final operational year of
the project; m = first year of the project schedule.
The CCR is the ratio of the profits generated by the project to the total capital investment
required to generate those profits. It is a measure of the undiscounted efficiency of the
investment. The project is worthwhile if the CCR is greater than one.
The undiscounted version of the DCFROR is known as the return on investment (ROI)
and is calculated by equation 6.4:
n n
∑ NPi ∑ NPi
1 1
n n (6.4)
ROI= = o
TCI
∑ NP j
m
where: NPi = net profit in year i; TCI = total capital investment; NPj = net profit in year j;
n = final operational year of the project; m = first year of the project schedule.
ROI measures the undiscounted efficiency of the investment and allows a simple and easy way
to compare small projects for economic worthiness.
Note that some authors use the FCI instead of the TCI in the undiscounted calculations.
For the simple retrofit projects where such calculations are valid, the two values are going to be
very similar if not the same. The one exception and the reason we have specified TCI in this text
is there may be cases where the initial charge of chemicals and catalysts is a significant portion
of the costs incurred in an otherwise simple project. For these projects, using the TCI is a more
accurate measure of project worthiness.
6.2.4.2 Other discounted economic measures
When comparing projects that are capital intensive and have different project execution
schedules and/or operational lifetimes, the NPV@HR can be cumbersome to use to evaluate
relative economic worthiness (see section 6.3.1.1 below). A useful measure for these cases is the
present value ratio (PVR) which is calculated via equation 6.5:
10
n
∑ PV i
1
PVR= 0 (6.5)
∑ PV j
m
where: PVi = present value in year i; PVj = present value in year j; n = final operational
year of the project; m = first year of the project schedule.
A PVR of 1 represents breakeven and is the equivalent of an NPV@HR = 0. The larger the
value, the more profitable the investment. This allows for a simple comparison of projects
regardless of project execution schedule or operational lifetime.
11
Table 6.1 Cash Flow Worksheet
Present
Present Value @
Time Since Value @ DCFROR
Evaluation Overall State Non- HR & &
Date (Yr or Operating Depreciatio Taxable Federal Taxable Taxable Evaluation Evaluation
Mo) Revenue Costs Gross Profit n Profit Taxes Profit State Tax Charges Net Profit Date Date
-3
-2
-1
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Basis Date Evaluation Date Hurdle Rate NPV@HR =
DCFROR =
12
6.3.1.1 Comparing alternative investments with the cash flow sheet method
The cash flow sheet can be used to compare different investment options, such as
different projects or process alternatives, to determine which is more economically worthwhile.
If the two alternatives have the same project execution schedule and operational life, the method
is straightforward:
1. Calculate the cash flow for each year for each alternative
2. Take the difference between the two alternatives being compared to obtain an
incremental net cash flow
3. Determine the NPV@HR of the incremental cash flow. If the NPV@HR>0, the first
alternative is preferred while if the NPV@HR<0, the second alternative is preferred.
[Dr. Kolodka will provide an example in class.]
When comparing alternatives that have different project execution schedules and/or
project lifetimes, it can be difficult to properly account for the time value of money. If the
project execution schedules are the only difference, simply follow the procedure outlines above.
If one alternative takes an extra year to complete, add this year as an additional negative year, so
that the entire cash flow sheet is still based on positive years starting when the project is placed
in service. For larger projects, you may want to reflect in the analysis the extra time before the
project generates revenue. One way to accomplish this is to use the evaluation date from the
shorter project as the evaluation date for the longer project. For example, if project 1 will take
two years to complete and project 2 will take three years to complete, you can discount both
project cash flows to the completion date for project 1 as follows:
Project 1 Project 2
Project Discounted cash Discounted Cash
Cash Flow Cash Flow Incremental
Year flow@15% Flow@15%
Cash Flow
-1 ($1,000,000) $ (1,200,000) ($600,000) $ (690,000.00) $ (510,000)
0 ($1,200,000) $ (1,200,000) ($600,000) $ (600,000.00) $ (600,000)
1 $400,000 $ 350,000 ($1,000,000) $ (870,000.00) $ 1,220,000
2 $400,000 $ 300,000 $400,000 $ 300,000.00 $ -
3 $400,000 $ 260,000 $400,000 $ 260,000.00 $ -
4 $400,000 $ 230,000 $400,000 $ 230,000.00 $ -
5 $400,000 $ 200,000 $400,000 $ 200,000.00 $ -
6 $400,000 $ 170,000 $400,000 $ 170,000.00 $ -
7 $400,000 $ 150,000 $400,000 $ 150,000.00 $ -
8 $400,000 $ 130,000 $400,000 $ 130,000.00 $ -
9 $400,000 $ 110,000 $400,000 $ 110,000.00 $ -
10 $400,000 $ 99,000 $400,000 $ 99,000.00 $ -
11 $0 $ - $400,000 86,000 $ (86,000)
Totals $1,800,000 ($401,000) $1,800,000 ($425,000) $ 24,000
13
projects, the increase of one year in the project execution schedule makes a difference in the
relative profitabilities of the two projects.
When the operational lifetimes are different, the procedure is a bit more complicated.
1. Determine the least common denominator for multiples of the two operational lifetimes.
For example, if one project has an operational lifetime of six years and the other has an
operational lifetime of eight years, the least common denominator is 24 (6x4 or 8x3).
2. Replicate the yearly cash flows for each alternative as required to match the least
common denominator. For the example from step 1, the yearly cash flows for the first
project would be replicated four times and for the second the cash flows would be
replicated three times. This includes the cash flows associated with the project execution
schedules.
3. Calculate the incremental net cash flow for each year.
4. Calculate the incremental NPV@HR. If the NPV@HR>0, the first alternative is preferred
while if the NPV@HR<0, the second alternative is preferred.
[Dr. Kolodka will provide an example in class]
14
The discounted
$400,000 Fully Discounted Payback Period
cash flow diagram using
data from this same $0
example is shown in
15
4. Taxes
Net Profit (GP-TAX)
The revenue and operating expenses are calculated as described in section 6.1. The annualized
capital cost is calculated by dividing the total capital investment by the project’s operational life
(in years). For example, if the TCI for a project is $10,000,000 and the operational life is 10
years, the ACC is:
ACC=$10,000,000/10 = $1,000,000/yr
There are three common conventions for using the balance sheet method. The first
convention is to calculate a “year 1” balance sheet. In this case, the revenues and operating
expenses from the 1st year of operation are used. Taxes are often calculated in a simplified
fashion by simply using the gross profit as the taxable profit. However, some companies require
that the taxes be calculated more accurately, which requires use of a more complete method,
such as the balance sheet method to do the tax calculation.
The second convention is to use the average basis date values of the revenues and
operating expenses. This convention has the advantage of incorporating significant changes in
operating expenses into the calculation. For example, if there is a large expense every five years
for a reactor catalyst changeout, the year 1 balance sheet fails to include this cost in the gross
profit calculation, but the “average basis date” balance sheet method includes them.
The third convention is to use the average values of the revenues and operating expenses.
Revenues and operating expenses are escalated using projected rates of inflation (or other
projected changes in value) over the project life. The average of the escalated values is then used
in the average value balance sheet calculations. This method can be considered to be a mid-
project life annual balance sheet.
[Dr. Kolodka will have an example in class]
16
life. If the revenues are dominant, it is useful to determine if most of the revenue comes from a
single product, two products, or if the revenues from a suite of products and by-products are
distributed fairly evenly. Similarly, if operating costs are one of the most significant elements on
the cash flow sheet, it is useful to identify which operating cost items makeup the majority of
these costs.
[add examples here]
6.4.2 Use of the gross margin
Often the primary product(s) and primary raw material(s) are economically linked. For
example, when the price of crude oil rises, the prices of gasoline, jet fuel, and diesel rise in
response. These types of facilities are known as “margin processors” because they make their
profit based on the margin between the unit price(s) of the primary product(s) and the unit
price(s) of the raw materials. This margin must be large enough to: 1) cover the on-going
manufacturing costs, 2) payback the original capital investment, and 3) provide an acceptable
level of profit. For these facilities, variations in the absolute values of the unit prices of the
products and raw materials are not as important as variations in the margin between the unit
prices. While product prices will follow the trend in the unit costs for raw materials, other
factors will influence the margin such as the retention or expansion of product market share.
For projects associated with these types of facilities, the gross margin can be used to
assess the uncertainty of product and raw material contributions to the economics. The gross
margin is the difference between the weighted average unit price of the products and the
weighted average unit price of the raw materials at a single time. By calculating the gross
margin for an economically relevant historical time period, the impact of variations in the gross
margin can be evaluated.
[add gross margin example here]
18
A good process design always maximizes the inherent safety of the facility. This topic is
covered in depth in Chapter 10.
Sustainability/Environmental Impact
Well designed processes maximize the conversion of raw materials into saleable/useable
products and minimize the generation of wastes. When wastes are generated, they should be
kept segregated and at as high of a concentration as possible to make waste treatment as cost
effective as possible. If your project generates wastes, you must also address how those
wastes are treated/disposed as part of your project scope. Thermal pollution should also be
avoided so that energy resources are maximized. Total life cycle sustainability concepts
should be incorporated into design decisions. This topic is covered in Chapter 11.
Constructability
No matter how efficient and profitable a project appears, it is a poor choice if it is impossible
or difficult to actually fabricate and assemble. When evaluating project alternatives, ask the
question, “are there any unusual factors that would make this project hard to build?” Note,
just because one project includes more stuff, does not mean it is more difficult to build. This
factor is about complexity than quantity.
Maintainability
Good projects minimize potential maintenance problems. For example, centrifuges can be
very efficient in separating solids out of a liquid or gas stream. However, these unit
operations typically require substantially greater maintenance than other separation options.
When evaluating project alternatives, ask the question, “are there any unusual factors that
would make this project hard to maintain?” Note, just because one project includes more
stuff, does not mean it is more difficult to maintain. This factor is about complexity than
quantity.
Figure 6.3 is an example of the type of comparison table that can be used to help organize
an analysis of all of the factors that go into selecting the “best” process alternative.
Figure 6.3 A Typical Project Comparison Chart
19
[add an example]
20