Transmittal Document Review Notice: D K C Uba A Y'
Transmittal Document Review Notice: D K C Uba A Y'
u b a l a l " r Y' D f K P C
44017
44017/KCfTl00642
Engineering
Contracting Co.)
To:
Samsung SDS Co. Ltd ley Baker
707 -19 Yoksam- 2 Dong Superintendent's Representative
Kangnam Gu Kuwait Oil Company K.S.C.
Seoul. Korea. 135-918 PO Box 9758
Fax: +82 2 3429 3983 Ahmadi 61008
Kuwait
No
Quality Plan (IMCO Engineering & Contracting
17-OOOOO-Q- PLN-00002
Document Review Notice Comments are attached hereto. Please proceed as per contract requirements.
If indicated. a response is required before the Reply by Date.
PROJECT EF/1700
Integrated Security System for all KOC Facilities
DRN TRANSMITIAL No. SUbject: Contractor Transmittal Reference
44017/CKlT/OOO36 ·
44017/KCfT/OO642 Subcontractor Quality Plan (IMCO Engineering & Contracting Co.)
Date Received
11-Nov-10
Seq I Document No Rev I KOC Comments Status I Contractor's Response
1 I 44017-00000-Q-PLN o INo Comment A I
/ <:"'""",
<?
_~1! OOCU~'ENT STATUS
tJ6lIf!I CLIENT;
44Q1:f .colJtJlJ-61.PJ.N·
ooco2
0 OAT~i . > ISIGNATiJRE'
. 1 ' "F
A - 'D
~
KOC FACILITIES
CONTENTS
1. GENERAL .................................................................................................................... 4
1.1 Purpose .................................................................................................................. 4
1.2 Contract Scope ....................................................................................................... 4
1.3 Overview ................................................................................................................ 4
1.4 Quality Policy .......................................................................................................... 5
1.5 References ............................................................................................................. 5
1.6 Definitions ............................................................................................................... 6
4. DESIGN CONTROL.................................................................................................... 15
4.1 Design and Development Planning ...................................................................... 15
6. PROCUREMENT ........................................................................................................ 16
6.1 Procurement Plan ................................................................................................. 16
6.2 Vendor Evaluation ................................................................................................ 16
6.3 Purchasing Data and Verification.......................................................................... 17
6.4 Handling, Storage, Packaging, Preservation and Delivery ................................... 17
6.5 Control of Fabrication, Construction and Installation ............................................ 17
6.6 Measurement and Control of Construction ........................................................... 18
1.0 GENERAL
1.1 Purpose
The contract scope is to provide for Kuwait Oil Company country wide oilfield sites
and associated control rooms with an integrated electronic security system,
physical perimeter protection and IP based video, audio and data transmitter
networks. The said systems will be installed across ninety six sites distributed
across the North, South, East & West regions of KOC key infrastructures linked to
three Asset Security Centre’s (ASC) & one KOC Security Center (KSC) shall be
carried out in accordance with this quality plan for E&I works as per KOC Contract
Specifications and relevant standards.
1.3 Overview
Project Policy and Objectives shall adhere to IMCO's corporate Quality Policy and
Objectives. This quality policy complies to the requirements of ISO 9001: 2008
Quality Management System International Standard. Refer to attachment # 1 of this
quality plan for IMCO Quality Policy.
1.5 References
1.6 Definitions
All definition concerning quality terms in this document are taken from ISO
9000:2005 known as Quality Management System-Fundamental and Vocabulary.
IMCO Project Team will be lead by Project Manager, who will be the contact point
for all site communications with SDS/KOC. All the site constructions activities will be
controlled by discipline Engineers who will be reporting to respective Site Project
Construction Manager(s) who will be directly in contact with the Project Manager.
This Project Quality Plan shall define as a minimum duties and responsibilities of
the top “key personnel” who are involved in execution of work until project
completion. The resumes of key personnel is as per “Subcontractor Organization
Details” Doc. # 44017-SI-0000-G-PRO-0002.
Job Description:
Project Manager
The Project Manager shall have overall control of the project under the subcontract
scope. His responsibilities include, but are not limited to the following:
The Project Manager shall ensure that only suitably qualified personnel
are assigned to the Project.
The Site Construction Manager shall report directly to the Project Manager. His
duties and responsibilities includes, but not limited to the following:
Organizes and coordinates the work of craft employees.
Exercise control over rate of construction progress in order to complete
the construction project within time limit.
Inspects construction work to enforce conformity to specifications.
Site Engineers
The Engineers shall report directly to the Site Construction Manager. Their
responsibilities include, but are not limited to the following:
Site Supervisors
Coordinate with Safety Officers to avoid any risk of work and report
The Quality Assurance Manager / Engineer shall report directly to the Project
Manager. His duties and responsibilities includes, but not limited to the following:
To coordinate the Quality Control activities and liaise with the third party
Inspectorate as necessary.
The Site QA/QC Engineer and his Section Inspectors/Officers shall ensure that all
installations are performed in accordance with customer/contract specifications,
generating and maintaining quality documents for electrical and instrumentation
works using Quality Control Guidelines and applicable KOC Codes. He shall
develop Quality Documents such as Method Statements, Procedures and
Proforma in co-ordination with the Site Engineers.
The Site QA/QC Engineer shall assist the QA personnel during quality audits
conducted as per audit schedules for carrying out internal audits within the
project. He will liaise with the designated QA Manager with regard to all site
related quality matters.
Conducts inspection of job sites, documents and reports any unsafe acts
& unsafe conditions to the responsible Engineer / Supervisor for
immediate corrective / preventive action.
Contract
Document Number Rev Date Sheet
Number
Ensures that unit supervisor conducts weekly “tool box” meetings with all
personnel in attendance provides appropriate topic or discussion and
initiates follow-up response to safety concerns addressed during these
meetings.
Investigates all incidents and accidents that could involve potential liability,
maintains adequate records of relevant data and complies the required
reports on experience.
Ensure that all required notices, posters and other related literature is
properly displayed for employees’ information. Organize necessary safety
propaganda program for promoting safety and health program for “Safety
Awareness’.
Recommends, selects and ensures that Safety, First Aid, Fire Protection.
Equipment are of relevant standards and also ensures that such material
is always at hand.
Contract
Document Number Rev Date Sheet
Number
Identifies the safe areas near by the work place, locations of emergency
facilities such as fire service, water, first aid clinic, etc.
The Projects Control Manager shall report directly to the Project Manager. His
responsibilities along with Planning Engineers / schedulers include, but are not
limited to the following:
Prepare and present schedules of work, often with visual aids such as bar
charts and procedures diagrams.
Pin Point the critical path of the project and monitor the same of any
deviation.
Contract
Document Number Rev Date Sheet
Number
2.3.1 This Project Quality Plan includes Project Management Review. Project Manager
shall conduct review or as may be required on a case basis. This review shall be in
accordance with IMCO Quality Management System and Standard Procedure -
IMCO/003 known as IMCO Management Review Procedure and shall be conducted
with the Project Top Key Personnel and related personnel involved in the
completion of subcontract activities as agreed with Samsung SDS.
2.3.2 This Project Management Review shall be documented and used as part of the
Project Quality records and consists of structured and comprehensive evaluation of
performance.
2.3.3 This Project Management Review shall be submitted to IMCO Head Office for any
necessary action required or needed and to comply with the ISO requirements.
3.1 General
3.1.1 This Project Quality Plan meets the Standards requirements of:
Electrical Procedures.
Contract
Document Number Rev Date Sheet
Number
3.1.4 The baseline and techniques of project completion with maximum satisfactory
acceptance of SDS / KOC shall be based on the Project Quality Control
Procedures, Method of Statement, Inspection and Test Plan and Construction
Quality Procedures. The list is as per attachment # 4.
3.2.1 IMCO's Contract Division shall review the contractual agreements between
KOC/SDS and SDS/IMCO and any further clarification pertaining to contractual
obligations shall be identified. All the codes and standards shall be highlighted on
its respective procedures, ITP’s and method of statements. IMCO shall be issued
with the Contract Documents / Specifications agreement between KOC / SDS.
Project Review Meeting will be conducted semi-annually and/or as required.
3.2.2 Kuwait's Laws and Regulations applicable to this project shall be identified during
the contract documents review.
3.2.3 IMCO's appointed Project Manager and his team shall review this document and
initiate execution plans, schedule (planning), standard procedures and method of
statements prior to project initiation for electrical area of work.
The Project Manager shall comply and abide to IMCO's Standard Procedure set out
in IMCO/007 known as the Project Management Procedure. The applicable
construction procedure for the project under IMCO work scope are as listed in
Attachment # 4.
Contract
Document Number Rev Date Sheet
Number
3.4.1 The Project Manager and IMCO Safety Manager shall nominate Project Safety
Engineers / Officers who shall be responsible in monitoring, reporting, filling safety
documents. His duties and responsibilities are as referred to clause 2.2 Project
Responsibility of this project quality plan.
3.4.2 IMCO HSE plan will be issued complying to requirements of KOC Safety Manual
and procedures. This plan will be in concurrence with that of SDS the main
contractor. IMCO Health, Safety & Environment policy is referred in Attachment # 3
of this quality plan.
3.4.3 SDS/IMCO Safety formats shall be used and accidents / near miss etc. reported to
KOC as per procedures set out by KOC. Safety gap analysis will be developed
based on the job factors and ensured that its approved by KOC.
4.1.2 IMCO's engineering and planning division shall review all documents submitted by
SDS/KOC and any clarification, information, codes, etc, shall be conveyed to the
Project Manager for notification.
4.1.3 CAD drafting shall be carried out as required based on KOC Engineering Practice
Code Doc. No. EG-DO-C-001 Rev 0. As-built drawing numbering to be followed as
per the said KOC code.
Contract
Document Number Rev Date Sheet
Number
5.1.1 Apart from IMCO's Documentation System, this project quality plan shall abide
and follow the system set out by SDS / KOC as per contract requirement.
5.1.2 Project Procedures and Design and Engineering deliverables will be submitted to
SDS and/KOC for approval.
5.1.3 The document numbering systems followed for submittals shall be the one as
approved by KOC through SDS “Document Distribution Procedure” Doc. # 44017-
00000-Q-PRO-00001.
6.0 PROCUREMENT
6.1.1 The requirements of this section shall comply with the International Standards ISO
9001:2008 as specified in clause 7.4 “Product Realization”.
6.1.2 Scope of IMCO purchase is project required bulk materials for Electrical and
Instrumentation works. Quality requirements shall be clearly specified in all material
requisition and purchase orders. IMCO to ensure all technical and commercial
documentation is complete and shall be established.
6.1.3 All purchasing activities shall be in accordance with IMCO’s standard procedure
IMCO/012 known as IMCO Procurement Procedure and in line with SDS / KOC
Procurement Standard Procedure.
assure that the material to be purchased complies with all the data’s/ specification
of KOC.
6.2.2 Selected Vendor particulars will be submitted to SDS and then KOC for final
approval as required.
6.3.1 Purchase data and verification shall be the sole responsibility of the Purchase
Manager as specified in IMCO/012 known as the Procurement Procedure.
6.3.2 Final approval of purchase request shall commence upon the approval of IMCO
Material Approval Request (MAR). In case of major items if any MAR will be issued
only after final approval is received from SDS/KOC.
6.4.1 Project specification and instructions shall identify any special requirements.
Procedures for handling, storage, packaging and delivery shall be as such to
ensure that they are suitable to prevent damage or deterioration.
6.4.3 Construction procedure spells out the basic preservation for equipments. IMCO will
also ensure that materials will be maintained at site and before installation as per
the vendor manual instructions.
6.5.1 Project requirements shall be clearly identified and provide methodologies for
control of fabrication, construction and installation to ensure control of activities and
subsequently, Inspection and Testing.
6.5.3 During every stage of Construction Activities, the safety of the personnel and
equipment will be ensured by implementation of the Safety Plan. The Safety
Engineer/Officer of IMCO will ensure that no compromise is made in this regard.
6.5.4 Construction, Installation, fabrication and other related activities prior to completion
of the project will be inspected using KOC approved ITP and documented in the
approved format. All applicable check lists will be “Witnessed & signed off” by
IMCO/SDS and finally Inspected and Approved by KOC based on Quality Control
Procedures and Inspection and Test Plan satisfying sub-clause 6.5.1 of this plan.
6.6.1 The progress of the project shall be measured and controlled based on the IMCO’s
work load schedule using “Construction Bar Chart Schedule” with the help of
Primavera Project Planner (P3).
6.6.2 The planning and scheduling of construction shall be in coordination with SDS and
on approval from KOC.
6.6.4 If “Approved for Construction Drawing” do not contain full details for re-
measurement of the work, then physical measurement at work site have to be
carried out. The actual quantities are re-measured in accordance with the method of
measurement as per bill of quantities.
7.1.3 A final / partial commissioning completion certificate shall be filled in and signed by
commissioning personnel and a responsible KOC representative. The documents
then shall be given to the Project Manager for distribution as per contract
requirements.
8.1.1 All contractual scope of works shall be inspected in accordance with KOC approved
Inspection and Test Plan (ITP).
8.1.2 QA/QC Engineer / Officer shall be fully responsible for this activity with a vast
knowledge based on experience from similar projects.
8.1.3 Only approved QC forms shall be used as specified in the Inspection and Test Plan.
On inspection by KOC relevant form complying to the specification, standards set
out by the KOC shall be reviewed / inspected and approved.
8.1.4 IMCO/SDS QMS forms shall be used for inspection during construction and
inspection activities. Wherever advised KOC forms shall be used.
8.1.5 Upon completion of this form, it shall be submitted to KOC and retaining a copy
with SDS/IMCO for future references.
8.1.6 All activities pertaining the inspection and test shall be in accordance with KOC
Inspection and Test Procedure. Refer to attachment # 4 List of Construction
Quality Procedure under IMCO scope.
Contract
Document Number Rev Date Sheet
Number
8.2.1 All in coming products and materials shall be subject for inspection and
approval based on IMCO’s Standard Procedure IMCO/013 and shall be in
accordance with KOC Standards in relation to material handling.
8.2.2 Final inspection and approval shall be performed as per approved quality
documents and the test results evaluated and accepted for compliance with the
specified requirements and meet the specific criteria of acceptance.
8.2.3 All documents and relevant approvals shall be arranged as per KOC requirements
for the completion of final dossier.
8.3.1 Contractual scope of works shall be inspected based on the approved ITP along
with the procedures, method statements and specification and standards.
8.3.2 This document shall provide sufficient information and subject for review as to
conform KOC satisfaction.
8.4.1 All the measuring and test equipment used on this project shall be controlled and
calibrated in accordance with IMCO’ Standard Procedure IMCO/011.
8.4.2 All the measuring and test equipment shall be inspected and approved based on
the supporting documents, e.g. calibration report with at least one year validity.
8.4.3 All the measuring and test equipment shall be recorded in the Site Test Equipment
Register and maintained as specified in the International Standard ISO 9001:2008.
8.5.1 The inspection and test status shall be identified and available with the Site QA/QC
Engineer at all times as mentioned in sub-section 8.4.3 of this plan.
Contract
Document Number Rev Date Sheet
Number
9.1.1 The non-conforming system is under the sole responsibility of the Project Manager
and Site QA/QC Engineer who carries out trend analysis of the raised non-
conformances with the QA section.
9.1.2 The Site QA/QC Engineer shall be responsible for taking corrective and preventive
action of the non-conformance in coordination with QA personnel and ensure that
non-conformance of the same kind shall not be repeated. The close-out of NCR’s
are by Quality Assurance Section.
9.1.3 The Site QA/QC Engineer shall maintain the records of all non-conformance issues
highlighting the action taken and the further steps to prevent recurrence.
9.1.4 The NCR’s and the relevant actions taken shall be discussed during the construction
meetings.
9.2.1 The Site QA/QC Engineer shall be responsible for monitoring corrective / preventive
action in accordance with IMCO’s Standard Procedure as stated in the IMCO/002
known as the Internal Audit Schedule.
9.2.2 All major non-conformances shall be forwarded to IMCO Head Office and proper
action shall be attended by the IMCO’s QA/QC Head and the Executive Manager
Projects Group.
9.2.3 All minor non-conformances shall be reported and the Site QA/QC Engineer who
shall be responsible for the action required to prevent the reoccurrence of the same
kind.
Contract
Document Number Rev Date Sheet
Number
9.3.1 The Project Manager and Site QA/QC Engineer shall be responsible in the
preventive action of project/site non-conformances and shall attend this non-
conformities on the basis of appropriate sources of information such as processes,
work operations and procedures that affect the quality, audit results and/or
KOC/SDS complaints. They shall initiate preventive actions in order to eliminate
potential or probable causes of non-conformities and recommend for improvement
and shall be recorded and documented in the site project file.
9.4.1 The Project Manager and Site QA/QC Engineer shall maintain the records and
documents of non-conformities and measurement of occurrences with detailed
action reflecting the responsible person/ persons liable to non-conformance. It shall
be noted that non-conformances are identified as Major and Minor. QA Manager will
also ensure that the actions are being taken and implemented accordingly.
First offense of non-conformances will be given disciplinary letter / action and re-
occurrence of 3 times of the same non-conformity either minor and major non-
conformances of top key personnel and its manpower resource shall be given a
notice for project.
10.1. The Quality Constructions Records like Signed Contract Document for KOC
Contract # 44017, KOC/Samsung SDS Approved: Project Quality Plan, HSE Plan,
Inspection and Test Plan, Installation Procedures, Method Statements, Test
Contract
Document Number Rev Date Sheet
Number
10.2. The Quality Control and inspection activities will be coordinated with KOC / SDS
personnel by IMCO QA Engineer/ QC Engineer & Officer.
10.3. IMCO QA Engineer / QC Engineer & Officer will be responsible to collect, store and
distribute all construction drawings and documents. He will ensure that any
revisions of drawings are conveyed immediately to the concerned groups and
obsolete documents are withdrawn.
10.4. He will be maintaining Drawing registers, recording receipts, issue and withdrawal
of all revisions. These obsolete drawings will be stamped “Superseded” as per
SDS requirements.
11.1.1 The Site QA/QC Engineer shall submit to the Project Manager the internal audit
schedule based on IMCO Head Office Internal Audit Schedule and forward a copy
to SDS /KOC.
11.1.2 The Project Manager shall disseminate this schedule to his staff for compliance and
the Site QA/QC Engineer shall be audited by the IMCO QA personnel. Audit reports
are issued to the Project Manager in order to improve the work performance and
evaluate with respect to quality and work status / progress.
11.1.3 The result of Internal Audits shall be submitted to KOC as two hard copies and one
electronic copy within two weeks on completion of the schedule audit.
11.2.1 The stages of internal audit shall depend on the Site QA/QC Engineer and the
Contract
Document Number Rev Date Sheet
Number
Project Manager depending on the necessity that affects the quality of work,
customer’s dissatisfaction and non-conformities.
12.0 TRAINING
12.1 The Project Manager shall be responsible to employ personnel to his project and
assures that they are qualified based on their previous experienced with applicable
codes and standards.
12.2 The Project Manager shall approve the nominated personnel required for training
for the purpose and interest of project quality work performance and related as
such. In house training may be suitable in cases for craft personnel and upgrading
their skills.
13.0 SERVICING
14.1 The project statistical techniques shall be applied in accordance with IMCO's
Standard Procedure IMCO/007 known as Project Management and shall be used
to assess the quality levels of workmanship as well as suitability of materials and
associated construction equipment.
15.0 REPORTING
15.1 Reporting to SDS / KOC shall be done as per contractual agreements and all
transactions shall be coordinated directly to Project Manager of IMCO. The base
document used for correspondence and communication is the KOC approved
Contract
Document Number Rev Date Sheet
Number
16.0 ATTACHMENTS