Professional Documents
Culture Documents
Internal Audit - Discussed
Internal Audit - Discussed
Internal Audit - Discussed
In context of para ante It is explained that Clearing & Stripping is not being determined as cft
but the amount of earth which is needed in Compacted Embankment is determined in form of
volumetric quantity as “cft” (for sake of easiness of Quantity surveyor) for precise reference its
applicability is mentioned in last sentence of Clause mentioned ante. However, it is elucidated
that quantity of Clearing & Stripping is same as Quantity of Earth which is needed in
Compacted Embankment after Clearing & Stripping. But, the only difference is that it would
not be taken in form of volumetric quantity such as “Cft” but it would be converted in to Area
such as “Sft” by dividing 0.5 ft (because Layer of Stripping is 6 inch)
According to Clause 1.9, The payment schedule submitted by contractor is presented below for
information and necessary action.