Form: GC-CP-M5

Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
No Major Items of Works Unit
Estimated Executed
Target Actual
1. Hairdin Carrier Drain The work
Extension from Chukhi to completed.
MKZP and 6km North of (from RD
Chukhi. 122+000 to
(Contract No.R-III (c)). 142+300 i-e
(i) Contractor’s Mobilization. -- 100% - - 100% Balochistan
Province
(ii) Survey and Setting Out -- 100% -- -- 100% portion has
Care and Handling of water -- 100% -- -- 100% been
(iii) handed
(iv) Earthwork in Drain over to
Govt. of
(Excavation & Embankment) 1,000 cft 142000 -- -- 141360 Balochistan
)
(v) Construction of VR Bridges
(9 No) & DR Bridge (1 No),
W/C (26 Nos.)

a) Piles(including tests) Nos. 243 - - 243

b) Sub- Structure Nos. 36 - - 36

c) Super Structure Nos. 36 - - 36


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
2. RBOD Extension from
MKZP to Hairdin Pump According
Station. to Contract
Clause 66.1
(Contract No.R-III (b)). of GCC,
(i) Contractor’s Mobilization - 100% - - 100% Contractor
was
(ii) Survey and Setting Out - 100% - - 81% released
from further
Care and Handling of water - 100% - - 73% Performanc
(iii) e due to
(iv) Earthwork in Drain financial
crunch.
(Excavation & Embankment) 1,000 cft 253,650 - - 222920

(v) Construction of VR
Bridges ,DR Bridge & W/C

Piles(including tests) Nos. 595 - - 595

Sub-Structure Nos. 86 - - 80

Super-Structure Nos. 86 - - 80

(vi) Syphon Nos. 2 - - 2

(vii) Out fall Nos. 3 - - 3

(viii) Drain fall Nos. 2 - - 2

(ix) Complex Structures Nos. 1 - - 1


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
3. Construction of Irrigation
Channel upto Chitti River Work
(Contract No. R-III (f)). completed.
(i) Contractor’s Mobilization -- 100% -- -- 100% (Contract
works
(ii) Survey and Setting Out -- 100% -- -- 96% handed over
to Govt. of
(iii) Care and Handling of water -- 100% -- -- 97% Balochistan).
(iv) Earthwork in Drain

(Excavation & Embankment) 1,000 cft 47,080 -- -- 46991

(v) Construction of VR
Bridges ,DR Bridge & Super
passages

Piles(including tests) Nos. 196 -- -- 196

Sub-Structures Nos. 14 -- -- 13 Nos.

Super-Structure Nos. 14 -- -- 13 Nos.

(vi) Drainage culverts Nos. 6 -- -- 6 Nos.

(vii) Escape Nos. 1 -- -- 1 No.

(viii) Cross / Head Regulator Nos. 1 -- -- 1 No.

(ix) Construction of Irrigation Nos. 60 -- -- 60 Nos.


Minor / Outlet
Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
4. Hadero Drainage Unit.

According
(i) Contractor’s Mobilization -- 100% -- -- 100% to Contract
Clause
(ii) Survey and Setting Out -- 100% -- -- 50 66.1 of
GCC,
Care and Handling of water -- 100% -- -- 33 Contractor
(iii) was
(iv) Earthwork in Drain released
from
(Excavation & Embankment) 1,000 cft 77715 -- - 39534 further
Performan
ce of
(v) Construction of VR
Contract
Bridges ,DR Bridge & Super R-III (d/1),
passages due to
financial
a).Piles(including tests) Nos. 146 -- -- 66 crunch.

b).Sub Structures Nos. 136 -- -- 54

c).Supper Structure Nos. 136 -- -- 54


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
5. Usta Muhammad Drainage
Unit.

(i) Contractor’s Mobilization -- 100% -- -- 100% According


to Contract
(ii) Survey and Setting Out -- 100% -- -- 63% Clause
66.1 of
(iii) Care and Handling of water -- 100% -- -- 50% GCC,
Contractor
(iv) Earthwork in Drain was
released
(Excavation & Embankment) 1,000 cft 70,020 -- -- 43050 from
further
Performan
(v) Construction of VR --
ce of
Bridges ,DR Bridge & Super
Contract
passages R-III (d/2),
due to
a).Piles (including tests) Nos. 160 -- -- 150 financial
crunch.
b).Sub-Structure Nos. 107 -- -- 80

c).Super-Structure Nos. 107 -- -- 80


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
6. Re-Modeling of Shahdadkot
Main Drain. Work
completed
(i) Contractor’s Mobilization -- 100% -- -- 100%

(ii) Survey and Setting Out -- 100% -- -- 100%

(iii) Care and Handling of water -- 100% -- -- 100%

(iv) Earthwork in Drain

(Excavation & Embankment) 1,000 cft 132909 -- -- 132019

(v) Construction of VR --
Bridges ,DR Bridge & Super
passages

a). V.R Nos. 7 -- -- 7

b). Water Course Nos. 12 -- -- 12

c). Drainage Inlets Nos. 5 -- -- 5

d). Drain out fall Nos. 4 -- -- 4

e). Drain Falls Nos. 1 -- -- 1

c). Drain Transition Nos. 3 -- -- 2


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
7. Arrangements for opening
of Syphon No. 2 at Saifullah Work
Magsi Canal. completed
(i) Contractor’s Mobilization -- 100% -- -- 100%

(ii) Survey and Setting Out -- 100% -- -- 100%

(iii) Care and Handling of water -- 100% -- -- 100%

(iv) Earthwork in Drain

(Excavation & Embankment) 1,000 cft 6746 -- -- 6746

(v) Structure --

a). Sealing of Bays of under Nos. 1 -- -- 1


pass
b). Box Culvert Nos. 1 -- -- 1
Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Total
Sr. Total Month Remarks
Major Items of Works Unit Execute
No Estimated
Target Actual d
8. Balance Work of RBOD
Extension Drain RD TOC issued.
161+000 to Rd 284+000, Issuance of
Contract R-III b/3 DLC under
(i) Contractor’s Mobilization -- 100% 100% -- 100% approval
process.
(ii) Survey and Setting Out -- 100% 100% -- 100%

(iii) Care and Handling of water -- 100% 100% -- 100%

(iv) Earthwork in Drain

(Excavation & Embankment) 1,000 cft 90,970 90,970 -- 120,300

(v) Construction of VR Bridges, Nos. 34 34 -- 28


DR Brides etc

a). VR Bridges / DR Bridges Nos. 05 05 -- 05

b). Water Course Crossings/ Nos. 09 09 -- 03


Foot Bridge

c). Drain Inlets Nos. 20 20 -- 20


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
8. Balance Work of Hadero
Drainage System, Contract The
R-III d/3 Contract
(i) Contractor’s Mobilization -- 100% -- -- -- work is
substantial
(ii) Survey and Setting Out -- 100% 100% -- 100% ly
completed;
(iii) Care and Handling of water -- 100% 100% -- 100% And TOC
has been
(iv) Earthwork in Drain issued
(Excavation & Embankment) 1,000 cft 77,360 77,360 -- 68,364

(v) Structures Nos. 183 -- -- 216

a). Single & D/box type VRC Nos. 22 22 -- 38

b). Water Course Crossings Nos. 51 51 -- 79

c). VRC cum Aqueduct Nos. 11 11 -- --

d). Drain Transition Nos. 09 09 -- 01

e). Outfall Structure Nos. 03 03 -- 03

f). Outfall cum culvert Nos. 01 01 -- 01


Structure

g). gated Structure Nos. 01 01 -- 01

h). Drainage Inlet Nos. 85 85 -- 93


Form: GC-CP-M5
Construction Projects
BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020

Project Completion Date: 30-06-2006 (as per PC-I)


: 30-06-2021

During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
8. Balance Work of Usta
Muhammad Drainage The
System, Contract R-III d/4 Contract
(i) Contractor’s Mobilization -- 100% -- -- -- work is
substantial
(ii) Survey and Setting Out -- 100% 100% -- 100% ly
completed;
(iii) Care and Handling of water -- 100% 100% -- 100% Issuance
of TOC
(iv) Earthwork in Drain under
(Excavation & Embankment) 1,000 cft 43,500 40,470 -- 40,470 approval
process
(v) Structures Nos. 163 -- -- 206

a). Water Course Crossings Nos. 29 29 -- 88

b). VRC cum Aqueduct Nos. 05 05 -- --

c). Drain Transition Nos. 09 09 -- 01

d). Outfall Structure Nos. 11 11 -- 04

e). pipe culvert Nos. 22 22 -- 23

f). Single & D/box type VRC Nos. 02 02 -- 11


culverts

g) Drainage inlets Nos. 85 85 -- 79