BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
SUMMARY OF QUANTITIES FOR MAJOR ITEMS UP TO 31st DECEMBER, 2020
During Current
Sr. Total Month Total Remarks
No Major Items of Works Unit
Estimated Executed
Target Actual
1. Hairdin Carrier Drain The work
Extension from Chukhi to completed.
MKZP and 6km North of (from RD
Chukhi. 122+000 to
(Contract No.R-III (c)). 142+300 i-e
(i) Contractor’s Mobilization. -- 100% - - 100% Balochistan
Province
(ii) Survey and Setting Out -- 100% -- -- 100% portion has
Care and Handling of water -- 100% -- -- 100% been
(iii) handed
(iv) Earthwork in Drain over to
Govt. of
(Excavation & Embankment) 1,000 cft 142000 -- -- 141360 Balochistan
)
(v) Construction of VR Bridges
(9 No) & DR Bridge (1 No),
W/C (26 Nos.)
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
2. RBOD Extension from
MKZP to Hairdin Pump According
Station. to Contract
Clause 66.1
(Contract No.R-III (b)). of GCC,
(i) Contractor’s Mobilization - 100% - - 100% Contractor
was
(ii) Survey and Setting Out - 100% - - 81% released
from further
Care and Handling of water - 100% - - 73% Performanc
(iii) e due to
(iv) Earthwork in Drain financial
crunch.
(Excavation & Embankment) 1,000 cft 253,650 - - 222920
(v) Construction of VR
Bridges ,DR Bridge & W/C
Sub-Structure Nos. 86 - - 80
Super-Structure Nos. 86 - - 80
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
3. Construction of Irrigation
Channel upto Chitti River Work
(Contract No. R-III (f)). completed.
(i) Contractor’s Mobilization -- 100% -- -- 100% (Contract
works
(ii) Survey and Setting Out -- 100% -- -- 96% handed over
to Govt. of
(iii) Care and Handling of water -- 100% -- -- 97% Balochistan).
(iv) Earthwork in Drain
(v) Construction of VR
Bridges ,DR Bridge & Super
passages
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
4. Hadero Drainage Unit.
According
(i) Contractor’s Mobilization -- 100% -- -- 100% to Contract
Clause
(ii) Survey and Setting Out -- 100% -- -- 50 66.1 of
GCC,
Care and Handling of water -- 100% -- -- 33 Contractor
(iii) was
(iv) Earthwork in Drain released
from
(Excavation & Embankment) 1,000 cft 77715 -- - 39534 further
Performan
ce of
(v) Construction of VR
Contract
Bridges ,DR Bridge & Super R-III (d/1),
passages due to
financial
a).Piles(including tests) Nos. 146 -- -- 66 crunch.
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
5. Usta Muhammad Drainage
Unit.
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
6. Re-Modeling of Shahdadkot
Main Drain. Work
completed
(i) Contractor’s Mobilization -- 100% -- -- 100%
(v) Construction of VR --
Bridges ,DR Bridge & Super
passages
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
7. Arrangements for opening
of Syphon No. 2 at Saifullah Work
Magsi Canal. completed
(i) Contractor’s Mobilization -- 100% -- -- 100%
(v) Structure --
During Current
Total
Sr. Total Month Remarks
Major Items of Works Unit Execute
No Estimated
Target Actual d
8. Balance Work of RBOD
Extension Drain RD TOC issued.
161+000 to Rd 284+000, Issuance of
Contract R-III b/3 DLC under
(i) Contractor’s Mobilization -- 100% 100% -- 100% approval
process.
(ii) Survey and Setting Out -- 100% 100% -- 100%
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
8. Balance Work of Hadero
Drainage System, Contract The
R-III d/3 Contract
(i) Contractor’s Mobilization -- 100% -- -- -- work is
substantial
(ii) Survey and Setting Out -- 100% 100% -- 100% ly
completed;
(iii) Care and Handling of water -- 100% 100% -- 100% And TOC
has been
(iv) Earthwork in Drain issued
(Excavation & Embankment) 1,000 cft 77,360 77,360 -- 68,364
During Current
Sr. Total Month Total Remarks
Major Items of Works Unit
No Estimated Executed
Target Actual
8. Balance Work of Usta
Muhammad Drainage The
System, Contract R-III d/4 Contract
(i) Contractor’s Mobilization -- 100% -- -- -- work is
substantial
(ii) Survey and Setting Out -- 100% 100% -- 100% ly
completed;
(iii) Care and Handling of water -- 100% 100% -- 100% Issuance
of TOC
(iv) Earthwork in Drain under
(Excavation & Embankment) 1,000 cft 43,500 40,470 -- 40,470 approval
process
(v) Structures Nos. 163 -- -- 206