Monthly Labour Proforma March2019
Monthly Labour Proforma March2019
Manpower (Helper/
Sr. Machinery/
Description Unit Operator) Remarks
No. Posts
Unskilled Skilled
1.0 Site Staff Excavation is in Progress
from RD 161+000 to RD
i. Excavator No. 10 10 10 283+190.
ii. Dozer No. 02 02 02
iii. Roller No. 02 01 02 Embankment is in Progress
from RD 162+000 to RD
iv. Grader No. 01 01 01 283+190.
v. Water Bouzer No. 02 0 02
One VRB at 202+040 along
vi. Tractor No. 15
with FTB 238+ 650 & FTB
Trolly/Dumper 263+720 is Completed,
0 15 Moreover One VRB at
271+385 is still Under
Construction.
2.0 Office Staff
i. Site Engineer No. 02 02
ii. Surveyor No. 03 03
iii. Supervisor No. 05 02
iv. Account No.
02 01
Assistant
v. Quantity No.
01 01
Surveyor
Contractors Representative
M/S RAMZAN & SONS(PVT) LTD