Professional Documents
Culture Documents
Guideline Maintenance Handbook 2018 02
Guideline Maintenance Handbook 2018 02
Guideline
Edition: 02
Maintenance Handbook
Guideline_maintenance_handbook_2018_02.docx Page 1 of 87
HeidelbergCement Group Guideline Edition: 02
1. FOREWORD ........................................................................................................................... 5
2. MAINTENANCE PHILOSOPHY.............................................................................................. 6
3. MAINTENANCE ORGANIZATION ......................................................................................... 7
Guideline_maintenance_handbook_2018_02.docx Page 2 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 3 of 87
HeidelbergCement Group Guideline Edition: 02
The Maintenance Handbook was established during the Pilot of the Maintenance Improvement
Project from March until September 2008. The final draft has been reviewed by more than 30
colleagues, all experts in Maintenance, throughout the Group. Their input has then been
implemented in the first version of the Maintenance Handbook, published as Version 1.0 on
October, 13th, 2008.
Version 1.0 has been revised between May and October 2009, taking into consideration first
experience with the Handbook application in the Pilot plants and during the first waves of the roll-
out. This revision, establishing Version 1.1, was published on October 30th, 2009.
Considering the fact that several years elapsed since the last revision, it was decided to thoroughly
review the handbook and release it as the version 2.0. A team of maintenance experts from HTC
(F. Hofko, F. Ritter, M. Jaiswal, R. McDermott, R. Reddy and T. Dijkstra) have carried out the
revision task. Please take a note that the core maintenance processes remained unaltered. Some
of the processes are explained in detail through the newly developed documents and for improved
understanding few maintenance pyramid elements were renamed. This revision, establishing
version 2.0, was published on 16th of April, 2018.
Hyperlinks guide you directly to the referred chapter, a tool / template download or a page on
UNITE, the HC intranet platform.
Guideline_maintenance_handbook_2018_02.docx Page 4 of 87
HeidelbergCement Group Guideline Edition: 02
1. Foreword
Dear Colleagues, Dear Maintenance Experts of HeidelbergCement
HeidelbergCement wants to be a top performer in our industry. To achieve this goal we have to
work in a smart way, professional in all what we do, work with the most qualified personnel and
apply the best knowledge available. Only if we transfer our vision, goals and expertise into real
practice, we can expect tangible changes in our daily work and performance of our plants.
The purpose of this Maintenance Handbook you just opened is to define the HeidelbergCement
philosophy in maintenance. The handbook provides practical guidance in all maintenance
matters. How we want to be organized and how we want to perform our work. It is developed
by HeidelbergCement maintenance experts around the world and meant for all maintenance
experts in our plants.
With the help of the Maintenance Handbook and its expert guidance, we expect to reduce our
maintenance cost, improve the reliability of our equipment and last but not leased improve our
employees’ working conditions.
Every manager, supervisor, engineer and craftsman in our global organization, who is actively
involved in maintenance activities, is asked to apply the procedures, software tools, templates
and implementation guidance given in the HeidelbergCement Maintenance Handbook, specific
local conditions certainly considered.
I herewith like to thank the entire team of all HTCs, Gorazdze (Poland), Ennigerloh (Germany),
Schelklingen (Germany), Ketton (Great Britain) and Brevik (Norway) and all the other people
around the world working so well together. I am deeply impressed about the result and
confident the handbook will bring us further to develop a true professional HeidelbergCement.
Guideline_maintenance_handbook_2018_02.docx Page 5 of 87
HeidelbergCement Group Guideline Edition: 02
2. MAINTENANCE PHILOSOPHY
The Maintenance Philosophy describes the basic ideas behind Heidelberg Cement’s new
maintenance system. The philosophy is based on the maintenance triangle:
The triangle defines the three core maintenance functions; Inspection, Planning and Execution and
their interactions that have a major contribution to maintenance performance. All the three
functions of the maintenance triangle must be existent in a HeidelbergCement plant. All functions
serve the strategic maintenance objectives of performing with competitive (minimum) costs for
maintenance and assuring high equipment availability. Each function has clearly defined roles:
Inspection: Identify needs for maintenance by measuring and following-up the condition of
equipment and analysing trends.
Planning & Scheduling: Define resources (manpower, tools, techniques, spares, etc.) securing
efficient and safe maintenance in agreement with the recommended procedure.
Execution: Carry out maintenance jobs with maximum quality, safety and effectiveness.
Guideline_maintenance_handbook_2018_02.docx Page 6 of 87
HeidelbergCement Group Guideline Edition: 02
3. MAINTENANCE ORGANIZATION
This section is a reference to Heidelberg Cement’s standard organization of maintenance
departments and its integration in a cement plant. All maintenance departments must be organized
according to the standard. The organization required must at least support the three core functions
Inspection, Planning and Execution.
Guideline_maintenance_handbook_2018_02.docx Page 7 of 87
HeidelbergCement Group Guideline Edition: 02
The centralized maintenance department has to comprise all maintenance related activities, e.g.
mechanical maintenance, electrical maintenance, automation, mobile equipment, buildings &
infrastructure, etc. Plants that have a different set-up must change their organization accordingly.
Maintenance Management
The given generic organizational chart for the centralized Maintenance Department defines
structure and reporting lines. The inspection function can be part of the Maintenance Control
Centre or alternatively report into the execution functions (Mechanical / Electrical Management).
Shift maintenance is optional and is reporting to production with a dotted line to maintenance
management. The number of staff of the maintenance department will depend on size and
complexity of the plant. For any support in organizational alignment or changes in the maintenance
department contact your Area HTC. ( Development of Maintenance Organisations)
Guideline_maintenance_handbook_2018_02.docx Page 8 of 87
HeidelbergCement Group Guideline Edition: 02
Ensuring high equipment availability and optimum reliability at lowest possible costs
Following-up and measuring equipment condition to prevent / detect necessary intervention
Preparing / scheduling the maintenance activities with respect to priority and securing spare
parts availability
Carrying out the maintenance jobs with high efficiency, optimum safety and at lowest
possible costs
Continuously improving equipment operational conditions and maintenance practices
Besides the general roles given above, each function has defined specific activities:
Maintenance Management
Define long, medium and short term goals in Contribute to reliability and utilization targets
agreement with plant’s objectives
Ensure compliance with HC’s “Occupational Support planning, acceptance and integration
Health and Safety Policy” for own staff and of new equipment and installations
contractors
Define, control and optimize the maintenance Trigger and control the continuous spare
costs parts optimization process; assure
cooperation with purchasing
Ensure adherence with HC’s policies and Validate and control repair work with
guidelines and the work law significant impact (costs, scope, methods,
etc.)
Ensure continuous training and skill Initiate and supervise RFCA linked to
development for maintenance staff maintenance issues
Guideline_maintenance_handbook_2018_02.docx Page 9 of 87
HeidelbergCement Group Guideline Edition: 02
Inspection
Activities
Ensure planned equipment inspections and initiate work orders based on inspection results
Control and follow-up condition and operational levels of all critical equipment
Check, validate and improve suppliers’ preventive maintenance plans; create respective
inspection sheets
Planning
Activities
Set detailed methodology to perform all maintenance jobs in agreement with priorities,
required resources, skills, coordination and supervision. Make or Buy decision procedure to
be used.
Ensure materials availability for all jobs; secure quantity and quality quality assurance
guidance papers
Set time and cost estimates for work orders to optimize resource utilization
Coordinate maintenance activities with all other departments and define the maintenance
master plan accordingly
Review priorities in the context of work orders and needs of other departments
Manage back-log
Execution
Guideline_maintenance_handbook_2018_02.docx Page 10 of 87
HeidelbergCement Group Guideline Edition: 02
Activities
Complete maintenance jobs according to the highest standards of safety, efficiency and
effectiveness
Execute the planning and preparation of planned stoppages using Shutdown management
guidance papers
Short interval control: Frequently review quality, content and adherence of work orders; active
supervision; use standard templates SIC guidance paper
After job completion, ensure that equipment and its surroundings are in good operating
condition, ready to meet operational requirements, fully inspected, tested, clean and safe
Report back on work orders and notifications (consumption of materials, tools, man hours, skills
and other data required for equipment history files and cost allocation)
Guideline_maintenance_handbook_2018_02.docx Page 11 of 87
HeidelbergCement Group Guideline Edition: 02
Implement job descriptions (JD) for all jobs in the Maintenance Department.
Inform the employees about the content of the JDs and the consequences on
their work.
Guideline_maintenance_handbook_2018_02.docx Page 12 of 87
HeidelbergCement Group Guideline Edition: 02
World Class
Maintenance
Process Integrated
Area Work Process Risk based
Maintenance Process/
Teams Maintena Maintenance
Teams
nce (RbM) Maintenance
Teams System
Computerized
Shutdown Maintenance
Multi Management Autonomous Business
Optimization
Skilling System s Maintenance Plan
(Ex. SAP)
Spares
Spares Standards
Standa Asset Maintenance Resource
Weekly Plan Weekly
Policy
Policy &
& and
rds and History Cost Report Skills Budget
Budget
MPI Report
Management
Managem Specifications
Specifications System Matrix
(GSPP)
ent
For direct link to each chapter move cursor over respective block in the
pyramid above and click CTRL + Left Mouse Button.
All elements coded in red are not considered in HeidelbergCement’s Maintenance System. All
elements coded in white are input elements from sources external to the maintenance department.
The definition, purpose and user group of each element is summarised in the following chapter,
and described in more detail starting in Chapter 4.1 .
Guideline_maintenance_handbook_2018_02.docx Page 13 of 87
HeidelbergCement Group Guideline Edition: 02
4A Management Elements
Maintenance Management has the mission to ensure optimum equipment availability and
performance at minimum cost in the short, medium and long term.
( Management Function Responsibilities)
Purpose:
The Maintenance Cost Structure gives an overview of Group practice on budgeting, accounting
and controlling of Maintenance and Repair Costs.
Purpose:
Efficiently report and follow-up the maintenance costs. Detect variances and take corrective action.
Purpose:
Rules and recommendations for spare part management and handling are given. This ranges from
definition of critical spare parts, inventory control to common stock keeping (one warehouse for
multiple plants) over several countries.
Guideline_maintenance_handbook_2018_02.docx Page 14 of 87
HeidelbergCement Group Guideline Edition: 02
Purpose:
The skills matrix is used to identify the skill level, the skill requirements and training needs for blue
and white collar maintenance employees. The matrix is also used to ensure that tasks are
assigned to employees with adequate skill level.
Multi Skilling
Purpose:
Multi skilling enables maintenance and production employees to cover a range of different jobs in
one workplace. It increases workforce flexibility.
Purpose:
Several Maintenance Performance Indicators (MPI’s) were developed to measure the efficiency
and effectiveness of the maintenance processes. They will be used by maintenance management
to analyse and optimize the performance of the maintenance department.
Guideline_maintenance_handbook_2018_02.docx Page 15 of 87
HeidelbergCement Group Guideline Edition: 02
Reliability management
Reliability coefficient and Mean Time Between Failure (MTBF) are the KPI indicators used for
managing the reliability. Both maintenance and process related kiln stoppages are considered for
the calculation of these KPI’s. Variance analysis triggers a systematic and organized process to
review all downtime incidents and develop action plans to avoid repetition of problems and chronic
failures.
4B Inspection Elements
The maintenance inspection function fulfils the mission of follow up and measure equipment
condition, analyzes trends, and identifies needs for any kind of maintenance, taking into account
the production constraints.
( Inspection Function Responsibilities)
Critical Assets
Purpose:
The identification of Critical Assets is the key element of the maintenance improvement process.
Each plant has to establish and maintain a critical asset list and apply appropriate predictive,
preventive and condition monitoring routines for these assets.
Purpose:
Potential failure modes for equipment and the risk associated will be assessed with the FMEA.
Efficient measures to avoid / minimize the risk must be derived.
Guideline_maintenance_handbook_2018_02.docx Page 16 of 87
HeidelbergCement Group Guideline Edition: 02
Purpose:
The equipment history consists of data covering observations, malfunctions and their causes,
downtime, maintenance work carried out, spares replaced and costs. The asset history is the main
source of data for the analysis of equipment availability and the identification of improvement
measures.
Purpose:
Predictive routines and Condition Based Maintenance (CBM) are described in this section.
Routines and tools combine and use all available information on the condition of a given piece of
equipment / part to make timely decisions about maintenance requirements.
Purpose:
The Root Cause Analysis is a set of tools used to effectively analyse equipment failures. The
techniques are used to support the maintenance improvement process. Recurring equipment
malfunctions must be assessed with the RCFA tools.
Guideline_maintenance_handbook_2018_02.docx Page 17 of 87
HeidelbergCement Group Guideline Edition: 02
Purpose:
Planned Maintenance Routines are activities designed to minimize the risk of unplanned failures.
The routines are integrated into the preventive maintenance system.
Autonomous Maintenance
Purpose:
Autonomous maintenance links maintenance and production departments. Plant operators perform
“five-sense-inspections”, as well as basic cleaning and lubrication routines. They immediately
report malfunctions to supervisors / planners for quick response.
4C Planning Elements
The planning function has the mission to define methodology, the manpower, the spares and other
resources necessary to achieve efficient and safe maintenance in line with technical standards.
( Planning Function Responsibilities)
Purpose:
Work orders are scheduled according to priority, capacity, service and material availability to create
a preliminary bi-weekly plan using SAP PM. Based on this plan, a make-or-buy decision is made to
resolve overload situations. Purchase requisitions are raised for the required non-stock items.
Guideline_maintenance_handbook_2018_02.docx Page 18 of 87
HeidelbergCement Group Guideline Edition: 02
Weekly Plan
Purpose:
The planning process is supported by a structured, weekly meeting where the bi-weekly plan is
reviewed and agreed upon between maintenance and production. Work orders and pick lists are
printed and handed out to maintenance supervisors and stores.
Daily Plan
Purpose:
In the daily plan work orders from the weekly plan are scheduled by the hour and assigned to
individuals.
Shutdown Optimisation
Purpose:
Approach for planning, controlling and reviewing activities during a shutdown period in order to
minimize downtime and costs:
Critical path planning to identify and manage parallel or critical
activities
Set-up the shutdown budget
Value Added / Non-Value Added analysis to identify and remove non-essential activities
Minimize equipment downtime by identifying activities which can be performed outside of a
shutdown or in parallel
Guideline_maintenance_handbook_2018_02.docx Page 19 of 87
HeidelbergCement Group Guideline Edition: 02
Purpose:
A standardized format of the Maintenance Performance Indicator (MPI) report allows the review
and analysis of maintenance efficiency and effectiveness.
Purpose:
Assets are numbered according to the HTC standard numbering system. The consistent
application of the same numbering system in all plants is compulsory. It enables the organization to
develop common strategies for specific critical assets, to source and stock spares and materials for
all technical plant equipment.
Guideline_maintenance_handbook_2018_02.docx Page 20 of 87
HeidelbergCement Group Guideline Edition: 02
Purpose:
List of all spare parts required to maintain an item or asset.
Purpose:
These documents contain standard short description of planned or routine maintenance activities
which provide clear and consistent instruction on the best way to perform a task.
4D Execution Elements
The maintenance execution function has the mission to complete maintenance jobs with the
highest level of quality, safety and effectiveness at minimum costs to maximize equipment
availability. The execution function is linked to many of the pyramid elements. These give
guidelines for performance of its daily tasks.
Purpose:
Short interval control (SIC) is a behaviour ensuring that any variations to the plan can be spotted
and dealt with before they become a problem. This needs a review of the work situation within
short intervals. The supervisor needs to actively seek out information and to follow up when a plan
is not being met.
Guideline_maintenance_handbook_2018_02.docx Page 21 of 87
HeidelbergCement Group Guideline Edition: 02
The generated Maintenance and Repair Costs are “collected” via work orders ( Work
Identification) and distributed to the respective cost centre. The Maintenance and Repair costs are
split according to:
Guideline_maintenance_handbook_2018_02.docx Page 22 of 87
HeidelbergCement Group Guideline Edition: 02
Besides work order types / CO elements 01, 03 and 05, types 06 (non-maintenance work /
technical services), 07 (refurbishment) and 09 (services for third parties) have to be considered
as base load too. Type 10 (insurance cases / dismantling, scrapping) may be part of the base
load or linked to a maintenance / CAPEX project.
Guideline_maintenance_handbook_2018_02.docx Page 23 of 87
HeidelbergCement Group Guideline Edition: 02
Please note that planning and tracking of this cost block is optional and decision can be
taken on plant level.
and
Maintenance Projects
Scope of project
Objective
Estimated cost
Other approval processes (e.g. AFE) may apply as rule of country. Your Area
HTC Maintenance Department must be informed about any approved
Maintenance Project.
In case of questions and for support when defining Base Load and Maintenance
Projects contact your Area HTC.
Guideline_maintenance_handbook_2018_02.docx Page 24 of 87
HeidelbergCement Group Guideline Edition: 02
Group Guidelines and Manuals on accounting and reporting apply. The given
rules are binding for all cement plants.
For each production step Maintenance and Repair costs are split into 7 cost types:
Liners (e.g. mill internals)
Refractories (bricks and monolithics)
Other wear material (e.g. cooler plates, etc.)
Third party repair services (e.g. labour of third parties)
Third party repair materials ( e.g. pre-manufactured spare parts)
Own labour (maintenance hours worked by plant staff)
Guideline_maintenance_handbook_2018_02.docx Page 25 of 87
HeidelbergCement Group Guideline Edition: 02
Additionally each production step is split into the cost blocks Basic Repairs, Base Load Projects
and Maintenance Projects as described in the ( Maintenance Cost Structure ).
To have a centralized tool for the yearly maintenance budget planning for all HC plants, a Repair
Cost Planning (RCP) Tool was developed in SAP-BI with an Excel front-end solution Repair
Cost Planning Guideline
Guideline_maintenance_handbook_2018_02.docx Page 26 of 87
HeidelbergCement Group Guideline Edition: 02
4-6 Repair Cost Planning Tool in BI; Baseload data entry sheet (Excel)
Guideline_maintenance_handbook_2018_02.docx Page 27 of 87
HeidelbergCement Group Guideline Edition: 02
4-7 Repair Cost Planning Tool; Maintenance Projects/ Approved Repairs data entry sheet (Excel)
Links
Group Accounting Manual
Management Accounting Guideline
CO Model
Accounting and Reporting Guideline
Maintenance and Repair Cost Planning Tool
Maintenance and Repair Cost Planning Tool Manual
PM Order Type Manual
Guideline_maintenance_handbook_2018_02.docx Page 28 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Plant / country controller to report, maintenance management to review and act upon
Group KPI report ( KPI Report; restricted access): High level report with maintenance and
repair costs aggregated in the specific Maintenance and Repair Cost per ton of equivalent cement
production
Group OCR report ( OCR Report; restricted access): The OCR Maintenance report shows the
Maintenance and Repair Costs split into:
SAP reports mentioned in this section work for SLO2 countries only. In other or non-SAP
environments (e.g. A/O or NAM) contact your Area HTC for further support on available
Maintenance Cost reports.
Responsibility
Plant maintenance management to report, review and act upon.
Guideline_maintenance_handbook_2018_02.docx Page 29 of 87
HeidelbergCement Group Guideline Edition: 02
SAP report S 501 shows the Maintenance and Repair Costs related to the respective work order
where the costs were accounted to. The costs are split in different cost types. The report is
available via SAP transaction MCIS.
Description
SAP report S501 only shows costs accounted to PM work orders. Other
orders are not considered.
Guideline_maintenance_handbook_2018_02.docx Page 30 of 87
HeidelbergCement Group Guideline Edition: 02
Cost types
Costs data
Guideline_maintenance_handbook_2018_02.docx Page 31 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Establishing / maintaining the skills matrix: Maintenance Manager / Supervisors
Training courses: Maintenance Management, HR department, Area HTCs
Update frequency
Once a year
Recommended Procedure
To develop an accurate skills matrix tool follow the 3 steps given below.
Guideline_maintenance_handbook_2018_02.docx Page 32 of 87
HeidelbergCement Group Guideline Edition: 02
Mechanical Supervisor
Maintenance Manager
Pneumatic knowledge
Electrical Supervisor
Training for workers
Reliability engineer
Cooler technology
Budget planning
ESP technology
EVA calculation
Communication
Kiln technology
RCM (FMECA)
Project leader
Electric motor
Head of MCC
Software Eng
Job Planning
Name, Surname
Transformer
Leadership
Team work
MS Project
Comments
SAP / MM
MS Office
SAP / PM
Foreman
Planner
English
E-plan
RCFA
CAD
PLC
Number required
Available good 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 4 3 0 2 0 3 0 12 0 0 0 0 0 0 0 0 0 0 0 2 2 2 0
Available average 7 12 10 4 4 8 12 10 3 10 1 11 4 4 4 1 5 0 0 2 9 6 0 7 8 8 7 7 6 3 3 6 11 10 2 2 2 2
1 L A L L L L A L L L L A L L A G A L U L A A G A L L L L L L L A A L A A A L ?
2 A A A L L L A A U A U A U U U U A U U A A L G L A A A A A U U A A A U U U U ?
3 A A A L L A A A L A L A L L U L A U U L A L G A A A A A A L L L A A U U U L X
4 L A A A A A A A L A L L L L U L L U U L A A G A L L L L L L L L A A U U U L X
5 L A A A A A A A L A L A L L U L L U U L A A G A A A L L L L L L A A U U U A X
6 L A A A A L A A L L U A U U U U L U U L A L G L L L L L L L L L L L U U U L X
7 A A A L L A A A A A U A A A A G G L G A G A G A A A A A A A A A A A G G G L X
8 L A L L L L A L L A L A L L U L L U U L A L G L L L L L L L L L A A U U U L X
9 A A A A A A A A A A A A G G U A A U U L G A G A A A A A A A A A A A L U U A X
10 A A A U U A A A U A U A A A A G G L G U G U G L A A A A A A A A A A A A G U X
11 A A A L L A A A L A L A A A A G G L L L A L G L A A A A A L L A A A G G A L X
12 A A A L L A A A A A L A A A U L A U U L A A G A A A A A L L L L A A U U U L X
13
14
15
16
17
4-10 Resource Skills Matrix
18
Guideline_maintenance_handbook_2018_02.docx Page 33 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Maintenance Manager / Plant Management / HR department / Area HTCs
Recommended Procedure
As a first step the actual skill level need to be analysed by a Resource Skills Matrix. The skills
matrix determines qualification / education requirements based on the existing work structure.
Additionally, age structure, succession planning, fluctuation and long term development plans of
the plant must be considered.
Based on these results a training and skills-enhancing activity program has to be developed. The
following steps can be used as a guideline to set up such a program. It may differ from country to
country and might need adjustment. Ask the responsible Area HTC for support.
Links
Basic Training Courses
Advanced Training Courses
Guideline_maintenance_handbook_2018_02.docx Page 34 of 87
HeidelbergCement Group Guideline Edition: 02
Understanding of the MPIs, their meaning and calculation is crucial to proper use. Maintenance
Managers have to make sure that they and their teams are properly trained in the use and
interpretation of the MPIs. Your Area HTC is able to offer training sessions on the MPIs.
Links
MPI Explanation
Guideline_maintenance_handbook_2018_02.docx Page 35 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 36 of 87
HeidelbergCement Group Guideline Edition: 02
also included in the calculation together with the maintenance causes. In HC group there are many
countries where uninterrupted power supply is still not possible and in such plants the MTBF will be
quite low. Hence it is difficult to benchmark the plants across the geographical regions on the basis
of only MTBF.
Hence, it is recommended to use the MTBF in combination with reliability coefficient to track the
plant maintenance performance.
Responsibility
Plant Manager, Production Manager, Maintenance Manager
Guideline_maintenance_handbook_2018_02.docx Page 37 of 87
HeidelbergCement Group Guideline Edition: 02
Recommended Procedure
The Critical Asset process consists of a 3-step-approach:
Guideline_maintenance_handbook_2018_02.docx Page 38 of 87
HeidelbergCement Group Guideline Edition: 02
1 Classification
Plant Structure
(SAP / EXCEL)
2 FMEA
Equipment Data
and History
3 Risk Control
Choose Sub-System Reduction of
– Failure probability
– Failure consequences
Measures
– Design: De-bottlenecking
– Preventative: Inspections
– Reactive: Repair
Criticality Analysis
– Logistics: Spares availability
Guideline_maintenance_handbook_2018_02.docx Page 39 of 87
HeidelbergCement Group Guideline Edition: 02
4-13 Critical Asset Map Example (not showing equipment with normal criticality)
Guideline_maintenance_handbook_2018_02.docx Page 40 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 41 of 87
HeidelbergCement Group Guideline Edition: 02
Tools
The Critical Asset Tool is a PowerPoint based assessment tree.
Failure
normally
results in
Yes Instant system shutdown No Potential system shutdown Potential system shutdown
Yes within 24 hours No Yes within 48 hours No
Yes Loss of life, limb or lost time No Potential safety hazard to Incidental safety hazard to
Yes personnel No Yes personnel No
Guideline_maintenance_handbook_2018_02.docx Page 42 of 87
HeidelbergCement Group Guideline Edition: 02
As FMEA process is quite cumbersome and requires deep knowledge concerning the equipment, it
could be quite possible that the process is not adequately executed. Hence, the process is
categorised as the optional process.
Responsibilities
FMEA Team
The FMEA Team will be staffed with the Maintenance Engineer, Maintenance
Supervisors, production staff and optionally other departments (temporarily).
The optimum team size is 4 to 5 members. When done for the first time, ask
HTC for mediation.
Basic Concept
The FMEA process aims at risk minimization linked to failures on critical assets. The risk
associated with a potential failure is calculated with the Risk Priority Number.
Guideline_maintenance_handbook_2018_02.docx Page 43 of 87
HeidelbergCement Group Guideline Edition: 02
In the next step all costs associated to the risk assessed must be taken into consideration. Actions
to reduce the risks with high Risk Priority Numbers must be derived and their costs
estimated/calculated. It is then a management task to decide which risk is acceptable and which
actions will be undertaken to reduce unacceptably high risks.
Guideline_maintenance_handbook_2018_02.docx Page 44 of 87
HeidelbergCement Group Guideline Edition: 02
FMEA template
FMEA documentation
RPN concept
Plant FMEAs
Guideline_maintenance_handbook_2018_02.docx Page 45 of 87
HeidelbergCement Group Guideline Edition: 02
Within SAP, maintenance work is processed via notifications, work orders and (order-) completion
confirmations. The data entered into the SAP system when creating and reporting back these
items documents the asset history and is the base for asset history analysis as described in the
Root Cause Failure Analysis chapter and mainly used in the course of the Critical Asset
process and FMEA.
Notifications: Contain the technical history: codes for causes and activities,
malfunction/system down times
Work orders: Document maintenance activity, material consumption and cost
To assure the quality of the asset history system some rules have to be met:
Responsibility
Maintenance Supervisors to report back on work orders / notifications, maintenance planning /
inspection function to oversee data completeness and quality. FMEA teams to utilise the data for
asset history analysis
Guideline_maintenance_handbook_2018_02.docx Page 46 of 87
HeidelbergCement Group Guideline Edition: 02
In course of the use of the Critical Asset and FMEA process, it is determined what
equipment is to be condition monitored in what respects and how often. All condition monitoring
routines must be integrated into the planned maintenance system. Any abnormal condition
detected has to result in the creation of a notification. The data obtained via condition monitoring is
a vital part of the Asset History and must be used for further reference and trend analysis.
Guideline_maintenance_handbook_2018_02.docx Page 47 of 87
HeidelbergCement Group Guideline Edition: 02
Links
Condition Monitoring Tools
Guideline_maintenance_handbook_2018_02.docx Page 48 of 87
HeidelbergCement Group Guideline Edition: 02
5 Why’s
Cause and Effect Diagram
Fault Tree Analysis
Pareto Analysis
The 5 Why’s, the Cause and Effect Diagram and the Fault Tree Analysis are used to logically
identify all causes that lead to failures. The Pareto Analysis is a simple statistical approach which
can be applied almost universally wherever sufficient data is available. All techniques will be
applied in combination, i.e. the 5 Why’s can be used to create a Cause and Effect Diagram or a
Fault Tree Diagram.
In combination with the other elements described in the inspection responsibilities chapter, these
techniques actually resemble a continuous improvement circle as show below.
Asset history
Condition monitoring
Reliability KPI
Asset History Determine root • 5 Why’s
Observe
Critical
CriticalAsset
Asset causes / • Cause / Effect Diagram
predominant causes • Fault Tree Diagram
FMEA
FMEA • Pareto Analysis
Implement Define
counter- counter-
measures measures Planned Maintenance
Maintenance Routines
Operating System Predictive routines
Improvements (work
order activity types 170,
900, 910)
Guideline_maintenance_handbook_2018_02.docx Page 49 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Maintenance Manager, production manager, maintenance planning, maintenance supervisors and
inspectors, FMEA teams
Recommended Procedure
Assemble a group with representatives and experts from all relevant functions
Schedule the event in advance; ensure that sufficient time and tools are available.
Define exactly the problem / failure to investigate
Conduct one or a combination of the methods described below
Define measures
Document the results
In preparation of a RCFA session, the Asset History of the equipment in question must be
analysed to obtain the data needed. Typical questions that have to be asked in the course of such
an analysis, and can be answered using the tools described below, include but are not limited to:
Question Tools / How To
What functional locations contributed mostly to the a) a) Downtimes can only be reported when documented in notifications - IW28/IW29
downtime, b) hours spend on maintenance, c) maintenance notification list
cost of the plant? b) Hours spend can be reported using the Operation list - IW37n
c) Maintenance costs can be reported using MCIS reporting
What pieces of equipment contributed mostly to the a) see above
downtime, b) hours spend on maintenance, c) maintenance
cost of these functional locations?
Of that equipment, which failures (failure codes) were Damage reporting is based on codes that are documented in notifications in
predominant? completion confirmation processes and can be reported in notification item list -
IW69. Alternatively, a customer specific info structure in PM IS can be created.
What reasons (reason codes) caused the equipment to fail / Damage cause reporting is based on codes that are documented in notifications in
malfunction most often? completion confirmation processes and can be reported in notification item list -
IW68/IW69. Alternatively, a customer specific info structure in PM IS can be
created
Which spares had to be replaced most frequently? Used spare parts can be listed using standard order list functionality - IW38/IW39
list PM orders for Equipment – goto menu: environment – goods movements
Have the preventative maintenance routines associated with Information on planned/actual operation data is retrieved from the Order/operation
that equipment been carried out timely and completely? list. To provide more detailed information, the new list IW37n should be used.
What repair work was done most frequently (activity code)? Activity code reporting is based on codes that are documented in notifications in
completion confirmation processes and can be reported in notification activities list
- IW64/IW65. Alternatively, a customer specific info structure in PM IS can be
created.
Were there several work orders linked to the same incident, A link between usage/ operation data and malfunctions could be determined in the
i.e. was the quality of the repair insufficient? If so, why? SAP system by comparing the development of a counter/measurement reading
and the malfunctions reported in notifications. This has to be done manually
Is there a link in between usage / operating parameters and Manually by comparing process parameters / frequency of malfunctions etc
malfunctions?
Guideline_maintenance_handbook_2018_02.docx Page 50 of 87
HeidelbergCement Group Guideline Edition: 02
4-21 RCFA for high abrasion on a dust dosing device (Lengfurt plant; Germany)
Tools
5 Why’s
Cause and Effect Diagram
Fault Tree Analysis
Pareto Analysis
RCFA flow template
Guideline_maintenance_handbook_2018_02.docx Page 51 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Inspection / Planning functions
Recommended Procedure
All planned maintenance routines are put together in a preventive maintenance program. The
preventive maintenance program covers all necessary inspections / service measures considering
time / counter based frequencies and follow manufacturer’s recommendations and own
experiences.
The basic content of any preventive maintenance program is lubrication ( lubrication plan),
cleaning and inspection.
Special preventive maintenance routines must be derived for all equipment rated critical or highly
critical ( Critical Assets), e.g. kilns, raw mills, cement mills, ID fans, etc. For support contact
your Area HTC
Tools
The standard inspection instructions for mechanical maintenance contain visual and functional
checks. For the mechanical equipment inspections no interval is given since the inspection
frequency varies with capacity utilization of the given equipment. The intervals must be defined on
plant level. Inspection frequencies for mechanical equipment can be determined using the
Critical Asset Assessment Tool.
Guideline_maintenance_handbook_2018_02.docx Page 52 of 87
HeidelbergCement Group Guideline Edition: 02
Inspection procedures and protocol templates are available to support liner inspections:
Shell liners of 1st / 2nd compartment
Slot liners for diaphragm(s) and outlet wall
Head liners for inlet wall and diaphragm(s)
Detailed check of all mill internals at least once per year. Higher frequency of
visual inspections is necessary for:
Mills grinding abrasive materials (e.g. slag)
Mills with a tendency to liner damage (perform RCFA!)
Mills with boltless liners
Preventive maintenance activities are planned and scheduled by work order type PM03 (
Guideline PM Order Types). Each preventive maintenance activity is supported by the following
documents:
Maintenance Plans
Maintenance & Inspection Instructions (ME/EL)
Links
Standard Maintenance Procedure – Ball Mills
Kiln walk-by inspection check sheet
Guideline_maintenance_handbook_2018_02.docx Page 53 of 87
HeidelbergCement Group Guideline Edition: 02
1. General inspection
2. Adapted instructions coming out of the preventive maintenance system
3. Using of checklists for cleaning and standard lubrication
4. Initial cleaning
5. Eliminating sources of contamination and inaccessible areas
6. Organization and housekeeping
7. Full Implementation Continuity
Links
Operator Inspection Instructions
Guideline_maintenance_handbook_2018_02.docx Page 54 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Planning function
Starting point is the identification of maintenance work from all different sources and the
consolidation of these items in one common list. With SAP/PM, the built in notification system must
be used; in case SAP/PM is not installed a similar methodology must be employed, e.g. an
EXCEL-solution. Next step is the collection of all information necessary to assess these
notifications and to execute the work.
Maintenance tasks can be identified from the following areas listed below:
Condition Monitoring
Health, Safety and Environmental Issues
Production / Process
Preventive Maintenance
Shutdowns and Projects
Emergencies
Verbal requests
Finally, a work order for the work identified has to be created. The work order creation process is
described in the last section of this chapter. When created the work order is fed into the Work
Order System.
Recommended Procedure
The person responsible for Health & Safety and Environmental Issues constantly maintains a list
of, and creates notifications for, all health, safety and environmental issues that require
maintenance intervention which are prioritised in accordance with the Prioritisation Matrix. A
Guideline_maintenance_handbook_2018_02.docx Page 55 of 87
HeidelbergCement Group Guideline Edition: 02
brief, weekly meeting with maintenance planning is used to talk through that list and review
progress. The notification numbers are used to follow-up on the issues. The status of all issues is
periodically reported to the management.
The HSE related issues may need to be dealt with timely or even immediately without by-passing
the standard process.
Recommended Procedure
After the shift manager’s handover meeting, the early morning production – maintenance meeting
takes place. The participants are: production representative(s), the maintenance planner and
maintenance supervisors.
1. List & describe equipment malfunctions that require immediate action today (shift manager)
2. Agree on priority of these using the prioritisation matrix (all)
3. Discuss shift managers log including any other observations that might require
maintenance
4. Shift manager to report on shift maintenance activity
Meeting duration approximately 10 minutes
Planning representative to create work orders for urgent issues immediately after the
meeting
Supervisors to incorporate urgent issues in today’s schedule prior to the work assignment
meeting
Guideline_maintenance_handbook_2018_02.docx Page 56 of 87
HeidelbergCement Group Guideline Edition: 02
Planning representative to print the notifications for all other issues prior to daily
maintenance review meeting
Guideline_maintenance_handbook_2018_02.docx Page 57 of 87
HeidelbergCement Group Guideline Edition: 02
OrderType Name
Recommended Procedure
A Work Preparation Checklist is used to conduct the technical clarification on-site. Planning
will then:
If the job is to be done in the course of a shutdown it is to put into a “revision list“. In case of a
project (priority 5 or 6) it will be handed over to the person tasked with project planning. Otherwise,
a work order has to be created from the notification, which needs to include:
Guideline_maintenance_handbook_2018_02.docx Page 58 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 59 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
All staff involved in the prioritisation of notifications and work orders
Recommended Procedure
Six (seven) different priorities are implemented within the SAP PM standard and must
be assigned to each job on the respective work order:
1 Immediately (Emergency)
2 Today
3 Within a week
4 Within a month or priority 5 and 6
5 Next shut down
6 Annual shut down
(9 Buffer work)
Each notification or work order is prioritised consistently using the priority codes. To ensure that
always the right prioritisation code is used an automatic procedure linked to the critical asset list
generates a priority example.
Guideline_maintenance_handbook_2018_02.docx Page 60 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 61 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Planning function
Recommended Procedure
The work order process consists of 4 main steps:
The next step is to identify those work orders that require external resources. These work
orders must be assigned to an appropriate work centre and linked to the person that will
manage the contractors on site.
Start with 30% allowance for corrective work and adjust over time.
Guideline_maintenance_handbook_2018_02.docx Page 62 of 87
HeidelbergCement Group Guideline Edition: 02
Capacity demand and available capacity are levelled as much as possible by moving
individual orders back & forth in time, or by working on the capacity availability (vacation
planning, temporary labour, overtime, etc.)
In case that overload situations could not be resolved (jobs postponed in accordance with
Prioritisation Matrix), a proposal is made by planning, with the collaboration of
workshop managers, which jobs could be supported by contractors, and how. The
procedure is described in the Make or Buy Decision guidance paper. This proposal, plus
the work orders outsourced by default, are being brought forward to management
(Maintenance Manager and/or Plant Manager) using a Contractor Approval Form.
Management will then make the final decision on using contractors based on the budget
and the Weekly Maintenance Report.
Never authorize contractor work w/o checking capacity plan and cost report.
The biweekly plan is updated accordingly and distributed in preparation of the Weekly
Maintenance Planning Meeting.
Tools
User Manual PM
Guideline_maintenance_handbook_2018_02.docx Page 63 of 87
HeidelbergCement Group Guideline Edition: 02
The more accurate the planning, the less time is needed for execution.
Responsibility
Planning function
Prerequisites
The following prerequisites must be met in order to enable order and capacity planning with SAP;
all cement plants are required to meet these prerequisites:
SAP PM work centres must exist for each supervisor group respectively for each workshop
(e.g. work centres for mechanical maintenance, electrical maintenance etc.; see
Maintenance Organisation)
The work centre capacity must be constantly maintained on a weekly basis to reflect the
current situation (vacation, absenteeism etc.) in the Graphical Work Order Scheduler
(GWOS). The “capacity utilization” field must be set to the average efficiency of that work
centre (see Weekly Maintenance Report). If no history is available start with 80%.
All work orders must contain work time, number of people required, and plan duration
(Exception: Order types PM05 and PM01 with activity type 150, emergencies). All work
orders have to include priority and must be assigned to the appropriate work centre.
Completed work orders must be reported back via completion confirmations daily. For
orders started but not finished, actual hours, actual duration and remaining work are
reported back. Each resource assigned with a task is responsible for timely and correct
feedback. The area supervisor coordinates and controls the feedback loop.
The cost booked onto work order type PM05 must be restricted to maximum 10 % of the
total monthly maintenance costs per plant.
The process described above can also be applied in non-SAP environments using EXCEL.
Templates and support are available from Area HTC.
Recommended Procedure
The weekly planning process overlaps with the work order system process and consists of 3 steps:
Step 1 – Create preliminary weekly plan
This is done in SAP with the GWOS planning tool (Guideline Graphical Work Order Scheduler
(GWOS)). Order planning and load balancing have to be done on work centre basis, i.e. each week
the plan for the next week is created. Capacity planning on the level of each individual employee is
not done with the GWOS tool in step 3 (Final Weekly Plan). The supervisor is in charge of this task
( Maintenance Coordination). The actual scheduling is done individually for each work centre by
the planners (Mechanical and Electrical) from the Maintenance Control Centre (MCC). The
following sequence is used to create the plan:
1. Preselect all relevant work orders you intend to schedule for the next week
2. Review the material availability of all work orders you intend to schedule within the next
week.
3. Release all work orders you intend to schedule for the next week.
4. Schedule next week’s orders in sequence of descending priority. When scheduling orders
of the same priority, those overdue are planned in first in the order of their delay.
Guideline_maintenance_handbook_2018_02.docx Page 64 of 87
HeidelbergCement Group Guideline Edition: 02
5. Allocate a percentage of the weekly work centre capacity to buffer work (low priority work
that can be interrupted / rescheduled / postponed at short notice). This allows reacting on
unplanned work and breakdowns.
6. Cluster jobs by area / asset (Functional location / Equipment), e.g. all work to be done at
the raw mill is scheduled for the same day.
7. Schedule work on equipment with high power consumption (e.g. mills) in periods when
electricity prices are high whenever possible; schedule multiple-crew jobs to start in the
morning.
8. Evaluate the weekly capacity load (GWOS capacity planner function).
9. In case overload situations cannot be resolved, use overtime, postpone vacations, borrow
personnel from other work centres.
10. If underutilisation occurs, schedule more work for the planning period
11. For remaining overload situations, it must be decided to either outsource that work (‘’Make
or Buy’’ decision),, to postpone it or not to do it ( Work Order System).
12. Evaluate the resulting capacity load. Level the daily capacity demand / capacity
requirement as much as possible by moving orders back and forth in GWOS.
13. If underutilisation occurs, schedule more work for that period
14. Maintain the work centres work buffer by identifying additional buffer work worth about 20%
of the weekly capacity. This work will be done in case other jobs cannot be done for
whatever reason in a first in – first out sequence. Work buffer orders are identified by
setting the priority to 9.
1. Review action log (Improvement Measures Board): The action log states all open actions
and a due date assigned.
2. Review MPIs and take actions for any variance (plan – actual – variance – action)
3. Review last week’s plan (plan – actual – variance – action)
4. Discuss the plan for the next week
5. Agree equipment shutdowns and preparatory work to be done by production
6. Summarize all changes to the preliminary plan and all new action in the action log
The preliminary weekly plan and the MPI report of the previous week must be distributed to
all participants in a timely manner.
The updated action list and the final plan must be available before the weekend.
Tip: Agreeing fixed weekdays for weekly shutdown routine work on key equipment (raw
mill, cement mill, etc.) reduces discussions during the meeting.
Guideline_maintenance_handbook_2018_02.docx Page 65 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 66 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 67 of 87
HeidelbergCement Group Guideline Edition: 02
Recommended Procedure
All craftsmen are split in working groups (if possible/ suitable) and the working time per task
including corresponding work order number is visible in the plan. The daily plan is maintained/
actualized by the planner in close coordination with the respective supervisor. In the morning the
Daily Plan is available for review and task assignment, and prior to the Daily Maintenance
Review Meeting the past plan is substituted by the actual one. Unplanned work of the current day
needs to be incorporated into the Daily Plan prior to the task assignment meeting by the
supervisor. For unplanned work arising after the task assignment meeting use the Prioritisation
Matrix as guidance. Within the Daily Plan, each individual’s working time is scheduled out by
100%, planning for zero lost time. Any allowance for unplanned corrective work is filled up with
backup/ buffer work (typically lower priority preventive maintenance work with priority 9).
Review the team performance of the previous day and discuss variances in plan vs actual
(e.g. schedule adherence, efficiency, potential problems or unwanted behaviour etc.)
Assign today’s tasks and communicate time targets to team members
Make sure that all tasks have been understood
Handover the printed work order
Discuss safety issues
Recommended Procedure
The work assignment meeting is done daily at the beginning of the maintenance day shift by the
supervisor with all his craftsmen. Normal duration of the meeting is not more than 10 minutes. In
preparation for the meeting, the supervisor has to
Guideline_maintenance_handbook_2018_02.docx Page 68 of 87
HeidelbergCement Group Guideline Edition: 02
Each team member briefly reviews his / her accomplishments. Any problem or variance that could
be prevented has to be recorded by the supervisor.
2) Task assignment
Referring to the daily plan, the supervisor explains all operators in detail the tasks assigned to
them and handed out printed work order.
3) Current and potential health & safety issues are addressed by the supervisor (at least one topic
every day)
Objectives
Once per week (e.g. every Monday) review maintenance performance from previous week,
identify variances and define improvement measure based on Maintenance
Performance Indicators
Review daily maintenance performance, identify variances and define improvement
measure
Review and agree on priorities & schedule.
Identification & prioritisation of new work
Review of safety issues and improvement measures due
Guideline_maintenance_handbook_2018_02.docx Page 69 of 87
HeidelbergCement Group Guideline Edition: 02
Recommended Procedure
The meeting is led by the maintenance manager. All maintenance managerial staff including the
supervisor level participates, as well as a production representative (i.e. shift manager, production
manager, process engineer, etc.). Other functions such as the quality manager or health & safety
advisor participate as required. The meeting lasts about 30 minutes and adheres to the following
agenda:
1) Review yesterday’s maintenance activity using the scheduling boards / the weekly plan
Each supervisor to present and highlight variances (plan vs. actual)
Define & record improvement measures if applicable (Improvement measure boards)
Re-prioritise jobs not done
2) Review all changes made to today’s schedule (unplanned work)
3) Review & agree on tomorrows schedules (each supervisor to prepare & present deviations from
weekly plan)
4) Review all relevant new notifications, agree on priority (planning to prepare)
5) Other requests from production, ongoing problems etc. Discuss, agree on action & priority
6. Discuss the interfaces between maintenance, production and laboratory.
7) Health & safety, environmental, quality issues
8) Review improvement measures due
Guideline_maintenance_handbook_2018_02.docx Page 70 of 87
HeidelbergCement Group Guideline Edition: 02
A standardised and structured process has been developed which must be implemented in all
cement plants.
Recommended Procedure
The process follows 8 steps:
Guideline_maintenance_handbook_2018_02.docx Page 71 of 87
HeidelbergCement Group Guideline Edition: 02
Step 2: Set up project team, structure, schedule – week 4 after last shutdown
Assemble planning team
Conduct kick-off meeting (plant manager to participate)
Agree on planning schedule, fix meeting dates until next shutdown
Task participants to collect data necessary to compile initial scope of work using the
Shutdown Management guidance paper
Step 3: Create scope of work and budget proposal – week 6 after last shutdown
Collect all proposals for work to be conducted in the next shutdown. The proposals must be
in a the standardised format, stating
o Functional location and equipment code
o Description of work to be done
o Justification why work is necessary and what risks are associated in doing / not
doing the work
o Estimated costs divided in materials and services
o Estimated man hours required
o Potential contractors that are capable to do the work
Consolidate all proposals in a common list and pre-prioritise
Discuss proposals with plant- and maintenance management and select measures to be
included in budget proposal / project planning
File budget proposal including list and allowance for unplanned work based on past
experience
Issues that arise after that, need to follow the same process to be included in the scope of
work
Step 4: Create a high level project plan – week 10 after last shutdown
Guideline_maintenance_handbook_2018_02.docx Page 72 of 87
HeidelbergCement Group Guideline Edition: 02
Enter all approved tasks into MS Project. Include Task description, SAP work order where
available, duration in days, man hours required, responsible person, predecessors. Sort by
functional location
Set project start date and arrange tasks in sequence. Identify critical path
Examine all tasks on the critical path and optimise (externalising, parallelising work,
allocating additional resources within reason etc.). Repeat until no further compression can
be achieved
Step 5: Bundle tasks and request quotes – week 12 after last shutdown
Bundle all tasks to fit available contractor capabilities
Request quotes for all bundles and material (see also Contractor Management).
Include high level plan in tender document. Bidders have to include a detailed project plan
(three hour increments) to fit into the high level plan. This must include dedicated safety
buffers (ask them not to hide safety buffers in task durations). Delivery dates / capacity
availability in line with the high level plan must be confirmed.
Guideline_maintenance_handbook_2018_02.docx Page 73 of 87
HeidelbergCement Group Guideline Edition: 02
Generate purchase requisitions from work orders and purchase orders for all materials and
services. Include detailed project plan in purchase order where applicable. Delivery date for
all materials is two weeks before shutdown start
Feedback confirmed delivery dates into SAP
Brief all staff responsible for supervising an area during the shutdown (project plan, scope
of work, authorisation procedure for unplanned work, expectation for follow-up ( Short
Interval Control) and reporting ( Daily Review Meeting Slides), final inspection
procedure for contractor jobs
Ensure all prerequisites to start the work are met (material / capacity availability, permits,
authorisations by local authorities, safety inductions…)
Two weeks prior to shutdown start, commission all materials
Links
Shutdown Management guidance paper
SIC Guidance paper
HTC NAM Outage Planning Manual
Shutdown Planning Tool
Guideline_maintenance_handbook_2018_02.docx Page 74 of 87
HeidelbergCement Group Guideline Edition: 02
Contractors are used only if the work cannot / should not be done by own personnel
Make or Buy decision (Link to Guidance Paper)
The best contractors are chosen with regards to quality, reliability, efficiency and cost
The scope of work, terms and conditions are defined precisely within the contracts
Contractors are managed efficiently: progress monitoring, variance detection and
elimination, control of costs, performance and quality
Recommended Procedure
Fixed price contracts (FPCs) are given preference over hourly rate contracts. Hourly rate contracts
should only be given e.g. in emergency situations. FPCs must be based on a comprehensive job
specification. Clear rules that apply for your plant must be developed and documented which
define
Guideline_maintenance_handbook_2018_02.docx Page 75 of 87
HeidelbergCement Group Guideline Edition: 02
For fixed price contracts, use the standard tender process as described in the Group
Purchasing Policy. Other examples can be found in the HTC NAM Outage Planning Manual
Agree the scheduled start and end dates of the job with the contractor in the purchase
order
Agree contractual penalty for any time delay, and optionally a bonus for early completion
Request safety documents
Discuss the scope of work, the agreed timelines and any possible health & safety issues
with the contractor’s supervisor on site prior to commencement of the job
In case of a problem with the quality of work, its timelines or any other issues review the
problems with contractor’s supervisor or higher. Agree on an action plan and implement to
ensure the issue is dealt with.
Recommended Procedure
Guideline_maintenance_handbook_2018_02.docx Page 76 of 87
HeidelbergCement Group Guideline Edition: 02
Each contractor job is assigned to a responsible person, who is ultimately responsible for
the on-site management and needs to know the scope of work.
At commencement of jobs with bigger volumes a potential daily task plan will be drafted. It
allows the follow-up on the progress of the assigned work and reaction in case any
obstacles in achieving this plan occur.
A Daily Monitoring Sheet for major contractor work supports short interval control of
contractor jobs. It is filled out by the person in charge responsible for dealing with the
particular company. It is required to go to the area where the job is being performed and to
check if everything is going according to the schedule.
A Contractor Management Board (i.e. whiteboard) shall be installed in a central location (i.e.
Maintenance Control Center or workshop). The contractor management board indicates the
presence of all external companies, tasks they are performing, time frames agreed, progress
checked, an employee responsible for dealing with the company and space available for
comments. It is maintained by the person in charge tasked to manage the job. It is regularly
reviewed by the maintenance manager in the course of the daily review meeting.
A final inspection of the work done by the contractor must be conducted and documented;
for major contractor jobs the Acceptance Report must be used. The inspection includes
the scope of work as defined in the specification, and general issues similar to those
described in Short Interval Control (e.g. cleanliness of the workplace)
Whenever possible, “hot commission” the equipment that was worked on
Additionally, the contractor evaluation form described below must be filled in, reviewed with
the contractor and then handed over to the corresponding departments (e.g. purchasing).
Guideline_maintenance_handbook_2018_02.docx Page 77 of 87
HeidelbergCement Group Guideline Edition: 02
Recommended Procedure
With regular reviews, both dimensions are connected to a specific scoring model ranging from 1
(very bad) to 5 (very good). The combined ratio of both efficiency and cost describes the
performance indicator for the supplier selection. Purchasing is obliged to award the contracts
according to the ranking of the contractors. Contractor Evaluation Sheet
Links
Make or Buy Decision
Guideline_maintenance_handbook_2018_02.docx Page 78 of 87
HeidelbergCement Group Guideline Edition: 02
NOTE: Until further notice, the report for each plant will be generated and
distributed by HTC.
This report contains all Maintenance Performance Indicators (MPI) in a condensed form
and also graphical representations to visualise trends.
The report is generated weekly for each maintenance work centre individually, and for each
plant maintenance department in total.
Until further notice, the reports will be generated and distributed by HTC on a weekly basis.
The significance of the measurement heavily depends on the data quality within SAP,
especially with regards to the data described in Weekly Planning Process.
Targets per MPI for each plant are agreed upon as soon sufficient historical data is
available.
Responsibility
Maintenance Management
Recommended Procedure
The report is distributed all employees fulfilling the Maintenance Management Function. It is also
displayed in frequently visited places on site, visible to all maintenance personnel.
The report is reviewed weekly in the course of the weekly planning meeting, and, when applicable,
in the daily maintenance review meetings, focussing on variances actual – target and trends (see
Maintenance Performance Indicators for the purpose of the individual figures)
Guideline_maintenance_handbook_2018_02.docx Page 79 of 87
HeidelbergCement Group Guideline Edition: 02
Guideline_maintenance_handbook_2018_02.docx Page 80 of 87
HeidelbergCement Group Guideline Edition: 02
Recommended Procedure
The SAP PM related processes described in this Handbook represent current best practice.
Improvements and changes which may come up over the time will be implemented in all plants.
Links
Responsibility
Planning function
Recommended Procedure
The plant equipment must be represented in by the following objects:
Functional location – represents a group of technical assets (e.g. kiln system, kiln drive,
etc.), to structure those in different hierarchical levels
Equipment – represents independent pieces of machinery (e.g. motor, gearbox, pump,
etc.). They are placed in a functional location and can be installed, replaced and
maintained.
Assembly – represents a group of parts (materials) for equipment. It can be used to divide
a spare part list in different groups.
Bill of Material (BOM) – represents a list of assemblies and/or spare parts (materials) for
equipment.
HeidelbergCement plants use one common functional location structure with 4 levels. The codes
for level 1 and 2 are given by the 4-digit (SAP) plant number (level 1) and the 2-digit production
area (level 2). For level 3 and 4 the HTC numbering system as illustrated below is applicable (
Asset Numbering System). Level 3 is mandatory to use and represents functional locations and
Guideline_maintenance_handbook_2018_02.docx Page 81 of 87
HeidelbergCement Group Guideline Edition: 02
refers to a cost center. Level 4 is optional and can be used primarily for equipment or subsystems
(function location again) of level 3 and to further sub-division of levels, if required.
Equipment Numbering
Computer created numbering for equipment is used, when installing new equipment. SAP:
automatic creation of a number between 80000000 – 89999999)
For preventive maintenance tasks Maintenance plans must be created. Use external numbering for
a maintenance plan. A plan code always starts with a 2-digit country prefix, e.g. PL for Poland. The
other digits can be defined by the country.
Guideline_maintenance_handbook_2018_02.docx Page 82 of 87
HeidelbergCement Group Guideline Edition: 02
Numbering – Equipments,
Maintenance Handbook Maintenance plants
Valid as of: 2018-04-16
– e.g.
– e.g.
All plants have to record all materials important to maintain their equipment. Plants with SAP PM
must record these materials into the “FL or Equipment BOM” of SAP. It must be avoided to use the
part list type “material” for maintenance. All other plants have to use the same procedure in a
similar system.
Responsibility
Planning function
Recommended Procedure
New Equipment
Whenever an equipment / asset is replaced or added, the spares list of that equipment is entered
into the system that will generate the BOM. The expressiveness and completeness of that spares
list is vital for the creation of the BOM. It ensures that all relevant components are recorded and
linked to the equipment.
Guideline_maintenance_handbook_2018_02.docx Page 83 of 87
HeidelbergCement Group Guideline Edition: 02
Step 1:
All work performed by the maintenance department has a work order that is linked to a piece of
equipment. The stores are handing out spare parts and book them against the appropriate
reservation.
Step 2:
All other material used must be booked directly on the work order by the person performing the
task. Also, any substitutions must be clearly indicated (e.g. material number x replaced by material
number y)
Step 3:
On receiving back the work order, all recorded materials used are added to the BOM. In case of
permanent substitution of a part the BOM is updated by adding the new components and removing
the old ones.
Inventory Review
As the BOM’s will grow with time, it is currently not possible to remove all spare parts of machines
that are taken out of service. Therefore, a list of non-moving items (10 years and 5 years) is
annually reviewed (SAP transaction MC 46, Pareto Analysis). The materials identified as being
redundant are then marked for deletion and need to be written off, scrapped or sold. In case that
equipment of the same make is being used in other Heidelberg plants, the redundant stock items
must be offered those plants first.
All BOM’s are assigned to Functional Location or Equipment. The list consists of spare parts and
materials. The BOM can be build up in one or more levels according the complexity of the
equipment. It is mandatory that the list is suitable to pick up the corresponding parts into the
working plan of the work order. Consumables are not part of the Bill of Material.
Guideline_maintenance_handbook_2018_02.docx Page 84 of 87
HeidelbergCement Group Guideline Edition: 02
Responsibility
Maintenance Expert Group
Recommended Procedure
Links
Standards & Specifications
Guideline_maintenance_handbook_2018_02.docx Page 85 of 87
HeidelbergCement Group Guideline Edition: 02
SIC Frequency: At least twice a day for own people and at least once a day for
major contractor jobs.
Recommended Procedure
Review the daily work plan with the assigned tasks and resources. Draft the SIC tour plan for the
day.
Step 2: Walking the work area
Visit each area where people are currently working according to the SIC tour plan. Investigate the
situation, problems and variances to the work plan.
Step 3: Investigate situation in the work area
Check the work progress in each area visited. Use the Walk-the-Floor Checklist as guidance.
Perform random quality of work checks.
Step 4: Manage variances and take actions
All problems encountered during the SIC tour need to be dealt with immediately. This will minimise
or remove their impact. Actions can take different formats; the aim is to ensure that the job is done
on time, cost efficient and in a safe manner.
Once the whole walk has been performed the supervisor (executor) must ensure that the required
actions are done. Likewise the actions that were the supervisor’s responsibility will need to be dealt
with by the supervisor.
Tools
Walk-the-Floor Checklist
SIC Methodology – guidance paper
Guideline_maintenance_handbook_2018_02.docx Page 86 of 87
HeidelbergCement Group Guideline Edition: 02
Reliability Management
The Forecasting System enables the plants to define the appropriate level of maintenance for its
assets. The criticality of every asset will be assessed Critical Assets and possible failure
modes identified FMEA. Based on the results the Preventive Maintenance Routines will be
reviewed / newly designed. Appropriate Condition Monitoring can subsequently be installed to
monitor the condition of every asset. Whenever failures occur they must be analysed using
RCFA, measures developed and put into practice. The procurement of appropriate spare parts and
their exchange frequencies, considering criticality, costs and lead time can be tailor-made using
the results from the process described. The whole process is designed to verify and document the
real maintenance need for each asset in a cement plant. Based on this need verification an
individual maintenance and repair budget can be planned for each plant.
Activity Management
The Activity Management comprises all processes linked to the utilization of existing resources.
With the tools of the Planning Function efficient and effective resource utilization in terms of
manpower, tools, time and spare parts is assured. Compliance to the plan is controlled by the
Maintenance Management through Short Interval Control and Maintenance Performance
Indicators. The Resource Skills Matrix, Multi Skilling and Autonomous Maintenance enable
maintenance and production employees enhancing their capabilities and ensure effective
cooperation.
Guideline_maintenance_handbook_2018_02.docx Page 87 of 87