Contents:: Field Service Planning
Contents:: Field Service Planning
Contents:
Simple order processing
Order entry and planning
Order processing
Order confirmation
Billing
Order completion
SAP AG 1999
SAP AG 1999
Planned
Helpdesk
Customer Service
SAP AG 1999
SAP AG 1999
Creation
Planning
Planning
Release
Printing
Execution
Confirmation
Technical completion
Billing document
Settlement
Completion
SAP AG 1999
The order processing steps shown here represent the maximum number involved. You can skip
certain steps, or perform several steps simultaneously. You can also automate steps such as billing,
settlement, and completion.
Planning
Description
Resources
Deadlines
Execution
Shop papers
Documentation of work progress
Confirmation
Settlement
Internal
External
SAP AG 1999
Customer
Who should do Which Estimated, Internal Technical
revenues
Dates
Reference object
SAP AG 1999
SAP AG 1999
The employee enters a service notification for the customer call. Since a technician is required, the
employee responsible generates a service order from the notification. Data is copied from the
notification to the order. The notification and order are assigned to one another, and can be processed
together.
Since each order must contain at least one operation, you can maintain the data for the first
operation on the order header screen. The system proposes the data for this operation from the order
header data.
The processor immediately puts the service order in process. The order receives the system status
“Released" and shop papers are printed.
After performing the work, the technician confirms the number of hours worked and the materials
consumed. Additional information regarding activities, damage, and causes of damage are entered in
the notification. The technician then technically completes the order, and simultaneously completes
the notification.
The employee responsible for order settlement creates a billing request from the service order. This
is the basis for the creation of a billing document.
SAP AG 1999
Enter directly
SAP AG 1999
You can create service orders directly. To do this, you must enter at least the order type and
planning plant.
While creating or changing a service notification, you can create a service order from the
notification. The notification and order are thereby assigned to one another and this assignment can
no longer be deleted.
You achieve the same result if you create an order using the function "Create for notification".
If several notifications are combined in an order, these will appear in the object list for the order.
You can automatically generate a service order for planning, executing, and confirming services sold
in this sales order from a sales order item. This is also the case for returns and repairs processing,
which is controlled by the requirements type and requirements class for the sales order item. The
material entered as sales order item must also be recorded in the table “service products”.
You can generate service orders from maintenance items at regular intervals in maintenance
planning.
Description of activity
Text
Service numbers
Sub-operations
Performing work center
Activity type
Deadlines
Relationships
SAP AG 1999
Work performed internally is planned in the operations for internal processing. The attributes of the
operation are defined by the operation control key.
The work to be performed is described in the short and long texts. Alternatively, you can describe
the work to be performed using the service numbers and quantities assigned to the operation.
Operations can be structured using sub-operations. However, the data for sub-operations is
transferred to capacity planning, not to order scheduling.
Assignment of personnel can be made on the requirements assignment overview screen. Capacity
requirements are generated at personnel level from the splits defined here.
The planned working time is important for determining capacity requirements, whereas the
duration of the operation is equally important for scheduling. The system determines the operation
deadlines using the scheduling function. You can enter scheduling restrictions for each operation.
The system proposes the activity type for determining planned costs from the master record of the
performing work center as a default.
Relationships represent the logical dependencies between the operations for one of more orders. A
network is a possible result of relationships.
Technician
Hurst
Peters
Jones
Russell
Gordon
The graphical monitor enables you to obtain an up-to-date overview of the work assigned to
individual technicians at a work center. The system automatically updates the monitor at defined
intervals.
The system displays the absence times from the Time Management component as well as the
capacity load records (assigned order operations) for all technicians assigned to a work center.
You can display, change, or confirm orders from the display.
Free
Required Available
capacity
... and for people
SAP AG 1999
Service - External:
Enter a text for an operation
Generate a purchase requisition with item category
"Standard purchase order"
SAP AG 1999
Work to be performed by a third party is planned as external operations in the order. This requires
the entry of the corresponding operation control key.
An operation for service - external is entered using the standard control key SM02. The external
service is described by the operation text.
An operation for service - external (with service sheet) is entered using the standard control key
SM03. The external service is described by one or more service numbers assigned to the operation.
You can enter additional purchasing information in the external processing data for the operation.
This information is transferred to the purchase requisition generated automatically.
External
operation
Purchase
requisition
Purchase order
Order
release
Goods receipt
Company
Invoice
xyz
Invoice
receipt
SAP AG 1999
Depending on the order type, the system generates one or more purchase requisitions (one purchase
requisition per external operation) when you save or release an order.
In Purchasing, purchase orders are generated from the purchase requisitions. The purchase order
items are assigned to the account for the service order, in other words, the service order is debited
with the costs of the procurement process. The system displays purchase requisitions and purchase
orders in the document flow for the order.
Goods receipts with reference to these purchase orders can be entered as soon as the order is
released.
When valuated goods receipts for external services are entered, the service order is debited with the
order value.
The service order is automatically credited or debited by invoicing differences on invoice receipt.
You can display the goods receipts entered in the list of goods movements for the order and in the
document flow.
External
operation
Purchase
requisition
Purchase order
Order
release
Service
entry
Service
accepted
Company
xyz Invoice
Invoice
receipt
SAP AG 1999
When external operations for services are entered in a service order, service specifications are
created for the operation. These specifications consist of one or more service numbers with
information on the service quantity or from text items.
Depending on the order type, the system generates one or more purchase requisitions when you
save or release an order.
In Purchasing, service purchase orders are generated from the purchase requisitions. The purchase
order items are assigned to the account for the service order, in other words, the service order is
debited with the costs of the procurement process. The system displays purchase requisitions and
purchase orders for the order in the document flow.
The services performed are entered in the function “Service entry" using service entry sheets.
When the services performed have been accepted, the service order is debited with the order value.
The service order is automatically credited or debited with invoicing differences on invoice receipt.
Stock items
Stock material
Creation of reservations
Non-stock items
Direct material reference
Creation of purchase requisitions
Text items
Materials without material master
Notes
SAP AG 1999
Component
assignment
Material
reservation
Order
Availability
release
check May
Printing
Automatic
availability
check May
Goods
issue
SAP AG 1999
You can perform an availability check for each component item or for all components in the order
when assigning components. The material availability list enables you to obtain an overview of the
availability situation.
Material reservations are generated when you save the order, and depending on the order type, are
effective when you save or release the order.
An automatic availability check may be made when you release an order. It is possible to release the
order even in the event of non-availability.
You can also print out a material pick list and withdrawal slip when you print the order papers.
Planned goods issues are entered with reference to the reservation or order number. The system
proposes the planned components for withdrawal posting as a default. If the goods issue is
unplanned, you must enter the order number, material number, and quantity.
Component
assignment
Purchase
requisition
Purchase order
Order
release
Goods receipt
Company
Invoice
xyz
Invoice
receipt
SAP AG 1999
When non-stock materials are assigned in the order, additional purchasing information can be
entered. This information is transferred to the purchase requisition generated automatically.
Depending on the order type, the system generates one or more purchase requisitions when you
save or release an order.
In Purchasing, purchase orders are generated from the purchase requisitions. The purchase order
items are assigned to the account for the service order, in other words, the service order is debited
with the costs of the procurement process. The system displays purchase requisitions and purchase
orders for the order in the document flow.
Goods receipts with reference to the order can be entered as soon as the order is released.
When valuated goods receipts are entered, the purchase value is debited to the service order.
The service order is automatically credited or debited with invoicing differences on invoice receipt.
You can display the goods receipts entered in the list of goods movements for the order and in the
document flow.
Creation of
service order Advance shipment
Item
1000783 PC Maxitec
R-1160 Screen 10
R-1120 Cable
20
R-1130 Keyboard
If the materials required for executing the work should be sent to the customer, you can create a sales
order for advance shipment from the component overview of the service order. You can thereby
create the material items for the sales order by selecting the components in the service order, or by
selecting from the structure list for the reference object.
In the following sales order dialog box, it is possible to supplement and change the material items
proposed from the service order. If changes are made to the items in the sales order, the service order
is not updated.
The sales order is saved together with the service order. The advance shipment sales order is
displayed in the document flow for the service order. The service order and the components copied
to the sales order are assigned the system status "Advance shipment occurred". The system also
automatically sets the indicator "Non MRP-relevant" in the service order for the spare parts.
Only one sales order is created for a service order. If an advance shipment of additional material
components is required later, the existing sales order can be enhanced from the service order.
Generating advance shipment sales orders using the sales document type consignment fill-up offers
you additional options (customer consignment).
SAP AG 1999
You can create a quotation from the planning data for a service order. The service order is used as a
planning tool for the cost estimate. The quotation items are either generated from the planned effort
for the service order or contain the service product in the service order header.
Alternatively, you can automatically generate a service order for the subsequent execution of the
work from a service item in the quotation when creating a quotation in the Sales and Distribution
(SD) application component. If you create a sales order with reference to this quotation, the service
order is then assigned to the corresponding sales order item.
Depending on the settings of the dynamic item processor profile (DIP profile), the services
performed are billed on the basis of planned effort, actual effort, and fixed price of the service
product. The DIP profile is located in the administrative data of the order header and controls
quotation creation as well as resource-related billing.
1
Create service Service 2 Create
order
order quotation for Quotation
Status service order
"Quotation
created"
Contents:
• Service product
• Result of planning
Status
"Quotation
3 Accept
quotation
accepted"
4 Create
billing document Billing
• Fixed price
with reference to document
• Planned effort
service order
• Actual effort
SAP AG 1999
You have created a service order. As long as you have not released it, you can generate a quotation
from this order. This contains the result of service order planning or a service product (service
material). The service order receives the status "Quotation created".
For this, you must have entered a dynamic item processor profile for creating quotations.
The service order cannot be released as long as the quotation has not been accepted.
If the quotation is accepted, the status "Quotation accepted" is set.
A billing request is created when the quotation is accepted. This billing request can be used as the
basis for billing with the fixed price from the quotation.
The service order is billed based on the quotation using the planned effort, actual effort, or fixed
price of the service product.
SAP AG 1999
Why?
Searching for a particular order
Simultaneous processing of several orders
Limiting the work list
Scope
Single or multi-level orders
Order operations
Order components
Order permits
Options
Field selection
Selection conditions
Sorting
Monitor
SAP AG 1999
There are many reasons why the system should support you in selecting order data:
You want to change or display a particular order, but you do not know its number.
You want to change or display several orders that have certain characteristics.
You want to perform particular functions simultaneously for several orders that have certain
characteristics.
You want to obtain an overview of all the operations, components, or permits that meet certain
criteria.
The system provides the following options:
Field selection: Display of the most important fields in the list.
Options for selecting and sorting based on the field contents displayed.
Monitor for orders with easy-to-understand symbols (traffic light colors). In the lists of orders, a
traffic light symbol can be displayed by selecting ‘Monitor'. This symbol provides information at a
glance. The information monitored can be: Priority, order start and end dates, scheduled start and
end dates.
Order
Order papers
papers
Put in process
Release Status
Status
'RELEASED'
'RELEASED'
SAP AG 1999
When you perform the function "Put in process", the order papers are printed and the order is
released (status ‘RELEASED').
The function "Release" is used to release the order without a printout.
The following functions can only be executed once the order has been released:
Printing of shop papers
Posting costs to the order (time confirmations, material withdrawals, goods receipt postings, and
so on)
Revenue postings to the order by generating billing documents
Technical completion and business completion of the order
Depending on the settings for the order type, you can check the availability of capacity, materials,
and production resources and tools when you release an order. You can also configure the system
reaction in the event of non-availability (no response, warning, or error message).
A settlement rule containing details of the settlement receiver can also be automatically defined
when an order is released.
Job ticket
Pick list
Time ticket
SAP AG 1999
Notification
/ order Paging = Sending short messages
using a pager
Availability:
Notification and order header
Notification / order - Partner overview
SAP AG 1999
During notification and order processing, you can send a pager message to one or more partners. The
paging service requires the components SAPoffice and SAPconnect.
These short messages can also be pre-defined standard texts that are extended individually.
Using the same technology, you can also send messages using the Internet or SAPoffice.
Possible recipients of this information are defined in the communication data for the respective
partner.
The system automatically sets the system status "Paging occurred" for the notification or order
when the first pager message is sent. Pager messages are only sent once the notification or order has
been saved. The paging status can be displayed from the header screen, partner screen, and graphical
monitor. The system displays a list of all notifications and orders from which pager messages have
been sent for each partner that you select. The last status that was transmitted for each pager message
is displayed.
An overview of all pager messages that have been sent for each partner is displayed in the action log
of the notification or order. All the pager messages that were sent and the transmission history are
displayed in the document flow for the notification and order (View "Object Links").
Service orders
Service notifications
Customer data
Technical object data
Contracts
Status changes
Time confirmation
Material withdrawals
Notification data
SAP AG 1999
You can use Mobile Service to download all the data the technician requires to perform their work
from the SAP System to a laptop and then process it independently of the R/3 System.
Service notifications and orders are entered in the SAP System, and downloaded to the laptop
together with customer data, technical objects, contracts, and so on.
The technician can update the notifications and orders for which they are responsible on the laptop
and enter confirmation information. This data is subsequently uploaded to the SAP System.
Order
Order Order Order
technically
created released completed
completed
Operation status:
• Created
• Released
• Partially confirmed
• Finally confirmed
SAP AG 1999
SAP AG 1999
External services
Goods receipt
Service entry sheet
Activities
Activity reports
Completion confirmation texts
Material postings
Planned withdrawals
Unplanned withdrawals
Goods receipt for purchase order
Object changes
All relevant information that has been created during execution of the order is entered during order
confirmation.
This information includes the hours worked by your technicians.
Services performed by a third party are documented as goods receipts or service entry sheets,
depending on the type of purchase order.
The activities performed are described in one or more notifications for the order. Completion
confirmation texts can also be created during the entry of time confirmations.
The system posts both material withdrawals from the warehouse and goods receipts of materials
ordered directly from the vendor.
Object changes, such as conversion tasks or the installation and dismantling of equipment, are
documented as changes to the master data for the corresponding technical objects.
Measurement values and counter readings are entered in the form of measurement documents for
the technical object.
The confirmation of internal services, material withdrawals, notification data, and measurement
documents on one screen is possible using the "Overall completion confirmation" function.
Functions:
Single entry
Collective entry with/without operation selection
Overall completion confirmation
Time Sheet
Entries:
Order and operation number or confirmation
number for operation
Performing work center
Personnel number (if required)
Actual working time
Scope: Partial or final confirmation
Further information
SAP AG 1999
The following functions are available for confirming the time required for internal activity: Single
entry (one screen per confirmation document), collective entry directly and with operation
selection, and overall completion confirmation. The cross application time sheet (CATS) enables
you to make a standard entry of the hours worked for different target applications.
Times are assigned by entering the order and operation numbers or by entering the internally
assigned confirmation number for the operation. The system proposes the performing work center
as a default from the planning data. The personnel number is an optional entry.
On confirmation, the operation and order are assigned the system status “Partially confirmed" or
“Finally confirmed". The order is assigned the status “Finally confirmed" once all the operations
for the order have been completely confirmed.
Material reservations that are still outstanding (material has not been withdrawn) can be posted
when times are recorded.
Further information that can be entered: The estimated remaining working time; date and time for
work start and end; a forecast for the operation end; a reason code that justifies the difference
between planned and actual times; user-defined short and long texts.
SAP AG 1999
You can confirm the activities performed, as well as confirming damage and malfunction data as
notification data using catalogs.
If a service notification already exists for the order, it can be updated in the completion confirmation.
You can also create one or more notifications of type “Activity report" and assign them to the order.
The activity reports created for an order appear in the order object list.
SAP AG 1999
You can confirm withdrawals of stock material either from a transaction in the Materials
Management application component, or from the time confirmation (single entry or overall
completion confirmation).
For planned withdrawals, the system proposes planned material after you have entered the
reservation or order number. You can then post the planned material.
In the case of backflushing (indicator in the order component), the system automatically posts
material withdrawals as soon as you have entered the first confirmation of time for the operation.
Unplanned material withdrawals are recorded simply by entering the order number, material
number, and quantity.
You can display the goods issues entered in the list of goods movements for the order and in the
document flow.
Goods receipt in MM
Order debiting
Value: Purchase order value
SAP AG 1999
When a valuated goods receipt is entered for non-stock material, the purchase order value (multiplied
by the goods receipt quantity) is debited to the order.
Should differences occur between the order and invoice values, these differences are credited or
debited to the service order when the invoice is processed.
SAP AG 1999
You can enter the reference time when technically completing the order. This is the date and time
with which the location and account assignment data for the reference object are read and saved in
the history. The orders are sorted in the history according to this reference time.
All outstanding planning data is canceled when you perform a technical completion:
Capacity requirements which have not been completely confirmed
Material reservations for which a withdrawal posting has not yet been performed
Purchase requisitions for which no purchase orders currently exist
You must have assigned a settlement rule to the order before you can technically complete it.
The technical completion of an order can be canceled.
SAP AG 1999
Service
order
Billing Billing
request document
Company
xy
Dynamic Invoice
items
SAP AG 1999
During billing, the system generates dynamic items from the information about the expenses
involved (for example, costs for material and personnel). Before a billing request is created, you see
a modifiable overview screen that enables you to determine what the billing request should look like,
and which amounts should be calculated, postponed, or canceled. You generate the billing request
from this overview screen.
You can work on this screen, for example, to simulate prices or save the dynamic items.
There are two summarization levels:
First level: The system summaizes the data records for the overview screen of the dynamic items.
Second level: The system generates a billing request using the data from the dynamic items. If
necessary, the system summairzes the data again. Summarization depends on the settings in the
dynamic item processor profile.
The billing request is a special form of sales order and forms the basis of the billing document. Each
item in the billing request has a material number that is determined by a material determination
procedure defined using the dynamic item processor profile.
You can create a billing request using single or collective processing. The functions "Create billing
document", "Process billing due list", and "Batch billing" are available to you for creating billing
documents.
SAP AG 1999
Warranty check:
Notification processing
Order processing
Creation of billing request
No billing:
Overall order:
Accounting indicator / user status
Expenditure item:
Accounting indicator
Dynamic items:
"Cancel" selection
SAP AG 1999
If the reference object has an active warranty, the system informs the user (assuming the
corresponding settings have been made) using the following functions:
Processing of the notification or service order
Creation of the billing request.
If you are unable to bill the overall order, you can do this by entering an accounting indicator in the
order header. Alternatively, you can set a user status which forbids the business operation "Create
billing document".
If only individual expenditure items are to be billed, you can configure this by entering an
accounting indicator in the time or material confirmation. For other expenditure items, you can set
the accounting indicator subsequently using the function "Repost accounting indicator".
An accounting indicator may result in no dynamic items being created, a particular material number
being determined for the billing request, or a discount being calculated.
You can also cancel the creation of a billing request for those expenditure items which should not be
invoiced.
SAP AG 1999
Service
order
SAP AG 1999
Costs and revenues are collected and displayed at order header level. Revenues are only represented
if the order type is classified as revenue-bearing.
There are two views for costs and revenues.
Estimated, planned, and actual costs as well as quantities are shown in the value category overview.
A value category contains one or more cost elements.
The planned and actual costs as well as quantities structured by cost elements appear in the
planned/actual comparison cost report (CO report).
Estimated costs can be entered manually as long as the order has not been released.
Planned costs are determined according to the planning data for the order (operations and
components). This occurs every time you save the order or call up the function "Costing".
Revenues cannot be estimated and planned.
Actual costs are the result of completion confirmations and other cost postings to the order.
Actual revenues result from the creation of billing documents for the order.
Settlement
receiver
Settlement = Further allocation of costs
and revenues for an order to the
settlement receiver(s).
SAP AG 1999
Prerequisites:
Order is released or technically completed
Order is completely settled
Consequences:
Order can no longer be changed
Order can no longer receive postings
Status "Completed"
SAP AG 1999
If technical completion has not yet been performed for the order, this is performed by the system
using the function "Complete".
Completion is possible as single or collective processing.
You can cancel the completion if the order must be posted to again after completion. You must fully
settle the order again before you can complete it.
SAP AG 1999
1-1-8 Display the printout of the first shop paper on the screen.
Create a goods issue for material number R-1120, quantity 1 from plant
1200, storage location 0001.
1-2-5 Enter a cause code and an activity code for the service notification.
1-2-6 Complete the order technically and save the confirmation data.
1-3-5 Create the billing request. What is the billing request number?
3-1-4 Mark the order for the PC installation and release it.
3-1-5 Exit the list editing.
3-1-6 Choose the function Print service order and enter the order number for the
PC installation. Confirm with Enter. Only choose the material issue slip and
the pick list for printing.
3-2 Paging
3-2-1 Change your order for the PC installation.
3-2-2 Assign the employee David Johnson (Personnel number 10139) to your
order as employee responsible. Confirm the warning message with Enter.
(C) SAP AG LO110 6-54
3-2-3 Send this employee a message using paging. Expand the standard text to
include an additional remark.
3-2-4 Save the order.
The hours worked are entered when the services are performed. The
activities are recorded. The materials taken from the stock are entered.
Finally, the completion of all activities is recorded.
4-3-3 Post goods issues for the planned components for the PC installation service
order. Refer to the order number.
5-1-6 What happens to the time confirmation for which you entered an accounting
indicator?
5-1-7 Save the billing request. What is the billing request number?
The service order results are transferred to Controlling where they are
analyzed in aggregated form.
After settlement the orders are locked for further postings.
6-2-2 Display the distribution rule detail screen and display the account
assignment there.
1-1-4
Service Order
Confirm the data in the dialog box with Enter.
1-1-5
Field name or data type Values
Person responsible Select using search help
Work durtn. 4 hours
1-1-8 You can display the printout using the menu path: System Own spool
requests.
1-2-3
Field name or data type Values
Order Your order number
Enter
1-2-4
Field name or data type Values
Actual work 3
Operation (second line) 10
Actual work (second line) 1
Activity type (second line) 1413
Material R-1120
Quantity 1
Plant 1200
Storage location 0001
1-2-5
Choose a cause code under Causes and an activity code under Activities.
1-2-6
Tech. completion
Save
1-3-2
Sales price view
1-3-3
The net value appears on the upper right side.
1-3-4
Choose Expand all nodes
1-3-5
Choose Save billing request and confirm with Yes.
The billing request is displayed.
1-3-6
Menu path:
Sales Document Billing
Save
1-3-7
Document number: See system message
1-3-8
Logistics Customer Service Service Processing Completion Billing
Document Display
Enter
2-1-2
Main work center: PC-SERVS
2-1-3
Field name or data type Values
Person responsible Select using search help
Order start Tomorrow 8.00
Order finish Tomorrow 8.00
2-1-5
Default activity type: 1410.
2-1-6
Field name or data type Values
Control key SM04
Short text operation Installation
2-1-7
Mark the operation and choose General.
Service selection
Mark Model service specifications, enter CS-INST and choose Enter.
Mark some of the services and choose Adopt services.
Enter planned work times in Work.
2-1-8
Back
2-1-9
Mark the third operation and choose Dates.
Enter the date for the day after tomorrow and time 8:00 as the Restriction Start
Point Must start on.
2-1-10
Back
Schedule
Start monitor
2-1-13
Mark one of the operations (green line) and choose Display object.
Operations
Back
2-1-15
Field name or data type Values
Control key SM03
Short text operation Services
2-1-16
Save
2-1-17
Operations
2-1-18
Mark both external operations and choose Act. data to display the purchase
requisition numbers.
Operations
2-2-2
Field name or data type Values
Component R-1133
Requirement quantity 1
Item category N
Enter
2-2-3
Mark the first component and choose Check material availability and then
Continue.
2-2-4
Back
Material availability, overall
2-2-5
Save
2-2-6
Components
2-2-7
Order Function Availability Availability List
(C) SAP AG LO110 6-71
Back
2-2-8
Mark the first component and choose Gen. data to display the reservation number.
Back
2-2-9
Mark the third component and choose Purchasing to display the purchase
requisition number.
2-2-10
Choose Back and then Costs to display the planned costs.
Enter
2-3-2
Field name or data type Values
Order short text PC installation
2-3-4
Mark the first operation and choose General.
2-3-5
Save
Order number: See system message.
2-3-7
Net value: See column Net value.
2-3-8
2-3-9
The quotation is displayed. Save.
2-3-10
Accepting a quotation
Logistics Customer Service Service Processing Order Service Order
Change
Header data
Execute
3-1-3
Mark the server enhancement order and choose Details.
Choose Put in process and then Print with online window.
Print/fax
3-1-4
Mark the PC installation order and choose Release order.
3-1-5
Back (x2)
Choose Enter, deselect the papers that should not be printed and choose Print/Fax.
3-1-7
You can display the printout using the menu path: System Own spool requests.
3-2 Paging
3-2-1
Logistics Customer Service Service Processing Order Service Order
Change
Header data
3-2-2
Field name or data type Values
Person responsible Personnel number 10139
Enter
3-2-3
Paging/Communication
Enter text, Continue
3-2-4
Save
4-1-2
Enter (x2)
4-1-3
4-1-4
At the fourth operation choose Operation data (magnifying glass symbol) and then
Services. Choose Service selection.
Mark Order and choose Continue.
Mark some of the services and choose Adopt services.
4-1-5
Save
4-1-7
Execute
4-1-8
Save
Enter
Yes (x2)
4-2-3
Notification
Continue
4-2-4
4-2-5
Back
Save
To order
Continue
Mark both components and choose Post.
4-3-2
Enter
Post
Continue
Mark the component and choose Post.
4-4-2
Execute
4-4-3
Mark your orders, choose Complete (technically) and then incl. notifications.
Header data
4-5-2
Document flow
Back
Extras Order Documents Completion Confirmations
Back
Extras Order Documents Goods Movements
Back
4-5-3
Objects
4-5-4
Costs
5-1-2
Expenditure view
5-1-3
Mark the line with material R-1150 and choose Cancel all.
5-1-4
Sales price view
5-1-5
The net value appears on the upper right side.
5-1-6
Expand all nodes
A rebate of 100% is determined for confirmations with an accounting indicator.
5-2-2
Field name or data type Values
Billing date from Yesterday
Sold-to party T-CSD##
Documents to be selected Order-related
5-2-3
Display billing list
Save
5-2-4
You can see the billing document numbers by marking the line with the group
number and choosing Documents.
Costs
6-1-2
Report planned/actual
6-1-3
Order result: line Debits, column Actual.
Back. Confirm with Yes.
6-2-2
You can display the settlement receiver by marking one line and choosing Details. Then
choose Profitability segment - Display account assignment.
Execute
Back
6-3-3
Logistics Customer Service Service Processing Order Service Order
Display
Costs
Report planned/actual
6-3-4
A credit was created; the order balance is 0.
Execute
6-4-3
Mark your orders and choose menu path
Order Completion Complete (Business)
Confirm with Yes.