Professional Documents
Culture Documents
Method Statement: Erection of Concrete Pole ACO-9-3004-043-T7-4-0
Method Statement: Erection of Concrete Pole ACO-9-3004-043-T7-4-0
:No.:
Date: 19-02-2020 CONTRACT OGC/14/2017 – EPC
Rev: 0 WORKS FOR PERMANENT STAFF
ACCOMODATION AT FAHUD &
NIMR
METHOD STATEMENT
02/03/2020
OGC ACO-9-3004-043-
Doc. No: T7-4-0
ARTCO
Doc. No:
ARTCO-673-EL-021 METHOD STATEMENT
ERECTION OF CONCRETE POLE
Rev 0
Date 13-02-2020
OGC Document
ACO-9-3004-043-T7-4-0
No:
Revision Status:
Date 13-02-2020
Date 13-02-2020
1. PURPOSE
The purpose of this instruction is to provide the guidelines for concrete pole erection work and associated
activities to satisfy all the relevant specifications and requirements.
2. SCOPE
This method statement is applicable for the offloading of concrete poles associated with this project. This
method statement is applicable for all over the project and provides details pertaining to working methods to
be adopted for installation works. It defines the activities, responsibilities, documentation and safety
measures that will be taken to prevent injury to personnel and damage to property and/or environment.
3. REFERENCES
➢ SP 1106 – Over Head Lines
➢ Contract HSE Plan – ACO-9-2001-01-T7-4-A
➢ HEMP - ACO-9-2001-98-T7-4-A
➢ Contract Quality Plan-ACO-9-2001-02-T7-4-A
➢ Approved Shop Drawings & SLD
➢ AFC & Shop Drawings
➢ Previous approved MS (Attached)
5. RESPONSIBILITIES
5.1. Construction Manager
Construction Manager shall be having the overall responsibility of the MEP works involved. Construction
Manager shall ensure, not limited to:-
• Responsible for control and operation and ensure that the works are carried out according to
Specifications, AFC, shop Drawings and Method Statements.
• Will ensure construction activities are carried out as per method statements.
• Activities are executed as per the scheduled programme.
• Monitor the timely completion of corrective actions.
• Will ensure availability of method statement, drawings on site and communicate to Sr. Construction
engineer.
• Liaison with Company on site activities on a daily basis.
Date 13-02-2020
QA/QC Manager shall have the overall responsibilities of the contract quality management in coordination with
the construction manager. The QA/QC manager shall:
Date 13-02-2020
• Implementation and monitoring of all contract specific requirements, review and monitoring
subcontractors quality management system, performances and QCPs.
• Assess the requirements relative to quality system requirements.
• QA/QC manager or the deputed personnel draft the contract quality plan and then again check that all
company’s requirements are met.
• Where possible he will ensure that documentation prepared for the project follows the format of quality
documentation.
• Initiate the relevant ITPs & method statements in coordination with construction manager.
• Prepare the audit schedule and review meeting schedules, QA/QC manager and or the deputed
personnel shall perform internal audits as per schedule.
• Periodic reviews of contract quality plan at least once in six months and shall make changes as
appropriate.
• Implementation of management reviews to monitor the relevance and effectiveness of the quality system.
• Monitor the completion of “CAPAR” MEP.
5.6. QC Inspector
The basic quality management functions and duties include the following, not limited to:
• Monitoring reporting and controlling Quality related activity as per this document.
• Review the Quality Risk assessments for the MEP activity in accordance with the approved CQP and
inform the changes if any to the Site QA/QC Manager.
• Raising Quality Alerts/ Improvement notice/ Non- conformities as applicable
• Establishment and use of a quality related control and reporting system.
• Routine inspections, technical queries if any with regard to works to be carried out.
• Maintaining the relevant test reports as per ITP
• Material Approvals, Material & work done inspections.
• Liaising with Company for the follow ups of Inspection Request Submitted for the work completed.
6. RESOURCES
6.1. Human Resources
Human Resources with valid approvals by the company as applicable shall be, not limited to
• Construction Manager
• Sr. Construction Engineer
• HSE Advisor
• QC Inspector
• Supervisor/ Foreman
• Equipments Operators
• Electrician
• Helpers
Date 13-02-2020
7. PROCEDURE
• The delivery (pole sections, steel parts, crates with accessories, pallets etc.), must be inspected on the
lorry or wagon at the time of receipt on basis of the delivery note to verify that it is correct, as well as for
the transport damages. If deviations or faults are found, a note must be made on the DO & informed to
the concerned PM.
• Accessory parts packed in crates or steel components delivered in bundles or loose must be checked
for completeness and transport damage.
• Complaints about the parts supplied must be reported to the site manager immediately by phone. A
copy of the delivery note should be attached to the written fault or damage inventory to be submitted
subsequently.
• The conical and cylindrical pole sections are unloaded by crane using two suitable web slings or with
steel ropes with protective covering. To avoid transverse cracks in the concrete, the suspension points
should be on either side of the center of gravity.
• To prevent damage and accidents the pole must be secured immediately after it is set down to prevent
distortion.
• All lifting equipment tools & tackles shall be inspected and certified by an approved third party.
• A Lifting plan shall be in place which shall be prepared by a trained & experience rigging professional
• Transportation & load restraining shall be identified.
Date 13-02-2020
• To prevent them from being getting dirty or damaged, concrete parts and steel components must be
stored on square timber on the building site until they are installed.
• All materials, especially small parts, must be protected against theft.
• A plane, horizontal, secure base must be provided and the height of the supporting structure must be
selected so that the circular blanks and joint plates do not come into contact with the ground when the
pole section (pole assembly) is lifted.
• These parts must be stored on dry, non-impregnated square lumber (with approx. 150mm ground
clearance) and with lumber between the layers. Store the parts at a slight inclination if possible.
• To prevent the formation of rust, avoid contact with wet grass, prevent water from collecting in the
support and ensure that the parts are not covered directly with plastic sheet or tarpaulins.
• Ensure sufficient ventilation.
• Before work begins the site engineer must satisfy himself that all aids required for erection are available
and that it is possible to assemble all components with them.
• If possible, all other accessories are mounted prior to erection. Other additional parts, cable fastening
rails etc. must be assembled according to the relevant detailed diagram and drawings.
• Before the work begins the site engineer / safety engineer must check that the lifting equipment is in full
working order.
Date 13-02-2020
The lower section of the pole is placed in the drop in foundation with the aid of lifting gear and centered
on the floor of the pit by means of fastening.
Before hoisting ropes are removed, the pole section must be fastened in place by means of steel
construction-type fastenings, winches or hardwood wedges. Guy ropes can also be used.
The perpendicular position of the lower pole section is checked and if necessary realigned.
The lower pole section may not be cast until it is exactly perpendicular and has been checked by the
site engineer (or until the pole is in an exact perpendicular position).
Date 13-02-2020
• The pole guys and/or fastenings that do not remain in the grouting concrete may not be removed until
the grouting concrete has become sufficiently hardened.
• If hardwood wedges are used for the purpose of fixation, they can be completely removed when the
concrete has hardened sufficiently and the resulting hollow space must be filled with grouting concrete.
If they are left in the grouting they would cause damage due to swelling.
• The surface of the grouting between the pole and the foundation is tapered with a 2% gradient and
smoothed flush with the surface of the foundation.
• All the steel components mentioned in the accessories list and/or the execution drawings must be
mounted according to the approved drawings and their bolted joints using the lock washers stated
therein.
• The required torque for bolted joints on steel parts is to be found in the approved drawings/diagrams
and must be applied accordingly.
Probability
Probability
Monitoring
Severity
Severity
Sl No (Routine/Nonroutine Hazards/ Aspects Impacts Significant Recommended Control Measure(s)
Risk
Risk
Records
) Abnormal
Probability
Probability
Monitoring
Severity
Severity
Sl No (Routine/Nonroutine Hazards/ Aspects Impacts Significant Recommended Control Measure(s)
Risk
Risk
Records
) Abnormal
Ensure
1. Adopthandsafeoperated powerprocedures.
manual lifting tools are 110V.
Ensure the equipment
2. Enforced to use Properis fitted
PPEwith the handle
including hand
and it iswhile
gloves not malfunctioned.
lifting.
Use industrial
3. Take sockets
assistance only
from for supply.
co-workers. Tool box talk
Electrocution
Contact with electricity All the electrical equipemt's to be routed through attendance sheet/
Personal Injury
flying particles ELCB. Training
4 Using Power Tools Injury to others - 3 2 M 1 1 L
improper tools Do not remove / alter safety guards on attendance sheet/
Stress
sharp edges machineries. Temp Monitoring
Slip,Trip
Ensure proper earth grounding to be done. Report
Maintain proper cable management.
Inspection of power tools prior to use and must
be equipped with dead man switch.
Probability
Probability
Monitoring
Severity
Severity
Sl No (Routine/Nonroutine Hazards/ Aspects Impacts Significant Recommended Control Measure(s)
Risk
Risk
Records
) Abnormal
Ensure
1. Adoptwork
safeplatforms height
manual lifting are fit for use.
procedures.
Ensure lifeline
2. Enforced are to
to use be provided
Proper to secure
PPE including hand Tool box talk
safety
gloves harness and personal trained on its
while lifting. attendance sheet/
useage.
3. Take assistance from co-workers. Scaffolding
Provide edge protection with sufficient bearing
Fall from height inspection
Uncovered Edges strength.
7 Working on Edges Injury to others - 2 2 M 1 1 L checklist/
Loose Materials Ensure safety net provided at critical location.
Material Damage Working at height
In case of mobile sacffold its must be secured
checklist/
against movement with a rigif point.
Illumination
Dont allow overreach/leaning.
checklist
Properly secure all loose materials at height.
Cover the floor opening with hard barrier.
Probability
Probability
Monitoring
Severity
Severity
Sl No (Routine/Nonroutine Hazards/ Aspects Impacts Significant Recommended Control Measure(s)
Risk
Risk
Records
) Abnormal
Heirarchy of Contol
Reduce Reduce
Elimination Substitution Reduction Enclosure Training EHS Signage Others PPE
Contact Person
* All Legal Requirements Shall be Considered as High Risk L- Low M- Medium H- High ALARP - As Low As Resonably Practicable
Doc. No.: TLS-OGC-EL-CL-001-00
PROJECT
PROJECT COMPANY
CONSULT ENGINEERING
CONTRACTOR
INSPECTION
Result
Sl. No Description of the Checks
A NA N/A
a Check whether all the material is as per approved MAS
b Check for completion of MRDR
c Check for any damages on the pole surfaces
d Check for the dimensions of the pole pits
Pole pits correctly made and compacted/back filled as per
e
standards.
Alignment verticality of the poles are found correct &
f
backfilling completed.
All materials /accessories of OHL are installed as per approved
g
documents & standards.
Anti climbing/danger plate/reflector plate/number
h
plate/phase plate are fitted.
i Earthing of the pole is done & checked.
Confirm area around the pole pits/guys are rammed and
j
leveled also shaped to eliminate water accumulation.
Remarks / Observation
NAME
DESIGNATION
SIGNATURE
DATE