Professional Documents
Culture Documents
Construction of Health Center Barangay Alegre, Bansalan, Davao Del Sur
Construction of Health Center Barangay Alegre, Bansalan, Davao Del Sur
Date
NAME OF PROJECT : CONSTRUCTION OF HEALTH CENTER
LOCATION : Barangay Alegre, Bansalan, Davao Del Sur
PROJECT DURATION : 75 Calendar Days
SOURCE OF FUNDS : CY 2018 - LGDF 20%
A. DIRECT COST
1. Materials and Supplies 57.56 % P 659,501.00
2 Labor 16.24 % P 186,040.80
3. Equipment Rental 1.90 % P 21,773.44
4. Equipt. Spareparts, Tires & Others
5 Fuel, oil
6. Hauling Cost 0.87 % P 10,000.00
B. INDIRECT COST
1 . OCM (Overhead Expenses, 11.07 % P 126,827.29
Contingency, Miscellaneous)
2 . Profit 7.60 % P 87,031.52
3 . VAT 4.76 % P 54,558.71
SUB - TOTAL
3. CONTINGENCY RESERVES
1 . Budgetary Reserve
2 . PBAC Honorarium
3 . Price Escalation
TOTAL ESTIMATED PROJECT COST 100.00 % P 1,145,732.76
1 - Civil Engineer
1 - Foreman
Implementation Procedure: By Contract
PART C
704 Masonry Units 11.88 sq.m. 156.04 104,262.44 668.18 876.98
1027 Cement Plaster Finish (Includes all exposed 3.81 sq.m. 225.80 33,462.00 148.19 194.50
masonry walls, conc.moulding & septic tank walls)
Structural Metal
712 10.21 sq.m. 81.73 89,589.80 1,096.17 1,438.72
( Roof Framing )
1014 Prepainted Metal Sheets Roofing 9.80 sq.m. 88.22 86,006.40 974.91 1,279.57
Carpentry & Joinery Works
1003 5.10 sq.m. 73.30 44,786.70 611.01 801.94
(Ceiling w/ moulding & Air vent)
1005 Steel Windows 6.37 sq.m. 15.96 55,860.00 3,500.00 4,593.75
1008 Aluminum Glass Window 1.19 sq.m. 3.48 10,440.00 3,000.00 3,937.50
1010 Wooden & PVC Doors 4.70 sq.m. 10.71 41,204.80 3,847.32 5,049.61
1002 Plumbing Works 2.36 fixtures 7.00 20,735.20 2,962.17 3,887.85
1018 Ceramic Tiles 0.63 sq.m. 2.85 5,548.60 1,946.88 2,555.28
1032 Painting Works 5.87 sq.m. 308.08 51,524.20 167.24 219.51
Sub-total C 63.48 63.475 543,420.14
PART D
1100 Electrical Works 2.85 outlets 18.00 25,028.20 1,390.46 1,824.97
Sub-total D 2.85 25,028.20
NOTE:
Specifications shall be in accordance with the DPWH Standard Specifications
for Public Works Structures.
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Carpenter 2 6 514.80 6,177.60
Laborer 3 6 396.00 7,128.00
SUB - TOTAL = P
GRAND - TOTAL = P 13,305.60
D Delivery
E Total Direct Cost 13,305.60
F OCM 1,995.84
G PROFIT 1,330.56
H VAT 831.60
I Total Cost 17,463.60
J Unit Cost 17,463.60
Page 3 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Foreman 1 3 712.80 2,138.40
Laborer 4 4 396.00 6,336.00
SUB - TOTAL = P
GRAND - TOTAL = P 8,474.40
D Delivery
E Total Direct Cost 8,474.40
F OCM 1,271.16
G PROFIT 847.44
H VAT 529.65
I Total Cost 11,122.65
J Unit Cost 490.85
Page 4 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Laborer 5 1 396.00 1,980.00
Page 5 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
Page 6 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
Page 7 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Mason 2 5 514.80 5,148.00
Labor 1 5 396.00 1,980.00
Page 8 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
Page 9 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Foreman 1 6 712.80 4,276.80
Roof Installer 2 6 514.80 6,177.60
Laborer 2 6 396.00 4,752.00
Page 10 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Foreman 1 2 712.80 1,425.60
Carpenter 2 6 514.80 6,177.60
Laborer 1 6 396.00 2,376.00
Page 11 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
SUB - TOTAL=P
Name and Specification QUANTITY UNIT UNIT COST TOTAL
2.10m x 1.20m, 6mm thk. clear glass steel casement window on
standard frame w/ 10mm squre bar built-in grills & complete 3 units 8,820.00 26,460.00
accessories (includes installation)
Page 12 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
SUB - TOTAL=P
Name and Specification QUANTITY UNIT UNIT COST TOTAL
1.20m x 1.20m, 6mm thk. fixed clear glass w/ 12mm thk. snap-on
1 unit 4,320.00 4,320.00
alunimum moulding (includes installation)
1.00m x 1.20m, 6mm thk. fixed clear glass w/ 12mm thk. snap-on
1 unit 3,600.00 3,600.00
alunimum moulding (includes installation)
0.70m x 1.20m, 6mm thk. fixed clear glass w/ 12mm thk. snap-on
1 unit 2,520.00 2,520.00
alunimum moulding (includes installation)
Page 13 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Mason 1 2 514.80 1,029.60
Carpenter 2 2 514.80 2,059.20
Labor 2 2 396.00 1,584.00
0.80m x 2.10m Panel Door, shop made, K.D. Gemelina or its 2 units 4,500.00 9,000.00
equivalent w/ 6mm thk. Clear glass and complete accessories
0.80m x 2.10m Panel Door, shop made, K.D. Gemelina or its
1 unit 4,000.00 4,000.00
equivalent
0.70m x 2.10m, 5mm thk. marine Flushed Door, on 2" x 3" Door
1 unit 2,800.00 2,800.00
Frame, Gemelina or its equivalent
0.60m x 2.10m PVC Door w/ door knob pad, bottom louvers &
1 unit 2,500.00 2,500.00
jambs
2" x 6" x 10' Jambs (Gemelina or Equiv.) ( 1 pc.) 10 bd.ft. 33.00 330.00
2" x 6" x 8' Jambs (Gemelina or Equiv.) ( 11 pcs.) 88 bd.ft. 33.00 2,904.00
Assorted Nails 3 kls. 66.00 198.00
C Door Knob,cylindrical, antique brass, twist lock ( Kwikset, Schlage
or equivalent)
4 sets 1,000.00 4,000.00
Handle set door knob w/ dead bolt lock (kwikset, schlage or
1 set 2,500.00 2,500.00
equivalent)
31/2" x 31/2' Brass Loose Pin Butt. Hinges 9 pairs 180.00 1,620.00
Black Coal Tar 1 qrt. 180.00 180.00
Page 14 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Mason 1 1 514.80 514.80
Plumber 1 3 514.80 1,544.40
Laborer 2 3 396.00 2,376.00
3.) FIXTURES
Water Closet, pail-flush-type (ceramics) w/ complete
1 set 3,000.00 3,000.00
accessories
Small Aluminum Sink w/ complete accessories 2 sets 1,800.00 3,600.00
4"x4" Floor Drain, heavy duty, stainless 1 pc. 240.00 240.00
12mmØ Plastic Faucet, heavy duty 3 pcs. 158.50 475.50
Page 15 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Tiler 1 2 514.80 1,029.60
Labor 1 2 396.00 792.00
Page 16 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Painter 2 7 514.80 7,207.20
Labor 2 7 396.00 5,544.00
Page 17 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
Page 18 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
Page 19 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Designation of Personnel NO. OF PERSON NO. OF DAYS RATE / DAY TOTAL
a. Part Time Safety Practitioner 1 10 712.80 7,128.00
b. First Aider 1 32 396.00 12,672.00
Page 20 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
Name and Specification QUANTITY UNIT UNIT COST TOTAL
SUB - TOTAL = P
GRAND - TOTAL = P 7,000.00
D Delivery
E Total Direct Cost 7,000.00
F OCM
G PROFIT
H VAT 350.00
I Total Cost 7,350.00
J Unit Cost 7,350.00
Page 21 of 50
Name of Project : CONSTRUCTION OF HEALTH CENTER
Location : Barangay Alegre, Bansalan, Davao del Sur
SUB - TOTAL=P
SUB - TOTAL=P
Name and Specification QUANTITY UNIT UNIT COST TOTAL
Billboard (2.40mX2.40m Tarpauline, white, w/ wooden frames) 1 unit 4,000.00 4,000.00
Cost of Permits lump sum lump sum 6,000.00 6,000.00
Page 22 of 50
APPROVED BUDGET FOR THE CONTRACT
LEONERL MARCH P. SUARIO FELIPE I. LUAYON DOUGLAS RA. CAGAS, LLB, MNSA, MBE
Engineer IV Provincial Engineer Governor
Chief-Planning & Programming Division
III. Concreteworks
bldg a dietary ilhz corr. vol total
wf1 - 2.90 2.98 3.84 9.71
wf2 0.39 0.66 0.63 1.04 2.72
f1 - 1.69 1.97 4.64 8.30
f2 - 0.23 0.45 - 0.68
c1 - 2.74 2.09 5.56 10.39
c2 2.97 0.38 0.58 3.93
c3 - - 1.74 1.88 3.62
floor 27.28 9.97 7.73 16.70 61.67
rb1 1.87 1.06 1.19 1.54 5.65
rb2 2.34 0.46 0.33 - 3.13
stwf 1.54 1.99 0.71 - 4.24
st slab 2.43 2.21 0.78 - 5.42
119.44
floor area 269.21 95.33 76.41 159.88 600.83
reinf.
bldg a dietary
lgth/no./A no.of ties 12mm 10mm #16 g.i. tw lgth/no./A no.of ties
wf1 - - - - - 48.27 161.90
wf2 10.30 35 - 4.91 0.40 17.50 59.33
f1 - - - - - 12.00 -
f2 - - - - - 1.00 -
c1 - - - - - 14.00 406.00
c2 30.00 18 - 72.04 11.89 4.00 64.00
c3 - - - - - - -
floor 272.80 - - 193.69 5.18 99.70 -
rb1 77.82 519 56.60 56.20 11.75 44.00 293.33
rb2 116.91 586 - 62.03 6.63 22.80 114.00
stwf 19.20 65 - 13.93 1.10 24.90 83.00
st slab - - - 32.65 3.02 - -
56.60 435.45 39.97
12mm 277.55
10mm 936.13
#16tw 102.38
IV. Masonry
4"A 6"A doorA winA
bldg. a 393.62 38.40 39.69 47.05 4" 6"
dietary 265.81 27.20 17.22 20.24 1,069.57 65.60
ilhz 280.70 8.61 14.79
corr. 321.32 7.56 36.72
1,261.45 65.60 73.08 118.80
V. Plaster
4"A 6"A doorA winA 4"&6" d&wA
bldg.a 724.84 45.60 79.38 94.10 770.44 173.48
dietary 438.70 32.30 34.44 40.49 471.00 74.93
ilhz 431.42 17.22 28.37 431.42 45.59
corr 471.74 15.12 73.44 471.74 88.56
16,643.64
ilhz c.corridor
12mm 10mm #16 g.i. tw lgth/no./A no.of ties 12mm 10mm #16 g.i. tw lgth/no./A
- 34.42 2.75 49.60 166.33 27.05 2.82 64.00
- 8.34 0.67 16.80 57.00 6.11 0.65 27.80
18.00 - 2.45 14.00 21.00 2.85 33.00
2.33 - 0.31 2.00 4.65 0.61
48.87 43.98 9.19 12.00 372.00 41.60 46.50 8.42 26.00
- 12.61 0.72 6.00 96.00 26.00 2.17
- 6.00 186.00 20.80 31.00 4.21 8.00
70.79 1.89 77.30 54.88 1.47 167.00
32.00 31.78 6.64 43.60 290.67 31.71 31.49 6.58 64.00
11.40 1.29 16.70 83.50 8.86 0.95
16.60 1.41 8.90 29.67 6.34 0.50
25.1 2.98 7.43 0.87
101.20 255.02 30.31 119.76 245.66 32.11
1,135.17
total
596.97
396.08
385.83
383.18
1,762.05
148.00
380.00
no.of ties 12mm 10mm #16 g.i. tw
214.33 34.91 3.64
93.67 10.11 1.06
49.50 6.72
4.65 0.61
806.00 112.67 100.75 18.25
- - -
248.00 27.73 41.33 5.62
118.57 3.17 616.80 61.68
426.67 46.55 46.22 9.66
- - -
- - -
7.43 0.87
241.10 359.33 49.60
TIME MOTION ANALYSIS
FINE & COURSE AGGREGATE (FOR ITEM III, IV & VIII) ; V = 76.00 cu.m.
GRAVEL FILL (FOR ITEM III, IV & VIII) ; V = 64.56 cu.m. (w/ 1.10 S.F.)
TOTAL VOLUME = 140.56.00 cu.m.
HAULING DIST. = 24 kms.
TIME ELEMENTS
Travel time w/ load = 24(60)/20 = 72.00 min.
Travel time w/o load = 24(60)/35 = 41.14 min.
Loading time and turning = 10.00 min.
Unloading time and turning = 5.00 min.
128.14 min.
TIME ELEMENTS
Travel time w/ load = 1.00(60)/35 = 1.71 min.
Travel time w/o load = 1.00(60)/40 = 1.50 min.
Loading time and turning = 13.50 min.
Unloading time and turning = 3.50 min.
20.21 min.
TOTAL = P 201,240.48
TIME ELEMENTS
TOTAL = P 301,860.72
TIME ELEMENTS
FUEL :
TOTAL = P 13,860.00
A. DIRECT COST
1. Materials and Supplies - % P -
2 Labor - % -
3. Equipment Rental - % -
4. Equipt. Spareparts, Tires & Others
5 Fuel, oil
6. Hauling Cost 10.00 % -
B. INDIRECT COST
1 . OCM (Overhead Expenses, - % -
Contingency, Miscellaneous)
2 . Profit - % -
3 . VAT - % -
CLAUDE P. BAUTISTA
Governor
LDING
0
Err:509
Err:509
6,000.00
Err:509
#DIV/0!
-
-
-
- #REF!
-
profit -
ocm 2,880,000.00
direct cost -
ocm % #DIV/0!
Err:509
PRICE LIST 2016
Nov-16
PRICES
Portland Cement ( 40 kgs. ) 295.00
Washed & Screened Sand 750.00
Washed & Screened Gravel 950.00
Gravel Fill 750.00
MOUNTAIN MIX
Earthfill 440.00
Aluminum Insect Screen (1/8" x 4') 220.00
0.400mm thk. x 0.457m x 2.440m Pre painted Wall Flashing
Solvent Primer (Boysen, Dutchboy, Davies or euivalent)
Solvent Cast (Boysen, Dutchboy, Davies or equivalent)
Solvent Top coat (Boysen, Dutchboy, Davies or equivalent)
Solvent Reducer (Boysen, Dutchboy, Davies or equivalent)
9" Paint Roller with Basin
4" Paint Brush
2" Paint Brush
Sand Paper (Assorted)
TILES
0.60m X 0.60m Ceramic Tiles
0.20m x 0.20m Ceramic Floor Tiles, unglazed
0.20m x 0.30m Ceramic Wall Tiles, glazed
Portland Cement Paste ( 40 kgs. )
Washed Sand
Tile Adhesive, 25kgs./bag
Tile Grout, 2kgs/bag
PVC Tile trim, 10mm x 3.00m
Tile Trim, 2.40m, stainless steel
PAINTING
Solvent Primer (Boysen, Dutchboy, Davies or euivalent)
Solvent Cast (Boysen, Dutchboy, Davies or equivalent)
Solvent Top coat (Boysen, Dutchboy, Davies or equivalent)
Solvent Reducer (Boysen, Dutchboy, Davies or equivalent)
2.) Misc. Items
9" Paint Roller with Basin
4" Paint Brush
2" Paint Brush
Sand Paper (Assorted)
FIXTURES
1.6 GPF Water Closet, (complete w/ Lever type flush handle water tank, fittings and accessories)
Lavatory, semi-counter top, above counter, single hole (complete w/ P-trap, fittings & accessories, includes stainless faucet: gooseneck type)
Stainless Kitchen Sink, single bowl
Urinal w/ Flush Valve & Control Valve
100mm x 100mm Stainless Steel Floor Drain
12mm dia. (1/2" dia) Plastic Faucet
Tissue Holder
Soap Holder
1.6 GPF Water Closet, (complete w/ Lever type flush handle water tank, fittings and accessories)
Lavatory, semi-counter top, above counter, single hole (complete w/ P-trap, fittings & accessories, includes stainless faucet: gooseneck type)
Panel Board with 4 Branches; 1 pair-30A, 2p, CB; 1 pair-15A, 2P, CB; 2 pair-20A, 2P, CB; Plug-in type
bd.ft.
bd.ft.
kgs.
pc.
pc.
ln.m
420.00 pcs
ln.m
80.00 pcs.
40.00 pcs.
40.00 pcs.
295.00 bags
750.00 cu.m.
418.00 bags
77.00 bags
36.50 lgths.
380.00 lgth.
990.00 gals.
580.00 gals.
739.50 gals.
456.00 gals.
83.00 sets
72.00 pcs.
39.00 pcs.
14.00 pcs.
ories) 8,579.00
6,500.00
des stainless faucet: gooseneck type)
92.50
158.50
250.00
250.00
363.00
51.00
33.00
51.00
286.00
59.50
20.00
8,579.00
ories)
1,716.00
des stainless faucet: gooseneck type)
ug-in type
BARS
Structural Metal
PRICES 6 " dia. x 6m G.I. Pipe, Sched 40 lgths.
6.0mm x 50mm x 50mm Angular Steel Bar lgths.
lgth. 85.00 5.0mm x 50mm x 50mm Angular Steel Bar lgths.
lgth. 110.00 4.0mm x 38mm x 38mm x 6m Angle Bars lgths.
lgth. 159.50 16mm dia. x 6m Plain Round Bars lgths.
lgth. 275.00 12mm dia. x 6m Plain Round Bars lgths.
lgth. 516.00 10mm dia. x 6m Plain Round Bars lgths.
lgth. 806.50 1.50mm x 50mm x 100mm x 6m Cee Purlins lgths.
3mm x 75mm x 75mm x 6m Angle Bars Cleats lgth.
3.20mm x 50mm x 6m Flat Bar (Purlin Connector) lgths.
lgths. 176.00 12mm dia. Standard Turn Buckle pcs.
lgths. 184.00 12mm dia x 50mm Heavy Duty Machine Bolt w/ n &w pcs.
lgths. 532.50 12mm thk x 4' x 8' B.I. Plate shts.
lgths. 665.50
Hacksaw Blade ( Sanvick ) pcs.
Welding Rods Ordinary 1/8" dia. (red) kgs.
Acetylene, Refill tanks
Oxygen, Refill tanks
Angle Bars
6.0mm x 50mm x 50mm Angle Bar lgths.
6.0mm x 38mm x 38mm Angle Bar lgths.
5.0mm x 50mm x 50mm Angular Steel Bar lgths.
4.5mm x 50mm x 50mm x 6m Angle Bar lgths.
4.5mm x 38mm x 38mm x 6m Angle Bar lgths.
4.0mm x 50mm x 50mm x 6m Angle Bars lgths.
4.0mm x 38mm x 38mm x 6m Angle Bars lgths.
4.0mm x 25mm x 25mm x 6m Angle Bars lgths.
3mm x 25mm x 25mm x 6m Angle Bar
Cee Purlins
1.50mm x 50mm x 150mm x 6m Cee Purlins lgths.
1.50mm x 50mm x 100mm x 6m Cee Purlins lgths.
1.50mm x 50mm x 75mm x 6m Cee Purlins lgths.
1.20mm x 50mm x 100mm x 6m Cee Purlins lgths.
1.20mm x 50mm x 75mm x 6m Cee Purlins lgths.
Flat Bars
3.20mm x 50mm x 6m Flat Bar (Purlin Connector) lgths.
6mm thk. X 100 x 6m Flat bar lgths.
5.5mm thk. X 100mm x 6m Flat bar lgths.
5.4mm thk. X 100mm x 6m Flat bar lgths.
5mm thk. X 63mm x 6m Flat bar lgths.
3.2mm thk. X 50mm x 6m Flat bar
3mm thk. 50mm x 6m Flat bar
3mm thk. 38mm x 6m Flat bar
3mm thk. X25mm x 6m Flat bar
Steel Plate
12mm thk. 1.20m x 2.40m steel plate lgths.
10mm thk. X 150mm x 150mm steel plate lgths.
9mm thk. X 100mm x 300mm steel plate lgths.
3mm thk. X 150mm x 250mm Steel Plate lgths.
Pre-painted Metal Sheet Roofing (Roofing,Gutter & Flashing)
11,800.00 0.40mm thk., x 1.220m Pre-Painted Roofing
1,088.00 2" Tekscrew Roof Fastener
916.00 Vulcaseal/Roof Sealant
502.00 5/32" dia. Blind Rivets
549.00 Touch Up Paint, Spray Type
231.00 0.40mm thk. x 0.763m x 2.440m Pre painted
195.00 Spanish Gutter (Pre-bended)
606.00 0.40mm thk. X 1.2 x 2.4 Pre-Painted Plain Sht. (Flashing)
1,298.00 3mm x 25mm x 25mm x 6m Angle Bar
567.00
72.00 4.0mm x 25mm x 25mm x 6m Angle Bars
141.00
12,030.00 Vulcaseal / Roof Sealant
2 1/2" Long Metal Tekscrew
59.50
119.00
1,750.00 Welding Rods Ordinary 1/8" dia. (red)
800.00 Acetylene, Refill
Oxygen, Refill
759.00
607.50
519.50
475.50 476
410.50
623.00
1,915.00
1,768.00
1,768.00
902.00
623.00
384.00
384.00
207.00
13,233.00
10,814.00
9,733.00
3,243.00
Gutter & Flashing) Plumbing
ln.m. 480.00 75mm dia., x 3.00m PVC Pipe, S-1000 lgths.
pcs. 2.50 75mm dia., x 90ᵒ PVC Elbow, S-1000 pcs.
gal. 1,540.00 75mm dia., x 45 PVC Bend, S-1000
ᵒ
pcs.
pcs. 1.00 75mm dia. Stainless Aluminum Strainer pcs.
cans 105.00 PVC Solvent (400 cc) cans
800.00
pcs.
13mm dia (1/2" dia) x 6.00m G.I. Pipe Sched. 40
shts. 1,087.00 13mm dia (1/2" dia) x 90° G.I. Elbow, Sched. 40
lgths. 325.00 13mm dia (1/2" dia) G.I. Coupling, Sched 40
13mm dia (1/2" dia) x 50mm (2") G.I. Nipple, Sched 40
lghts. 13mm dia. (1/2" dia) G.I. Union Patente
13mm dia. (1/2" dia) G.I. Gate Valve
gal. 1,540.00 13mm dia. (1/2" dia) G.I. TEE, Sched. 40
pcs. 2.50 Teflon Tape (Big)
13mm dia. (1/2" dia) Stop Cock
13mm dia. (1/2" dia) G.I. End Plug
kgs. 110.00 13mm dia. (1/2" dia) x 9mm dia. G.I. Bushing Reducer
tanks 1,925.00
tanks 880.00
1,342.00
621.50
Painting
569.00 C.1. Steel Truss, Girt & Gutter Frames
62.50 Metal Red Oxide (Boysen, Davies or Equiv.) gals.
62.50 Silver Aluminum Paint (Boysen, Davies or Equiv.) gals.
167.00 Paint Thinner gals.
101.00 Rust Remover / Rust Converter (Boysen, Davies or Equiv.) gals.
4" Paint Brush pcs.
2" Paint Brush pcs.
Steel Brush pcs.
C.2. Stage
Gloss Latex Paint (Boysen, Davies or Equiv.) gal.
Flat Latex Paint (Boysen, Davies or Equiv.) gal.
Latex Tinting Color pints.
Paint , Enamel Semi-Gloss (white) gals
4" Paint Brush pcs.
2" Paint Brush pcs.
Sand Paper doz.
GI Plallete pairs
540.00
653.00
330.00
656.00
72.00
39.00
26.00
708.00
608.00
60.50
605.00
72.00
39.00
168.00
20.00