BALANCE POINT CONTROL BV

Equipment Specification Sheet

600K HWO/SNUBBING UNIT


Operational activities:
• Removal and installation of all types of completion and casing.
• Packer Setting / milling.
• Underbalance operations / Snubbing.
• Milling / Drilling / Well deepening / Casing drilling.
• Well Clean Out.
• Fishing Operations.
• Removal and Installations of Liners.
• Remedial Operations.
• Well Head Re-configurations.
• Installation and removal of ESP Pumping Systems.

Advantages:
• High capacity.
• Small Footprint.
• Flexible.
• Mobile.
• Excellent Cost/Quality ratio.
• Multi-functional.

Long Service record


• The 600k Unit is widely used by Snubbing Service Companies
around the world and is famous for its reliability and mobility.

Operational area
• All European Union Countries and USA.
(Other countries on request).

Transport
• The 600k can be disassembled in easy transportable sections
with a weight less than 10t.

1/6
BALANCE POINT CONTROL BV
Equipment Specification Sheet

BOP Change out & Well Head re-configurations


• Balance Point Control has designed special support frames
which makes it possible to change out BOP’s and perform
modifications to the Well Head without disassembling the
600k Unit. These systems are also very useful during Well
Head repairs and re-configurations.

Custom Specific Solutions


• As part of the Job planning, a Rig-Up Configuration will be
selected, which optimizes operational performance. This
customer specific approach ensures optimal results during
each operation.

Rig-Up Time
1. The Rig-Up time varies based on the configuration and the
type of operation between 12 and 36 hours.

Pipe Handling
• The 600k Unit is equipped with a flexible and reliable Pipe
Handling System based on the Gin Pole-Lay Down Winch
principle. Large flexibility allows variable Pipe Deck locations,
easy handling of all types of tubular and changing Rig-Up
configurations without modifications.
• The Gin Pole contains two Counter Balance Winches both
rated at 1,5 mTon.

2/6
BALANCE POINT CONTROL BV
Equipment Specification Sheet

BOP Change out & Well Head re-configurations


• Balance Point Control has designed special support frames
which makes it possible to change out BOP’s and perform
modifications to the Well Head without disassembling the
600k Unit. These systems are also very useful during Well
Head repairs and re-configurations.

Auxiliary Equipment
• Dependent from the scope of work the following equipment may be needed:
»» Data Acquisition System (DAS-System).
»» Hydraulic Power Pack.
»» Well Control Equipment
(Blow-out preventers, Flow-lines, Choke, etc.).
»» Mud Pump.
»» BOP Remote Control Unit.
»» Office Container.
»» Tool Container.
»» Guy Wire Container.
»» Substructures as per client specifications.

Figure 1: 600k Unit 3/6


BALANCE POINT CONTROL BV
Equipment Specification Sheet

   
600k Snubbing in UK (Live Well) 600k HWO in Germany (Dead Well)

   
600k Snubbing in Germany (Live Well) 600k on a gas-cavern redevelopment project

4/6
BALANCE POINT CONTROL BV
Equipment Specification Sheet

Figure 3: 600k handling Casing in UK


 

5/6
BALANCE POINT CONTROL BV
Equipment Specification Sheet

 
Figure 4: 600k in combination with Coil tubing in UK

6/6