Professional Documents
Culture Documents
Detailed Project Report (DPR) On 100 KLPD Multifeed Distillery Plant Based On Molasses and Grains
Detailed Project Report (DPR) On 100 KLPD Multifeed Distillery Plant Based On Molasses and Grains
At
Village Aurangabad, Tal. Nawabganj,
Dist. Bareilly, Uttar Pradesh
Prepared by:
Prepared for:
Mantras Green Resources Ltd.
Hall No.1, First Floor, NICE
Oswal Overseas Ltd.
Regd. Office :- Sankul, Plot No. A-9, Opp.-Nashik
72, Ground Floor, Taimoor Nagar, Merchant Co-op Bank Ltd., ITI
Opp. New Friends Colony,
Signal,
New Delhi – 110 065
MIDC Satpur, Nasik-422007
INDEX
2 Introduction 8–12
3 Market 13–22
Detailed Project Report on 100 KLPD Multifeed Distillery Plant by OOL at Aurangabad, 1
UP
CHAPTER – 1
EXECUTIVE SUMMARY
Project at a Glance
1. M/s. Oswal Overseas Ltd. having its registered office at 72, Ground
Floor, Taimoor Nagar, Opp. New Friends Colony, New Delhi – 110
065, is a listed Public Limited Company registered under the
Companies Act, 1956.
5. The physical performance of the sugar factory for last two seasons is
given below.
The unit is situated in the cane and food grains rich area in central
Uttar Pradesh. The availability of sugar cane is sufficient for 3500
TCD sugar mill.
Project Background
The company has obtained IEM from the Ministry of Commerce &
Industry, Govt. of India for setting up Distillery.
The Company has also received sanction from Ministry of Food and Public
Distribution, Government of India for 50% subvention in interest for a
term loan of Rs.68.12 Cr for initial 5 years.
The proposed distillery plant of 100 KLPD capacities will employ state-of-
art-technology for production of ENA / ethanol i.e. milling and cooking,
fermentation, multi pressure distillation system, integrated and
standalone evaporation section and slop fired incineration based Cogen
power plant. Sugar factory will supply molasses, while the incineration
boiler and turbine will supply steam and power to the proposed ethanol
plant. It will employ high pressure incineration boiler of 22 TPH and 2.00
MW Back Pressure turbine for 60 KLPD molasses based plant and high
pressure boiler of 10 TPH boilers and 1 MW back pressure turbine for 40
KLPD grain based distillery.
The total requirement of molasses for the entire year operation (330 days a
year) of the proposed 60 KLPD fuel ethanol plant at 100% capacity
utilization will be around 79200 MT. Considering the crushing of about 5
lakh MT, in-house molasses will be available around 22,500 MT with an
average molasses recovery of 4.5% and the balance 56700 MT of molasses
will be met out through procurement through nearby sugar factories or
through use of own B-heavy molasses.
The total requirement of damaged grains for the entire year of operation
(330 days a year) for the proposed 40 KLPD grain based distillery at 100%
capacity utilization will be around 32195 MT. The company proposes to
procure the damaged grains from the district through traders / farmers.
OOL has earmarked about 22 acres of land for the proposed 100 KLPD
distillery plant which is sufficient including future expansion.
OOL also applied for various NOCs and Permissions and expected to get
all the NOCS and permissions within 5-6 months.
FINANCIAL HIGHLIGHTS
Project Cost:
Total Project Cost : (Rs. in Lakh)
Land : 0.00
Site Development : 159.30
Civil works & Buildings : 1758.20
Indigenous Plant and Machinery : 10325.00
Miscellaneous Fixed Assets : 1062.00
Prelim & Preoperative Expenses : 743.80
Contingencies : 140.42
Working Capital Margin : 279.62
Total : 14468.34
Means of Finance:
Implementation Schedule
Conclusions
Over all, the project is well conceived and conceptualized, with sound
commercial viability. The expected financial returns are quite satisfactory.
The project is being implemented by promoters having requisite
background and experience and with employment of experienced
professionals, experts and consultants; all perceived risks have adequate
safe guards.
CHAPTER – 2
INTRODUCTION
2.1.1 This Detailed Project Report (DPR) has been prepared for
M/s Oswal Overseas Ltd. (OOL) by Mantras Green Resources
Ltd., Nasik, for setting up 100 KLPD Distillery Plant based
on molasses and grains as feed stock at Aurangabad, Tal.
Nawabganj, Dist. Bareilly in the Uttar Pradesh State.
2.1.2 M/s. Oswal Overseas Ltd. having its registered office at 72,
Ground Floor, Taimoor Nagar, Opp. New Friends Colony,
New Delhi – 110 065, is a listed Public Limited Company
registered under the Companies Act, 1956.
2.1.6 The physical performance of the sugar factory for last two
seasons is given below.
Sr. Season Crushing Sugar Sugar
No. (MT) Production Recovery
(MT) (%)
1 2016-17 220680 21254 9.63
2 2017-18 409661 35838 10.15
The unit is situated in the cane and food grains rich area in
central Uttar Pradesh. The availability of sugar cane is
sufficient for 3500 TCD sugar mill.
2.2.5 The total requirement of damaged grains for the entire year of
operation (330 days a year) for the proposed 40 KLPD grain
based distillery at 100% capacity utilization will be around
32195 MT. The company proposes to procure the damaged
grains from the district through traders / farmers.
OOL has initiated the following steps for establishing ethanol plant:
Earmarked 22 Acres of land for the proposed plant
Appointed Technical Consultant
Received for IEM for Distillery
Applied for Environment Clearance
Received 50% subvention in term loan interest from Government
of India
Now, OOL has now been fully geared up to commission this project
on or before April, 2020. Latest technologies for ethanol plant and
generation of power will be employed in this project to ensure
optimum efficiency and operating costs.
OOL also applied for various NOCs and Permissions and expected
to get all the NOCS and permissions within 5-6 months.
A dedicated Project Team of OOL has been functioning since 2017,
along with appointed experts and consultants, for speedy and
successful commissioning of this project.
2.4 Promoter’s Background & Experience
OOL’s management comprises experienced and
competent professionals.
2.5 Acknowledgements
MARKET
3.1.1 Background
Carew & Co. Ltd. set up the first distillery in the country at
Cownpore (Kanpur) in 1805 for manufacture of Rum for the
British army. The technique of fermentation, distillation and
blending of alcoholic beverages was developed in India on the
lines of practices adopted overseas, particularly in Europe.
During the Second World War, the demand for the industrial
alcohol increased 4-5 times, above the prewar period, due to
the production of smokeless powder for weapons. The imports
of molasses were hampered due to war conditions. This leads
to evolving the process of grain fermentation for meeting the
requirement of Ethanol.
In India, after the protection granted to the sugar Industry in
1932, a large number of sugar factories were established in
the country, particularly in Maharashtra and Uttar Pradesh
where irrigation facilities existed for cultivation of sugarcane.
Increase in sugar production resulted in accumulation of
molasses, which resultantly, caused unmanageable
environmental problems. At that time the demand for
molasses was almost insignificant and the sugar mills had to
incur considerable expenditure for disposal of molasses. For
resolving these problems a joint committee of U.P. and Bihar
was constituted in 1938 to explore the possibilities of using
molasses for developing alcohol-based industries. The
Committee recommended establishment of distilleries for
production of alcohol, utilizing molasses as a substrate.
Data Source: F.O. Licht, cited in Renewable Fuels Association, Ethanol Industry
Outlook 2008-2014 reports. Available at www.ethanolrfa.org/pages/annual-
industry-outlook
25
Billion Gallons
Rest of World
20
Canada China Europe Brazil
USA
15
10
-
20072008200920102011201220132014
gov/data/
3.1.7 ENA Marketing
There are two types of brandy one is white and other is brown.
White brandy is used for the use by human beings and the
brown for other purpose.
This has been growing over the years at an average rate of 12-
15% per annum. Whiskey accounted for the largest share in
the total IML market (about 53%). There is a good scope for
new entrants.
4.1.2 The plant will operate on molasses as feed stock. The design
parameters of the Distillery plant are given in the following
table:
4.2.1 Process
a) Distillery
Fermentation
Yeast Recycling :
Distillation
Primary Distillation
The CO2 and the degasifying section help remove the CO2
and other non-condensable entrained in the wash. The wash
column is first column in the distillation section. It is also
called the analyzer. Wash is boiled in this column with
steam either supplied as live steam from the boiler (after
pressure reduction and de-superheating) or from a reboiler
which generates steam by evaporating effluent wash.
Spent wash is the wash from which all alcohol has been
removed; this emerges from the bottom of the wash column
at about 105 deg C. Some of the heat is recovered to
preheat fermented wash entering the degasifying column.
Propagation
Flexibility :
Wash Clarification:
a) Distillery project
Advantages of System:
Minimal Labor.
Stable operation.
Near theoretical recovery.
Steam consumption minimized by multi-stage preheating
to permit substantial heat recovery and reuse.
An advanced control system, developed through years of
experience, to provide sustained, stable, automatic
operation.
Consistent excellent product quality maintain
4.3.1 Power
4.3.2 Steam
4.3.3 Water
The water for ethanol plant will be met from existing water
supply scheme of the sugar mill. However, the process water
will be treated separately in the water treatment plant to be
provided in the ethanol project.
Hence, OOL will not face any difficulty to operate its Distillery
plant based on molasses for 330 days if the company make the
firm tie ups with the nearby sugar factory / traders.
a) Urea
b) Turkey red oil
c) Caustic soda lye
d) Potassium permanganate
e) Lub oils, etc.
4.6.2 The plant will operate on grains as feed stock. The design
parameters of the grain based Distillery plant are given in the
following table:
4.7.1 Milling
4.7.4 Distillation
The Refining column is fed with the ENA from the Rectifier
column, which is boiled off in the Refining column to remove
the low boiling impurities like methanol and mercaptants.
4.7.6 Evaporation
4.8 UTILITIES
4.8.1 Power
OOL proposes to have own power generation through boiler &
turbine. Power supply from its own DG set during start up
and in case of emergency and later on only through own
generation. The estimated load will be 1.00 MW.
4.8.2 Steam
4.8.3 Water:
OOL proposes to use ground water from own bore well from
the site. However, the process water will be treated separately
in the water treatment plant to be provided in the distillery
project. Stand alone DM water plant, software plant is
proposed for this project.
Company has already acquired land for their sugar mill &
earmarked about 22 acres of land for its distillery project. Details of
location & infrastructure advantages are as below:
The proposed site is ideal for the proposed distillery project, due to
following reasons:
The Plant is well connected by road, railway and air port. Bijaria
Railway station is 7 Km away from the site. The nearest town is
Nawabganj which tehsil head quarter 5 Km away from the site.
4.12.1 Land
# Particulars Amount,
Rs. Lakh
1 Distillery Building 450.00
2 Raw and treated water storage, WTP Building
& Foundations 100.00
3 Spent wash Storage Lagoons 150.00
4 Bulk Molasses Tank Foundation 80.00
5 RS/ENA/Ethanol Storage Tank Foundations 180.00
6 Grain Silo Foundation 90.00
7 Boiler & Auxiliaries Civil work 200.00
8 Turbine & Auxiliaries Foundations 100.00
9 Ash & Fuel Handling System, civil work 60.00
10 CPU Civil work 60.00
11 Distillery and Excise Office 20.00
12 Sub-total 1490.00
13 Add : GST 268.20
14 Total 1758.20
4.12.4 Plant and Machinery
The erected cost of plant and machinery for 100 KLPD
Distillery plant including boilers and turbines is estimated at
Rs. 10325.000 lakh based on the discussions with the
machinery suppliers. The detail breaks up of cost of plant and
machinery is given below:
# Particulars Amount,
Rs. Lakh
1 Turnkey supply of 60 KLPD distillery based 3600.00
on molasses and 40 KLPD distillery based on
Grain incl. and 60 KLPD ethanol plant, Plant
electrical, auxiliary cooling tower, Air
Compressor, etc.
2 Alcohol/Ethanol / ENA Storage Tanks and
Staging Structure for distillery plant 700.00
3 Condensate Polishing Unit (CPU) 200.00
4 Integrated and Standalone evaporation 950.00
5 Turnkey supply of Boiler & Turbine,
auxiliaries and fuel & ash handling 3300.00
6 Sub-total 8750.00
7 Add : GST 1575.00
8 Total 10325.00
# Particulars Amount,
Rs. Lakh
1 Project Report / TEV Study 4.00
2 Legal fees and other expenses 2.00
3 Establishment charges 3.00
4 Rent, rates and taxes 3.00
5 Travelling Expenses 5.00
Government Clearances 7.00
6 Start up expenses including wages &
salaries 7.00
7 Technical Consultant's Fees 25.00
8 Architect Fees 38.35
9 Project Insurance during construction 2.04
10 Interest During Construction (IDC) 587.41
11 Mortgage expenses, bankers charges, stamp
duty, etc. 60.00
Total 743.80
4.12.7 Contingencies
4.13 Manpower
4.13.1 The category wise details of personnel required for
production, maintenance, administration and marketing,
including their salary levels and total manpower cost.
These have been worked out on the basis of discussions
with the experts in the industry.
Company shall engage suitably qualified and experienced
key technical staff by offering attractive remuneration
packages. The key staff shall be recruited at such a time
that it will receive on the job training on production,
maintenance, quality control, etc. when the plant is being
commissioned and trial runs are being taken.
Company shall operate human resource development policy
as ongoing basis, through formalised in-plant training on
key activities and also deputing its personnel to participate
in seminars, training programmes, etc. for keeping abreast
with the latest developments in process, products,
applications, etc.
Distillation Section:
Others
# Description Tech. Specs. Qty.
1 FO Decanters As Per Standard 2
2 Mixing Bottle As Per Standard 1
3 Vapour Bottles As Per Standard Lot
4 Manometer Bottles As Per Standard 2
5 Seal Pot As Per Standard 1
6 Siphon For Recovery Column As Per Standard 1
7 TA Mixing Bottle As Per Standard 1
8 Pipes, Valves and Instrument As Per Standard Lot
Storage Section for RS, Ethanol Section
# Equipment Technical MOC Qty.
Specification
1 RS Receivers Capacity: 70 m3 MS 3
2 IS Receivers Capacity: 10 m3 MS 1
3 Ethanol Receiver Capacity :70m3 MS 3
4 RS Bulk Storage Tank * Capacity: 700 m3 MS 3
5 Ethanol Bulk Storage Tank * Capacity: 700 m3 MS 3
6 IS Bulk Storage Tank * Capacity: 400m3 MS 1
7 FO Storage Capacity: 10 m3 MS 1
8 Alcohol Pumps with Flameproof Centrifugal CF 8 Suitable
Motor
9 Issue Measures PD Flow meters Standard 43
10 Piping & Fittings Standard Std 1 Lot
Integrated Evaporator:
# Description Qty. Technical data M.O.C.
1 Multiple effect Suitable Shell & Tube type, SS304
evaporator Falling Film
2 Vapor Separator Suitable Cylindrical SS304
3 Surface condenser 1 Sheet & Tube SS304
type
4 Circulation pump Suitable Double Mech Contact Part SS
Shaft 304
5 Process 1+1 Contact Part SS
Condensate pump 304
6 Concentrated 1+1 Contact Part SS
Spent wash 304
transfer pump
7 Condensate Pump 1+1 Contact Part SS
304
8 Vacuum pump 1+1 Contact Part SS
304
9 Piping & Valves Lot Suitable
10 Electrical & Lot Std. Specification
Instrumentation
Detailed Project Report on 100 KLPD Multifeed Distillery Plant by OOL at Aurangabad, UP 56
Independent Evaporator:
# Description Qty. Technical data M.O.C.
1 Feed and Product Tank 2 Type:- Rectangular SS304
Detailed Project Report on 100 KLPD Multifeed Distillery Plant by OOL at Aurangabad, 57
UP
Slop Fired Incinerator Boiler & Turbine
# Particulars Specification
Fire Fighting & Protection system common for molasses and grain
based plant-Fire protection system to be offered based on site plan. The
system is designed as per International rules (NFPA) & equivalent
standards.
Liquefaction
Sr. Item Technical QTY MOC
No. Specification
1 Liquefaction Tank with Type-Cylindrical/ 1 SS 304
sparger and Agitator vertical
Type- Cylindrical,
Acid Dosing
18 Vertical Capacity- 1 1 MS
Tank
m3
Type- Cylindrical,
Antifoam Dosing
20 Vertical Capacity- 1 1 MS
Tank
m3
Shell : Dow
Simmering Column Dia: 900 mm
6 Cu Trays: 1
(Bubble Cap) No. of Trays : 50
Dow Cu
Storage
Sr. Technical
Equipment MOC Qty
No. Specification
1 TA Receivers Capacity: 5 m3 MS 1
Independent Evaporator
Sr.
Description Qty Technical data M.O.C.
No.
1 Feed Tank 1 Type:- Rectangular SS304
Capacity :- Suitable
2 Feed Pump 1+1 Type - Centrifugal type SS 316
Cap Suitable
FINANCIAL VIABILITY
7.1.2 The contingency provision has been made on all firm and
non-firm items of the project cost and has been considered
at 1% for each component of the project, including
preliminary and pre-operative expenses (Refer annexure 6).
7.1.4 The stock levels for various items of working capital have
been worked out. (Refer Annexure-7). The margin money has
been considered at 25% of total requirement of the first year
and c/c facility at 75% of total requirement. The interest rate
on c/c facility is taken at 10%, prevailing banking rate for
that level of c/c limit.
7.3.3 Following table shows the estimated turn over, profits, and the
financial viability indicators like DSCR & IRR.
Post Tax IRR works out to 22.99% and the calculations are
presented in Schedule – I.
CHAPTER – 8
OOL has the experience and know how for adopting the latest
technologies. Consultants and experts have been appointed for
implementation of this project.
OOL has already brought the required equity, as well as provide the
negotiated securities to the bankers and financial institutions. The
term loan and working capital loan will be taken from nationalized
banks / FIs.
OOL will not face any difficulty for arranging technical and financial
tie ups required for the captioned project.
SOCIO-ECONOMIC AND
ENVIRONMENTAL BENEFITS
9.2 The socio-economic benefits arising out of this project for the local
populace will include creation of direct and indirect jobs and
consequent rise in the income levels, associated commercial and
social infrastructure development in the mofussil areas, better
environment and higher returns for the cane crop due to higher
yield and cane price.
9.3 At the national and the State levels, the benefits include reduced
emissions, increased tax revenues and reduction in the
transportation costs.
9.4 At the project and promoter levels, the captioned project offers
excellent opportunities for manufacture of fuel ethanol and improved
returns from trade of emission reductions from the upcoming
international emissions trade market, under the Kyoto Protocol.
9.5 The project will have excellent multiplier effect and will become
truly a win-win situation for all the stakeholders. Thus, the proposed
project has substantial socio-economic and environmental benefits
at the local, the State, the Regional and the National levels.
CHAPTER – 10
10.1.1Strengths:
Authorized Signatory