DAILY ACCOMPLISHMENT REPORT

Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA, M. APARECE
(PROJECTBASED)
No. of Manpower : 7
ACTIVITY FOR THE DAY
BH No. : P-87
Target Depth
Of Boring : 50.00 METERS Date: JUNE 26, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 4:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- MAINTENANCE DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue working.
E. Aparece, D. Jalover, M. Aparece, C. Relota and J. Divinagracia.
- Cleaning of the work area for the preparation for mobilization.
-
-
The mobilization didn’t push through due to the permit that is needed by the city
Of Manila Engineering Office. The permit for the local government is under
No. of boreholes
process. Required
Total Depth Required
END OF WORK (4:00PM) - DRILLERS
No. of Boreholes
END OF WORK (5:00PM) – B. FAMA ARRIVED FOR CHECKING OF TEAM AND Completed
OTHER Total Depth to Date
REPORTS ON TOHO AND C150-5 TEAM FROM TM 10-1. %Accomplishment

`
DAILY ACCOMPLISHMENT REPORT
Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA, M. APARECE
(PROJECTBASED)
No. of Manpower : 7
ACTIVITY FOR THE DAY
BH No. : P-87
Target Depth
Of Boring : 50.00 METERS Date: JUNE 27, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 4:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- MAINTENANCE DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue working.
E. Aparece, D. Jalover, M. Aparece, C. Relota and J. Divinagracia.
- Cleaning of the work area for the preparation for mobilization.
-
-
The mobilization didn’t push through due to the permit that is needed by the city No. of boreholes
Required
Of Manila Engineering Office. The permit for the local government is under Total Depth Required
process. No. of Boreholes
END OF WORK (4:00PM) - DRILLERS Completed
Total Depth to Date
END OF WORK (4:00PM)
%Accomplishment

`
DAILY ACCOMPLISHMENT REPORT
Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA, M. APARECE
(PROJECTBASED)
No. of Manpower : 7
ACTIVITY FOR THE DAY
BH No. : P-87
Target Depth
Of Boring : 50.00 METERS Date: JUNE 28, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 5:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- MAINTENANCE DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue working.
E. Aparece, D. Jalover, M. Aparece, C. Relota and J. Divinagracia.
-
-
-
The mobilization didn’t push through due to the permit that is needed by the city No. of boreholes
Required
Of Manila Engineering Office. The permit for the local government is under Total Depth Required
process. No. of Boreholes
END OF WORK (4:00PM) - DRILLERS Completed
Total Depth to Date
END OF WORK (5:00PM) – ENGINEER B. FAMA ARRIVED AT P24 FOR CHECKING
%Accomplishment
OF TOHO AND C150-5 RIG. CHECKING OF TEAMS FOR REPORT AND REQUESTS.

`
DAILY ACCOMPLISHMENT REPORT
Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA,
No. of Manpower : 6
ACTIVITY FOR THE DAY
BH No. : P-87
Target Depth
Of Boring : 50.00 METERS Date: JUNE 29, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 4:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- MAINTENANCE DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue working.
E. Aparece, D. Jalover, M. Aparece, C. Relota and J. Divinagracia.
-
-
-
The mobilization didn’t push through due to the permit that is needed by the city
Of Manila Engineering Office. The permit for the local government is under No. of boreholes
Required
process. Total Depth Required
END OF WORK (4:00PM) - DRILLERS No. of Boreholes
Completed
END OF WORK (4:00PM) – ENGINEER Total Depth to Date
%Accomplishment

`
DAILY ACCOMPLISHMENT REPORT
Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA, CJ BOLASOC
(PROJECTBASED)
No. of Manpower : 7
ACTIVITY FOR THE DAY
BH No. : P-41
Target Depth
Of Boring : 50.00 METERS Date: JUNE 30, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 7:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- MOBILIZATION DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue working.
- From the complaints of enforcers, it is requested to the Engineering office
- of Manila to allow us to mobilized for us to transfer the rig and avoid the reason
why there is a traffic jam.
- All equipments, rods and other accessories are loaded to the forward truck.
- Disassemblinf of the tent and other kitchen and bed accessories. No. of boreholes
Required
- The rig of TOHO and C150-5 is loaded to the forward truck. We waited for the Total Depth Required
confirmation of the NLEX after the site visit that proceed after lunch. No. of Boreholes
Completed
-Upon arrival, assembling of tent. Unloading of items such as tools and kitchen Total Depth to Date
and bed accessories. All are placed in safekeeping. %Accomplishment
- It is already dark when they finished settling things which is located
at BH-P41. END OF OPERATION AND WORK (7:00PM)

`
DAILY ACCOMPLISHMENT REPORT
Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA, C. BOLASOC
(PROJECTBASED)
No. of Manpower : 7
ACTIVITY FOR THE DAY
BH No. : P-41
Target Depth
Of Boring : 50.00 METERS Date: JULY 1, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 5:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- CLEAN UP DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue working.
E. Aparece, D. Jalover, C. Bolasoc, C. Relota and J. Divinagracia.
- Cleaning of the location and preparing the tools.
- Getting the combination tools.
- Canvas of other needed parts of the rig.
- assembling other equipments needed for drilling. No. of boreholes
Required
Total Depth Required
No. of Boreholes
Completed
END OF WORK (5:00PM) - DRILLERS Total Depth to Date
END OF WORK (6:00PM) – ENGINEER B. FAMA ARRIVED AT THE RIG AND CHECKED %Accomplishment
FOR UPDATES AND REQUESTS. THIS IS AFTER SETTLING THINGS WITH THE
MTPB DUE TO THE REASON THAT THE ELF TRUCK HAS BEEN CLAMPED.

`
DAILY ACCOMPLISHMENT REPORT
Name of Project : NLEX HARBOR LINK PORT ACCESS MOBILITY FACILITY PROJECT
Location : NAVOTAS TO ANDA CIRCLE, MANILA
Name of Client : NLEX
Engr. In Charge : BOJO I. FAMA, J. REYES
Drill Rig Type : TOHO
Driller’s Name : E. APARECE, D. JALOVER, J. DIVINAGRACIA, C. RELOTA, CJ BOLASOC
(PROJECTBASED)
No. of Manpower : 7
ACTIVITY FOR THE DAY
BH No. : P-41
Target Depth
Of Boring : 50.00 METERS Date: JULY 2, 2021

Work Start : 7:00 AM Rig 1 2 3 4 5 6 7 8 9 10 11 12 13 14


Work End : 5:00PM No
.
7:00AM – START OF DAY (Preparation of materials &
equipments,
team’s meeting for today’s objectives and other things to do.)
- BEGIN OPERATION Fair
- MAINTENANCE DAY Stormy
Rainy

- The temporary permit that allows the operation for 14 days already lasted.
-The Office of the Engineering Department of the City of Manila temporarily suspend
the drilling operations of the team without the issuance of the city permit that will
allow the team to continue.
- According to the latest update, the team can now operate and start drilling.
- Assembling the rig of TOHO. The repaired items are now brought to the site.
- R. Diaz picked up the gear that Is not fitted last time.
- The team is helping Diaz in assembling the rig’s parts.
- The team started setting up at the Bh-41. No. of boreholes
Required
- All equipments and tools are placed in safekeeping. Total Depth Required
No. of Boreholes
END OF WORK (5:00PM) - DRILLERS Completed
Total Depth to Date
END OF WORK (6:00PM) – ENGINEER – ARRIVED AT BH-P41 FOR CHECKING OF
%Accomplishment
OTHER RIGS REQUEST AND ACCOMPLISHMENT AS OF TODAY.

`
`