i] KOLER
CONSTRUCTION EXCELLENCE
‘October 23,2018
‘City of uinte West
7 Creswell Orve,
PO 809490
“Trentox, ON, KBV SRG
Attention: Bob Forder
RE: CITY OF QUINTE WEST ANSWER LETTER TO KOLER DELAY NOTICE -
ocra6, 2018
‘As was mentioned in our previous Notice of Delay from Septemter 17, 2018 the project delays.
are 25 a result of numerous changes issued in this project. The latest change orders issued
affected the project critical path:
4-NOC-25 Gas pipe rerouting- Approved on October 9, 2018
2.NOC-27-New fire rated mezzanine work-approved on October 9, 2018
3-NOC-28R Approved on October 9, 2018
‘As per our discussion during the site meeting on Oct 2 & Oct 8, 2018 we informed the client
‘that the Project cannot be completed on the new approved date of November 9, 2018, That is
due to these new changes listed above which were not approved before the first extension of
the project requested with our Notice of Delay sent on September 17, 2018. At the time of the
Notice of Delay issued Sep 17, 2018 we updated the Schedule version E to reflect the delays due
‘oll approved changes to date. These changes NOC-25, NOC-27 & NOC-28 were not included in
the Schedule version E. These were added later on the Schedule version F once that the changes
were approved and we consult with our trades in order to schedule the work accordingly.
After consulting with our trades it was realized that the November 9, 2018 date can not be met
considering the new work that need to be completed under these changes. For that reason we
sent a new Notice of Delays dated October 16, 2018 with the ugdated Schedule version F that,
reflects the new Substantial Performance Date of November 29, 2918
AAS we explained in last two site meetings these changes not only that add up addtional work to
the project, but were delaying the complete work in the mezzanine area. Until the new
mezzanine concrete slab was poured, the sprayed fireproofing material work couldn't start.
Consequently the partition work under mezzanine can not start‘These changes ate addtional work that delayed the project according with the terms of our CCDC 2
contract GC 6 5- Delays
Based on the information we have ‘rom trades we estimated that the new substantial
Performance of the project will be November 28, 2018.
Koler is trying to mitigate these delays and we'll do all possible efforts in order to
minimize these delays.
100 YONGE STREET, SUITES, TORONTO, ONTARIO WASICE —OFRCEAAEATSAIDD FAK sTat6ATBAID