University of Engineering and Technology

Lahore

Subject:
PP-Lab OEL
Design and Analysis of Turbo Generators in Thermal Power Plants

Submitted to:
Sir Jawad
Submitted by:
Group 2 (2018-ME-52,60,70,76)

Department of Mechanical Engineering


Abstract:
The work detailed in this paper assesses the exhibition of the super generator subsystem
of a warm power plant by utilizing a molecule swarm streamlining technique. The significantly
chosen frameworks considered for the review are turbine administering, turbine oil, generator oil
framework, generator gas framework, and generator excitation framework. The Markov based
accessibility demonstrating is embraced for the super generator framework. The Markov
probabilistic methodology-based accessibility reenactment model is accounted for. Through this
review, the Markov based outcomes uncover that the turbine grease and generator excitation
subsystems influence the framework benefit capacity probably. Hence, these basic subsystems
are on higher need according to a support viewpoint. Besides, framework accessibility is
upgraded to get the enhanced accessibility boundaries utilizing the molecule swarm advancement
technique. The PSO based outcomes uncovered that the greatest upgraded accessibility of
98.9394 % is acquired for 30 molecule sizes. The outcomes uncover that with an increment in
molecule size of more than 30, the framework accessibility stays steady. Further, the enhanced
accessibility boundaries are utilized to re-praise an appropriate upkeep methodology for the
plant's super generator framework.

Introduction:
Power plants are important components of energy generation. If we can say that it is the
part and parcel of our daily life energy generation then that’s not wrong. Basically, power plant
is an industrial and commercial facility which is used to generate electricity. So, the prime
purpose of the power plant is to produce electricity. Electricity produced by power plants is used
to run the industrial and household needs of one’s country [1,2]. So, the progress of the any
country depends on the generation of electricity it is producing. Power plants contain generator
which can be one or more which converts the mechanical energy into electrical energy which
then goes to grid station for meeting the needs of household and industry [3].
So, there are lot of power plants producing energy with different outputs. The main topic
of our discussion is the analysis and design of turbo generator in thermal power plant. The
thermal power plant is used to convert the heat energy into electrical energy. Almost all the
power plants operating under the coal, nuclear, geothermal, and solar and natural gas power
stations are the thermal power plants [4].The heat which comes through the combustion of these
fuels is used to raise the temperature of the water which then converted into stem. Then this
steam passes through the turbine, which is used to rotate the blades of the turbines. The turbine is
directly connected to the shaft of the turbo generator. When the blades rotate, the shaft of the
generator also rotates. Then the generator converts this mechanical energy of rotating shaft into
electrical energy. After when steam is passed through the turbine, it passes through the steam
condenser which then recycled to the boiler where it was heated [5].
Now comes to the turbo generator, basically it is a turbine which is connected to the
generator which works together to transform the mechanical energy of moving fluids like fuel,
water steam, natural gas or air into electrical energy [6].
Accessibility is a critical extent of structure execution under portrayed working
conditions of nuclear energy station (TPP). The criticality of the system is related to the impact
of its failures on system performance. To keep TPP working at a higher rate, the maintenance
planning needs to organize in a good manner [7]. The majorly used subjective and quantitative
strategies in prior investigations incorporate shortcoming tree examination (FTA),
disappointment mode impact investigation, utilitarian examination (FA), dependability block
graph (RBD), Markov approach, Monte Carlo reenactment. Choi introduced harm-based
development model and forecast technique for the leftover valuable life (RUL) matured for
steam turbine utilizing the Bayesian induction [8].
To assess the force plant, Celin broke down for both cases from the perspective of
dependability of the force framework to think about the substitution of thermal energy stations
by wind turbines. The work zeroed in on the deficiency of burden assumption. In the refreshed
technique, plant execution is considered as an element of time as opposed to their appraised
power. The first model of a genuine force framework comprises of twelve force plants, including
a thermal energy station [9]. The plant is then re-put with three breeze turbines, the all-out power
than the force of the thermal energy station multiple times more noteworthy. An examination of
the dependability concerning the correlation of the deficiency of burden assumption is performed
utilizing the real climate information for one schedule year. The outcomes
showthatthereplacementofthenuclearpowerplantpassesthroughseveralwind turbines with a five
times bigger breeze power limit than the atomic limit in a decrease of the unwavering quality of
the power net-work [10].
The important distributed writing uncovered that to improve plant accessibility, the
streamlined accessibility boundaries could be utilized to choose/adjust the current upkeep plan.
In ongoing examinations, less consideration was paid to utilize present day streamlining
strategies for the accessibility enhancement of TPP-subsystems. In addition, a requirement for a
systematic approach for performance analysis of subsystems in the case of TPP systems can be
clearly sensed. An attempt is made to bridge the current research hole through the current work
[11]. As said before, profit capacity examination-based execution assessment could be a more
suitable strategy for focusing on the hardware support plan. The presentation assessment and
accessibility advancement of a super generator, by and large known as the turbine-generator
subsystems (TGS), will be accounted for in this review [12].
In the current review, Markov pro-cabalistic based accessibility reenactment model will
be created for the turbine-generator (super generator) arrangement of the nuclear energy station.
The progress state outline is produced based on different conditions of the framework. The
differential conditions addressing various conditions of the framework will be made, and the
exhibition of the framework is assessed for the known upsides of accessibility boundaries
(disappointment rate and fix rate) [13]. Likewise, Markov-based ideal qualities for the
accessibility parameter (failure rate and fix rate) will be gotten, and the support need of the
turbine-generator subsystem will be furnished as per the criticality. Besides, the use of molecule
swarm enhancement technique for improving the accessibility of the turbine-generator
framework will be taken on in the current review [14].
The impact of the quantity of particles on the presentation of the turbine generator
framework will be researched. The subsequent improved accessibility boundaries will be utilized
to change/adjust the current support technique of the tur-bine-generator arrangement of the
nuclear energy station [15].

Methodology:
As already discussed, the purpose of our research paper is to design and analyze the turbo
generators in the thermal power plant. The introduction to these terms such as turbo generators
and thermal power plant is already provided in the introduction section [16]. Here in this section,
we are trying to discuss the pattern which we are trying to follow in order to design and analyze
the turbo generators being used in thermal power plant plus which are the parameters that are
important in regard to the design and analysis. We will also discuss that which are the tests that
our designed turbo generator has to go through in order to get the final approval of being used in
the thermal power plants [17].
The tests are being conducted under the exact same conditions as being used in any
thermal power plant in order to get the accurate results. These tests provide us with the
experimental data like the efficiency, temperature limit, fuel consumption etc which helps us a
lot in the design and analysis of the turbo generator [18]. Theme testing is one of the basic tests
which we perform on the turbo generator to ensure the quality of both components and the
products. Generally, generator testing and investigation administrations will be accomplished for
a wide range of fossil and atomic generators working with practically a wide range of hardware
and can offer total and exact testing administrations [19]. They will review and test all pieces of
your hardware during your generator testing administration. This intensive examination will
permit to produce exact reports and make total proposals to keep your gear working
appropriately and at most extreme effectiveness [20].
Turbo generator system TGS is very important for the continual production of electricity
in any thermal power plant. Therefore, we usually call the TGS a critical system and in order to
get the TGS working in a positive direction we use Markov test. This test allows us to collect the
past failure data and name it as a time difference between failure and repair of the TGS [21].
The TGS consists of five major parts out of which the turbine governor and the generator
gas system are the most critical because they don’t have any standby due to which their failure
leads to the failure of TGS and in turn the whole power plant [22]. As far as the rest of
components of TGS are concerned, their failure causes the power plant to work in the reduced
conditions. In order to study the TGS system some assumptions are made for the ease purpose
like we are going to assume that at one time no more than one component would fail plus the
components that we have as standby are of same capacity being used originally [23]. Similarly,
we’ll have to assume that the repaired part must be like the new part plus the repairing of each
and every part of TGS is statically independent [24].
The simulation of turbo generator of the thermal power plant is being done with respect
to the Markov approach. We’ll use the LaPlace transform techniques to get the new
mathematical equations. In order to show the working of whole system at different levels of
capacity here is a diagram which will help to understand the whole process [25]. The different
levels of capacity are represented in terms of mathematical numbers ranging from 0 to 25 where
0 represents the conditions where the system is at full power. Similarly, 1 to 6 numbers are
showing the reduced capacity at which system is being work and the numbers 7 to 25 represents
the system failure [26]. These are the generalized levels while detailed discussion is being done
below:

The mathematical equations are being derived using some initial conditions as
for time t=0 , Pi ( t )=1 for i=0∨else Pi ( t )=0 for long run availability , theTGS is examine using 0 d dt ∧t →∞[27].
We’ll solve these equations simultaneously for all limiting conditions to get some useful values
as discussed below:
Results and Discussion:
Following figure elaborates the idea that is important for the explanation of the failure
rate on the overall turbo generator system availability. Whereas, the figure 2 indicates the effect
of the repair rate on the overall turbo generator system availability. However, table 1, table 2 and
table 3 indicate several values of μ∧ λ. When the value of λ is maximum, the overall availability
can be reduced rapidly. From the Markov technique, the values of optimum parameters can be
determined.

Fig. 1. Effect of failure rate on TGS availability.


Whereas, the figure 2 indicates the effect of the repair rate on the overall turbo generator system
availability.

Fig. 2. Effect of repair rate on TGS availability


Conclusion:
Following are the conclusions that can be made from this research paper:
 Markov approach and particle swarm optimization are the concepts that are used in the
design and analysis of the turbo generator in the steam power plant.
 The performance of the system can be calculated and its best level of availability can be
recorded by PSO method.
 If the system fails many time during a certain period of time, we can say that the system
is allowing the maintenance of the resources of the turbo generator and the thermal power
plant as well.
 The time which is essential for the data which has to be repair for the purposes of the
maintenance can be used for the better thinking and utilization of the activities used for
the maintenance.
 The research on this topic can be elongated further and further by employing other
techniques such as ant colony algorithm, genetic algorithm etc.

References:
[1] Pariaman H, Garniwa I, Surjandari I, Sugiarto B. Availability improvement
methodology in thermal power plant. Sci J PPI-UKM 2015;2(1):43–52.
[2] Moeinedini M, Raissi S, Khalili-Damghani K. A fuzzy fault tree analysis based risk
assessment approach for enterprise resource planning projects : a case study in an
iranian foodservice distributor. Int J Qual Reliab Manag 2018;35(5):1115–41.
[3] Nord LO, Anantharaman R, Rausand M, Bolland O. A qualitative reliability and
operability analysis of an integrated reforming combined cycle plant with CO2
capture. Int J Greenh Gas Control 2009;3(4):411–21.
[4] Bhangu NS, Singh R, Pahuja GL. Availability performance analysis of thermal power
plants. J Inst Eng Ser C 2018;3:439–48.
[5] Sagayaraj MR, Anita SP, Merceline A. Markov models in system reliability with
applications. Int J Innov Res Dev 2014;3(11):328–36.
[6] Inoue S, Yamada S. Markovian software reliability modeling with change-point. Int
J Reliab Qual Saf Eng 2018;25(1):1–13.
[7] Du S, Zeng Z, Cui L, Kang R. Reliability analysis of Markov history-dependent
repairable systems with neglected failures. Reliab Eng Syst Saf 2017;159:134–42.
[8] Choi W, Youn BD, Oh H, Kim NH. A Bayesian approach for a damage growth model
using sporadically measured and heterogeneous on-site data from a steam turbine.
Reliab Eng Syst Saf 2019;184:137–50.
[9] Cepin M. Evaluation of the power system reliability if a nuclear power plant is
replaced with wind power plants. Reliab Eng Syst Saf 2019;185:455–64.
[10] Özgür-Ünlüakın D, Türkali B, Karacaörenli A, Çağlar Aksezer S. A DBN based
reactive maintenance model for a complex system in thermal power plants. Reliab
Eng Syst Saf 2019;190:106505.
[11] Cheung H, Wang S. Reliability and availability assessment and enhancement of
water-cooled multi-chiller cooling systems for data centers. Reliab Eng Syst Saf
2019;191:106573.
[12] Kim H, Kim JT, Heo G. Failure rate updates using condition-based prognostics in
probabilistic safety assessments. Reliab Eng Syst Saf 2018;175:225–33.
[13] Chen Y, Wang Z, Li YY, Kang R, Mosleh A. Reliability analysis of a cold-standby
system considering the development stages and accumulations of failure mechanisms.
Reliab Eng Syst Saf 2018;180:1–12.
[14] Kumar R, Sharma AK, Tewari PC. Effect of various pump hot-cold redundancy on
availability of thermal power plant subsystems. Int J Intell Enterp
2014;2(4):311–24.
[15] Yogesh Kumar RS, Kumar S. A Markov model for reliability analysis of coal handling
unit of Badarpur thermal power plant. Int J Innov Sci Res 2013;1(6):17–22.
[16] Kumar R, Sharma AK, Tewari PC. Markov approach to evaluate the availability
simulation model for power generation system in a thermal power plant. Int J Ind
Eng Comput 2012;3(5):743–50.
[17] Kumar R. Availability analysis of thermal power plant boiler air circulation system
using Markov approach. Decis Sci Lett 2014;3:65–72.
[18] Turgay S. Multi objective simulated annealing approach for facility layout design.
Int J Math Eng Manag Sci 2018;3(4):365–80.
[19] Mohanta DK, Sadhu PK, Chakrabarti R. Deterministic and stochastic approach for
safety and reliability optimization of captive power plant maintenance scheduling
using GA/SA-based hybrid techniques: a comparison of results. Reliab Eng Syst Saf
2007;92(2):187–99.
[20] Pant S, Anand D, Kishor A, Singh B. A particle swarm algorithm for optimization of
complex system reliability. Int J Perform Eng 2015;11(1):33–42.
[21] Zhao H, Ru Z, Chang X, Li S. Reliability analysis using chaotic particle swarm
optimization. Qual Reliab Eng Int 2015;31(8):1537–52.
[22] Jagtap H, Bewoor A, Kumar R, Ahmadi MH, Lorenzini G. Markov-based
performance evaluation and availability optimization of the boiler–furnace system in
coal-fired thermal power plant using PSO. Energy Rep 2020;6:1124–34.
[23] Okafor C, Atikpakpa A, Okonkwo U. Availability assessment of steam and gas turbine
units of a thermal power station using Markovian approach. Arch Curr Res Int
2016;6(4):1–17.
[24] Cullum J, Binns J, Lonsdale M, Abbassi R, Garaniya V. Risk-Based Maintenance
Scheduling with application to naval vessels and ships. Ocean Eng
2018;148:476–85.
[25] Xia X, Gui L, Zhan Z. A multi-swarm particle swarm optimization algorithm based
on dynamical topology and purposeful detecting. Appl Soft Comput J
2018;67:126–40.
[26] Kumar MRP, Kumaar PP, Kameshwaranath R. Roundness error measurement using
teaching learning based optimization algorithm and com- parison with particle
swarm optimization algorithm. Int J Data Netw Sci 2018;2:63–70.
[27] Orhorhoro EK, Orhorhoro OW, Atumah EV. Performance evaluation of design AD
system biogas purification filter. Int J Math Eng Manag Sci 2018;3(1):17–27.