POWER TRANSFORMERS
&
REACTORS
INSTALLATION, COMMISSIONING,
OPERATION AND MAINTENANCE
INSTRUCTIONS
VOL-II of II
Page No.
SECTION 1 GENERAL INFORMATION
1.1 INTRODUCTION 11
1.2 TRANSPORT OF TRANSFORMER / REACTOR 13
SECTION 2 INSTALLATION
2.1 RECEPTION AND ASSEMBLING OF TRANSFORMERS
/ REACTORS DESPATCHED PARTLY DISMANTLED
AND FILLED WITH NITROGEN 21
2.2 STORING OF TRANSFORMER / REACTOR DESPATCHED
FILLED WITH NITROGEN 33
2.3 ASSEMBLING OF EXTERNAL PIPES 35
2.4 INSULATING OIL, QUALITY AND TREATMENT 37
2.5 OIL FILLING UNDER VACUUM 43
2.6 OIL FILLING INSTRUCTIONS FOR CONSERVATORS
WITH AIR CELL 47
2.7 UNTANKING OF ACTIVE PART 53
2.8 MOUNTING OF GASKETS 55
2.9 WELDED COVER (IF APPLICABLE) 57
2.10 EARTHING OF ACTIVE PART AND CORE
INSULATION TEST 59
2.11 TOUCH-UP PAINTING 69
SECTION 3 COMMISSIONING
3.1 TESTING AFTER ASSEMBLY OF THE TRANSFORMER
/ REACTOR AT SITE 77
3.2 COMMISSIONING CHECKS - TRANSFORMER 79
3.3 COMMISSIONING CHECKS - REACTOR 93
SECTION-1
GENERAL INFORMATION
1.1 INTRODUCTION
1.1.1 POWER TRANSFORMERS
Unlike shunt reactor and Neutral Grounding Reactors where standard
specification is generally followed by utilities, requirements of power
transformers vary depending upon the system design. Hence a tailor made
product becomes the answer. Depending upon the requirements two winding/
three winding/ auto connection/ split winding arrangement with ON LOAD or
OFF CIRCUIT tap changer, five limbs/ three limbs core construction, welded
or bolted tank construction are adopted.
Variation in capacity, impedance and transport profile result in different
sizes of transformer. Refer VoI I for specific requirements of the equipment.
1.1.2 SHUNT REACTORS
Shunt Reactors are used in high voltage systems to compensate
capacitive generation from long lightly loaded overhead lines or extended cable
systems and also for control of dynamic over voltages.
Gapped core construction is preferred for high system voltages over
coreless construction due to the high energy density that can be achieved in
gapped core construction. The core sections between consecutive air gaps
are moulded in epoxy resin to prevent movement between individual laminations.
The spacers forming the air gaps are blocks of ceramics with a high modules
of elasticity and the whole stacking of core modules is cemented together
during the assembly to form a solid column without possibility of rocking , or
rubbing between individual parts.
The core segments are of radial laminated configuration. The radial
laminations prevent fringing flux from entering flat surfaces of core steel which
would result in eddy current overheating and hot spots.
Five limbed core construction is adopted to achieve high zero sequence
impedance. In addition to the three gapped core limbs with windings, there
are two continuous outer return limbs. The two unwound side limbs help in
achieving zero sequence impedance approximately equal to the positive
sequence impedance. Other construction type can be a three limbed
construction. For single phase reactors e.g. 800 KV class middle leg wound
with two return legs type of construction is adopted.
Interleaved disc winding has been used for rated voltages 220 KV and
above. This type of winding configuration provides better impulse voltage
distribution. For lower voltage classes a continuous disc winding or a multi
layer helical winding are used. The tank is rectangular in construction with flat
cover welded to the tank rim at top. The associated cooling control equipment
is housed in a tank mounted weather proof marshalling box. The reactors are
equipped with all standard measuring and controlling fittings and accessories
as described in Volume I.
SECTION-2
INSTALLATION
2. INSTALLATION
2.1 RECEPTION AND ASSEMBLING OF TRANSFORMER/REACTOR
DESPATCHED PARTLY DISMANTLED AND FILLED WITH NITROGEN.
To ensure that a Transformer will function satisfactorily it is important
that handling, lifting, storing and assembling are carried out with great care
and cleanliness by experienced personnel who know the various working
operations very well.
This section gives instructions how handling, lifting, storing and
assembling should be carried out. For large Transformers it is recommended
that the work is done by BHEL or is under supervision by experts from BHEL.
2.1.1 INSPECTION
In connection with receiving and unloading at site, and at the final storing
place before assembling, the transformers shall be inspected carefully. External
visible damages as dents, paint damages etc. may imply that the transformer
has been subjected to careless handling during transport and/or re-loadings,
and a careful investigation is therefore justified.
After the arrival of the material at receiving points, the customer should,
in case of possible damage/loss of any component, make the necessary claims
with the contractors representatives under intimation to supplier so that such
claims can be registered with the transport agents. Before unloading, the
condition of packing and of the visible parts should be checked and possible
traces of leaks verified (condenser bushings). If necessary, appropriate
statements and claims should be made.
Drums containing oil which have been despatched separately should be
examined carefully for leaks or any sign of tampering. All drums are despatched
filled up to their capacity and any shortage should be reported.
In order to protect the active part against moisture, the transformer
tank is filled with nitrogen during transport at an over pressure of 0.17 kg/
sq.cm (2.5 psi) approximately at room temperature.
Check immediately the gas pressure at the arrival. A positive pressure
indicates that the tank and the transformer components respectively are tight,
and that the active part including the insulation materials is dry.
If there is no positive gas-pressure, transformer should be immediately
filled with dry Nitrogen gas at a pressure of 0.17 kg/cm2 (2.5 psi) without loss
of time as per instructions given para 1.2.3
Otherwise, it should be checked if the core isolation is satisfactory and
that accessories packed separately have not been damaged during the transport.
Instructions for checking of the core isolation are given in clause 2.10
2.1.2 UNLOADING
Typical unloading arrangement of the transformer is shown in fig 2.1.
Whenever rollers/trolleys are supplied with transformer, movement of
transformer at site is carried out by mounting these rollers/trolleys. For mounting
of rollers refer roller mounting drawing included in Vol.I.
The equipment required for vacuum treatment and oil-filling under vacuum
should generally be as per Annexure 2.2. The transformer tank and electrical
terminals shall be earthed for safety reasons.
No electrical test on the Transformer is permitted during the evacuation.
Fig. 2.3 shows a typical example of pipe work and valve positioning.
Oil conservators are not evacuated. Valve 7 shall be closed. Valve 6
shall be open unless a breather is fitted.
2.5.6 OIL FILLING
2.5.6.1 OIL QUALITY
The transformer/reactor shall be filled under vacuum with oil which has
been purified and degassed according to Clause 2.4
2.5.6.2 OIL FILLING IN MAIN TANK
The oil shall be heated to a temperature of 500- 60°C measured at the
filter outlet valve. The pressure during the filling shall be max. 1 torr. During
the oil-filling, a transparent plastic tube (5) can be used as an oil-level gauge.
The tube which should be a wall thickness of 5-8 mm, may be connected to a
top and a bottom valve on the transformer.
Oil-filling of the tank is done through valve (12) at a low level on the
transformer and at a maximum rate of 4-5 kL/hour. The pressure in the oil
pipes shall be kept positive and shall be checked by a manometer 13 (if
provided). When the oil-level has reached about 50 mm below the cover/the
vacuum pump is stopped it is preferred that dry nitrogen is introduced in the
tank by opening valve (8). Valve (7) is then opened .and valve (6) closed and
the filling is continued in tank and conservator until the correct oil- level has
been reached in the conservator.
Conservator supplied with rubber air cell shall be filled according Clause
2.6. For oil filling in diverter switch assembly of a OLTC refer leaflet (Vol.1).
TABLE 2.4
ARRIVAL AT
SITE
MEASUREMENT OF
PRESSURE
ASSEMBLY
OIL-CIRCULATION
THROUGH FILTER
STANDING TIME
ACCORDING TO TABLE 2.2.
VOLTAGE APPLICATION
Force Volume
1 kp = 9.807 N 11itre = 0.26 US gallons
1 US gallon = 3.781itres
11itre = 0.22 Imp gallons
1 Imp = 4.551itres gallon
Temperature
C = 5 x (F-32)/9
F = 9 x (C+32)/5
70
Fig. 2.1 Typical Unloading Arrangement of the Transformer
ÊSÉjÉ 2.1 ]ÅõÉƺɡòɨÉÇ®ú EòÉä =iÉÉ®úxÉä EòÒ ´ªÉ´ÉºlÉÉ EòÉ xɨÉÚxÉÉ
Fig. 2.4
ÊSÉjÉ 2.4
GENERAL ARRANGEMENT
ºÉɨÉÉxªÉ ´ªÉ´ÉºlÉÉ
SL.No. DESCRIPTION Ê´É´É®úhÉ
Gò. ºÉÆ.
1. AIR CELL BªÉ®ú ºÉä±É
2. MAGNETIC OIL GAUGE ¨ÉäMÉxÉäÊ]õEò +É<±É MÉäVÉ
3. BREATHER ¥ÉÒnù®ú
4. DRAIN VALVE bÅä÷xÉ ´Éɱ´É
5. AIR RELEASE PLUGS BªÉ®ú Ê®ú±ÉÒVÉ {±ÉMÉ
6. FLANGE FOR TRANSFORMER CONNECTION ]ÅõÉƺɡòɨÉÇ®ú ºÉä VÉÉäc÷xÉä Eäò ʱɪÉä }±ÉåVÉ
7. AIR CELL SUPPORTING LUGS BªÉ®ú ºÉä±É Eäò +ÉvÉÉ®ú ±ÉMÉ
8. OIL iÉä±É
9. PRESSURE GAUGE CONNECTION (WITH PLUG) |Éä¶É®ú MÉäVÉ EòÉ EòxÉäC¶ÉxÉ ({±ÉMÉ Eäò ºÉÉlÉ)
10. PRESSURE GAUGE |Éä¶É®ú MÉäVÉ
11. BREATHER CONNECTING FLANGE ¥ÉÒnù®ú VÉÉäc÷xÉä ´ÉɱÉÒ }±ÉåVÉ
12. CONSERVATOR END COVER EòxVÉ®ú´Éä]õ®ú Bxb÷ Eò´É®ú
Fig. 2.5
ÊSÉjÉ 2.5
Fig. 2.7
ÊSÉjÉ 2.7
SECTION-3
COMMISSIONING
3 COMMISSIONING
3.1 TESTING AFTER ASSEMBLY OF THE TRANSFORMER/ REACTOR
AT SITE.
After the transformer/reactor has been assembled at site, it shall be
tested in order to check that it has not been damaged during transport and
assembly to such an extent that its future operation will be at risk. Regarding
the performance of the test, refer to the testing method as per standards. The
results of the test shall be documented as detailed in Clause 3.2 "commissioning
checks -Transformers" and Clause 3.3 commissioning checks - Reactors.
3.1.1 APPLICATION OF VOLTAGE
If possible, the voltage should be increased step by step up to rated
voltage. This may be done by connecting the transformer/reactor to a generator
whose voltage is raised slowly. The higher the rated voltage of transformer/
reactor the more important it becomes that the application of the voltage is
done as described. If it is not possible to use a generator, the transformer/
reactor may be connected directly to a live line after ensuring voltage &
frequency are same.
After the first application of voltage, the transformer/reactor shall be
checked carefully (gas relay, temperatures, leakages).
When the transformer/reactor has been is service for some weeks with
normal working temperature, all sealing joints shall be re-tightened.
3.1.2 ENERGISING
Low voltage test carried at site after erection and drying out, shall be
compared with factory test results. In case of any difference in values BHEL
must be informed & clearance to be obtained for energisation. DGA of
transformer oil shall be carried out after 24 hrs of commissioning & the
value should be informed to BHEL. The initial magnetising current at the time
of switching will be very high. This depends on the particular moment in the
cycle. The transformer should always be soaked for few hours under constant
care i.e. keep it energized. If the breaker trips on differential, Buchholz or
any other device, the cause must be investigated before re-energising the
transformer or reactor. After successful charging, performance of the
transformer/reactor , OTI, WTI readings should be monitored for 24 hours
and ensured that they are as per loading.
3.1.3 ANALYSIS OF GAS
The gas collected in the relay will help to identify the nature of the
fault. It is suggested that the following checks are made at convenient
intervals or following the indication of accumulation of gas through alarm
signal.
1. Rate of gas collection- The greater the rate of gas collection, the more
severe is the nature of the developing fault.
2. Colour of the gas helps in finding the affected material as follows.
3. Solution 2 -turning to
Dark brown precipitate : Gas of decomposed paper,
cotton or wood insulation.
3.2.4 TESTS ON CT
1. Ratio
2. Polarity
3. Magnetising current
4. IR value.
3.2.5 ON LOAD TAP CHANGER
IV
Winding
LV
Winding
1.
2.
3.
4.
5.
6.
7.
8.
9. (a)
9. (b)
9. (c)
10.
11.
12.
13.
14.
15.
16.
17.
Alarm Alarm
Trip Trip
Fan Start
Fan Stop
Pump Start
Pump Stop
1. Tank
Top Sample
Bottom Sample
2. Cooling system
Top Sample
Bottom Sample
3.3.4 TESTS ON CT
1. Ratio
2. Polarity
3. Magnetising current
4. IR value
3.3.5 MEASUREMENT OF WINDING RESISTANCE
Phase U Phase V Phase W Temp. Remarks
Winding
SECTION-4
MAINTENANCE AND OPERATION
(70oC-40oC)=30oC.
K for 30oC temperature difference = 4.2
So the value at 40oC = 4.2x300 = 1260 M. Ohms.
Value thus converted fairly tally with the actual
Value when cooling the transformer. The factors are tabulated as below:
Nitrogen leak Step up Nitrogen gas pressure The following are susceptible
(in case of to 0.17 kg/cm2 to leakage
Nitrogen sealed (1) Accessories for pressure
system) relief
(2) Flanges
(3) Welded parts
Table 4.8
TRANSFORMER (B)
H.V. Delta Star Delta Star
L.V. Star Delta Delta Star
H.V./L.V.
Delta/Star Yes Yes No No
TRANSFORMER (A) Star/Delta Yes Yes No No
Delta/Delta No No Yes Yes
Star/Star No No Yes Yes
4. Load amps/Load Check against rated figures An improper tap position can
voltage cause excessive core loss. Voltage
and tap position should be
corrected.
DAILY
1. Oil level in Check oil level from oil Top up, if found low.
transformer gauge
conservator
2. Oil level in tap Check oil level from the Top up, if found low.
changer diverter gauge glass.
switch.
3. Oil level in Check the oil level from Top up, if found low.
bushings. gauge glass/gauge.
4. Pipework and Inspect the transformer for If leakages are observed tighten
accessories for leakages. evenly the gasket joints. Replace
leakages ‘O’ ring or washer suitably.
Replace gasket if needed.
MONTHLY
1. Buchholz Relay Check oil level Release collected gas/air
2. Dehydrating Check colour of silicagel. Reactivate/replace with new
breather charge, if found pink Investigate
3. Leakages of - and rectify after taking shutdown.
water into
cooler.
QUARTERLY
1. Bushings Examine for dirt deposition Cracked porcelain should be
and tightness of oil filling rectified/replaced.
plugs. Examine for cracks
in porcelain.Clean and
tighten plugs.
2. Transformer oil Check for di-electric Take suitable action to restore
and tap changer strength and moisture quality of oil.
oil content.
3. Cooler fan, Check contacts, manual Lubricate the fan bearings.
bearing and control and interlocks. Replace worn out contacts and
controls, other parts. Clean/ adjust controls
pumps. and interlocks.
5. Dehydrating Check oil level in the cup Top up, if found low. Clean air
breather and ensure air passages passages.
are free.
YEARLY
1. Transformer oil Check for characteristics in Filter/replace as required to restore
line with IS:1866 the quality.
2. Cable box Check for proper scaling of Replace sealing washer, if found
compound filling holes. damaged.
Check for cracks in the
compound (if used).
3. Alarm and Check all protections and Replace burnt out fuses Adjust the
protection alarm circuits by actual setting and check wiring circuits.
circuits. external initiation. Check Adjust relay setting, if needed.
operation of relays and Replace damaged relays.
their sensitivity.
4. OTI & WTI Check oil in the WTI and Replenish, if required
pockets OTI pockets.
7. Fan motors Check IR value of motor Dry out, if found low, check
winding after rainy season. balancing of fans.
Noise & vibration of fans.
13. Tank cover and Dirt, Dust, Surface Clean touch-up painting.
conservator
NOTES:
1. In addition to the above instructions, reference should be made to
IS:10028 “Code of practice for selection installation and maintenance
of transformer’’
2. Reference of IS:1866 "Code of practice for Maintenance and
Supervision of Mineral insulating oil in equipments'' should be made
for maintenance of oil while transformer is in service. Table 1&2 of
IS:1866 are given at annexure 4.2 & 4.3 for ready reference.
3. The inspection schedule specified for longer periods automatically
includes those specified for shorter period.
4. All maintenance test results and observations should be specifically
recorded.
5. Where matter given in the inspection book differs from that given in
standards referred to, the transformer user should follow the instruction
book.
6. In case of anything abnormal occuring during service, advice from
BHEL should be obtained giving them complete particulars as to the
nature and extent of occurrence, together with the name plate
particulars in order to assist identification of the transformer.
7. As efforts are being constantly made to improve designs and service,
the transformer supplied may differ in minor details from data given
herein.
(ii) water content 145 kV and IS:335-1983 L After filling 25 PPM Recondition oil
(ppm) above or re-filling (Max) or alternatively
prior to If more econmic
Below 145 kV energizing, 35 PPM or other tests
3 months dictate, replace
and after one year oil.
(iii) Specific resistance All voltages IS:6103-1971 L After filling 0.1X1012 Recondition if
(resistivity or re-filling ohm-cm the value of the
ohm-cm) at prior to (Min) at DDF permits,
900C (see Note 9) energizing, 900C reclaim or replace
3 months if not.
and after 2 years
(iv) Dielectric dissipation 145 kV and IS:6262-1971 L After filling 0.2 (Max) Reclaim or
factor (tan δ) above or re-filling replace oil (limit
at 900C Below 145 kV prior to 1.0 (Max) to be adopted
energizing, then depends on the
after 2 years type of equipment
and instructions
from the
manufacturer).
(v) Neutralisation All voltage IS:1448 (P:2) F do 0.5 mg Reclaim or replace
value (total 1967 or KOH/g oil
acidity (see L (Max)
Note 10)